11.2 Formwork
P.S. For circular man holes difficulty factor for preparation and forming to be considered as 0.45
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
12.0 Laying Pipework/Ductwork
B. BUILDINGS
Plant =1 No
Mixer machine (14/10) =1 No
Dumper
Labour =3 Nos
Mason =2 Nos
Carpenter =1 No
Pump =1 No
Vibrator =1 No
Production =17 M³/Day
5.5 Concrete for beams, slabs and big sections (using pump)
Carpenter =2 Nos
Helper =1 No
Carpenter =2 Nos
Helper =1 No
P.S. Average Production Rate of complete operation shall be 4.40 M²/Man Day
Carpenter =2 Nos
Helper =1 No
Carpenter =2 Nos
Helper =1 No
Carpenter =4 Nos.
Helper =2 Nos.
Carpenter =4 Nos
Helper =2 Nos
(2 x 4 x 4 x 3.40 M) =107 M³
Scaffolders =5 Nos
Helpers =3 Nos
P.S. Average Production Rate of complete operation shall be 2.90 M²/Man Day
P.S.
1) Average production rate for complete operation including
cutting, bending, handling, placing and tying =147 kg/ Man Day
2) Average production rate for handling placing and tying =263 kg/Man Day
8.0 Masonry
Mason =1 No
Helper =1.5 No
Average Production =5.3 M²/Man Day
14.0 Skirtings
Mason =1 No
Helper =1 No
Production =19 M/Day or
9.5 M/Man Day