Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
1. 2. 3. 4 5. 6
Discuss various objects of construction management. What are functions of construction management? Explain briefly each. Write short note on Work breakdown structure. List out construction management techniques and Explain Gantt bar chart with its uses. Explain LOB Techniques. A Project consist of eight activites P,Q,R,S,T,U,V and W with their times of completion as follows Activities P Q R S T U V W Duration (days) 3 5 3 5 7 5 6 5
The precedence relationship are as follows: P & Q are performed parallel R & S can not start until P is completed. T cannot start until half the work of activity R is complete. U can start only after activity S is complete. V succeds R. W is the last activity, which should succed T. (a) Draw bar chart (b) Give your comments and conclusion.
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
1. 2 3. 4. 5 6. 7 8
Define Network, Activity and Event. Define dummy and state its uses. Explain types of events with examples Discuss various rules for providing dummies in a network. Explain Fulkersons rules for numbering the events. Discuss various network rules. Differentiate between Activity Oriented Network and Event Oriented Network. Draw the network of a project having eight activities. Activities predecessor relationships are as follows. Activities B,C,D E F G H Duration (days) A B C D E,F,G
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
1. 2 3. 4. 5.
Define: (a) Optimistic Time (b) Passimistic Time (c) Most Likely time (d) Earliest Expected Event time (e) Latest Allowable Occurance time (f) Critical Path Define: Earliest start time (EST), Earliest Finish Time (EFT), Latest Start Time (LST), Latest Finish Time(LFT) Define Float. Explain briefly various types of floats. What is meant by Time-grid diagram? Describe time Grid diagram method. What are purposes and advantages of time-grid diagram? The following network shown in figure 1 has the estimated duration for each activity marked. Determine the critical path. Also determine total float and free float for each activity.
From the data given below in table. Prepare network diagram and Determine the critical path. also determine total float and free float and interfering float for each activity. Activities A B C D E F G H I J K L Activity Arrow 1-2 1-3 1-4 2-5 2-7 3-5 4-5 4-6 5-6 5-7 6-7 7-8 Duration 8 6 10 8 15 10 8 10 10 10 8 7 Activity Immediately Preceding Following None D,E None F None G,H A I,J A L B I,J C I,J C K D,F,G K D,F,G L H,I L E,J,K None
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
From the data given below in table. Prepare network diagram and Determine the critical path. Also determine total float and free float and interfering float for each activity. Activities P Q R S Dummy T U V W Sequence Code 1-2 2-3 2-4 3-5 3-4 4-6 5-7 6-7 7-8 Duration 7 6 5 6 0 9 4 2 3
8.
From the data given below in table. Prepare network diagram and Determine the critical path. Also determine total float and free float and interfering float for each activity. Activities A B C D E F Dummy G H I Sequence Code 1-2 1-3 2-4 2-6 3-4 3-5 4-5 4-7 5-7 6-7 Duration 8 9 12 7 15 10 0 12 5 11
9.
From the data given below in table. Prepare network diagram and Determine the critical path. Also determine total float and free float and interfering float for each activity. Activities A B C D E F G H I Duration 10 2 8 0 18 8 12 4 1 Activity Immediately Preceding Following B,C A D,F A E B E C,D G B H E I F I H,G -
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE: 10. From the data given below in table. Prepare network diagram and Determine the critical path. Also determine total float and free float and interfering float for each activity. Activities P Q R S T U V W X Y Z 11. Duration 2 4 3 5 8 3 6 3 5 4 9 Activity Immediately Preceding Following S T,X U,W P V Q,U V R T,X S,T,X R Z Q,U V,Y X W -
From the data given below in table. Prepare network diagram and Determine the critical path. Also determine total float and free float and interfering float for each activity. Activities A B C D E F G H I J K L Duration 3 4 6 3 6 4 5 3 6 4 4 4 Activity Immediately Preceding Following B,C A D A D,E B,C F C G D I E H,J G I F,H L G L J L I,K -
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE: 12 Following activities are observed in a project. Prepare network diagram and find out (a) Critical path (b) Critical activities (c) project duration Activities Sequence Code Duration
P 1-2 7 Q 2-3 6 R 2-4 5 S 3-5 6 Dummy 3-4 0 T 4-6 9 U 5-7 4 V 6-7 2 W 7-8 3 Further the network is to be updated after 7 days of its execution. Following conditions exist at the end of 7 days. (i) Activity P is completed as per schedule (ii) Activity Q was drastically delayed, 5 more days. (iii) Start of activity R was delayed drastically and can be started after 3 days of completion of activity P but will require 4 more days instead of 5 days. (iv) Activity S is not started yet and will require 12 days instead of 6 days and can be started immediately after completion of Q. (v) Activity T is as per schedule. (vi) Activity U is not started yet and will require 7 days instead of 4 days (vii) All other activities are unchanged and the original time estimates for these activities still appeared to be accurate. Update the network, determine the revised critical path and calculate revised TE and TL for all events.
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
The project overhead costs are Rs. 3000 per week. Find the optimum duration and the cost associated with it.
7.0
The following table gives the data for the data f or the duration and costs of each activity of project network shown in figure 2.0. the indirect cost of project is RS. 3000/- week. Determine the optimum duration of the project and the corresponding minimum cost. Draw the time scaled version of the network. Activity 1-2 1-3 2-3 2-4 3-4 Normal Duration 6 8 4 5 5 Normal Cost (Rs.) 7000 4000 6000 8000 5000 Crash Duration ( weeks) 3 5 1 3 3 Crash cost (Rs.) 14,500 8,500 9,500 15,000 11,0000
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
8.0
Following table give data for the duration and costs of each activity of the project. The indirect cost of project is R.S. 75/- per day. Determine the optimum duration of the project and the corresponding minimum cost. Activity Sequence Code 1-2 1-3 2-3 2-4 3-4 3-5 4-6 5-6 Normal Duration 2 7 6 5 0 9 11 6 Normal Cost (Rs.) 1000 500 300 200 0 600 600 700 Crash Duration ( weeks) 2 3 3 4 0 4 6 3 Crash cost (Rs.) 1000 900 420 250 0 900 1000 910
A B C D E F G H
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
1. 2 3.
Write short note on Resource Allocation Write short note on resource scheduling. Following activities are observed in a project. The data regarding the requirements of masons per day given in table. Carry out resource allocation for the project and arrange the network in such a manner the requirement of masons is almost uniform throughout project without delaying the project. Assuming that unlimited no. Of masons is available draw histogram for requirement of masons for original and revised schedule. Activities P Q R S T U V W Sequence Code 1-2 2-3 2-4 3-5 4-6 5-7 6-7 7-8 Duration(days) 3 3 5 3 3 2 5 2 Required Nos. Of masons 5 3 4 4 6 4 3 6
4.
Following activities are observed in a project. The data regarding the requirements of concrete mixers per day given in table. Carry out resource allocation for the project and arrange the network considering maximum 3 concrete mixers available per day on site. Project duration can be updated if required no. Of concrete mixers are more than 3. Draw histogram of requirement of concrete mixers for original and revised schedule. Required Nos. Of concrete mixers. 1 2 1 1 2 1 2
Activities A B C D E G H
Duration(days) 4 5 3 5 3 6 5
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
TUTORIAL 6.0 Programme Evaluation & Review Technique analysis , job layout & cash flow analysis.
1.0 2.0 3.0 4.0 5.0 6.0 7.0 Give difference between CPM and PERT. Define: Optimistic time, Pessimistic time, most likely time , earlest expected time, slack. Define (i) Mean (ii) Variance (iii) Standard deviation. What do you understand by frequency distribution? Write short note on cash flow analysis and use of S Curve. Briefly explain factors affecting job layout and advantage of job layout. Draw job layout for three storeyed building block. Following activities are observed in a project. Prepare network diagram and find out (i)critical path and standard deviation (ii) Probability of completion of project in 30 days. (iii) Time duration that will provide 90 % probability of its completion in time (iv) Prepare schedule of PERT Sequence Code 1-2 2-3 2-4 3-5 3-4 4-6 5-7 6-7 7-8 Duration (days) To 5 5 3 6 0 7 2 2 2 Tm 7 6 5 6 0 9 4 2 3 Tp 8 6 7 9 0 12 5 4 4
Activity P Q R S DUMMY T U V W
8.0
Following activities are observed in a project. Prepare network diagram and find out (i)critical path and standard deviation (ii) Probability of completion of project in 35 days. (iii) Time duration that will provide 90 % probability of its completion in time (iv) Prepare schedule of PERT
Sequence Code 1-2 1-3 2-4 2-6 3-4 3-5 4-5 4-7 5-7 6-7 Duration (days) To 5 5 9 6 12 7 0 10 4 9 Tm 8 9 12 7 15 10 0 12 5 11 Tp 9 12 14 9 16 12 0 14 5 14
Activity A B C D E F DUMMY G H I
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE: Following activities are observed in a project. Prepare network diagram and find out (i)critical path and standard deviation (ii) Probability of completion of project in 15 days. (iii) Time duration that will provide 80 % probability of its completion in time (iv) Prepare schedule of PERT Sequence Code 1-2 1-3 2-4 2-5 3-5 4-5 4-6 5-6 Duration (days) To 2 5 2 4 1 0 4 4 Tm 4 5 3 5 3 0 6 5 Tp 8 7 3 6 4 0 9 8
9.0
Activity A B C D E F G H
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
5.0
12.0
13.0 15.0
Page ___
GOVERNMENT ENGINEERING COLLEGE, PATAN B.Tech VII SEM CIVIL ENGINEERING SUB: CONSTRUCTION MANAGEMENT AND EQUIPMENTS (170601) DATE:
TUTORIAL 8.0 ENGINEERING FUNDAMENTALS OF MOVING EARTH & TYPES OF EQUIPMENTS. 1.0 2.0 3.0 4.0
Explain in brief the following soil fundamentals. 1. Materials properties 2. Soil weight volume relationships Explain Rolling Resistance and drawbar pull. What is effect of grade on required tractive effort. Write short notes on following. 1. Crawler tractor 2. Wheel tractor 3. Bulldozer 4. scrapers What are the uses of power shovels? Describe with neat sketch basic parts and operation of power shovel Write short notes on following. 1. Conveyor belt 2. Idlers Write short notes on following. 1. Dumper 2. Wagons Give difference between Dragline and power shovel. Write short note on 1. Derrick cranes and gantry cranes. 2. Pile driving equipments.
Page ___