GASTOS GENERALES

DESCRIPCION COEF. COSTO MESES


PARTIC. UNITARIO

INGENIERO RESIDENTE 0.50 1,800.00 2.50


MAESTRO DE OBRA 1.00 1,200.00 2.50
MOVILIDAD Y VIATICOS RESIDENTE 0.50 200.00 2.50
UTILES DE ESCRITORIO 1.00 100.00 2.50
CARTEL DE OBRA 1.00 150.00 1.00
MOVILIDAD Y VIATICOS TESORERO 0.50 350.00 2.50

TOTAL GASTOS GENERALES S/.

GASTOS DE INSPECCION

PARTIC. UNITARIO

INGENIERO INSPECTOR 0.50 2,400.00 3.00


MOVILIDAD Y VIATICOS INSPECTOR 0.50 200.00 3.00
UTILES DE ESCRITORIO 1.00 100.00 3.00

TOTAL GASTOS DE INSPECCION S/.

COSTO TOTAL

COSTO DIRECTO TOTAL .......... ........................... ...................... S/.


GASTOS GENERALES DE OBRA .......... ........................... ...................... S/.

COSTO DE LA OBRA .......... ........................... ...................... S/.

GASTOS DE INSPECCION .......... ........................... ...................... S/.

COSTO TOTAL DEL PROYECTO .......... ........................... ...................... S/.


SUB
TOTAL

2,250.00
3,000.00
250.00
250.00
150.00
437.50

6,337.50

TOTAL

3,600.00
300.00
300.00

4,200.00

48,290.63
6,337.50
--------------------------
54,628.13
--------------------------
4,200.00
===============
58,828.13
===============
1.-DISEÑO DE LA LINEA DE SUCCION, IMPULSION, CONDUCCION Y RED DE DISTRIBUCION

A).-LINEA DE CONDUCCION / IMPULSION

*)- NOMBRE DEL PROYECTO: :CONSTRUCCION DE I ETAPA DEL SISTEMA DE AGUA HUANABAL

*)- POBLACION ACTUAL 2665


*)- TASA DE CRECIMIENTO (%) 1
*)- PERIODO DE DISEÑO (AÑOS) 20
*)- POBLACION FUTURA 3198
Pf = Po * ( 1+ r*t/100 )

*)- DOTACION (LT/HAB/DIA) 150


*)- CONSUMO PROMEDIO ANUAL (LT/SEG)
Q = Pob.* Dot./86,400 5.552

*)- CONSUMO MAXIMO DIARIO (LT/SEG)


Qmd = 1.30 * Q 7.218
*)- CAUDAL DE LA FUENTE (LT/SEG) 6.83
*)- VOLUMEN DEL RESERVORIO (M3)
V = 0.25 * Qmd *86400/1000 155.90
A UTILIZAR : 156.00
*)- CONSUMO MAXIMO HORARIO (LT/SEG)
Qmh = 2.00 * Qmd = 2.60 Q 14.435

B)- CALCULO DE PRESIONES

ELEMENTO NIVEL LONGITUD PENDIENTES DIAMETRO DIAMETRO VELOCIDAD hf COTA PRESION


DINAMICO (KM) (o/oo) (") COMERCIAL ( " ) FLUJO ( m/s ) (m) TERRENO (m) (m)
CAPTACION 1,284.00
RESERVORIO 905.50 4.500 7337.46 1.00 1.00 14.24 33018.55 904.00 -32638.55

TOTAL 4.500

C)-CONCLUSIONES Y RECOMENDACIONES:
-)La Línea de Conducción y Distribucion tendrá un Diámetro de 1", pues se tiene una Velocidad de Flujo admisible
de 0.72 m/seg. , y con Pérdidas de Carga permisibles.
-)Se considera un Reservorio de 5 m3. de capacidad, el que regulará el 23.48 % del consumo máximo diario
C)-LINEA DE ADUCCION Y RED DISTRIBUCION

PROYECTO :CONSTRUCCION DE I ETAPA DEL SISTEMA DE AGUA HUANABAL


GASTO DE DISEÑO (Qmh) : 14.435 lts/seg.
LONG. TOTAL DE LA RED : 3,753.00 m.
GASTO UNITARIO : 0.00384637 lts/seg/m.

GASTO GASTO VELOC. Sumatr. COTAS PIEZOM. COTAS TERRENO PRESION


TRAMO TRAMO TRANSITO LONGITUD DIAM. FLUJO hf Hf
(lt/seg) (lt/seg) (m) (") (m/seg) (m) (m) ARRIBA ABAJO ARRIBA ABAJO ARRIBA ABAJO

R-A 2.962 14.435 770.00 2.00 7.12 696.51 696.51 905.50 208.99 904.00 2,303.00 1.50 -2,094.01
A - CRP Nº1 0.154 1.308 40.00 1.00 2.58 12.45 708.96 208.99 196.54 2,303.00 2,298.00 -2,094.01 -2,101.46
CRP Nº1 - B 0.212 1.154 55.00 1.00 2.28 13.58 722.54 2,298.60 2,285.02 2,298.00 2,269.00 0.60 16.02
B-C 0.077 0.308 20.00 0.75 1.08 1.74 724.27 2,285.02 2,283.28 2,269.00 2,269.10 16.02 14.18
C-D 0.231 0.231 60.00 0.75 0.81 3.06 727.34 2,283.28 2,280.22 2,269.10 2,266.00 14.18 14.22
D-E 0.115 0.635 30.00 0.75 2.23 9.95 737.29 2,285.02 2,275.07 2,269.00 2,266.00 16.02 9.07
E-F 0.519 0.519 135.00 0.75 1.82 30.89 768.17 2,275.07 2,244.19 2,266.00 2,258.00 9.07 -13.81
F-G 0.096 10.166 25.00 2.00 5.02 11.82 779.99 208.99 197.17 2,303.00 2,302.00 -2,094.01 -2,104.83
G-H 0.327 10.070 85.00 2.00 4.97 39.49 819.48 197.17 157.68 2,302.00 2,291.00 -2,104.83 -2,133.32
H-I 0.346 0.346 90.00 0.75 1.21 9.73 829.21 157.68 147.96 2,291.00 2,267.00 -2,133.32 -2,119.04
C-P7 0.038 9.397 10.00 1.50 8.24 16.59 845.80 157.68 141.09 2,291.00 2,291.50 -2,133.32 -2,150.41
P7-D 1.596 9.358 415.00 1.50 8.21 683.43 1,529.24 141.09 -542.35 2,291.50 2,292.00 -2,150.41 -2,834.35
D-CRP7#2 0.154 7.762 40.00 1.00 15.32 335.75 1,864.99 -542.35 -878.10 2,292.00 2,260.00 -2,834.35 -3,138.10
CRP7#2-P8 0.415 3.839 108.00 1.00 7.58 246.41 2,111.40 2,260.60 2,014.19 2,260.00 2,236.00 0.60 -221.81
P8-E 0.154 3.423 40.00 1.00 6.76 73.84 2,185.24 2,014.19 1,940.35 2,236.00 2,232.00 -221.81 -291.65
E-P9 0.346 0.346 90.00 0.75 1.21 9.73 2,194.96 1,940.35 1,930.62 2,232.00 2,211.00 -291.65 -280.38
E-P10 0.173 2.923 45.00 1.00 5.77 62.03 2,256.99 1,940.35 1,878.32 2,232.00 2,228.00 -291.65 -349.68
P10-P11 0.173 2.750 45.00 1.00 5.43 55.40 2,312.39 1,878.32 1,822.92 2,228.00 2,214.00 -349.68 -391.08
P11-CRP7#3 0.077 2.577 20.00 1.00 5.09 21.83 2,334.22 1,822.92 1,801.09 2,214.00 2,211.00 -391.08 -409.91
CRP7#3-F 0.308 2.500 80.00 1.00 4.93 82.57 2,416.80 2,211.60 2,129.03 2,211.00 2,197.00 0.60 -67.97
F-P12 0.231 0.231 60.00 0.75 0.81 3.06 2,419.86 2,129.03 2,125.97 2,197.00 2,192.00 -67.97 -66.03
F-P13 0.327 1.962 85.00 0.75 6.88 227.37 2,647.22 2,129.03 1,901.66 2,197.00 2,190.50 -67.97 -288.84
P13-P14 0.750 1.635 195.00 0.75 5.74 372.27 3,019.49 1,901.66 1,529.39 2,190.50 2,180.00 -288.84 -650.61
P14-P15 0.885 0.885 230.00 0.75 3.10 141.00 3,160.50 1,529.39 1,388.39 2,180.00 2,174.00 -650.61 -785.61
D-G 3.154 3.769 820.00 1.50 3.31 251.11 1,780.35 -542.35 -793.46 2,292.00 2,290.00 -2,834.35 -3,083.46
G-P16 0.250 0.250 65.00 0.75 0.88 3.85 1,784.20 -793.46 -797.31 2,290.00 2,290.00 -3,083.46 -3,087.31
G-P17 0.115 0.365 30.00 0.75 1.28 3.58 1,787.78 -797.31 -800.89 2,290.00 2,290.00 -3,087.31 -3,090.89
P17-P18 0.250 0.250 65.00 0.75 0.88 3.85 1,791.63 -800.89 -804.74 2,290.00 2,290.00 -3,090.89 -3,094.74

TOTALES 14.435 3,753.00 D = 2" : 880.00 D = 1 1/2" : 1245.00 D=1": 473.00 D = 3/4" : 1,155.00