Sunteți pe pagina 1din 23

FIDIC Contracts Guide 1st Edition 2000

The FIDIC Contracts Conditions of Contract Conditions of Contract Conditions of Contract

Guide 1st Edition 2000 for Construction for Plant and design-Build for EPC/Turnkey Projects

FIDIC Contracts Guide 1st Edition 2000 ACKNOWLEDGEMENTS FOREWORD CONTENTS FIDIC Contracts Guide to the Construction, Plant and Design-Build and EPC/Turnkey Contracts (1st Edition, 2000) Compares the Construction, Plant and Design-Build and EPC/Turnkey Contracts in a side-by-side fashion, with commentary. Each of the three Books is in three parts: General Conditions, the part which is intended to be incorporated (by reference) into each contract, and whose Sub-Clauses are often referred to in this Guide without the use of the word Sub-Clause (for example: CONS 1.1); Guidance for the Preparation of the Particular Conditions, the part which is referred to in this Guide as GPPC, which commences by proposing suitable wording to incorporate the appropriate General Conditions into a contract, and which concludes with annexed example forms of securities; and Forms of Letter of Tender, Contract Agreement and Dispute Adjudication Agreement, the part which is referred to in this Guide as the Example Form(s).

In this FIDIC Contracts Guide 1st Edition 2000 the texts in the Books are reproduced in a three-column layout. The texts should be identical to the corresponding texts in the Books, but the reader should refer to the Books in order to determine the necessary authentic wording in case of any discrepancy. For the convenience of those who are familiar with the General Conditions of Contract contained in FIDICs previous publications, the reference numbers of their sub-clauses which cover similar subject-matter are included within an insert box after these three-column texts reproduced from the Books, the sub-clause reference numbers being related to: RB: Conditions of Contract for Works of Civil Engineering Construction 4th edition 1987 amended 1992 (which was commonly referred to as the Red Book) YB: Conditions of Contract for Electrical and Mechanical Works 3rd edition 1987 amended 1988 (which was commonly referred to as the Yellow Book) OB: Conditions of Contract for Design-Build and Turnkey 1st edition 1995 (which was commonly referred to as the Orange Book) FIDIC Contracts Guide 1st Edition 2000 In each Contract, the Conditions of Contract governing the rights and obligations of the parties will comprise the appropriate General Conditions together with Particular Conditions. It will be necessary to prepare the Particular Conditions for each individual contract, taking account of the comments in this Guide and the appropriate GPPC. It is essential that all these drafting tasks, and the entire preparation of the tender documents, are entrusted to personnel with the relevant expertise, including the contractual, technical and procurement aspects. Although this FIDIC Contracts Guide 1st Edition 2000 may include useful material for the training of personnel in procurement, it is not intended to provide complete training material for the expertise required for the preparation of tender documents. The comments in this Guide are intended to assist users of the Books who have such expertise, such users being those who write or administer building and/or engineering contracts. The comments in this FIDIC Contracts Guide 1st Edition 2000 are not exhaustive and are only intended to provide general guidance. They should not be relied upon in a specific issue or situation. Expert legal advice should be obtained whenever appropriate, and particularly before entering into or terminating a contract. Neither FIDIC nor the persons named in this Guide accept any responsibility or liability arising from any use of this Guide or of any other publication named herein. FIDIC receives requests from time to time to assist in the interpretation of individual contracts which are based upon conditions of contract incorporating FIDIC publications. However, as the international federation of consulting engineers, FIDIC

cannot undertake to give legal advice. For this reason, and because the legal interpretation of a contract will depend upon such matters as the precise wording of the various documents comprising the particular contract, as well as upon the governing law, FIDIC cannot assist in the interpretation of individual contracts. ISBN : 2-48432-029-6 Number Page : 353 Download Type : PDF File, FIDIC Contracts Guide 1st Edition 2000 Free Download FIDIC Contracts Guide :

FIDIC Gold book - DBO Conditions of Contract for Design Build and Operate Projects, Download Fidic Book When preparing these Conditions of Contract for Design, Build and Operate Projects, the drafting task group has attempted to include all conditions of a general nature, which are likely to apply to the majority of DBO contracts, into General Conditions, fidic book FIDIC MDB Harmonised - construction contract mdb harmonised, Download Fidic Book Conditions of Contract for Construction, fidic contract which are recommended for building and engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However, fidic contract the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works. Contracts and Agreements, fidic contracten FIDIC orange book - Conditions of Contract for Design Build and Turnkey The object of this Guide is to comment on the provisions contained in Part 1 of the first edition of the Conditions of Contract for Design-Build and Turnkey. Informally titled the Orange Book, it was published by the Federation Intemationale des Ingenieurs-Conseils (FIDIC) in 1995. A Test Edition had been published in 1994, and the many reactions to it were reviewed before the first edition was completed, fidic contract FIDIC Contracts Guide 1st Ed 2000 The FIDIC Contracts Guide First Edition 2000 Conditions of Contract for Construction Conditions of Contract for Plant and design-Build Conditions of Contract for EPC/Turnkey Projects, fidic conditions FIDIC silver book - Conditions of Contract for EPC Turnkey Projects First Edition 1999 The Conditions of Contract for EPC/Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fully-equipped facility, ready for operation (at the turn of the key). This type of contract is usually negotiated between the parties. Download Fidic Book FIDIC white book - Client Consultant Model Services Agreement

Agreement General Conditions Particular Conditions Appendices 1, 2, 3 and 4 The terms of the Client Consultant Model Services agreement (The White Book) have been prepared by FIDIC and are recommended for general use for the purposes of pre-investment and feasability studies, designs and administration of construction and project management, where proposals for such services are invited on an international basis: They are equally adaptable for domestic agreements. FIDIC green book -Short Form of Contract 1st Ed 1999 Green Book - Agreement - General Conditions - Rules for Adjudication - Notes for Guidance These Conditions of Contract are recommended for engineering and building work of relatively small capital value. However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. FIDIC yellow book - Conditions of Contract for Plant and (DB) Design Build First edition 1999 Conditions of Contract for Plant and Design-Build, which are recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employers requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works, fidic contract conditions FIDIC Red book - Conditions of Contract for Construction first edition 1999 Construction Contract : Conditions of Contract for Construction FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER First Edition, 1999 - General Conditions - Guidance for the Preparation of the Particular Conditions - Forms of Tender, Contract Agreement and Dispute Adjudication Agreement, fidic conditions of contract Download Fidic Book

FIDIC construction contract mdb harmonised

FIDIC construction contract mdb harmonised, Conditions of Contract for Construction which are recommended for building and engineering works designed by the Employer or by his representative, the Engineer. FIDIC construction contract mdb harmonised, fidic construction contract fidic mdb harmonised download fidic free download fidic download free fidic Conditions of Contract download fidic contracts download. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However FIDIC construction contract mdb harmonised, fidic contract the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works. Contracts and Agreements. Table of content Fidic construction contract mdb harmonised 1. GENERAL PROVISIONS 1.1 Definitions 1.2 Interpretation 1.3 Communications 1.4 Law and Language 1.5 Priority of Documents 1.6 Contract Agreement 1.7 Assignment 1.8 Care and Supply of Documents 1.9 Delayed Drawings or Instructions 1.10 Employers Use of Contractors Documents 1.11 Contractors Use of Employers Documents 1.12 Confidential Details

1.13 Compliance with Laws 1.14 Joint and Several Liability 2 THE EMPLOYER 2.1 Right of Access to the Site 2.2 Permits, Licences or Approvals 2.3 Employers Personnel 2.4 Employers Financial Arrangements 2.5 Employers Claims 3 THE ENGINEER 3.1 Engineers Duties and Authority 3.2 Delegation by the Engineer 3.3 Instructions of the Engineer 3.4 Replacement of the Engineer 3.5 Determinations 4 THE CONTRACTOR 4.1 Contractors General Obligations 4.2 Performance Security 4.3 Contractors Representative 4.4 Subcontractors 4.5 Assignment of Benefit of Subcontract 4.6 Co-operation 4.7 Setting Out 4.8 Safety Procedures 4.9 Quality Assurance 4.10 Site Data 4.11 Sufficiency of the Accepted Contract Amount 4.12 Unforeseeable Physical Conditions 4.13 Rights of Way and Facilities 4.14 Avoidance of Interference 4.15 Access Route 4.16 Transport of Goods 4.17 Contractors Equipment 4.18 Protection of the Environment 4.19 Electricity, Water and Gas 4.20 Employers Equipment and Free-Issue Material 4.21 Progress Reports 4.22 Security of the Site 4.23 Contractors Operations on Site 4.24Fossils 5 NOMINATED SUBCONTRACTORS

5.1 5.2 5.3 5.4

Definition of nominated Subcontractor Objection to Nomination Payments to nominated Subcontractors Evidence of Payments

6 STAFF AND LABOUR 6.1 Engagement of Staff and Labour 6.2 Rates of Wages and Conditions of Labour 6.3 Persons in the Service of Others 6.4 Labour Laws 6.5 Working Hours 6.6 Facilities for Staff and Labour 6.7 Health and Safety 6.8 Contractors Superintendence 6.9 Contractors Personnel 6.10 Records of Contractors Personnel and Equipment 6.11 Disorderly Conduct 7 PLANT, MATERIALS AND WORKMANSHIP 7.1 Manner of Execution 7.2 Samples 7.3 Inspection 7.4 Firsting 7.5 Rejection 7.6 Remedial Work 7.7 Ownership of Plant and Materials 7.8 Royalties 8 COMMENCEMENT, DELAYS AND SUSPENSION 8.1 Commencement of Works 8.2 Time for Completion 8.3 Programme 8.4 Extension of Time for Completion 8.5 Delays Caused by Authorities 8.6 Rate of Progress 8.7 Delay Damages 8.8 Suspension of Work 8.9 Consequences of Suspension 8.10 Payment for Plant and Materials in Event of Suspension 8.11 Prolonged Suspension 8.12 Resumption of Work 9 TESTS ON COMPLETION 9.1 Contractors Obligations

9.2 Delayed Tests 9.3 Retesting 9.4 Failure to Pass Firsts on Completion 10 EMPLOYERS TAKING OVER 10.1 Taking Over of the Works and Sections 10.2 Taking Over of Parts of the Works 10.3 Interference with Firsts on Completion 10.4 Surfaces Requiring Reinstatement 11 DEFECTS LIABILITY 11.1 Completion of Outstanding Work and Remedying Defects 11.2 Cost of Remedying Defects 11.3 Extension of Defects Notification Period 11.4 Failure to Remedy Defects 11.5 Removal of Defective Work 11.6 Further Firsts 11.7 Right of Access 11.8 Contractor to Search 11.9 Performance Certificate 11.10 Unfulfilled Obligations 11.11 Clearance of Site 12 MEASUREMENT AND EVALUATION 12.1 Works to be Measured 12.2 Method of Measurement 12.3 Evaluation 12.4 Omissions 13 VARIATIONS AND ADJUSTMENTS 13.1 Right to Vary 13.2 Value Engineering 13.3 Variation Procedure 13.4 Payment in Applicable Currencies 13.5 Provisional Sums 13.6 Daywork 13.7 Adjustments for Changes in Legislation 13.8 Adjustments for Changes in Cost 14 CONTRACT PRICE AND PAYMENT 14.1 The Contract Price 14.2 Advance Payment 14.3 Application for Interim Payment Certificates 14.4 Schedule of Payments

14.5 Plant and Materials intended for the Works 14.6 Issue of Interim Payment Certificates 14.7 Payment 14.8 Delayed Payment 14.9 Payment of Retention Money 14.10 Statement at Completion 14.11 Application for Final Payment Certificate 14.12 Discharge 14.13 Issue of Final Payment Certificate 14.14 Cessation of Employers Liability 14.15 Currencies of Payment 15 DEFAULT OF CONTRACTOR 15.1 Notice to Correct 15.2 Termination by Employer 15.3 Valuation at Date of Termination 15.4 Payment after Termination 15.5 Employers Entitlement to Termination for Convenience 16 DEFAULT OF EMPLOYER 16.1 Contractors Entitlement to Suspend Work 16.2 Termination by Contractor 16.3 Cessation of Work and Removal of Contractors Equipment 16.4 Payment on Termination 17 RISK AND RESPONSIBILITY 17.1 Indemnities 17.2 Contractors Care of the Works 17.3 Employers Risks 17.4 Consequences of Employers Risks 17.5 Intellectual and Industrial Property Rights 17.6 Limitation of Liability 18 INSURANCE 18.1 General Requirements for Insurances 18.2 Insurance for Works and Contractors Equipment 18.3 Insurance against Injury to Persons and Damage to Property 18.4 Insurance for Workers 19 FORCE MAJEURE 19.1 Definition of Force Majeure 19.2 Notice of Force Majeure 19.3 Time of Notice 19.4 Duty to Minimise Delay

19.5 Consequences of Force Majeure 19.6 Optional Termination, Payment and Release 19.7 Release from Performance under the Law 20 CLAIMS, DISPUTES AND ARBITRATION 20.1 Contractors Claims 20.2 Appointment of the Dispute Adjudication Board 20.3 Failure to Agree Dispute Adjudication Board 20.4 Obtaining Dispute Adjudication Boards Decision 20.5 Amicable Settlement 20.6 Arbitration 20.7 Failure to Comply with Dispute Adjudication Boards Decision 20.8 Expiry of Dispute Adjudication Boards Appointment FIDIC construction contract mdb harmonised ISBN : 2-88432-044-X Number page : 146 pages Download Type : PDF File, FIDIC construction contract mdb harmonised Free Download FIDIC mdb harmonised :

FIDIC Silver Book - EPC Turnkey Contract 1st Edition 1999

FIDIC Silver Book - EPC Turnkey Contract 1st Edition 1999 The Conditions of Contract for EPC/Turnkey Projects fidic silver book, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Conditions of Contract for EPC Turnkey Projects, fidic silver, fidic epc fidic silver book fidic contracts guide, fidic subcontract, fidic contract management, fidic contracts pdf, construction contract. FIDIC Silver Book - EPC Turnkey Contract 1st Edition 1999 Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fully-equipped facility, ready for operation (at the turn of the key) . This type of contract is usually negotiated between the parties. FIDIC Silver Book - EPC Turnkey Contract 1st Edition 1999 1. GENERAL PROVISIONS 2 THE EMPLOYER 3 THE EMPLOYERS ADMINISTRATION 4 THE CONTRACTOR 5 DESIGN 6 STAFF AND LABOUR 7 PLANT, MATERIALS AND WORKMANSHIP 8 COMMENCEMENT, DELAYS AND SUSPENSION 9 TESTS ON COMPLETION 11 DEFECTS LIABILITY 12 TESTS AFTER COMPLETION 13 VARIATIONS AND ADJUSTMENTS 14 CONTRACT PRICE AND PAYMENT 15 TERMINATION BY EMPLOYER 16 SUSPENSION AND TERMINATION BY CONTRACTOR 17 RISK AND RESPONSIBILITY

18 INSURANCE 19 FORCE MAJEURE 20 CLAIMS, DISPUTES AND ARBITRATION FIDIC Silver Book - EPC Turnkey Contract 1st Edition 1999 Which may be suitable for the provision on a turnkey basis of a process or power plant or factory or similar facility, or of an infrastructure project or other type of development, fidic silver fidic epc silver book silver book fidic guide fidic subcontract fidic contract management fidic contracts pdf construction contract. where (i) a higher degree of certainty of firm price and time is required, and (ii) the Contractor takes total responsibility for the design and execution of the project, with little involvement of the Employer. Under the usual arrangements for turnkey projects, the Contractor carries out all engineering, procurement, and construction EPC: providing a fully equipped facility, ready for operation at the turn of a key. ISBN : 2-88432-021-0 Number page : 150 pages FIDIC Silver Book EPC Turnkey Contract 1st Edition 1999

FIDIC Yellow Book - Plant and Design Build Contract 1st Edition 1999

FIDIC Yellow Book - Plant and Design Build Contract 1st Edition 1999 FIDIC Conditions of Contract for Plant and Design Build, which are recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employers requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works. keyword : fidic yellow book, fidic conditions of contract, fidic contract conditions, fidic conditions, fidic contract documents fidic publications fidic conditions of contract. Table of Content FIDIC Yellow Book - Plant and Design Build Contract 1st Edition 1999 GENERAL CONDITIONS 1 GENERAL PROVISIONS 2 THE EMPLOYER 3 THE ENGINEER 4 THE CONTRACTOR 5 DESIGN 6 STAFF AND LABOUR 7 PLANT, MATERIALS AND WORKMANSHIP 8 COMMENCEMENT. DELAYS ANS SUSPENSION 9 TESTS ON COMPLETION 10 EMPLOYERS TAKING OVER 11 DEFECTS LIABILITY 12 TESTS AFTER COMPLETION 13 VARIATIONS AND ADJUSTMENTS 14 CONTRACT PRICE AND PAYMENT 15 DEFAULT OF CONTRACTOR 16 DEFAULT OF EMPLOYER 17 RISK AND RESPONSBILITY 18 INSURANCES 19 FORCE MAJEURE 20 CLAIMS, DISPUTES AND ARBITRATION FIDIC Yellow Book - Plant and Design Build Contract 1st Edition 1999 FIDIC Conditions of Contract for Construction, which are recommended for building or engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, th Contractor constructs the works in accordance with a design provided by the Employer. However, the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works. FIDIC Conditions of Contract for Plant and Design-Build, which are recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Under the usual

arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employers requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works. FIDIC Conditions of Contract for EPC Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fully-equipped facility, ready for operation (at the turn of the key). This type of contract is usually negotiated between the parties. fidic yellow book fidic contract documents fidic publications fidic conditions of contract fidic contract conditions fidic conditions FIDIC Short Form of Contract, which is recommended for building or engineering works of relatively small capital value. Depending on the type of work and the circumstances, this form may also be suitable for contracts of greater value, particularly for relatively simple or repetitive work or work of short duration. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer or by his representative (if any), but this form may also be suitable for a contract which includes, or wholly comprises. FIDIC Yellow Book - Plant and Design Build Contract 1st Edition 1999.

FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey

FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey, The object of this Guide is to comment on the provisions contained in Part 1 of the first edition of the Conditions of Contract for Design-Build and Turnkey. Informally titled the Orange Book, it was published by the Federation Intemationale des Ingenieurs-Conseils (FIDIC) in 1995. FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey, A Test

Edition had been published in 1994, and the many reactions to it were reviewed before the first edition was completed. This FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey (informally titled the Orange Book Guide) is intended to assist the users of the fidic Orange Book, namely those who write, and those who administer, contracts based on these Conditions of Contract. This assistance is focused on particular features of the Orange Book: the Guide is not intended to provide complete training material for the expertise required for the preparation of tender documents. Also, the comments are not intended to provide an authoritative legal interpretation of every aspect of each subject, which must depend on the law applicable to the particular contract. It is envisaged that the FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey can be the basis of all contracts which involve the provision of facilities designed by the Contractor, whether such facilities comprise building, civil engineering, chemical engineering, electrical engineering, mechanical engineering, or any combination. Throughout the drafting, the intention was to incorporate provisions applicable to (for example) housing, roads, refineries, generators, turbines, treatment works, etc. However, the Orange Book is not appropriate for the provision of facilities designed by the Employer or his consulting engineer, or for similar arrangements where the Contractor is not to be responsible for design. Project Procurement the Design-Build Option, FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey Under the Orange Book design-build form of contract, design is the responsibility of the construction organization. This arrangement reduces the problems which may on occasions arise from the division of responsibility between designer and constructor. Design-build may also encourage economies, not only in terms of price, but at the expense of quality. Therefore, it is considered essential that the Employer has (or procures) expert technical services, in order to ensure that his requirements are elaborated in the tender documents and are achieved in practice. If expertise is unavailable, problems may arise, particularly in respect of the need for variations. FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey, Ideally, variations under a design-build contract should be instructed by reference to requirements (not by a redesign by the Employer); and their costs and other consequences should be agreed in advance, in order to minimize disputes. In practice, these aspects can make the design-build process appear somewhat inflexible. The design-build process is thus less amenable to variations initiated by the Employer, compared with the alternative where the designer is separately employed by the Employer and is independent of the Contractor. The design-build option prevents the Employer from having a close involvement in the design process. However, it enables him to have the benefits of lump-sum

pricing, of the Contractors undivided liability for the works (including design), and of the potential savings (in cost and time) due to a degree of overlap of design and construction. The latter overlap may (or may not) lessen the total period between the commencement of the preparation of tender documents and the completion of construction. The saving in time due to this overlap may be offset by the effects of the lack of continuity of the design processes during the pre-contract stages Project Procurement Options At the inception stage of a project, procurement options should be reviewed and a decision made as to the most appropriate option; FIDICs publication of the Orange Book does not constitute any indication of a preferred option. The Employer should first analyze the project financing arrangements, their consequences, the risks inherent in the type(s) of works and the other factors which affect the procurement process. After that analysis, decisions can be made as to which procurement option is appropriate; and as to which standard form of contract is closest to the Employers requirements and will thus require less text in Part 11 than would be the case if another form were to be used. FIDIC Orange Book - Conditions of Contract for Design Build and Turnkey.

FIDIC Red Book - Construction Contract 1st Edition 1999

FIDIC Red Book - Construction Contract 1st Edition 1999 FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER First

Edition, 1999. fidic red book fidic tendering procedure fidic Construction Contract pdf fidic latest edition fidic contracts fidic dredging contract fidic bookshop. FIDIC Red Book - Construction Contract 1st Edition 1999 - General Conditions - Guidance for the Preparation of the Particular Conditions - Forms of Tender, Contract Agreement and Dispute Adjudication Agreement TABLE OF CONTENTS FIDIC Red Book - Construction Contract 1st Edition 1999: 1 GENERAL PROVISIONS 2 THE EMPLOYER 3 THE ENGINEER 4 THE CONTRACTOR 5 NOMINATED SUBCONTRACTORS 6 STAFF AND LABOUR 7 PLANT, MATERIALS AND WORKMANSHIP 8 COMMENCEMENT, DELAYS AND SUSPENSION 9 TESTS ON COMPLETION 10 EMPLOYERS TAKING OVER 11 DEFECTS LIABILITY 12 MEASUREMENT AND EVALUATION 13 VARIATIONS AND ADJUSTMENTS 14 CONTRACT PRICE AND PAYMENT 15 DEFAULT OF CONTRACTOR 16 DEFAULT OF EMPLOYER 17 RISK AND RESPONSIBILITY 18 INSURANCE 19 FORCE MAJEURE 20 CLAIMS, DISPUTES AND ARBITRATION FIDIC Red Book - Construction Contract 1st Edition 1999 fidic red book fidic tendering procedure fidic contracts pdf fidic latest edition fidic contracts fidic dredging contract fidic bookshop The Conditions of Contract comprise the General Conditions, which form part of the Conditions of Contract for Construction First Edition 1999 published by the Fdration Internationale des Ingnieurs-Conseils (FIDIC), and the following Particular Conditions, which include amendments and additions to such General Conditions. FIDIC Red Book - Construction Contract 1st Edition 1999, Conditions of Contract for Construction, which are recommended for building or engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in

accordance with a design provided by the Employer. However, the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works. The forms are recommended for general use where tenders are invited on an international basis. Modifications may be required in some jurisdictions, particularly if the Conditions are to be used on domestic contracts. FIDIC Red Book - Construction Contract 1st Edition 1999 dredging contracts, FIDIC considers the official and authentic texts to be the versions in the English language. fidic red book fidic tendering procedure fidic green book fidic contracts pdf fidic latest edition fidic contracts fidic dredging contract fidic bookshop. In the preparation of these Conditions of Contract for Construction, it was recognised that, while there are many sub-clauses which will be generally applicable, there are some sub-clauses which must necessarily vary to take account of the circumstances relevant to the particular contract. The sub-clauses which were considered to be applicable to many (but not all) contracts have been included in the General Conditions, which will facilitate their incorporation into each contract. The General Conditions and the Particular Conditions will together comprise the Conditions of Contract governing the rights and obligations of the parties. It will be necessary to prepare the Particular Conditions for each individual contract, and to take account of those sub-clauses in the General Conditions which mention the Particular Conditions. ISBN : 2-88432-022-9 Number page : 120 pages FIDIC Red Book - Construction Contract 1st Edition 1999 Free Download FIDIC Red Book :

FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects

FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects, When preparing these Conditions of Contract for Design, Build and Operate Projects, the drafting task group has attempted to include all conditions of a general nature, which are likely to apply to the majority of DBO contracts, into General Conditions. FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects, fidic free download fidic dbo contract fidic gold fidic gold book construction contracts employment contract form of contract templates fidic seminars fidic form fidic claims. However, FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects it was recognised that there are many essential provisions which are particular to each individual project. These are to be included as Contract Data and are to be found in the Particular Conditions Part A Contract Data. In addition, it was recognised that many Employers or governments, or even different jurisdictions, particularly if the General Conditions were to be used on domestic contracts, may require special conditions of contract, or indeed particular procedures, which differ from those included in the General Conditions. For this reason, the document also allows for Particular Conditions Part B Special Provisions which includes advice to drafters of contract documents who may wish to add Special Provisions to replace or supplement the clauses to be found in the General Conditions. Drafters of contract documents are reminded that the General Conditions of all FIDIC contracts are protected by copyright and trademark and may not be changed without specific written consent, usually in the form of a licence to amend, from FIDIC. If drafters wish to amend the provisions found in the General Conditions, the place for doing this is in the Particular Conditions Part B Special Provisions, as

mentioned above, and not by making changes in the General Conditions as such. FIDIC also recognises that the successful performance of a long-term DBO contract requires that the Parties understand the overall time framework and the need for a long-term commitment by both the Employer and the Contractor. In trying to achieve this understanding and commitment, it has been necessary to introduce new procedures and new terminology which are not to be found in the other FIDIC forms of contract. This FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects also includes a number of sample forms to help both Parties have a common understanding of what is required by third parties such as providers of securities and guarantees, and what is considered to be accepted good practice by FIDIC and the major international funding agencies. While copyrighted, these forms are expressly provided to users of the Conditions of Contract for completion by users. Users are warned that if these forms are changed in any significant way, there is a great risk that the balance of the contract and the specific wording of the Clauses may be compromised. fidic dbo contract, fidic gold, fidic gold book, construction contracts, employment contract, form of contract, templates fidic, seminars fidic, form fidic claims This FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects begins with a series of comprehensive flow charts which show, in visual form, the critical sequences of activities which are specific and unique to the FIDIC Conditions of Contract for DBO Projects, 1st Edition, 2008 DBO form of contract. These have been included by the drafting task group to facilitate an understanding of the new procedures and new terminology found in these FIDIC Conditions of Contract for Design, Build and Operate Projects. These flow charts cover: - The Overall Contract Period - The Design-Build Period - Commencement to Design-Build Commissioning - The Operation Service Period - Payment during the Design-Build Period - Payment during the Operation Service Period - Determinations by the Employers Representative - Contractors Claims Submission - Contractors Claims Determination - Settlement of Disputes ISBN : 2-88432-052-0 Number page : 200 pages FIDIC Gold Book DBO Conditions of Contract for Design Build and Operate Projects Free Download FIDIC Gold Book :

FIDIC Green Book Short Form of Contract

FIDIC Green Book Short Form of Contract 1st Edition 1999 - Agreement - General Conditions - Rules for Adjudication - Notes for Guidance These Conditions of Contract FIDIC Green Book Short Form of Contract are recommended for engineering and building work of relatively small capital value. However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. fidic green book fidic 4th edition fidic epc contract what is fidic full form fidic 2010 fidic clauses fidic 1987 fidic rules fidic 1992 fidic 1987 download FIDIC Green Book Short Form of Contract 1st Edition 1999 They are considered most likely to be suitable for fairly simple or repetitive work or work of short duration without the need for specialist sub-contracts. This form may also be suitable for contracts which include, or wholly comprise, contractordesigned civil engineering, building, mechanical and/or electrical works. Table of content FIDIC Green Book Short Form of Contract GENERAL CONDITIONS 1. GENERAL PROVISIONS 2. THE EMPLOYER 4. THE CONTRACTOR

5. DESIGN BY CONTRACTOR 6. EMPLOYERS RISKS 7. TIME FOR COMPLETION 8. TAKING-OVER 9. REMEDYING DEFECTS 10. VARIATIONS AND CLAIMS 11. CONTRACT PRICE AND PAYMENT 12. DEFAULT 13. RISK AND RESPONSIBILITY 14. INSURANCE 13 RESOLUTION OF DISPUTES Foreword These Conditions of Contract FIDIC Green Book Short Form of Contract 1st Edition 1999 have been prepared by the Fdration Internationale des Ingnieurs-Conseils (FIDIC) and are recommended for engineering and building work of relatively small capital value. However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. fidic green book fidic 4th edition fidic epc contract what is fidic full form fidic 2010 fidic clauses fidic 1987 fidic rules fidic 1992 fidic 1987 download They are considered most likely to be suitable for fairly simple or repetitive work or work of short duration without the need for specialist sub-contracts. The main aim has been to produce a straightforward flexible document which may be used for all types of engineering work with a variety of administrative arrangements, including all essential commercial provisions. Under the usual arrangements for this type of contract, the Contractor constructs the Works in accordance with design provided by the Employer or by his representative (if any), who is not required to act impartially. However, this form may also be suitable for contracts which include, or wholly comprise, contractor-designed civil engineering, building, mechanical and/or electrical works. In addition, the Employer has a choice of valuation methods. Furthermore, although there is no reference to an impartial Engineer, the Employer may appoint an independent Engineer to act impartially, should he wish to do so. The form is recommended for general use, though modifications may be required in some jurisdictions. fidic green book fidic 4th edition fidic epc contract what is fidic full form fidic 2010 fidic clauses fidic 1987 fidic rules fidic 1992 fidic 1987 download FIDIC Green Book Short Form of Contract, FIDIC considers the official and authentic text to be the version in the English language. The intention is that all necessary information should be provided in the Appendix to the Agreement, the latter incorporating the tenderers offer and its acceptance in one simple document. The General Conditions are expected to cover the majority of contracts. Nevertheless, users will be able to introduce Particular Conditions if they wish, to cater for special cases or circumstances. The General Conditions and the Particular Conditions will

together comprise the Conditions governing the rights and obligations of the parties. To assist in the preparation of tender documents using these Conditions, Notes for Guidance are included. These Notes will not become one of the documents forming the Contracts. Finally, applicable Rules for Adjudication are also included. The attention of users is drawn to the FIDIC publication Tendering Procedure, which presents a systematic approach to the selection of tenderers and the obtaining and evaluation of tenders. agreement contract, contract agreement. FIDIC Green Book Short Form of Contract ISBN : 2-88432-024-5 Number page : 36 pages Download Type : PDF File, FIDIC Green Book Short Form of Contract

S-ar putea să vă placă și