Documente Academic
Documente Profesional
Documente Cultură
PROJECT: KUNDARKI
JOB NO.: 10-2I-0044
REPORT DATE: 25.04.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 RAFT 522
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
9 FANDECK 114
12 SLUDG PIT 37
13 STAIR CASE 26
14 PC BLOCK CASTING 89
15 OUT LET 26
TOTAL:
DAILY PROGRESS REPORT
PROJECT: KUNDARKI
JOB NO.: 10-2I-0044
REPORT DATE: 25.04.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
WALL UP TO
2 BOTTOM OF SLAB 421
TOTAL: 873
(IV) MISC.
TOTAL:
DAILY PROGRESS REPORT
PROJECT: KHAMBERKHERA
JOB NO.: 10-2I-0046
REPORT DATE: 27.04.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
HELPER
TOTAL
DATE
TOTAL
1 2 3 4 5 6 (B)
SHUTTERING &
ABOVE 3RD LEV.
5 UPTO 4TH LEV. 142 30 0 30 112 7 5 7 16 28 REINF OF CELL 1 & 2,
LEV. 4
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
HELPER
TOTAL
DATE
TOTAL
1 2 3 4 5 6 (B)
12 SLUDG PIT 37 0 0 0 37 0
13 STAIR CASE 26 0 0 0 26 0
P C BLOCK CASTING
14 PC BLOCK CASTING 89 9 0 9 80 1 4 2 6 & ERECTION
15 OUT LET 26 7 0 7 19 0
TOTAL COOLING
TOWER: 2323 934 0 934 1388 8 4 2 5 7 16 34
DAILY PROGRESS REPORT
PROJECT: KHAMBERKHERA
JOB NO.: 10-2I-0046
REPORT DATE: 27.04.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
HELPER
TOTAL
DATE
TOTAL
1 2 3 4 5 6 (B)
2
WALL UP TO
421 346 346 75 1 2 7 10 SHUTTERING &
BOTTOM OF SLAB REINFORCEMENT
SHIFTING OF CONS.
(IV) MISC. 10 2 12 MATERIALS /
FINISHING WORK
TOTAL: 8 40 7 7 10 23 87
DAILY PROGRESS REPORT
PROJECT: UTRAULA
JOB NO.: 10-2I-0047
REPORT DATE: 19.01.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
12 SLUDG PIT 37 0 37
13 STAIR CASE 26 0 26
14 PC BLOCK CASTING 89 0 89
15 OUT LET 26 0 26
TOTAL: 2323 0
DAILY PROGRESS REPORT
PROJECT: UTRAULA
JOB NO.: 10-2I-0047
REPORT DATE: 19.01.11
QTY. PLANNED
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
WALL UP TO
2 BOTTOM OF SLAB 421
TOTAL: 873 0
(IV) MISC.
TOTAL:
DAILY PROGRESS REPORT RCC
PROJECT: MAQSUDPUR
JOB NO.: 10-2I-0043
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
12 SLUDG PIT 43 7 0 0 0 0 0 0 0 7 36
13 STAIR CASE 26 9 0 0 0 0 0 0 0 9 17
14 PC BLOCK CASTING 91 19 0 0 0 0 0 0 0 19 72 1
15 OUT LET 71 32 0 0 0 0 0 0 0 32 39
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
TOTAL OF CT &
FORE BAY 3273 2074 6 2080 1193 12
2 L - CURING.
(IV) MISC. 4 2 2 M +2 H - FINISHING
TOTAL LABOUR: 18 3 0 0 0 0
DAILY PROGRESS REPORT SHUTTERING
PROJECT: MAQSUDPUR
JOB NO.: 10-2I-0043
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 RAFT 85 85 0 0 0 0 0 0 0 85 0
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
14 PC BLOCK CASTING 0 0 0 0 0 0 0 0 0
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 BOTTOM SLAB 97 97 0 97 0
WALL UP TO TOP
2 OF SLAB 1834 1677 24 1701 133 8 5 FIXING. MAKING 10 SQM
TOTAL OF CT &
FORE BAY 18768 7929 109 8037 10731 90
(IV) MISC.
TOTAL LABOUR: 0 0 0 0 33 29
DAILY PROGRESS REPORT REINFORCEMENT
PROJECT: MAQSUDPUR
JOB NO.: 10-2I-0043
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 RAFT 98 98 0 0 0 0 0 0 0 98 0
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
9 FANDECK 24 2 0 0 0 0 0 1 1 4 20 2 4 3
10 FAN CYLINDER 15 0 0 0 0 0 0 0 0 0 15
12 SLUDG PIT 4 1 0 0 0 0 0 0 0 1 3
13 STAIR CASE 5 1 0 0 0 0 0 0 0 1 4
14 PC BLOCK CASTING 0 0 0 0 0 0 0 0 0
15 OUT LET 5 5 0 0 0 0 0 0 0 5 0
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 BOTTOM SLAB 20 20 0 20 0
WALL UP TO TOP
2 OF SLAB 44 41 1 42 2 1 2 2
3 TOP SLAB 15 9 0 9 6
TOTAL: 78 69 1 70 9 1
TOTAL OF CT &
FORE BAY 386 218 4 221 165 5
(IV) MISC.
TOTAL LABOUR: 0 0 11 10 0 0
DAILY PROGRESS REPORT RCC
PROJECT: BARKHERA
JOB NO.: 10-2I-0045
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
12 SLUDG PIT 43 2 0 2 41
13 STAIR CASE 26 6 0 6 20
14 PC BLOCK CASTING 91 19 0 19 73
15 OUT LET 71 12 0 12 59
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
WALL UP TO
2 BOTTOM OF SLAB 482 344 1 344 138
TOTAL OF CT &
FORE BAY 3273 1989 6 1994 1279 0
TOTAL LABOUR: 30 2 0 0 0 0
DAILY PROGRESS REPORT SHUTTERING
PROJECT: BARKHERA
JOB NO.: 10-2I-0045
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 RAFT 85 85 0 85 0
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
WALL UP TO
2 BOTTOM OF SLAB 502 344 344 159
TOTAL OF CT &
FORE BAY 17492 4413 42 4455 13036 35
(IV) MISC.
TOTAL LABOUR: 0 0 0 0 12 26
DAILY PROGRESS REPORT SHUTTERING
PROJECT: BARKHERA
JOB NO.: 10-2I-0045
REPORT DATE: 29.04.11
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
1 RAFT 98 96 0 96 2
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
9 FANDECK 24 2 3 3 5 19 16 16
10 FAN CYLINDER 15 0 0 0 15
12 SLUDG PIT 4 1 0 1 3
13 STAIR CASE 5 0 0 0 4
14 PC BLOCK CASTING 0 0 0
15 OUT LET 5 3 0 3 1
QTY. PLANNED
CARPENTER HELPER
PREVIOUS DAY (A)
BALANCE QTY. ON
NEXT DAY
TOTAL CUM. QTY.
QTY. ACHIEVED ON DATE
ACHIEVED (A+B)
(SQM)
ACHEVED TILL
BAR BINDER
SL.
CARPENTER
TOTAL QTY.
ITEM REMARKS
LABOUR
MASON
NO.
DATE
TOTAL
1 2 3 4 5 6 (B)
WALL UP TO
2 BOTTOM OF SLAB 502 344 344 159
TOTAL OF CT &
FORE BAY 1265 932 3 935 330 0
(IV) MISC.
TOTAL LABOUR: 0 0 16 16 0 0
SUMMARY OF PROGRESS BASED ON PCC/RCC & SHUTTERING AS ON : 30.05.2011
CUSTOMER: SPML INFRA LIMITED
PROJECT: 1X 160 MW CCPP, STAGE-III AT RAMGARH GTPP
SITE: SPML-INFRA/RAMGARH/JAISALMEER/RAJASTHAN.
WO No. SPML-11/10-11/Ramgarh/WO 09 Dated 27.08.2010
DELIVERY DATE AS PER WO: 26.11.2010 ( FOR AUXILARY Cooling Tower), 26.06.2010 ( Main Cooling Tower)
CT MODEL:-84242-5.0-07
TOTAL QTY.(Theoritical)
PROGRESS ON FROM
BALANCE AS ON DATE
LABOUR STRNGTH REPORT ON INCREASE OF CARPENTER
PREVIOUS DAY
NT DATE ………
% ACHIEVED
ACTIVITY
JOB NO.
DATE
SITE
Increased as on
Available as on
Total Required
AVAILABLE AS
Further req.
ON 30.05.11
ACHIEVED
ACHIEVED
PLANNED
PLANNED
(C-A)
(B-C)
date
date
(A)
(B)
(C)
DAY L M C CH F FH TOTAL
ON
JAISALMEER
PCC/RCC IN
CUM 1650 135 0 0 135 1515 8% 0** 129 135 DATE 6 2 2 7 1 2 20
10-2I-0086 SOUMIK MITRA 2 14 2 0 12
(08696838108) SHUTT IN PREV.
19008 95 25 20 115 18893 1% 28 271 115 6 2 2 7 1 2 20
SQM DAY