IBS TRAINING
PREPARED BY: JAYAN.Y ADA CELLWORKS,PUNE
ADA Cellworks
CONTENTS
IBS SURVEY LINK BUDGET CALCULATION IMPLEMENTATION QUALITY CHECKLIST VENDOR HANDLING TIPS REPEATER BASIC OF LOS SURVEY BASIC OF RF SURVEY
ADA Cellworks
What is IBS/DAS ?
1.In-building Solution (IBS) / Distributed Antenna System (DAS) 1.Small Cell Coverage within building premises 2.Signal is restricted inside the building 3.Antenna installed inside the building 4.Low Transmit Power of Antenna 5.Smaller Antenna size
ADA Cellworks
ADA Cellworks
IBS Project 1.Site Survey (IBS and LOS) 2.Design report preparation of the survey 3.Implementation work 4.Frequency planning and database preparation 5.Walk test 6.Optimization and site handover
ADA Cellworks
PLANNING PROCESS
Survey, IBS Planning
ADA Cellworks
ADA Cellworks
PRELIMINARY SITE SURVEY/PRE- PLANNING 1. 2. 3. 4. Building Information. Surrounding Network Information. Draft Solution Design. Budgetary Cost Estimation.
ADA Cellworks
SITE SURVEY 1. 2. 3. 4. Propagation Measurement. Final BTS & Antenna location. Final Cable routing. Photos of Antenna Location, BTS Location, Microwave Pole location.
ADA Cellworks
DETAIL DESIGN REPORT 1. 2. 3. 4. System Diagram (Trunking Diagram). Power Budget Calculation. Solution Description Template. TSSR (Technical Site Survey Report) for BTS & Microwave details.
ADA Cellworks
ADA Cellworks
ADA Cellworks
TOOLS REQUIRED FOR IBS SURVEY 1. GPS 2. Digital Camera. 3. Magnetic Compass. 4. Binoculars. 5. Measuring Tape. 6. Net Monitor Phone. 7. Floor Plan of that Particular Site
ADA Cellworks
STEPS IN IBS SURVEY 1. Study the building architecture, with the help of floor plans & guidance from Building authorities 2. Understand the requirements need in terms of Coverage, Capacity, future Subscriber growth etc. 3. Identify the duct for the cable routing & component location. 4. Survey on each floor using net monitor and floor plan. 5. Mark the present signal level and the antenna location to be installed in the floor plan. 6. Note down all the present serving cell information like CELL ID, BCCH, Rx. Level, etc. 7. Identify the BTS location, antenna locations and mark on the floor plan. 8. Also not down the type of ceiling, whether pop cutting is required or not
ADA Cellworks
LOS SURVEY MAKE TERRACE LAY OUT TAKE LAT LONG BY GPS ASK FOR FAR END TO SURVEY CO ORDINATOR DECIDE TOWER HEIGHT( e. g POLE,RTT, GBT )REQUIREMENT ( ALSO CONSIDER CUSTOMER SPECIFICATION , NOT MENDATORY ) CHECK POSSIBILITY OF CABLE ROUTING UPTO BTS LOCATION IF PCM CABLE OR A-BTS IS REQUIRED FOR TX ,THEN MAKE NOTE THAT PCM CABLE LENGTH IS NOT EXCEEDING BY THAT OF GIVEN SPECIFICATION( UPTO 250 M). ( DO NOT COMPROMISE WITH BTS LOCATION IT AFFECTS POWER CALCUTAION )
ADA Cellworks
INDOOR PROPOGATION Indoor channels are different from traditional mobile radio channels in two different ways The distances covered are much smaller The variability of the environment is much greater for a much smaller range of Tx-Rx separation distances. The propagation inside a building is influenced by Layout of the building Construction materials Typical building type Sports arena, residential home, factory,... Indoor propagation is dominated by the same mechanisms as outdoor reflection, scattering, diffraction.
ADA Cellworks
However, conditions are much more variable Doors/windows open or not The mounting place of antenna On the wall, ceiling, etc. The level of floors In building path loss factors Partition losses (same floor) Partition losses between floors
ADA Cellworks
PARTITION LOSSES There are two kind of partition at the same floor: Hard partitions: the walls of the rooms Soft partitions: moveable partitions that does not span to the ceiling The path loss depends on the type of the partitions PARTITION LOSSES BETWEEN FLOORS The losses between floors of a building are determined by External dimensions and materials of the building Type of construction used to create floors External surroundings Number of windows Presence of tinting on windows
ADA Cellworks
ADA Cellworks
14M SP4W5F01 27M SP3W5F01 15M J 08M
AN6F001
3M
06M 11M
AN5F004 AN5F003
24M SP2W5F01
04M
AN5F015
13M
AN5F002 AN5F001
AN5F021
12M
08M
5M
14M
10dB
CP10dB5F01
7dB
CP7dB5F01
SP2W5F06 CP7dB5F02
7dB
07M
10M
20M
7dB
15M 15M
CP7dB5F03 SP4W5F03
10M 21M
ADA Cellworks
17M
11M
13M
23M
AN5F010
AN5F011
AN5F0139
AN5F018
AN5F019
J
AN5F003
SP4W5F01
7M
21M 5M
SP4W5F03
18M
J 7dB
AN5F020
08M
SP2W5F04
11M 08M
AN5F022 AN5F023
AN5F017
AN5F009
10M SP2W5F01
J
AN5F002
SP2W5F03 CP7dB5F01
J 7dB
AN5F005
25M
AN5F012
23M SP3W5F01
20M
CP7dB5F03
23M 13M
AN5F016
7dB
3M
CP7dB5F02
19M
30M
AN5F013
09M 14M
10dB
SP2W5F02 14M 6M 8M
10M
AN5F008
14M 8M
14M
SP2W5F06
AN5F021
CP10dB5F01 SP4W5F02
8M
AN5F140 AN5F006 AN5F007
4M
AN5F001
AN5F014
AN5F015
DUCT 1( ELECTRICAL)
ADA Cellworks
IT IS BASICALLY FOR POWER THAT REQUIRED AT ANTENNA END.IT DEPENDS ON THE COMPONENTS THAT HAS BEEN USED FROM BTS TO ANTENNA THAT IS ERP( EFFECTIVE RADIATED POWER ). We generally deal with EIRP ( Effective Isotropic Radiated Power ),which is defined below.
EIRP( Effective Isotropic Radiated Power )= ERP( Effective Radiated Power ) + Gain of that component
LIST OF COMPONENTS WITH LOSSES ARE AS FOLLOWS:: 1) 2) 3) 4) 5) 6) SPLITTERS COUPLERS CABLES ANTENNAS COMBINER JUMPER CABLE
1) SPLITTERS::
ADA Cellworks
TYPE
LOSS (dB)
ADA Cellworks
2 WAY
3 WAY
4 WAY
2) COUPLERS::
ADA Cellworks
TYPE
7 dB 10 dB 15 dB
-7 -10 -15
NOTE: Ideally there should be 0 dB loss at through port. But there is always some loss, which is mentioned in table.
ADA Cellworks
THROUGH PORT COUPLED PORT
INPUT
3) CABLES::
ADA Cellworks
TYPE
ADA Cellworks
4) ANTENNAS::
ADA Cellworks
TYPE
Gain (dBi )
ADA Cellworks
OMNI ANTENNA
ADA Cellworks
PANEL ANTENNA
ADA Cellworks
12 cm
12 cm
5) COMBINER::
ADA Cellworks
TYPE LOSS
A combiner is the device that enables several transmitters to transmitter from the same antenna.
3 dB
TX 1
e. g TRX
TX 2
A N T E N N A
ADA Cellworks
6) LINK BUDGET CALCULATION :: Example with Trunking Diagram:
ADA Cellworks
ADA Cellworks
To connect female port of other component like our antennas and splitter.
ADA Cellworks
Connect with male port like 7/8 to inch connector Or Kaveri combiner
ADA Cellworks
Connect with 7/8 cable( LDF 5-50A ) To connect female port of 7/8 cable at one side and female port of cable or splitter
ADA Cellworks
Connect with female port of jumper cable or directly to Port of BTS which is Generally at the top of Ultra BTS
Connect with 7/8 cable( LDF 5-50A ) To connect female port of 7/8 cable at one side and BTS port or jumper cable
( 5 ) EXTERNAL COMBINER(AVANTEL)
ADA Cellworks
Female Port
Female Port
Female Port
( 6 ) EXTERNAL COMBINER(KAVERI)
( 6 ) EXTERNAL COMBINER(KAVERI)
ADA Cellworks
Female Port
Female Port
Female Port
ADA Cellworks
THIS PORT HAS SIZE SAME AS 7/8 CABLE
AT COMBIER END
AT BTS END
ADA Cellworks
Nominal Voltage:230AC/-48VDC
2) METRO BTS
ADA Cellworks
85cm
25cm
35cm
Configuration: 2+2 Power: 40 dBm
ADA Cellworks
SECTORS JUMPER CABLE
ADA Cellworks
ADA Cellworks
DETAILED DESIGN REPORT 1. Building Information: Co-ordinates, No. of Floors, Basements, Lobbies. 2. BTS Information: BTS Type, BTS O/P power, TRX Configuration, Sectorization. 3. TSSR Form Transmission & RF details if planned with outdoor sectors also) 4. Trunking Diagram - Schematic Presentation of Antenna to BTS connection via different components like, splitters, combiners & couplers. 5. Link Budget Calculations EIRP calculation at all antenna ports, considering all the losses. 6. Planned Antenna Location with coverage area. 7. Bill of Quantity - Material Requirement for the Implementation of DAS.
ADA Cellworks
It amplifies and converts weak signal into stronger signal by adding some gain to it.
There are 2 types of repeaters. 1) BAND SELECTIVE: It amplifies and boost frequency of particular BAND
2) FREQUENCY SELECTIVE: It amplifies and boost particular frequencies only (Generally 2 / 3 frequency.
ADA Cellworks
ADA Cellworks
PICK UP ANTENNA(HIGHLY DIRECTIONAL ) NEARER SITE
ADA Cellworks
CONNECTED TO ANTENNA
INDOOR REPEATER
ADA Cellworks
IBS IMPLEMENTATION
ADA Cellworks
ADA Cellworks
GENERAL IMPLEMENTATION ISSUE IN IBS OPEN CONNECTION Antenna, splitter, coupler port is open
LABELING All the splitters and couplers should be labeled for easy identification
ANTENNA PLACEMENT OR ORIENTATIONS IS NOT AS PER PLAN Shift in antennas if any due to route / customer problem.
THERE IS NO PROPER SADDLING, TYING OF CABLES No Saddling/tying done on site, typical requirement is as follows i.e., every 1mtr or 1.5mtr cable is to be tied
ADA Cellworks
VENDOR HANDLING 1. Handover site to vendor with all details like work permission, material storage space, proper cable routing. 2. Generate MRF for delivery of material to this site. 3. Ask vendor for daily update. 4. Must visit site 2-3 day in week. 5. Ask all details after completion of full site. 6. Get the material details from the vendor 7. Get the BOM (Bill of Material) from the vendor and generate cam Form for the site after reconciling the material
ADA Cellworks
IMPLIMENTATION AUDIT Visit site daily if possible otherwise 2-3 day in week Check installation is as par plan or change Decide any changes in antenna location (if require according to aesthetic, permission, cable routing etc..)
ADA Cellworks
IBS IMPLEMENTATION QUALITY STANDARDS. 1. No Extra Cable is left rolled near the BTS Equipment. 2. Feeder Cable and components have to be independently & properly clamped (saddling) to the wall or laid over the cable tray . 3. Combiner is clamped and the various cables to and from the combiner are secured properly on the Cable tray or Wall mount. 4. Feeder Installation for all the sectors should have appropriate bending radius for both 1/2 & 7/8. 5. Connector have to be weather proofed 6. Feeders & components should be anchored at fixed intervals by saddling/cable tie 7. Aesthetic rectification should be completed with cleanliness
ADA Cellworks