Sub: About Welding Machine for CSS Date 29-2-2012 To Manager, Production and Maintenance CSS Corporation (BD)

Ltd.

Sir With due respect I am informing you that we have finished one fume extraction hood. Now we are starting to build the second fume extraction hood. While building first one we have faced few problems. We have only one welding machine. If we not get another welding machine it will be very difficult for us to build the second one in-time. For doing the work properly and quickly we need another welding machine. Because the environment authority will come soon to visit our factory. I look forward to a favorable reply. Thank you for your consideration. Sincerely yours,

.. (Simul Das) Assistant Engineer (Mechanical) Production and Maintenance Department BSIL & CSS Corporation Ltd. CC: 1) 2) 3) 4) Honorable Director General Manager, Admin & HR Department Personal Profile Department Profile

S-ar putea să vă placă și