Performed Maintenance US Apparel & Textile Private Limited

Date: 00-00-2010

Equipment Ozone Machine PM Nature Monthly Basis

Sr No. Maintenance Tasks Performed By Perfromed Date Remarks


Clean the electrical pannel from inside by vaccumming
1 Technician
i) For the outside cleaning of painted parts use neutral detergent and soft cloth
ii) For display and keyboard use soft damp cloth

2 Clean the pannel ventilation filter. Technician

Check the fuctioning of the AC inside of the pannel


3 Technician
If not working properly check the compressor and if necessary refill the gas

Check the functioning of all the sensors


4 Remove the carbon or rust from the contact wiring Technician

5 Clean all the probes Technician

Check the functioning of the hydraulic motor, main motor and the chemical dosing
6 Technician
pump motor.

Check & Clean the pneumatic box on the back side of the machine.All valves must be
7 Technician
in properly operation condition

Inspected By Checked By