Documente Academic
Documente Profesional
Documente Cultură
May 2012
5/8/2012
5/8/2012
Introduction
Dominica:
Known as "The Nature Island of the
Caribbean" due to its abundant plant and animal life, extensive park system, volcanic peaks, lava craters, the largest boiling lake in the world, waterfalls, rivers, and lakes.
Blessed with abundant resources and
5/8/2012
Introduction continued
Economy is predominantly agriculturally based: - high level of dependence on bananas;
Dominica requires reliable and cost-effective types of infrastructure, and especially in energy.
Electricity and transport sectors represent considerable challenges for Dominica.
5/8/2012 5
Introduction continued
resources.
Small size of the market, therefore
of the current electricity distribution system and public transportation is extremely limited.
Dominica possesses considerable
natural resources to provide for its energy security with a combination of renewable energy technologies hydro, wind, solar, biomass, geothermal and improved energy efficiency.
5/8/2012 6
Introduction continued
Use of clean renewable energy and energy
Strategy states that major investments in electricity generation and distribution are necessary to facilitate the requirements for the further diversification of the economy.
Dominica can demonstrate the viability of
Electricity Services
Currently, diesel generators fuelled by imported oil (70%) and hydropower plants
Electricity Services
continued
EC$0.70/kWh (US$0.26) for the first 50kWh and EC$0.81/kWh (US$0.30) for additional kWh.
Fuel surcharge is calculated monthly
among the highest in the Eastern Caribbean - a source of concern and protest among many residents.
Slow economic growth resulted in a
electricity services comprises domestic, commercial, hotel, industrial, lighting and street lighting.
Dominica Electricity
firm WRB (51%). The Dominica Social Security owns 20%. Local corporate and private citizens own the remaining 29%.
5/8/2012 10
- Diesel
10,036
10,036
11,090
11,090
12,840
12,840
12,840
13,590
14,440
15,890
15,890
17,170
17,170
Total
17,636
17,636
18,690
18,690
20,440
20,440
20,440
21,190
22,040
23,490
23,490
24,770
24,770
5/8/2012
11
Hydro
36,226
33,841
33,670
32,410
31,590
27,036
35,929
28,523
33,736
27,876
27,797
21,885
20,554
Diesel
23,867
31,942
36,630
42,226
45,925
53,929
44,203
48,404
45,493
55,779
57,619
64,497
66,944
Total
60,093
65,783
70,300
74,636
77,515
80,965
80,132
76,927
79,229
83,655
85,416
86,382
87,498
5/8/2012
12
Total 48,581 52,293 57,294 60,594 62,005 63,914 64,194 62,735 66,419 67,789 69,571 71,421 73,686 % change 7.64 9.56 5.76 2.33 3.08 0.44 2.27 5.87 2.06 2.63 2.66 3.17
5/8/2012
13
Domestic
10,000
5,000 -
Lighting
Street Lighting
5/8/2012
14
5/8/2012
15
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
10,130
11,390
12,348
13,010
12,966 13,866
13,043 12,923
13,190
14,368
14,467
14,501
14,663
Growth (%)
12.44
8.41
5.36 -
0.34
6.94 -
5.94 -
0.92
2.07
8.93
0.69
0.24
1.12
5/8/2012
16
10,000
8,000 6,000 4,000 2,000 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
5/8/2012
17
deal with regulatory matters for the generation, transmission, distribution and supply of electricity services, among other things.
5/8/2012
18
5/8/2012
19
on a programme to explore and develop Dominicas geothermal resources, primarily to generate clean and lower cost electricity. Dominica embarked on a European Union funded 1.5 million Euro geothermal resource exploration project, Preparation of a Geothermal based Cross-Border Electrical Connection in the Caribbean. The project is co-funded by the AFD and the FFEM with an additional 4.5million, the EIB for 1.1 million for a submarine interconnection study. The Government of Dominica contributed in excess of 5 million.
5/8/2012 20
and interconnection to supply neighbouring islands of Guadeloupe and Martinique with 4050 MW of electricity each.
The project required exploratory drilling to
characterize the resource, particularly pressure, temperature, and mineral content, and to determine the feasibility and long term viability of the investment required.
5/8/2012 21
to manage the implementation of the project. All required staff was in place at September 2010. PMU responsible to Minister for Public Works, ENERGY and Ports PMU budget is approximately 450,000 euros for the first three years.
5/8/2012 22
the results of initial surface investigations at the Wotten Waven Geothermal Resource area. Tests were conducted under a Transnational Partnership Agreement between Dominica, Guadeloupe, and Martinique, and ADEME and BRGM partly funded under the EUs INTERREG IIIB (Caribbean Space) programme. This "Gothermie Carabe" project was the preliminary phase of the more comprehensive EU funded initiative in Dominica. Cost was approximately 1.1m. Activities were conducted by consultants
and technical staff of the CFG (French Geothermal Company) of the BRGM.
5/8/2012 23
which will ensure the success of the project from a technical, administrative and legal point of view. This project had four (4) main objectives: To validate the information in the OAS studies
carried out in 2005; To make a preliminary analysis of the environmental impact of the proposed project; To make a preliminary analysis of the legal and institutional framework of the project; and To revise and update the economic assessment of the project.
the INTERREG IIIB phase submitted and presented at a conference of the Partners in December 2009.
5/8/2012 24
divided into two (2) principal Activities. Activity I will deal with the final characterization of the Geothermal Power Production potential that will specify the power production areas, undertake an investment prospectus for the proposed development, and undertake test drilling in those specific areas. Activity II will support the establishment of the PMU and provide TA in respect of policy, environment, regulation, communication and public relations, and monitoring. Will include advice on PPA with existing and potential electricity distributor.
5/8/2012 25
electricity each to Guadeloupe and Martinique. Up to 20 MW will be reserved for the Dominican market. Total investment required for 120 MW plant estimated at US$450M to US$500M. Plan to start with small geothermal power plant of 5-10MW for local market. will help to test and evaluate the resource and the reservoir. Production can begin by the year 2014. Project can reduce the cost of electricity from US$0.27/KWh to US$0.060.10/KWh, before fuel surcharge (Geothermal Power plant will require practically NO fuel )
5/8/2012 26
Geothermal Project
Interreg IIIB funded studies, and with support from technical advisors.
Government/PMU secured sites. EIA for test drilling conducted by French firm -
Coring mining technique. A level area of approximately 3000 square meters was prepared for the drilling rig and related equipment to carry out the drilling and testing activities.
5/8/2012 27
Geothermal Project
Well Locations Well Site 1: Trafalgar/Wotten Waven
Well Site 2: Laudat - Adjacent to the Aerial Tram Rain Forest facility
5/8/2012
28
Geothermal Project
Contractors Drilling Contractor: Iceland Drilling Company (IDC)
Original Contract Sum: (exclusive of VAT (15%): 3,976,702.00 Euros
Site Preparation Contractor: Offshore Civil & Marine Inc. Lot One XCD$ 715,672.60
arrived in Dominica;
December 4, 2011: Drilling rig taken to site;
5/8/2012
29
Geothermal Project
First Well Drilled Site 2 o Drilling started on December 16, 2011 o Drilling completed on January 28, 2012 o Final depth of well: 1469 metres o Depth of 4 slotted liner: 1337m o Highest temperature logged: 241 degrees Celsius o Highest Pressure logged: 82 Bars (1190 psi) o Number of days drilling: 41 o Total Number of work days: 65 o Date of flow test: March 9th and 10th 2012 Results of Flow Test Total flow estimated at 6.4 6.6 kg/s with 4.9-5.1l/s liquid flow and 1.5kg/s of steam
Enthalpy 940-980kJ/kg Fluctuating gas concentrations between 34 and 63
wt%
Dominant gas is CO2 (93.6 to 96.2 vol%)
5/8/2012
30
Geothermal Project
Second Well Drilled Site 3 Commencement date of WW-3: February 15, 2012 Completion date of WW-3: March 14, 2012 Final depth of well WW-3: 1613 meters Depth of 4 slotted liner: 1605m Highest temperature logged: 245 degrees Celsius Highest Pressure logged: 98 Bars (1421 psi) Number of days drilling: 29 Total Number of work days: 40 Date of flow test: April 17, 2012 Preliminary results of flow test Total flow estimated at 22 kg/s Well thermal output equivalent to 3.5MW
5/8/2012
31
Geothermal Project
Third Well Drilled Site 1 o Commencement date of WW-1: March 28, 2012 o Completion date of WW-1: April 27, 2012 o Total depth: 1200m o Depth of 4 slotted liner: 1200m o Highest temperature logged: 180 degrees Celsius o Maximum pressure logged: 108 Bars (1566psi) o Total number of days drilling: 31 o Total number of work days: 42 Preliminary results suggest that Well 1 is very permeable, and it has the potential to be a very good well for geothermal energy. The projected date for opening up and flowing the well is the week of June 10, 2012. By that time the well would have had sufficient time to recover thermally and allow for a good flow test.
Final Results and Reports of the exploratory drilling are expected by September 2012.
5/8/2012 32
Geothermal Project
Government is very satisfied with preliminary results of the test wells drilled
5/8/2012
33
Geothermal Project
Next phase will involve: Evaluation of test drilling results. Deciding on the approach for: o Power Plant development: small plant for domestic market, and large plant for export market; o Project ownership/corporate structure; o Nature and extent of Governments participation and involvement; Complete/finalize feasibility for small (10MW) power plant; Undertake feasibility studies of submarine electrical interconnection between Martinique, Guadeloupe and Dominica;
5/8/2012
34
Geothermal Project
Results of flow tests will allow for the creation of a model of the geothermal field (including the geothermal reservoir), and to identify the location of the power plant, production and reinjection wells, and allow for the sustainable exploitation of the geothermal resource.
5/8/2012
35
Act (ESA) of 2006;- CREDP/GTZ/CSEP (OAS) Prepare Regulations for the ESA; CREDP/GTZ Enact Geothermal Resources Development Bill; - supported by the World Bank
Geothermal Resources Development Bill drafted. Planning and Environmental Regulations for Renewable Energy drafted. BOTH documents submitted for review and vetting by the Attorney Generals chambers.
Road Map (support from the OAS); and Prepare a Sustainable Energy Plan; CARICOM, the OAS, and the GTZ.
5/8/2012 36
Plan:
Lays out a strategy by which the energy
production and use in Dominica may be transformed, becoming more economically and environmentally sustainable, while enhancing the electricity generation mix. Ensure the existence of adequate energy supplies at affordable rates to sustain economic development, while meeting current and projected power demand. Provide for stable, reliable, and affordable electricity supplies for all customers. Lower the price of electricity for consumers.
5/8/2012 37
sectors of the economy. Allow reasonable incomes for businesses engaged in the local energy sector. Attract international investment where appropriate tourism; manufacturing; agro-processing... Promote energy efficiency and conservation at all levels of the economy in order to achieve optimum economic use of renewable and non-renewable sources of energy.
5/8/2012
38
maximizing the use of renewable-energy and energy-efficiency alternatives where viable. This is especially relevant in Dominica as much of the renewable energy generation may take place in nature preserves or rain forest areas. It is essential that this be done in a manner that does not threaten biodiversity, forestation levels, and other environmental aspects.
Promote the generation of income through energy
generating plant of 15 MW with financial assistance from the Govt of Venezuela as a short term energy security measure, and to safeguard against power failure. Preparing an Electricity System Development Study and Electricity Generation Plan for the country; Studies to identify sites for NEW hydro power plants around the island; Geothermal Resource assessment in the north of Dominica; Undertake Energy Audit of Govt facilities and street lights; Encourage use of solar hot water systems in homes and hotel sector;
40
5/8/2012
5/8/2012
41
Outstanding Matters
1.
2.
Finalize and approve, and implement Sustainable Energy Plan important component is the Energy Efficiency programme for Dominica.
Need for a comprehensive strategy and approach to implementing host of Technical Assistance activities and programmes for both RE and EE, in the context of sustainable development.
3.
4.
5. 6. 7.
Need for TA to review and validate project and renewable energy resource evaluation reports.
Need for TA to undertake electricity system generation study and generation plan - USTDA considering similar support to DOMLEC. TA to undertake Energy Audit of Government facilities and street lights. Energy Efficiency audits in tourism/hotel sector including cost reduction measures including use of solar power hot water and AC refrigeration. Capacity development in RE technologies.
42
8.
5/8/2012
Thank You.
5/8/2012
43