SL NO: 275 M RCC CHIMNEY

1 2 3 4 5 6 7 8 9

Activity Descripition

DAYS

Base line schedule Start

Earth Work Excavation Ist Stage Pile Breaking Works 1st Stage Earth Work Excavation 2nd Stage Dewatering Works below 2nd Stage Low Level Water Drying Pile Breaking Works 2nd Stage Earth Work Excavation 3rd Stage PCC - Pilecap Reinforcement Fixing - Pilecap

3 3 3 2 3 9 9 4 21 9 6

7-Feb-11 8-Feb-11 10-Feb-11 13-Feb-11 15-Feb-11 16-Feb-11 21-Feb-11 3-Mar-11 7-Mar-11 28-Mar-11 8-Apr-11

10 Shuttering work - Pile cap 11 RCC - Pile cap LABOUR REPORT 1 Mason Helpers 2 Bar benders Helpers 3 Carpenters Helpers 4 Unskilled 5 Chipper 6 Dewatering 7 Supervisor 8 Welders Helpers

MEENAKSHI E PROJECT:-2 x300 MW CO

DAILY PROGR Base line schedule Finish


9-Feb-11 10-Feb-11 12-Feb-11 14-Feb-11 17-Feb-11 24-Feb-11 1-Mar-11 6-Mar-11 27-Mar-11 5-Apr-11 13-Apr-11

Previous forecast Start Finish

Present forecast Start Finish

15/07/2011

31/07/2011

MEENAKSHI ENERGY PRIVATE LIMITED PROJECT:-2 x300 MW COASTAL THERMAL POWER PROJECT DAILY PROGRESS REPORT on 22.07.2011 Actual Finish Date CUMULATIVE QUANTITY UOM
cum Nos cum

TOTAL
2500 384 2500

PLANNED
2500 384 2500

COMPLETED
2500 384 2500

11/4/2011 11/4/2011

Nos cum cum MT Sqm cum Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos

384 4500 105 410 1470 5800 4 7 10 11 9 17 0 0 0 0 5 4

384 4500 105 400

384 4500 105 394 1080 5235

67

22/7/2011 TARGETED COMPLETED

% OF COMPLETION (cumulative)

10 30

3 20

96% 73% 90%

REMARKS

% OF COMPLETION (Up to Previous day)

COMPLETED. COMPLETED. COMPLETED. COMPLETED. IP COMPLETED. COMPLETED. COMPLETED. Haunch portion R/F WIP Pile Cap 50 % Haunch shuttering WIP 50% Haunh completed on 20/07/2011

100% 100% 100%

100% 100% 100% 95% 72% 90%

Base line schedule SL NO: Activity Descripition DAYS Start CLARIFIED WATER TANKS
1 2 3 4 5 6 Jetting work water lowering Earth Work Excavation PCC - Raft RCC Raft RCC Column & Wall 1st lift NYS NYS 19-Apr-11 NYS NYS 16-May-11 NYS NYS 1-Jun-11

7 RCC Column & Wall 2nd lift 8 RCC Column & Wall 3rd lift 9 RCC Roof slab at +3.70m LABOUR REPORT 1 Mason Helpers 2 Barbenders Helpers 3 Carpenters Helpers 4 Unskilled 5 Welders Helpers

MEENAKSHI PROJECT:-2 x300 MW C

DAILY PROG Base line schedule Finish


NYS NYS NYS NYS 8-Aug-11 NYS NYS 8-Sep-11 20-Sep-11

Previous forecast Start Finish

Present forecast Start Finish

MEENAKSHI ENERGY PRIVATE LIMITED PROJECT:-2 x300 MW COASTAL THERMAL POWER PROJECT DAILY PROGRESS REPORT on 22.07.2011 Actual Finish Date CUMULATIVE QUANTITY UOM TOTAL PLANNED COMPLETED

20/06/2011

cum cum cum cum cum cum cum Nos Nos Nos Nos Nos Nos Nos Nos Nos Total Nos

11000 445 3525 704 704 120 1405 0 0 3 6 5 4 8 0 0 26

11000 445 527 704

10480 303 2083 48

22/7/2011 TARGETED COMPLETED

% OF COMPLETION (cumulative)

95% 68% Drawing yet to Release for Part-4, Pump room 15 0 59% 7%

REMARKS

% OF COMPLETION (Up to Previous day)

95% PCC Part-1,2,3,5,6 completed Part - 1,2,5,6 Raft Concrete completed, Part - 3 R/F work in progress. Part - 1 wall 1st lift Column shuttering WIP 68% 59% 7%

5.7 210 1 1 1

0.7 370 370 370

0.7 0.5 0.5 0.5

5.7 2.4 2.4 0.4

586.53 444 444 74

246.96 246.96 41.16

102.9

690.96 690.96 115.16