Documente Academic
Documente Profesional
Documente Cultură
DATE: 02.03.2012 TIME: 11.00AM MEETING NO: 3/2012 VENUE: DR. SUNARTIS ROOM MEETING CALLED BY TOPIC SUPERVISOR NOTE TAKER TIMEKEEPER ATTENDEES
Nor Shafiza Binti Ghazali Plant Design 2 Dr. Sunarti Binti Abd Rahman Nor Shafiza Binti Ghazali Nor Shafiza Binti Ghazali All present Group Members of 5 person (Group 41)
Agenda:
DISCUSSIONS Brainstorming
1. Update progress from each group members. 2. Show the new process flow diagram (PFD) to madam- Recheck with madam and seek for advice. 3. Update the new mass balance. 4. Proceeds with each jobs Settle with new energy balance.
CONCLUSIONS
1. Each person should study more about each part for equipment sizing and then should start with the calculation for reactor, cyclone, heat exchanger, quench tower, absorption unit and distillation column. 2. Based on the new PFD, need to be revising back about the temperature, any additional unit such as separator and so on. 3. The new mass balance has done and proceeds with energy balance. Make sure that the condition at the equipment is suitable such as the temperature at heat Exchanger is enough to cool down the gas temperature in the tube heat exchanger. 4. Advise from supervisor- study about synthetic gas and syn gas, the difference/similarity between both gases.
ACTION ITEMS PIC DUE DATE STATUS
1. Perform calculation for each equipment. 2. Recheck PFD and consult with Dr. Sunarti 3. Select equipment for further calculation and read necessary notes to enhance the calculation skills. 4. Review on Mass Balance. 5. Energy Balance review. Meeting Adjourned: 11.35am
Inba, Sara, Shafiza, Sufinah, Irsyad Inba Inba, Sara, Shafiza, Sufinah, Irsyad Inba Sara