COMMENTS RESOLUTION

SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0107

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

QP PROJECT NUMBER

3392

The Planning Package

Engineering

No.

QP COMMENTS

CONTRACTOR RESPONSE

Engineering plan submitted is not acceptable as the rate of deliverable


submission to QP is un realistic. Contractor to review the rate of
deliverable submission to QP, leveling to be carried out.

Page 1 of 6

Done (EDR is part of the PMS)

COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0047

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

QP PROJECT NUMBER

3392

The Planning Package

Schedule

No.

QP COMMENTS

CONTRACTOR RESPONSE

Contractor is advised to review the critical path activities considered for


the Pre comm and commissioning, It is unrealistic to assume all
activities under the pre comm. and commissioning are activities are
critical. No forced critical activities are allowed repeated comments
were raised on the same subject

Done

Original duration of commissioning included in the schedule


program according to:

Please clarify the duration allowed and basis of assumption for the
pipeline precomm activities for 60 days??

On Plot Piping Tie in works at station area to be included in the schedule


Done
and construction verification sheet with wt factor

Page 2 of 6

contract Appendix A Page No 201 10.1 General


(9.The operators shall provide coverage 24 hrs/day 7
days per week, for a duration of 60 days, working a 12
hour per day shift system)

COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0047

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

QP PROJECT NUMBER

3392

The Planning Package

Schedule

No.
4

QP COMMENTS

CONTRACTOR RESPONSE

On Plot Piping Tie in works at station area to be included in the schedule


Done
and construction verification sheet with wt factor
EPIC contractor is obliged to achieve the Mechanical
completion and the Pre-commissioning & Commissioning for
PL and all related facilities as per Appendix(H)

Response against the comments # 3 under the section schedule


(Previous QP comments) is not acceptable, advised to provide the list of
compliance/ non compliance (with dates) to the key events table in the
appendix H in tabular format.

Page 3 of 6

Achieving commencement of construction activation shall


not start as appendix (H) demands finalizing the drawing of
Route and Alignment sheets, which hasn't started yet due to
Topography survey delay. Thus, PETROJET cannot start this
activity at the date of Key events (completion date from the
Effective Date (26-2-2012)

COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0047

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

QP PROJECT NUMBER

3392

The Planning Package

Progress measurements

No.
1

QP COMMENTS

CONTRACTOR RESPONSE

Project handover and closeout activities such as built submission , dossier ,

Done and listed in the construction phase

closeout , ACS et are not appearing in the progress measurement system

Progress Curves and histogram

No.
1

QP COMMENTS

CONTRACTOR RESPONSE

Contractor has not provided the Late curves as per the item #2 under the
section Progress Curves and histogram (Previous QP comments)

Page 4 of 6

Done

COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0047

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

No.

QP PROJECT NUMBER

3392

The Planning Package

QP COMMENTS

CONTRACTOR RESPONSE

Procurement

It is advised adopt the wt factor allowed for individual line item under
the procurement based on the overall value of procurement rather
than based upon long lead and other item individually ( however long
lead /Bulk item category shall be retained as it is ) .

Done

It is noted in the Procurement Status Register that Bulk Progress scale


is adopted for other items listed in the sheet, there are many of the
items in the list cannot be considered as bulk items. Please clarify?

Done

Page 5 of 6

COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER

GC11106200

CONTRACT TITLE

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3

QP EXTERNAL TRANSMITTAL REFERENCE

EDL/GC11106200/EXT/TN/0047

DATE

19/7/2012

DOCUMENT NUMBER
DOCUMENT TITLE

3392-00-69-00-0003

DOCUMENT REVISION

QP PROJECT NUMBER

3392

The Planning Package

Construction

No.

QP COMMENTS

CONTRACTOR RESPONSE
Done
Some point was taken into consideration:

The Rate of ROW is 200m/Day because of ROW include


that(Grading and compacting of the ROW and access road
Response against the comment # 03 under the Construction
including any fill and cutting of the existing ground &
section(Previous QP comments) on production rate is not reasonable. reinstatement of other pipeline access tracks in the corridor
It cannot be construed the standard production rate (200Mtrs) for all where used during the construction of the new pipelines &
activities in the pipeline and prepare schedule, for eg. It is not
removal of obstructions alone the ROW , Removal of
appropriate to consider Survey, Row, the Pipeline line stringing rate
obstructions shall be extended to include obstructions
is 200 mtr / day. Contractor review this schedule accordingly.
between pipelines and the new pipeline) Page No 80
Appendix(A) so that ROW does not include right of way
only but include the previous demands.
The rate of survey = 400 m/ Day
The rate of stringing = 300 m/Day

Page 6 of 6

Page 1 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
METHOD STATEMENT FOR PROJECT
CONTROL
______________________________________

Page 2 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

CONTENTS

1. METHOD STATEMENT FOR PROJECT CONTROL AND PROGRESS


MEASUREMENT .
2. WORK BREAKDOWN STRUCTURE .
3. INTEGRATED PLANNING NETWORK .
4. MANPOWER SCHEDULE AND HISTOGRAM .
5. EQUIPMENT DEPLOYMENT .
6. PROGRESS MEASUREMENT SYSTEM (PMS) .

Project Overall Progress Measurement .

Engineering Document Register (EDR) .

Procurement Status Register (PSR) .

Construction Progress Measurement .

Pre-Commissioning & Commissioning Progress Measurement .

The Optional Items Progress Measurement .

7. PROGRESS S-CURVES & TABLES .

Project Overall Progress S-Curve .

Engineering Progress S-Curve

Procurement Progress S-Curve.

Construction Progress S-Curve.

Pre-Commissioning & Commissioning Progress S-Curve.

The Optional Items Progress S-Curve .

Page 3 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

PLANNING PACKAGE

8. CONSTRUCTION VERIFICATION SHEET.


9. MARCHING CHART
10. CASH FLOW CURVE & TABLE .
11. INVOICING SYSTEM .
12. ATTACHMENT .

Daily Progress Report (DPR) Format .

Weekly Progress Report (WPR) Format .

Monthly Progress Report (MPR) Format .

Page 4 of 266

DATE

July 19,2012

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

1. Introduction
This method statement outline the procedure and requirements of the progress measurement
methodology and control for the project EPIC of 16" - 36 km Jet A1 Fuel Pipeline from the QP
refinery to BSV-3 .
2. Purpose
The purpose of this method statement is to ensure that the project schedule will be monitored and
implemented on time without any delay according to appendix-H as the following dates : Contract Effective Date : Feb 26,2012
Achieve Mechanical Completion of Pipeline and all Facilities : Nov 25,2013.
Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : May 25,2014 .
Complete Baseline Survey (Optional) : July 25,2014
Scheduled Project Completion :Aug 25,2014 (30-Months from the Effective Date)
3. Project Control
3.1 General
Petrojet will develop comprehensive project control procedures and detailed plans based upon
the Appendix-H of the contract and Appendix-D (Attachment D-3) of the contract .
It is the responsibility of the project control to identify the scope of the work in complete details
and project control will support the project in order to ensure its completion on time by the
following functions :

Highlight the Milestones for the project , highlight the interfaces of the project with
others.

Close coordination and monitoring of sub-contractors and suppliers progress of works for
their scope through an agreed progress reporting mechanism .

Detecting any obstacle which may affect the planned dates/cost, studying the situation,
and determining both the best solution and any corrective action which will ensure that the
baseline end date of the project is met without any deviation .

Analysis Assuring that the project progress is occurring in accordance with the approved
time schedule .

Page 5 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

Using a specialized software Primavera Version 6.7 to provide electronic schedules that
can be used in either electronic or printout forms to illustrate planning information, look
ahead/behind schedules, etc.

Preparing a periodic reports to be submitted to the client management.

Integrating all of the work to ensure the quality of the project.

Petrojet project control, as deliverables will issue ninety days lookahead schedule and within the
time specified in the contract , will develop Comprehensive Project Planning Package which
will form the basis for the monitoring of the works .
The Planning Package will be submitted to QP for approval and once approved will be used as
the basis of progress monitoring .
To retain the consistency on progress reporting , the weight factors shall not be modified during
the course of the contract .
3.2 Integrated Planning Network
Petrojet project control will establish a comprehensive time schedule using primavera P6 . the
schedule will be resource loaded . The total project schedule will be fully integrated showing
all activities more than 1000 activities - related to engineering, procurement, construction,
pre-commissioning, commissioning in addition to the optional items .
The CPM network will include all aspects of the work and will be sufficiently detailed to the
satisfaction of the QP representative . Detailed activities of the work/service will include all
parties, vendors and sub-contractors necessary to complete the works .
3.3 Progress Measurement
Petrojet project control will develop, maintain and update a computerized progress
measurement system . the progress measurement system will enable monitoring and follow-up
of progress (actual versus planned) for all activities performed by Petrojet.
The progress will be calculated from the lowest control level and electronically rolled up to the
upper levels .
The progress basis shall be as the following : The engineering progress will be Milestone progress and based on the estimated manhours that will be related to the engineering document register (EDR).
The procurement progress will be Milestone progress and based on the cost that will be
related to the procurement status register (PSR) .

Page 6 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

The construction progress will be based on the estimated man-hours/efforts that will be
exported from Primavera time schedule to the progress control Excel sheets.
The pre-commissioning and commissioning progress will be based on the manhours/efforts that will be exported from Primavera time schedule to the progress control
Excel sheets .
The progress of optional items (Laying new FOC, Kahrama option (1) and the Baseline
survey) will be based on the man-hours/efforts that will be exported from Primavera
time schedule to the progress control Excel sheets .

3.4 Weight Factors


Level (1) weight factor will be as the following : Engineering

5%

Procurement

40 %

Construction

48 %

Pre commissioning & Commissioning

5%

Optional Items

2%

-----------------------------------------------------------------------------------------------------------------------------The Engineering progress chain milestones will be according to the contract as the following : Started

5%

Cumulative

5%

Issued For QP Review (IFR)

35 %

Cumulative

40 %

Issued For QP Approval (IFA)

25 %

Cumulative

65 %

Issued as AFC with hold

20 %

Cumulative

85 %

Issued Approved For Const. (AFC)

10 %

Cumulative

95 %

Issue As Built

5%

Cumulative

100 %

-----------------------------------------------------------------------------------------------------------------------------The Procurement progress chain milestones will be as the following :A)

Equipment

Issue MR for QP Approval

5%

Cumulative

5%

Issue RFQ to Vendors

5%

Cumulative

10 %

Issue Purchase Order

5%

Cumulative

15 %

Vendor Drawing Approval

15 %

Cumulative

30 %

Receipt of Filled SPIR

10%

Cumulative

40%

Page 7 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

Inspection Cleared and Factory Tested

20%

Cumulative

60 %

Ex-Works Delivery

10 %

Cumulative

70 %

Material Received & Inspected at Site

15 %

Cumulative

85 %

QP Inspected & cleared Material at Site

5%

Cumulative

90 %

All Spare Parts Recd &SPIR Completed

10%

Cumulative

100 %

Issue RFQ to Vendors

5%

Cumulative

5%

Place Order For Bulk Material

10 %

Cumulative

15 %

Material Delivery Ex-Works (50% of Qty)

15 %

Cumulative

30 %

Material Delivery Ex-Works (90% of Qty)

10 %

Cumulative

40 %

Material Received at Site (50% of Qty)

10 %

Cumulative

50 %

Material Received at Site (90% of Qty)

30 %

Cumulative

80 %

All Material Received

20 %

Cumulative

100 %

B)

Bulk Material

3.5 Progress S-Curves


Project control will provide the progress S-Curves for different phases of the project and
overall S-Curve derived from the information contained in the EDR & PSR & Construction
progress measurement & Pre-commissioning and Commissioning progress measurement &
the optional items progress measurement.
4. Progress Reporting
4.1 General
Petrojet will report to QP on the progress of the work throughout the duration of the contract.
The purpose of these reports is to apprise all parties involved regarding the comprehensive
status of the project.
The Daily reports will be submitted next day, Weekly reports will have the cut off date of last
Thursday and will be issued each Sunday and the Monthly reports will have a cut off date of
last Thursday of the month and will be submitted by first week of succeeding month.
4.2 Daily Reports
The Daily Progress Report (DPR) will be submitted on daily basis through e-mail for the
construction activities.

Page 8 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

The reports will be generated from the day of commencement of ROW activity. This report
will be indicating quantitative scope and the progress achieved daily and the cumulative
progress in terms of quantity and percentage in addition to the planned quantity for each
activity.
The report will include the progress achieved in all disciplines in both pipeline and QP
refinery. This report will indicate the weather conditions.
4.3 Weekly Reports
The Weekly Progress Report (WPR) will be submitted covering all activities under each
phase during the entire duration of the contract.
The report will be generated on weekly basis with progress cut-off every Thursday. Hard and
soft copy of this report will be officially submitted to QP.
The contents of the WPR will be as per the Appendix D (Attachment 3 Clause 4.3).
4.4 Monthly Reports
The Monthly Progress Report (MPR) will be submitted during the entire duration of the
contract within 3 working days from the cut off date, Last weekly cut off-date in a calendar
month will be treated as monthly as agreed with QP.
The contents of the MPR will be as per the Appendix D (Attachment 3 Clause 4.6) .
4.5 Engineering Document Register
The Engineering Document Register (EDR) will be submitted as part of the planning
package.
Once approved it will be used as the main tool for monitoring the progress of the engineering
deliverables .
Updated engineering document register (EDR) will be submitted along with the weekly
progress report. The register will be updated on weekly basis with progress cut-off every
Thursday.
All deliverables will be listed and will be monitored as per agreed percentage weightings .
The register will serve as a tool in registering, planning, tracking, monitoring, expediting and
reporting the status of all engineering deliverables .

Page 9 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

4.6 Procurement Status Register


The Procurement Status Register (PSR) will be submitted as part of the planning package.
Once approved it will be used as the main tool for monitoring the progress of all items
related to the procurement phase .
Updated procurement status register (PSR) will be submitted along with the weekly progress
report. Two different sheets will be used for monitoring the long lead items and the Other
items .
The register will be updated on weekly basis with progress cut-off every Thursday .
The register will indicate the important milestone stage from receipt of material requisition
until the delivery of material at site . Agreed percentage weightings will be used throughout
the duration of the project to monitor each progress .
4.7 Subcontracting Status Register
Major subcontractors that will be mobilized for the entire project activities will be reported
accordingly . Subcontractor company profile will be submitted for QP approval prior to site
mobilization .
4.8 Construction Verification Sheet
The Construction Verification Sheet will be submitted at the end of the month as supporting
documents for the monthly invoice .
The progress will be reviewed and approved by disciplined QP representative .
This includes project activities, Man-hours for each activity , and Percentage weightings .
4.9 Project Close Out Report
Petrojet will prepare and submit the Project close out report in line with the requirements laid
down in the contract .
The report will be based on all the data accumulated throughout the course of the project
especially the lessons learnt and will be submitted to QP for future reference for upcoming
QP projects .
5.

Invoicing
The monthly invoice will be prepared and issued based on the following : Invoice will be submitted on monthly basis .
All the standard invoicing formats will be used .

Page 10 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

July 19,2012

PLANNING PACKAGE

The cut-off date of the monthly progress report will be used as the same cut-off date
for the invoicing .
Advanced copy of draft invoice will be submitted to QP by email prior to official
issuance .
The supported document for the monthly invoice will be the engineering document
register, Procurement different Documents and the approved construction verification
sheet .
The monthly progress payment will be submitted to QP thru an official letter .
6. Cost Control
The purpose of the Project Cost Control System is to provide the Project Manager with a
status of the Project with respect to the financial budget .
For this reason the cost control engineer will perform the following:
Coordinate change control program, as required and initiate change identification and
develop approximate cost impact to serve as decision making tool. Follow up with
more detailed estimate to meet Project and contractual requirements.
Maintain cost and commitment data to assist in forecasting.
Monitor Sub-contractors costs. Update forecast for each subcontract as variances are
identified through the change control program.
Prepare monthly cost control report.
7. Project Calendar
The Progress Review Meeting will be held on weekly basis on Monday .
The Weekly Progress Report will be submitted every Sunday .
The Monthly Progress Report will be submitted on the first Sunday of the month.
The Monthly Invoice for the achieved works will be submitted during the first week
of the month.
Achieve Mechanical Completion of Pipeline and all Facilities : (21) Months.
Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : (27) Months .
Scheduled Project Completion : (30) Months from the Effective Date

Page 11 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

PLANNING PACKAGE

8. References
Appendix A:

Scope of Work.

Appendix B:

Schedule of Prices

Appendix D:

Administration Instruction

Appendix F:

FEED Drawings & Documents

Appendix H:

Contract Execution Plan

Page 12 of 266

DATE

July 19,2012

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
WORK BREAK DOWN STRUCTURE
______________________________________

Page 13 of 266

EPIC For 16"-36 Km Jet A1 Fuel Pipeline From QP Refinery To BSV-3


Contract Number

Document Description

Date

Issued For

GC 11106200

Work Breakdown Structure

July 19,2012

Review & Approval

ETROJET

EPIC FOR 16" - 36 KM JET A1 FUEL PIPELINE


FROM QP REFINERY TO BSV-3

100.00%

ENGINEERING

PROCUREMENT

CONSTRUCTION

PRECOMMISSIONING &
COMMISSIONING

OPTIONAL

5.00%

40.00%

48.00%

5.00%

2.00%

GENERAL
=4.65%
PROCESS
=6.42%
LOSS PREVENTION
=1.44%
FIRE & GAS
=6.77%
PIPELINES
=8.55%
MECH/PIPING
=10.76%
INSTRUMENTATION
=10.36%
TELECOMMUNICATION =1.00%
ELECTRICAL
=16.88%
CIVIL & STRUCTURAL
=28.21%
BUILDING & SERVICES =2.26%
CATHODIC PROTECTION =2.70%
____________________________
TOTAL
=100%

LONG LEAD ITEMS

BULK MATERIALS

PIPELINE FROM QP
REFINERY TO BSV-3

QP REFINERY

BSV-3

77.25%

22.75%

47.75%

46.88%

5.37%

PIG LAUNCHER
=1.44%
EOT CRANE
=2.27%
JIB CRANE
=0.62%
MAINLINE PUMPS
=28.33%
BOOSTER PUMPS
=15.75%
SWITCHGEAR PANELS =12.11%
DISTRIBUTIONBOARDS =0.31%
UPS SYSTEM
=1.18%
CONTROL VALVE
=2.73%
ESD VALVE
=0.57%
ISOLATION VALVES
=0.47%
MOV
=5.49%
ALL OTHER VALVES
=2.85%
CORIOLLIS FLOWMETER =3.22%
JUNCTION BOXES
=1.29%
FIRE DETECTORS
=0.93%
SCADA
=16.79%
TELECOM EQUIPMENS =0.33%
LEAK DETECTION SYSTEM=3.31%
___________________________
TOTAL
=100%

PIPES & FITTINGS


=46.90%
INSULATION JOINTS
=0.95%
STUD BOLTS, NUTS
=0.36%
LOCAL CONTROL PANELS =0.95%
LIGTIING FIXTURES
=1.93%
ELECTRICAL CABLES
=4.85%
PRESSURE TRANSMITTERS=2.61%
TEMP. TRANSMITTERS =0.33%
INSTRUMENT CABLES
=15.20%
INST. CABLE ACCESSORI. =17.61%
CORROSION MONITORI =0.72%
TEMPORARY CP
=1.90%
PERMANENT CP
=5.70%
___________________________
TOTAL
=100%

STRAIGHT RUN
=63.85%
OPEN CUT CROSSING =8.43%
HDD CROSSING
=13.29%
CATHODIC PRPTECT. =4.22%
ANCHOR BLOCK
= 1.90%
HYDRAULIC TEST
=4.75%
COMMON ACTIVITIES=3.56%
________________________
TOTAL
= 100%

Page 14 of 266

CIVIL WORKS
=49.64%
MECH. WORKS
=34.38%
E&I WORKS
= 15.98%
________________________
TOTAL
= 100%

CIVIL WORKS
=25.71%
MECH. WORKS
=18.57%
E&I WORKS
= 55.72%
________________________
TOTAL
= 100%

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
INTEGRATED PLANNING NETWORK
______________________________________

Page 15 of 266

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

EPIC For 16" - 36 Km Jet A1 Fuel Pipeline


General
Milestones

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

781

26-Feb-12

25-Aug-14

18-Jan-12

25-Aug-14

651

26-Feb-12

25-Aug-14

18-Jan-12

25-Aug-14

911

26-Feb-12

25-Aug-14

26-Feb-12

25-Aug-14

26-Feb-12

GCM1100

Contract Effective Date

GCM1110

Milestone (1) : Achieve


Commissioning Of Pipeline And
All
FacilitiesCompletion Date
Scheduled

25-May-14

25-May-14

25-Aug-14

25-Aug-14

GCM1120

Essential Documents to be Issued

GED1100
GED1110
GED1120

26-Feb-12

Total
Float 2012

28-Mar-12

26-Aug-12

16-Apr-12

15-Sep-12

17

Project Management
Documents (PL. PKG.,HSE
Plan,PQP,Etc.)
Cost Break Down

90

28-Mar-12

14-Jul-12

16-Apr-12

01-Aug-12

17

20

20-May-12

13-Jun-12

09-Jun-12

02-Jul-12

17

Government and Other Legal


Authorities Permits to be Issued

75

29-May-12 26-Aug-12

17-Jun-12

15-Sep-12

17

110

04-Mar-12

05-Aug-12

18-Jan-12

09-Sep-12

26

04-Mar-12

07-Mar-12

18-Jan-12

24-Jan-12

-31

26-Apr-12

14-May-12

03-Jul-12

49

GMOB1100

Mobilization Of Key Personnel

GMOB1110

TCF To Be Established

36

07-Mar-12

GMOB1120

Mobilization For Labour &


Equipment

48

29-May-12 05-Aug-12

03-Jul-12

09-Sep-12

26

193

27-Mar-12

24-Jan-12

25-Aug-14

563

Engineering Phase

Actual Work

Critical Re...

Remaining Work

Milestone

06-Nov-12

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 16 of 266

2014

127

Mobilization

2013
J

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

General

EGN-1000

Original
Duration

Early Start

114

27-Mar-12

Early Finish

03-Sep-12

Late Start

24-Jan-12

Late Finish

02-Aug-12

27-Mar-12

EGN-1010

18

27-Mar-12

EGN-1080

Engineering Kick off Meeting

22-Apr-12

19-Feb-12

-45

EGN-1130

Design Review Meeting

03-Sep-12

02-Aug-12

-22

192

28-Mar-12

06-Nov-12

21-Feb-12

25-Aug-14

563

106

08-Apr-12

02-Sep-12

21-Feb-12

20-Nov-12

57

24-Apr-12

26-Apr-12

21-Feb-12

23-Feb-12

-45

Common

19-Apr-12

24-Jan-12

16-Feb-12

-45

Site Visits / Data Collection

EGN-1030

Site Visit Report

46

29-Apr-12

01-Jul-12

26-Feb-12

29-Apr-12

-45

EGN-1040

Design Basis Memorandum

73

16-Apr-12

25-Jul-12

15-Mar-12

25-Jun-12

-22

EGN-1050

FEED Design Review Report

76

08-Apr-12

22-Jul-12

07-Mar-12

20-Jun-12

-22

EGN-1110

Tie-in and Commissioning


Philosophy

42

05-Jul-12

02-Sep-12

23-Sep-12

20-Nov-12

57

86

29-May-12 25-Sep-12

29-May-12

25-Aug-14

499

67

29-May-12 29-Aug-12

29-May-12

25-Aug-14

518

54

29-May-12 12-Aug-12

29-May-12

12-Aug-12

Reports

EPR-1010 Steady State Hydraulic


Analysis/Report

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 17 of 266

2014

-45

EGN-1020

Process

2013
J

-22

Detailed Design Awarding to


Penspen
Penspen Team Mobilization

Detail Engineering

24-Jan-12

Total
Float 2012

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EPR-1020 Transient/Surge Analysis Report

50

10-Jun-12

16-Aug-12

15-Jul-12

20-Sep-12

25

EPR-1030 Operating Control and


Safeguarding Philosophy
EPR-1040 HAZOP & SIL Closeout Report

47

21-Jun-12

26-Aug-12

21-Aug-12

25-Oct-12

44

45

25-Jun-12

26-Aug-12

23-Jun-14

25-Aug-14

521

EPR-1080 Instrument air consumption


calculation

46

27-Jun-12

29-Aug-12

13-Sep-12

18-Nov-12

57

83

03-Jun-12

25-Sep-12

03-Jun-12

25-Aug-14

499

EPR-1100 Schematic Flow Diagrams

44

04-Jun-12

02-Aug-12

03-Jun-12

02-Aug-12

EPR-1110 PFDs

45

03-Jun-12

02-Aug-12

03-Jun-12

02-Aug-12

EPR-1120 P&IDs

13

04-Jun-12

20-Jun-12

03-Jun-12

20-Jun-12

EPR-1130 -- Review by Company

12

21-Jun-12

08-Jul-12

20-May-14

05-Jun-14

499

15-Aug-12

21-Aug-12

14-Jul-14

21-Jul-14

499

10

22-Aug-12

04-Sep-12

21-Jul-14

04-Aug-14

499

15

05-Sep-12

25-Sep-12

04-Aug-14

25-Aug-14

499

83

17-Jun-12

09-Oct-12

16-Aug-12

22-Nov-12

32

65

04-Jul-12

02-Oct-12

11-Sep-12

15-Nov-12

32

45

01-Aug-12

02-Oct-12

13-Sep-12

15-Nov-12

32

Process - Drawings

EPR-1140 -- Issue for HAZOP


EPR-1150 -- HAZOP Comments
Incorporated and re-issue
EPR-1160 -- Receive approval
Loss Prevention

Lists/Schedules/Reports

ELP-1000 Fire Protection and Safety


Philosophy

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 18 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

ELP-1010 Hazardous Area Schedule

45

25-Jul-12

25-Sep-12

11-Sep-12

13-Nov-12

35

ELP-1020 Safety Equipment List

47

04-Jul-12

06-Sep-12

11-Sep-12

15-Nov-12

50

68

17-Jun-12

18-Sep-12

16-Aug-12

20-Nov-12

45

ELP-1030 Specs- Fire Protection

51

17-Jun-12

26-Aug-12

16-Aug-12

28-Oct-12

45

ELP-1040 Specs - Safety Equipment

51

17-Jun-12

26-Aug-12

16-Aug-12

28-Oct-12

45

ELP-1050 Specs - Hydrants & Related


Accessories
ELP-1060 Specs/Data Sheet Deluge
System
ELP-1070 Specs - F&G Detection System

51

17-Jun-12

26-Aug-12

16-Aug-12

28-Oct-12

45

51

17-Jun-12

26-Aug-12

16-Aug-12

28-Oct-12

45

51

10-Jul-12

18-Sep-12

10-Sep-12

20-Nov-12

45

48

05-Aug-12

09-Oct-12

17-Sep-12

22-Nov-12

32

48

05-Aug-12

09-Oct-12

17-Sep-12

22-Nov-12

32

48

05-Aug-12

09-Oct-12

17-Sep-12

22-Nov-12

32

44

05-Aug-12

03-Oct-12

17-Sep-12

18-Nov-12

32

46

05-Aug-12

07-Oct-12

17-Sep-12

20-Nov-12

32

105

12-Jun-12

05-Nov-12

24-Jul-12

25-Aug-14

470

79

12-Jun-12

30-Sep-12

24-Jul-12

26-Dec-12

63

Specifications

Safety & Loss Prevention - Drawings

ELP-1090 Fire Protection and Safety


Equipment Layout - Pump
ELP-1100 House
Fire Protection and Safety
Equipment Layout - Pig
Launcher
Area
ELP-1130 Escape Evacuation
Route Pump House
ELP-1140 Escape Evacuation Route - Pig
Launcher Area
F&G Detection System

Specifications

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 19 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

47

12-Jun-12

15-Aug-12

24-Jul-12

27-Sep-12

31

48

03-Jul-12

06-Sep-12

27-Sep-12

04-Dec-12

63

41

05-Aug-12

30-Sep-12

30-Oct-12

26-Dec-12

63

41

05-Aug-12

30-Sep-12

30-Oct-12

26-Dec-12

63

70

14-Jun-12

19-Sep-12

26-Jul-12

17-Dec-12

63

EFG-1050 Flame Detectors

49

14-Jun-12

21-Aug-12

26-Jul-12

03-Oct-12

31

EFG-1060 Manual Call Points

49

14-Jun-12

21-Aug-12

26-Jul-12

03-Oct-12

31

EFG-1070 Smoke Detectors

49

14-Jun-12

21-Aug-12

26-Jul-12

03-Oct-12

31

EFG-1080 Heat Detectors

49

14-Jun-12

21-Aug-12

26-Jul-12

03-Oct-12

31

EFG-1090 HSSD system

44

22-Jul-12

19-Sep-12

16-Oct-12

17-Dec-12

63

EFG-1100 Hydrogen Detectors

49

14-Jun-12

21-Aug-12

26-Jul-12

03-Oct-12

31

EFG-1110 Beacons/Warning lights

49

14-Jun-12

21-Aug-12

12-Sep-12

20-Nov-12

65

EFG-1120 Horns

49

14-Jun-12

21-Aug-12

12-Sep-12

20-Nov-12

65

52

13-Jun-12

23-Aug-12

25-Jul-12

25-Aug-14

522

42

13-Jun-12

09-Aug-12

25-Jul-12

23-Sep-12

31

EFG-1020 Specification for F & G Devices


(Detectors & Alarm Devices)
EFG-1030 Specifications for F&G System (
Modfication)
EFG-1035 Specifications for FIRE
Supression System (
Modfication)
EFG-1040 Specifications for HSSD system
Data Sheets

Material Requisitions

EFG-1130 MRs for F&G Devices


(Detectors & Alarm Devices)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 20 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

42

27-Jun-12

23-Aug-12

23-Sep-12

20-Nov-12

63

42

27-Jun-12

23-Aug-12

26-Jun-14

25-Aug-14

522

42

27-Jun-12

23-Aug-12

23-Sep-12

20-Nov-12

63

77

22-Jul-12

05-Nov-12

05-Aug-12

25-Aug-14

470

59

15-Aug-12

05-Nov-12

12-Sep-12

20-Nov-12

11

EFG-1190F&G devices typical installation


details
EFG-1200F&G cable schedule

42

09-Sep-12

05-Nov-12

23-Sep-12

20-Nov-12

11

45

15-Aug-12

16-Oct-12

12-Sep-12

14-Nov-12

21

EFG-1210F&G JB schedule

45

21-Aug-12

22-Oct-12

18-Sep-12

20-Nov-12

21

62

22-Jul-12

15-Oct-12

05-Aug-12

25-Aug-14

485

EFG-1220F&G Cause and Effect

54

01-Aug-12

15-Oct-12

15-Aug-12

30-Oct-12

11

EFG-1230F&G I/O schedule

46

22-Jul-12

23-Sep-12

05-Aug-12

08-Oct-12

11

EFG-1240Cable Block Diagrams

46

22-Jul-12

23-Sep-12

19-Aug-12

22-Oct-12

21

EFG-1250F&G Interconnection &


Termination Diagrams
EFG-1260F & G Loop Diagrams

45

24-Jul-12

24-Sep-12

10-Jun-14

12-Aug-14

491

44

07-Aug-12

07-Oct-12

24-Jun-14

25-Aug-14

491

EFG-1270F & G Devices Layout


(Detectors & Alarm Devices)

43

30-Jul-12

26-Sep-12

22-Jun-14

20-Aug-14

495

EFG-1140 MRs for F&G System (


Modfication)
EFG-1145 MRs for FIRE Supression
System ( Modfication)
EFG-1150 MRs for HSSD system
Documents / Drawings

Common

QP Refinery

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 21 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

EFG-1280F&G Cable Routing Layout


Drawing
Pipelines

Reports

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

43

02-Aug-12

01-Oct-12

25-Jun-14

25-Aug-14

495

160

28-Mar-12

06-Nov-12

14-Mar-12

20-Nov-12

10

160

28-Mar-12

06-Nov-12

14-Mar-12

20-Nov-12

10

EGN-1090 Receive Survey Data

03-Jun-12

10-May-12

-15

EGN-1100 Design Issue for Construction

06-Nov-12

20-Nov-12

10

EGN-1120 Receipt of Soil Investigation


Report
EPL-1030 Pipeline Pigging Philosophy

19-Aug-12

09-Oct-12

37

50

21-Jun-12

29-Aug-12

11-Sep-12

20-Nov-12

59

EPL-1040 SOW - Topographical Survey

42

28-Mar-12

24-May-12

14-Mar-12

10-May-12

-10

56

09-May-12

25-Jul-12

30-Aug-12

18-Nov-12

82

EPL-1050 Pipeline Wall Thickness


Calculation
EPL-1060 Upheaval Buckling Calculations

36

09-May-12

27-Jun-12

30-Aug-12

21-Oct-12

82

51

16-May-12

25-Jul-12

06-Sep-12

18-Nov-12

82

EPL-1070 Elastic Bend Radius &


Combined Stress
EPL-1080 Pipeline Crossing Design Report

50

17-May-12

25-Jul-12

09-Sep-12

18-Nov-12

82

33

14-May-12

27-Jun-12

04-Sep-12

21-Oct-12

82

EPL-1090 Pipeline Anchor Force


Calculation

50

17-May-12

25-Jul-12

09-Sep-12

18-Nov-12

82

58

29-Apr-12

17-Jul-12

28-May-12

20-Nov-12

90

Calculation

Specifications

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 22 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

55

30-Apr-12

15-Jul-12

29-May-12

14-Aug-12

22

55

30-Apr-12

15-Jul-12

03-Jun-12

19-Aug-12

25

56

29-Apr-12

15-Jul-12

28-May-12

14-Aug-12

22

56

29-Apr-12

15-Jul-12

28-May-12

14-Aug-12

22

53

06-May-12

17-Jul-12

04-Jun-12

16-Aug-12

22

41

07-May-12

02-Jul-12

24-Sep-12

20-Nov-12

101

39

09-May-12

02-Jul-12

07-Jun-12

16-Aug-12

33

EPL-1200 Data Sheet for Hot Induction


Bends
EPL-1210 Data Sheet for Isolation Joints

39

09-May-12

02-Jul-12

07-Jun-12

01-Aug-12

22

27

09-May-12

14-Jun-12

07-Jun-12

16-Jul-12

22

EPL-1220 Data Sheet for Pipeline Barred


Tees
EPL-1230 Data sheet for Pipeline Anchor
Flanges

27

09-May-12

14-Jun-12

12-Jun-12

19-Jul-12

25

27

09-May-12

14-Jun-12

11-Jul-12

16-Aug-12

45

35

05-Jun-12

23-Jul-12

04-Jul-12

24-Sep-12

45

EPL-1000 MR for Isolation Joints

35

05-Jun-12

23-Jul-12

05-Aug-12

20-Sep-12

43

EPL-1010 MR for Pipeline Barred Tees

35

05-Jun-12

23-Jul-12

09-Jul-12

27-Aug-12

25

EPL-1020 MR for Pipeline Anchor Flanges

35

05-Jun-12

23-Jul-12

04-Jul-12

22-Aug-12

22

EPL-1110 Specifications for Electrical


Isolation Joints
EPL-1120 Specifications for Pipeline
Barred Tees
EPL-1130 Specifications for Hot Induction
Bends
EPL-1140 Specifications for Pipeline
Valves
EPL-1160 Specification for Pipeline fittings
and flanges
EPL-1170 Specification for Pig signaller
Data sheets

Material Requisitions

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 23 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

EPL-1100 MR for Pipeline Hot Bends

35

05-Jun-12

23-Jul-12

04-Jul-12

22-Aug-12

22

EPL-1150 MR for Coating of Fittings

35

05-Jun-12

23-Jul-12

04-Jul-12

22-Aug-12

22

EPL-1180 MR for Field Joint Coating

35

05-Jun-12

23-Jul-12

04-Jul-12

22-Aug-12

22

EPL-1190 MR for Pipeline


35
Flanges/Fittings/Gaskets/StudBolts
Drawings
76

05-Jun-12

23-Jul-12

07-Aug-12

24-Sep-12

45

10-Jun-12

23-Sep-12

09-May-12

23-Oct-12

22

EPL-1280 Pipeline Overall Route Map

46

12-Jun-12

15-Aug-12

13-May-12

15-Jul-12

-22

EPL-1290 Key Plan Pipeline Route Map

50

18-Jun-12

26-Aug-12

17-May-12

25-Jul-12

-22

EPL-1300 Pipeline Routing Plan

50

18-Jun-12

26-Aug-12

17-May-12

25-Jul-12

-22

EPL-1310 Keyplan Pipeline Alignment


Sheets
EPL-1320 Pipeline Alignment Sheets

44

03-Jul-12

02-Sep-12

03-Jun-12

01-Aug-12

-22

42

05-Jul-12

02-Sep-12

05-Jun-12

01-Aug-12

-22

EPL-1330 Pipeline Station Approach


Drawing - Block Sectionalizing
Valve
Station
(BSV3)
EPL-1340 Pipeline
Station
Approach
Drawing - QP Refinery
EPL-1350 Typical Details

45

23-Jul-12

23-Sep-12

21-Aug-12

23-Oct-12

22

44

10-Jul-12

09-Sep-12

22-Aug-12

23-Oct-12

32

52

10-Jun-12

20-Aug-12

09-May-12

19-Jul-12

-22

EPL-1370 Crossing Matrix - Roads & 3rd


Party Services

43

05-Jul-12

03-Sep-12

22-Jul-12

19-Sep-12

12

10

10-Jul-12

23-Jul-12

08-Aug-12

22-Aug-12

22

MTO

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 24 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

10

10-Jul-12

23-Jul-12

08-Aug-12

22-Aug-12

22

Mechanical / Piping

115

09-May-12

16-Oct-12

21-May-12

20-Nov-12

25

Specifications

58

24-May-12 13-Aug-12

24-May-12

19-Nov-12

70

EME-1000 Specs - Pumps

50

24-May-12 01-Aug-12

24-May-12

01-Aug-12

EME-1010 Specs - Pig Launcher

44

05-Jun-12

05-Aug-12

02-Jul-12

02-Sep-12

20

EME-1020 Spec for Surge Relief skid

44

07-Jun-12

07-Aug-12

18-Sep-12

19-Nov-12

74

EME-1110 Piping Material Specifications

52

03-Jun-12

13-Aug-12

03-Jun-12

13-Aug-12

EME-1120 Specs- Station CS Pipes

46

29-May-12

31-Jul-12

15-Jul-12

17-Sep-12

34

EME-1130 Specs- CS Fittings and Flanges

46

29-May-12

31-Jul-12

15-Jul-12

17-Sep-12

34

EME-1140 Specs- Nuts and Bolts

46

29-May-12

31-Jul-12

16-Jul-12

18-Sep-12

35

EME-1150 Specs-Gaskets

46

29-May-12

31-Jul-12

16-Jul-12

18-Sep-12

35

EME-1160 Specs - Gate Valves

46

29-May-12

31-Jul-12

14-Jun-12

19-Aug-12

13

EME-1170 Specs - Ball Valves

46

29-May-12

31-Jul-12

14-Jun-12

19-Aug-12

13

EME-1180 Specs - Globe Valves

46

29-May-12

31-Jul-12

14-Jun-12

19-Aug-12

13

EME-1190 Specs - Check Valves

46

29-May-12

31-Jul-12

01-Jul-12

03-Sep-12

24

EPL-1250 Pipeline Material Take-Off

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 25 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

93

03-Jun-12

09-Oct-12

10-Jun-12

20-Nov-12

30

EME-1030 Data sheet for EOT Crane

49

17-Jun-12

22-Aug-12

09-Aug-12

17-Oct-12

40

EME-1040 Data sheet for Surge relief skid

43

11-Jun-12

08-Aug-12

20-Sep-12

20-Nov-12

74

EME-1050 Datasheet for Main Transfer


Pumps
EME-1060 Datasheet for Booster Pumps

40

10-Jun-12

02-Aug-12

10-Jun-12

02-Aug-12

40

11-Jun-12

05-Aug-12

11-Jun-12

05-Aug-12

EME-1070 Datasheet for Pig Launcher with


Jib Crane
EME-1200 Data Sheet for Gate Valves

47

05-Jun-12

08-Aug-12

02-Jul-12

05-Sep-12

20

42

07-Jun-12

05-Aug-12

10-Jul-12

06-Sep-12

24

EME-1210 Data Sheet for Ball Valves

42

03-Jun-12

30-Jul-12

15-Jul-12

11-Sep-12

31

EME-1220 Data Sheet for Globe Valves

42

07-Jun-12

05-Aug-12

25-Jun-12

22-Aug-12

13

EME-1230 Data Sheet for Check Valves

42

07-Jun-12

05-Aug-12

10-Jul-12

06-Sep-12

24

EME-1240 Data Sheet for Strainers

42

07-Jun-12

05-Aug-12

16-Jul-12

12-Sep-12

28

EME-1250 Data Sheet for Special Items

44

09-Aug-12

09-Oct-12

17-Sep-12

18-Nov-12

28

109

14-May-12

11-Oct-12

21-May-12

20-Nov-12

28

EME-1520 MR for EOT Crane

45

21-May-12

22-Jul-12

15-Jul-12

16-Sep-12

40

EME-1530 MR for Surge relief skid

41

13-Jun-12

08-Aug-12

24-Sep-12

20-Nov-12

74

Data sheets

Technical Requisitions

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 26 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EME-1540 MR for Main Transfer Pumps

44

21-May-12

19-Jul-12

21-May-12

19-Jul-12

EME-1550 MR for Booster Pumps

44

21-May-12

19-Jul-12

21-May-12

19-Jul-12

EME-1560 MR for Pig Launcher with Jib


Crane
EME-1570 MR for Gate Valves

45

21-May-12

22-Jul-12

18-Jun-12

19-Aug-12

20

45

20-May-12

19-Jul-12

20-Jun-12

22-Aug-12

24

EME-1580 MR for Ball Valves

45

14-May-12

15-Jul-12

18-Sep-12

20-Nov-12

92

EME-1590 MR for Globe Valves

45

20-May-12

19-Jul-12

18-Sep-12

20-Nov-12

88

EME-1600 MR for Check Valves

45

20-May-12

19-Jul-12

20-Jun-12

22-Aug-12

24

EME-1610 MR for Strainers

45

20-May-12

19-Jul-12

18-Sep-12

20-Nov-12

88

EME-1620 MR for Special Items

44

13-Aug-12

11-Oct-12

19-Sep-12

20-Nov-12

28

EME-1630 MR for CS station Pipes, Fittings


& Flanges
EME-1640 MR for Bolts, Nuts and Gaskets

41

15-May-12

10-Jul-12

01-Jul-12

27-Aug-12

34

41

15-May-12

10-Jul-12

04-Jul-12

30-Aug-12

37

94

30-May-12

08-Oct-12

12-Jun-12

20-Nov-12

31

EME-1260 Line Schedule

44

10-Jul-12

09-Sep-12

06-Aug-12

07-Oct-12

20

EME-1270 Equipment Schedule

52

13-Jun-12

23-Aug-12

10-Jul-12

20-Sep-12

20

EME-1280 Valve Schedule

44

12-Jul-12

11-Sep-12

08-Aug-12

09-Oct-12

20

Piping Calculations/Schedules/Reports

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 27 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EME-1290 Tie-in Schedule

45

07-Jun-12

08-Aug-12

18-Sep-12

20-Nov-12

74

EME-1300 Pipe support Schedule

48

14-Jun-12

20-Aug-12

13-Sep-12

20-Nov-12

66

EME-1320 Stress Analysis Report System1


EME-1321 Stress Analysis Report System2
EME-1322 Stress Analysis Report System3
EME-1330 Pipe wall Thickness Calculation

44

08-Aug-12

08-Oct-12

04-Sep-12

05-Nov-12

20

44

08-Aug-12

08-Oct-12

04-Sep-12

05-Nov-12

20

44

08-Aug-12

08-Oct-12

04-Sep-12

05-Nov-12

20

54

30-May-12 13-Aug-12

12-Jun-12

27-Aug-12

10

EME-1331 Material Handling Study Report

51

28-Jun-12

06-Sep-12

10-Sep-12

20-Nov-12

53

115

09-May-12

16-Oct-12

23-May-12

20-Nov-12

25

EME-1335 Overall Plot Plan - QP Refinery

49

09-May-12

16-Jul-12

23-May-12

31-Jul-12

11

EME-1336 Overall Plot Plan BSV-3

49

09-May-12

16-Jul-12

23-May-12

31-Jul-12

11

EME-1340 Plot Plan - Jet A1 Pump House

49

09-May-12

16-Jul-12

09-Jul-12

16-Sep-12

44

EME-1350 Plot Plan - BSV-3

49

09-May-12

16-Jul-12

23-May-12

31-Jul-12

11

EME-1360 Plot Plan - Pig Launcher Area

51

14-Jun-12

23-Aug-12

28-Jun-12

09-Sep-12

11

EME-1410 Piping Key Plan QP Refinery

51

14-Jun-12

23-Aug-12

28-Jun-12

09-Sep-12

11

EME-1420 Piping GA Jet A1 Pumps areaQP Refinery

50

10-Jul-12

17-Sep-12

24-Jul-12

02-Oct-12

11

Drawings

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 28 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EME-1430 Piping GA Pig Launcher area QP Refinery


EME-1440 Piping GA BSV-3

50

10-Jul-12

17-Sep-12

13-Aug-12

22-Oct-12

25

52

05-Jul-12

16-Sep-12

05-Aug-12

16-Oct-12

22

EME-1450 Piping GA Unit 32 - QP Refinery


(Sector-31,32,39,40,41,42,20)
EME-1460 Piping GA Unit 32 - QP Refinery
(Demolition Sector 20)
EME-1470 Piping GA - Deluge Piping
System (1 to 4)
EME-1480 Isometrics for above ground
Piping
EME-1490 Isometrics for underground
piping
EME-1500 Standard Pipe Support Details

49

10-Jul-12

16-Sep-12

06-Aug-12

14-Oct-12

20

49

10-Jul-12

16-Sep-12

06-Aug-12

14-Oct-12

20

48

29-Jul-12

02-Oct-12

23-Aug-12

30-Oct-12

20

60

19-Jul-12

10-Oct-12

22-Aug-12

14-Nov-12

25

44

16-Aug-12

16-Oct-12

19-Sep-12

20-Nov-12

25

49

14-May-12

19-Jul-12

12-Sep-12

20-Nov-12

88

19-Jul-12

25-Jul-12

19-Aug-12

03-Sep-12

28

EME-1310 Piping Bulk MTO

19-Jul-12

25-Jul-12

27-Aug-12

03-Sep-12

28

EME-1510 Valve MTO

23-Jul-12

25-Jul-12

19-Aug-12

22-Aug-12

20

109

20-May-12

17-Oct-12

04-Jun-12

25-Aug-14

483

68

24-May-12 27-Aug-12

19-Jun-12

20-Dec-12

83

47

20-Jun-12

23-Aug-12

16-Jul-12

19-Sep-12

19

51

14-Jun-12

23-Aug-12

30-Jul-12

09-Oct-12

33

MTO

Instrumentation and Control

Specifications

EIN-1130
EIN-1140

Modification to PMS/UPS for


Data Transfer to DCS/SCADA
Specification for PLC/RTU
System @ BSV-3 for 16" Jet A1
Fuel P/L.

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 29 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

EIN-1230

Specification for Pressure


Gauges
Specification for Pressure & DP
Transmitters
Specification for Temperature
Gauges
Specification for Tempertaure
Element & Transmitters
Specification for ESD & On-Off
Valves
Specification for Electric Motor
Operated Valves
Specification for Mass Flow
Meter & Flow Computer
Specification for Safety Relief
Valves
Specification for Control Valves

47

20-Jun-12

23-Aug-12

01-Jul-12

04-Sep-12

EIN-1240

Specification for Pig Signallers

47

20-Jun-12

23-Aug-12

15-Jul-12

18-Sep-12

18

EIN-1250

47

20-Jun-12

23-Aug-12

12-Aug-12

16-Oct-12

38

48

24-May-12

30-Jul-12

19-Jun-12

26-Aug-12

19

48

24-May-12

30-Jul-12

19-Jun-12

26-Aug-12

19

EIN-1290

Specification for
Instrument,F&G,Control &
Telecommunication
Cables
Specifications for conditioning
monitoring system ( new UCP)
interface
( as per
Specifications
for design)
Leak
Detection System
Specification for DCS

47

06-Jun-12

09-Aug-12

05-Jul-12

10-Sep-12

22

EIN-1292

Specification for ESD

48

05-Jun-12

09-Aug-12

04-Jul-12

10-Sep-12

22

EIN-1150
EIN-1160
EIN-1170
EIN-1180
EIN-1190
EIN-1200
EIN-1210
EIN-1220

EIN-1270
EIN-1280

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 30 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

EIN-1295

Specification for SCADA-RTU

51

12-Jun-12

21-Aug-12

11-Jul-12

20-Sep-12

22

EIN-1300

Specification for Instrument /


Mech / Pneumatic hook ups and
Mech/Pneumatic
Bulk material
Specification for Electrical
hook
up and electrical bulk Material
(Junction boxes and cable

52

17-Jun-12

27-Aug-12

04-Oct-12

17-Dec-12

80

52

17-Jun-12

27-Aug-12

09-Oct-12

20-Dec-12

83

59

28-May-12 16-Aug-12

19-Jun-12

21-Oct-12

46

Data Sheet for Pressure & DP


Gauges
Data Sheet for Pressure & DP
Transmitters
Data Sheet for Temperature
Element & Transmitters
Data Sheet for Temperature
Gauges
Data Sheet for ESD Valves

47

28-May-12

31-Jul-12

12-Aug-12

16-Oct-12

55

47

28-May-12

31-Jul-12

15-Aug-12

21-Oct-12

58

47

28-May-12

31-Jul-12

12-Aug-12

16-Oct-12

55

47

28-May-12

31-Jul-12

12-Aug-12

16-Oct-12

55

38

10-Jun-12

31-Jul-12

05-Jul-12

28-Aug-12

20

50

10-Jun-12

16-Aug-12

25-Jun-12

03-Sep-12

12

50

10-Jun-12

16-Aug-12

01-Aug-12

10-Oct-12

39

50

10-Jun-12

16-Aug-12

19-Jun-12

28-Aug-12

EIN-1390

Data Sheet for Electric Moter


Operated Valves
Data Sheet for Mass Flow meter
& Flow Computer
Data Sheet for Safety Relief
Valves
Data Sheet for Pig Signallers

50

10-Jun-12

16-Aug-12

04-Jul-12

11-Sep-12

18

EIN-1400

Data Sheet for Control Valves

50

10-Jun-12

16-Aug-12

19-Jun-12

28-Aug-12

100

20-May-12

04-Oct-12

04-Jun-12

20-Nov-12

33

EIN-1305
Data Sheets

EIN-1310
EIN-1320
EIN-1330
EIN-1340
EIN-1350
EIN-1360
EIN-1370
EIN-1380

Material Requisitions

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 31 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

EIN-1680

MR for Pressure Gauges

42

24-May-12

22-Jul-12

08-Aug-12

07-Oct-12

55

EIN-1690

42

20-May-12

16-Jul-12

07-Aug-12

04-Oct-12

58

42

24-May-12

22-Jul-12

08-Aug-12

07-Oct-12

55

EIN-1710

MR for Pressure & DP


Transmitters
MR for Temperature Element &
Transmitters
MR for Temperature Gauges

42

24-May-12

22-Jul-12

08-Aug-12

07-Oct-12

55

EIN-1720

MR for ESD & On-Off Valves

42

24-May-12

22-Jul-12

04-Jun-12

01-Aug-12

EIN-1730

46

24-May-12

26-Jul-12

04-Jun-12

07-Aug-12

46

24-May-12

26-Jul-12

17-Jul-12

19-Sep-12

39

EIN-1750

MR for Electric Moter Operated


Valves
MR for Mass Flow meter & Flow
Computer
MR for Safety Relief Valves

46

24-May-12

26-Jul-12

24-Jun-12

27-Aug-12

22

EIN-1760

MR for Pig Signallers

46

22-May-12

24-Jul-12

17-Jun-12

19-Aug-12

18

EIN-1770

MR for Control Valves

46

24-May-12

26-Jul-12

24-Jun-12

27-Aug-12

22

EIN-1780

39

24-May-12

17-Jul-12

16-Jul-12

09-Sep-12

38

46

02-Aug-12

04-Oct-12

17-Sep-12

20-Nov-12

33

46

24-May-12

26-Jul-12

17-Sep-12

20-Nov-12

83

EIN-1800

MR for Instrument,F&G,Control
& Telecommunication Cables
MR for Instrument / Mech /
Pneumatic hook ups and
Mech/Pneumatic
Bulk up
material
MR for Electrical hook
and
electrical bulk Material (Junction
boxes
glandsSystem
MR forand
Leakcable
Detection

46

24-May-12

26-Jul-12

19-Jun-12

22-Aug-12

19

EIN-1810

MR for DCS

46

24-May-12

26-Jul-12

24-Jun-12

27-Aug-12

22

EIN-1700

EIN-1740

EIN-1790
EIN-1795

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 32 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

EIN-1820

MR for ESD

46

24-May-12

26-Jul-12

24-Jun-12

27-Aug-12

22

EIN-1825

MR for SCADA-RTU

46

24-May-12

26-Jul-12

24-Jun-12

27-Aug-12

22

46

24-May-12

26-Jul-12

09-Jul-12

11-Sep-12

33

46

24-May-12

26-Jul-12

09-Jul-12

11-Sep-12

33

91

13-Jun-12

17-Oct-12

02-Aug-12

25-Aug-14

483

71

01-Jul-12

07-Oct-12

02-Aug-12

22-Nov-12

34

EIN-1510 Instrument process hook-up


Diagrams
EIN-1520 Instrument Installation details

43

18-Jul-12

16-Sep-12

17-Sep-12

15-Nov-12

44

43

23-Jul-12

19-Sep-12

20-Sep-12

20-Nov-12

44

EIN-1530 Interface Block Diagrams

42

09-Aug-12

07-Oct-12

24-Sep-12

21-Nov-12

33

EIN-1540 Instrument Cable schedule

44

24-Jul-12

23-Sep-12

10-Sep-12

11-Nov-12

35

EIN-1550 Instrument JB Schedule

45

30-Jul-12

30-Sep-12

16-Sep-12

18-Nov-12

35

EIN-1555 JB Connection Diagram

45

05-Aug-12

04-Oct-12

20-Sep-12

22-Nov-12

35

EIN-1560 Instrument and Instrument


signal earthing
EIN-1570 Instrument Bulk MTO

43

05-Aug-12

02-Oct-12

20-Sep-12

20-Nov-12

35

30-Jul-12

01-Aug-12

12-Sep-12

17-Sep-12

33

EIN-1580 Overall Control System


Architecture Diagram
(Modification)

46

01-Jul-12

02-Sep-12

02-Aug-12

07-Oct-12

25

EIN-1830

MR for Modification to
PMS/UPS for Data Transfer to
DCS/SCADA
EIN-1840 MR for PLC/RTU System at
BSV-3 for 16" Jet A1 Fuel
Pipeline
Documents / Drawings
Common

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 33 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

91

13-Jun-12

17-Oct-12

13-Aug-12

17-Aug-14

477

EIN-1850 Cause and Effect Diagrams (As


per SOW)
EIN-1860 Alarm & Trip Schedule

52

13-Jun-12

23-Aug-12

13-Aug-12

24-Oct-12

44

48

18-Jul-12

23-Sep-12

02-Oct-12

09-Dec-12

55

EIN-1870 Instrument Schedule

49

26-Jun-12

02-Sep-12

22-Aug-12

30-Oct-12

42

EIN-1875 I/O Schedule DCS

52

01-Jul-12

10-Sep-12

27-Aug-12

07-Nov-12

42

EIN-1878 I/O Schedule ESD

48

18-Jul-12

23-Sep-12

13-Sep-12

20-Nov-12

42

EIN-1880 I/O Schedule SCADA-RTU

44

23-Jul-12

20-Sep-12

07-Oct-12

06-Dec-12

55

EIN-1890 Instrumentation Cable Block


Diagrams
EIN-1900 Instrument Interconnection
Wiring Diagram
EIN-1910 Instrument Loop Diagrams

44

23-Jul-12

20-Sep-12

05-Sep-12

06-Nov-12

33

42

16-Aug-12

14-Oct-12

01-Oct-12

28-Nov-12

33

43

15-Aug-12

14-Oct-12

30-Sep-12

28-Nov-12

33

EIN-1920 Instrument Location Layout

43

24-Jul-12

20-Sep-12

17-Jun-14

17-Aug-14

496

EIN-1930 Instrument Cable Routing/Cable


tray Layouts
EIN-1940 Instrument Equipment Room
Layouts (Modification Scope)

43

20-Aug-12

17-Oct-12

03-Oct-12

03-Dec-12

33

43

20-Aug-12

17-Oct-12

23-Sep-12

21-Nov-12

25

90

13-Jun-12

16-Oct-12

23-Aug-12

25-Aug-14

484

44

13-Jun-12

13-Aug-12

23-Aug-12

24-Oct-12

52

QP Refinery

BSV-3

EIN-2050 Cause and Effect Diagrams (As


per SOW)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 34 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EIN-2060 Alarm & Trip Schedule

47

18-Jul-12

20-Sep-12

02-Oct-12

06-Dec-12

55

EIN-2070 Instrument Schedule

49

24-Jun-12

29-Aug-12

19-Sep-12

27-Nov-12

64

EIN-2075 I/O Schedule DCS

44

24-Jun-12

22-Aug-12

19-Sep-12

20-Nov-12

64

EIN-2078 I/O Schedule ESD

44

24-Jun-12

22-Aug-12

19-Sep-12

20-Nov-12

64

EIN-2080 I/O Schedule SCADA-RTU

43

23-Jul-12

19-Sep-12

11-Oct-12

11-Dec-12

59

EIN-2090 Instrumentation Cable Block


Diagrams
EIN-2100 Instrument Interconnection
Wiring Diagram
EIN-2110 Instrument Loop Diagrams

43

23-Jul-12

19-Sep-12

10-Sep-12

08-Nov-12

36

43

30-Jul-12

26-Sep-12

01-Oct-12

29-Nov-12

46

43

01-Aug-12

30-Sep-12

25-Oct-12

25-Dec-12

62

EIN-2120 Instrument Location Layout

43

09-Aug-12

08-Oct-12

25-Jun-14

25-Aug-14

490

EIN-2130 Instrument Cable Routing/Cable


tray Layouts
EIN-2140 Instrument Equipment Room
Layouts (Modification Scope)

42

20-Aug-12

16-Oct-12

04-Oct-12

03-Dec-12

34

42

20-Aug-12

16-Oct-12

23-Sep-12

20-Nov-12

25

86

03-Jun-12

30-Sep-12

04-Jul-12

25-Aug-14

496

45

15-Jul-12

13-Sep-12

14-Aug-12

25-Aug-14

507

45

15-Jul-12

13-Sep-12

14-Aug-12

16-Oct-12

23

45

15-Jul-12

13-Sep-12

14-Aug-12

16-Oct-12

23

Telecom

Specification

ETL-1010 Specifications for Existing


TELECOM systems
modifications
ETL-1020 Specifications for Existing
PA/GA systems modifications

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 35 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

45

15-Jul-12

13-Sep-12

23-Jun-14

25-Aug-14

507

42

03-Jun-12

30-Jul-12

04-Jul-12

30-Aug-12

23

42

03-Jun-12

30-Jul-12

04-Jul-12

30-Aug-12

23

42

03-Jun-12

30-Jul-12

04-Jul-12

30-Aug-12

23

46

29-Jul-12

30-Sep-12

17-Sep-12

20-Nov-12

37

43

29-Jul-12

25-Sep-12

17-Sep-12

15-Nov-12

37

43

01-Aug-12

30-Sep-12

20-Sep-12

20-Nov-12

37

127

08-May-12

02-Oct-12

23-May-12

25-Aug-14

593

Specifications

73

10-May-12 20-Aug-12

23-May-12

24-Sep-12

25

Common

44

15-May-12

15-Jul-12

28-May-12

09-Sep-12

40

EEL-1000Specification for Electrical Bulk


Materials
EEL-1120Specification for Distribution
Boards
EEL-1530Specification for Electrical
Power, Control & Earthing
Cables
QP Refinery

44

15-May-12

15-Jul-12

28-May-12

26-Jul-12

44

15-May-12

15-Jul-12

01-Jul-12

29-Aug-12

33

44

15-May-12

15-Jul-12

09-Jul-12

09-Sep-12

40

67

10-May-12 12-Aug-12

23-May-12

23-Aug-12

EEL-1540Specification for 11KV & 3.3KV


Switchboard Modifications

50

15-May-12

28-May-12

05-Aug-12

ETL-1100 Specifications for BMS ,Acess


control System and CCTV
Material Requisitions

ETL-1000 MRs for Existing TELECOM


systems/Network modifications
ETL-1070 MRs for Existing PA/GA
systems modifications
Drawing/Matrix

ETL-1030 Overall TELECOM system cable


block diagram
ETL-1040 BSV-3 PA/GA (Telephone)
system modification
Electrical

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

23-Jul-12

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 36 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EEL-1550Specification for 415V


Switchboard Modifications
EEL-1570Specification for Interposing
relay panel
EEL-1580Specification for 110V AC UPS

42

14-Jun-12

12-Aug-12

26-Jun-12

23-Aug-12

42

14-Jun-12

12-Aug-12

26-Jun-12

23-Aug-12

41

10-May-12

05-Jul-12

23-May-12

18-Jul-12

EEL-1590Specification for HV Motors

41

13-May-12

08-Jul-12

24-May-12

19-Jul-12

43

21-Jun-12

20-Aug-12

25-Jul-12

24-Sep-12

25

43

21-Jun-12

20-Aug-12

25-Jul-12

24-Sep-12

25

43

21-Jun-12

20-Aug-12

25-Jul-12

24-Sep-12

25

84

08-May-12 13-Aug-12

10-Jun-12

20-Nov-12

85

42

21-May-12

17-Jul-12

05-Jul-12

20-Nov-12

90

42

21-May-12

17-Jul-12

23-Sep-12

20-Nov-12

90

42

21-May-12

17-Jul-12

05-Jul-12

02-Sep-12

33

70

08-May-12 13-Aug-12

10-Jun-12

19-Sep-12

27

45

15-May-12

16-Jul-12

08-Jul-12

06-Sep-12

38

43

14-Jun-12

13-Aug-12

23-Jul-12

19-Sep-12

27

43

13-May-12

10-Jul-12

10-Jun-12

08-Aug-12

21

BSV-3

Option-1

EEL-1600
Specification for 415V
Switchboard modificaion
(Option-1
Kahrama connection)
Data Sheets
Common

EEL-1080Data Sheet for Power, Control


and Earthing Cable
EEL-1110Data Sheet for Distribution
Boards
QP Refinery

EEL-1070Data Sheet for 11 & 3.3 KV


Switchgear Modification
EEL-1630Data Sheet for 415V
Switchboard Modifications
EEL-1640Data Sheet for 110V AC UPS

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 37 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EEL-1650Data Sheet for 11KV Motors

43

08-May-12

05-Jul-12

23-Jul-12

19-Sep-12

54

EEL-1660Data Sheet for 3.3KV Motors

43

08-May-12

05-Jul-12

10-Jul-12

06-Sep-12

45

BSV-3

Early Finish

Late Start

Late Finish

Material Requisitions

Common

EEL-1700MR for Distribution Boards


QP Refinery

EEL-1710MR for 11KV, 3.3KV & 415V


Switchboard Modifications
EEL-1720MR for 110V AC UPS
BSV-3

Option-1

EEL-1730
MR for 415V Switchboard
modificaion (Option-1 Kahrama
connection)
EEL-1920
MR for 415V Switchboard
modificaion (Substation 6003)
Calculations/Reports

QP Refinery

Actual Work

Critical Re...

Remaining Work

Milestone

Total
Float 2012

2013
J

2014

71

16-May-12 22-Aug-12

13-Jun-12

25-Aug-14

523

44

23-May-12

23-Jul-12

09-Jul-12

06-Sep-12

33

44

23-May-12

23-Jul-12

09-Jul-12

06-Sep-12

33

48

16-May-12

22-Jul-12

13-Jun-12

28-Aug-12

27

44

22-May-12

22-Jul-12

28-Jun-12

28-Aug-12

27

44

16-May-12

16-Jul-12

13-Jun-12

14-Aug-12

21

42

26-Jun-12

22-Aug-12

23-Sep-12

25-Aug-14

523

42

26-Jun-12

22-Aug-12

23-Sep-12

25-Aug-14

523

42

26-Jun-12

22-Aug-12

23-Sep-12

20-Nov-12

64

42

26-Jun-12

22-Aug-12

26-Jun-14

25-Aug-14

523

97

15-May-12 26-Sep-12

15-Jul-12

22-Jan-13

84

97

15-May-12 26-Sep-12

23-Aug-12

22-Jan-13

84

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 38 of 266

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EEL-1010Cable Sizing

43

26-Jun-12

23-Aug-12

23-Aug-12

22-Oct-12

42

EEL-1030Lighting Calculations

43

22-Jul-12

18-Sep-12

16-Sep-12

14-Nov-12

41

EEL-1040UPS/Battery Sizing Calculations

43

15-May-12

12-Jul-12

09-Sep-12

07-Nov-12

84

EEL-1050Power system study

43

30-Jul-12

26-Sep-12

22-Nov-12

22-Jan-13

84

EEL-1060Protection co-ordination study

49

20-May-12

25-Jul-12

12-Sep-12

20-Nov-12

84

58

12-Jun-12

30-Aug-12

15-Jul-12

16-Oct-12

33

EEL-1760Cable Sizing Calculation

45

12-Jun-12

13-Aug-12

15-Jul-12

13-Sep-12

23

EEL-1770Lighting Calculation

44

02-Jul-12

30-Aug-12

15-Aug-12

16-Oct-12

33

04-Jul-12

20-Nov-12

47

BSV-3

Early Finish

Late Start

Late Finish

Total
Float 2012

Lists/Schedules

82

24-May-12 16-Sep-12

QP Refinery

52

27-Jun-12

06-Sep-12

12-Aug-12

20-Nov-12

53

EEL-1125Electrical load list

43

27-Jun-12

26-Aug-12

12-Aug-12

10-Oct-12

33

EEL-1130Electrical Equipment List

44

02-Jul-12

30-Aug-12

15-Aug-12

16-Oct-12

33

EEL-1140Electrical Cable Schedule

45

08-Jul-12

06-Sep-12

29-Aug-12

30-Oct-12

38

25-Jul-12

31-Jul-12

29-Aug-12

04-Sep-12

25

44

02-Jul-12

30-Aug-12

23-Aug-12

23-Oct-12

38

EEL-1150Electrical Bulk MTO


EEL-1160Electrical Tie-in Schedule

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 39 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

EEL-1190DB Schedules

Original
Duration

Early Start

45

08-Jul-12

Early Finish

Late Start

Late Finish

Total
Float 2012

06-Sep-12

18-Sep-12

20-Nov-12

53

82

24-May-12 16-Sep-12

04-Jul-12

20-Nov-12

47

EEL-1780Electrical load list

44

24-May-12

24-Jul-12

04-Jul-12

03-Sep-12

29

EEL-1790Electrical Equipment List

45

19-Jun-12

20-Aug-12

18-Sep-12

20-Nov-12

66

EEL-1800Electrical Cable Schedule

45

16-Jul-12

16-Sep-12

26-Aug-12

25-Oct-12

29

23-Jul-12

29-Jul-12

02-Sep-12

06-Sep-12

29

EEL-1820Electrical Tie-in Schedule

45

17-Jun-12

16-Aug-12

26-Jul-12

26-Sep-12

29

EEL-1830DB Schedules

45

24-Jun-12

23-Aug-12

18-Sep-12

20-Nov-12

63

101

15-May-12

02-Oct-12

18-Jul-12

03-Dec-12

44

EEL-1290 Typical Installation Details

46

21-Jun-12

23-Aug-12

19-Jul-12

20-Sep-12

20

SLD

98

15-May-12 27-Sep-12

18-Jul-12

03-Dec-12

47

98

15-May-12 27-Sep-12

18-Jul-12

03-Dec-12

47

BSV-3

EEL-1810Electrical Bulk MTO

Drawings/Layouts

QP Refinery

EEL-1200
11KV SLD

43

23-Jul-12

19-Sep-12

25-Sep-12

25-Nov-12

47

EEL-1210
3.3KV SLD

43

26-Jul-12

24-Sep-12

30-Sep-12

28-Nov-12

47

EEL-1220
415V SLD

43

31-Jul-12

27-Sep-12

03-Oct-12

03-Dec-12

47

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 40 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EEL-1230
110V AC UPS SLD

49

15-May-12

22-Jul-12

18-Jul-12

25-Sep-12

47

EEL-1240
MOV DB SLD-Pump House

45

28-May-12

29-Jul-12

31-Jul-12

02-Oct-12

47

EEL-1250
LPN SLD modification- SER 12
Extension
EEL-1260
MOV DB-Pig Launcher area

43

10-Jul-12

06-Sep-12

12-Sep-12

12-Nov-12

47

45

03-Jun-12

02-Aug-12

06-Aug-12

08-Oct-12

47

EEL-1270
LPN - Pig Launcher area

43

15-Jul-12

11-Sep-12

17-Sep-12

15-Nov-12

47

EEL-1280
LPN SLD - Pump house

43

18-Jul-12

16-Sep-12

20-Sep-12

20-Nov-12

47

46

05-Jul-12

06-Sep-12

11-Sep-12

20-Nov-12

53

EEL-1840
415V SLD

46

05-Jul-12

06-Sep-12

11-Sep-12

14-Nov-12

49

EEL-1850
LPN SLD - Plant area

46

05-Jul-12

06-Sep-12

17-Sep-12

20-Nov-12

53

44

15-Jul-12

12-Sep-12

19-Sep-12

20-Nov-12

49

44

15-Jul-12

12-Sep-12

19-Sep-12

20-Nov-12

49

73

21-Jun-12

01-Oct-12

24-Jul-12

20-Nov-12

36

71

25-Jun-12

01-Oct-12

09-Aug-12

20-Nov-12

36

46

24-Jul-12

25-Sep-12

28-Aug-12

30-Oct-12

25

44

24-Jul-12

23-Sep-12

30-Aug-12

30-Oct-12

27

BSV-3

Station-T1

EEL-1870
DB SLD modification
Layouts

QP Refinery

EEL-1300
Cable Routing Layout - Pump
House/SS/SER-12
EEL-1310
Cable Routing Layout - Pig
Launcher area

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 41 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

EEL-1320
Earthing Layout - Plump
House/SS/SER-12
EEL-1330
Earthing Layout - Pig Launcher
area
EEL-1340
Lighting Layout - Pump House

44

01-Aug-12

01-Oct-12

19-Sep-12

20-Nov-12

36

44

30-Jul-12

27-Sep-12

19-Sep-12

20-Nov-12

38

44

25-Jul-12

24-Sep-12

19-Sep-12

20-Nov-12

41

EEL-1350
Lighting Layout - Pig Launcher
area
EEL-1360
Lighting Layout-SER 12
Extension
EEL-1370
Lightning Protection
Layout-SER 12 Extension
EEL-1380
Equipment Layout
modification-S/S 6003
EEL-1390
Equipment Layout-SER 12
Extension

44

25-Jul-12

24-Sep-12

19-Sep-12

20-Nov-12

41

44

25-Jul-12

24-Sep-12

19-Sep-12

20-Nov-12

41

44

08-Jul-12

05-Sep-12

19-Sep-12

20-Nov-12

54

45

15-Jul-12

13-Sep-12

12-Sep-12

14-Nov-12

44

45

25-Jun-12

26-Aug-12

09-Aug-12

11-Oct-12

34

52

04-Jul-12

13-Sep-12

15-Aug-12

31-Oct-12

34

EEL-1400
Cable Routing Layout

44

15-Jul-12

12-Sep-12

15-Aug-12

15-Oct-12

23

EEL-1410
Earthing Layout

45

15-Jul-12

13-Sep-12

29-Aug-12

31-Oct-12

34

EEL-1420
Lighting Layout

42

04-Jul-12

30-Aug-12

20-Aug-12

17-Oct-12

34

43

21-Jun-12

20-Aug-12

24-Jul-12

20-Sep-12

23

43

21-Jun-12

20-Aug-12

24-Jul-12

20-Sep-12

23

45

01-Aug-12

02-Oct-12

18-Sep-12

20-Nov-12

35

BSV-3

Station-T1

EEL-1445
Cable Routing Layout (Station
T1)
Area classification drawings

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 42 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

45

01-Aug-12

02-Oct-12

18-Sep-12

20-Nov-12

35

44

01-Aug-12

01-Oct-12

19-Sep-12

20-Nov-12

36

44

22-Jul-12

19-Sep-12

19-Sep-12

20-Nov-12

44

44

22-Jul-12

19-Sep-12

19-Sep-12

20-Nov-12

44

Civil and Sructural

192

28-Mar-12

06-Nov-12

17-May-12

27-Dec-12

44

Specifications

52

06-May-12

16-Jul-12

03-Jun-12

14-Aug-12

21

Specifications for Structural


Steel
Specifications for Fencing

42

06-May-12

02-Jul-12

03-Jun-12

31-Jul-12

21

44

08-May-12

08-Jul-12

05-Jun-12

06-Aug-12

21

Specifications for Concrete


Works
Specifications for Earth works

44

08-May-12

08-Jul-12

05-Jun-12

06-Aug-12

21

44

08-May-12

08-Jul-12

05-Jun-12

06-Aug-12

21

Specificaitons for Building &


Architectural Works
Specifications for Road and
Paving Works

44

16-May-12

16-Jul-12

13-Jun-12

14-Aug-12

21

44

16-May-12

16-Jul-12

13-Jun-12

14-Aug-12

21

43

28-Mar-12

27-May-12

17-May-12

17-Jul-12

37

43

28-Mar-12

27-May-12

17-May-12

17-Jul-12

37

102

27-May-12

15-Oct-12

11-Jun-12

20-Nov-12

26

EEL-1880Hazardous Area Classifications QP Refinery


EEL-1890Hazardous Area Classifications BSV-3
Protection & Control Schematics

EEL-1910Scheme for HV motors

ECI-1000
ECI-1010
ECI-1020
ECI-1030
ECI-1040
ECI-1050
Scope of Work

ECI-1140

Scope Of Work For


Geotechnical Investigation

Typical Details / Calculations

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 43 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

43

27-May-12

24-Jul-12

11-Jun-12

09-Aug-12

12

86

05-Jun-12

02-Oct-12

20-Jun-12

18-Oct-12

12

43

17-Jul-12

13-Sep-12

01-Aug-12

01-Oct-12

12

46

13-Aug-12

15-Oct-12

17-Sep-12

20-Nov-12

26

44

19-Jun-12

19-Aug-12

27-Aug-12

25-Oct-12

49

46

02-Jul-12

03-Sep-12

09-Sep-12

11-Nov-12

49

44

31-May-12

31-Jul-12

30-Jul-12

30-Sep-12

43

45

02-Jul-12

02-Sep-12

29-Aug-12

31-Oct-12

43

46

01-Jul-12

02-Sep-12

17-Sep-12

20-Nov-12

57

104

09-Jul-12

06-Nov-12

02-Aug-12

27-Dec-12

44

87

09-Jul-12

06-Nov-12

02-Aug-12

27-Dec-12

37

ECI-1180 Civil GA - Pump Area

47

21-Aug-12

24-Oct-12

05-Sep-12

11-Nov-12

12

ECI-1190 Civil GA - Pig Launcher Area

47

20-Aug-12

23-Oct-12

24-Oct-12

27-Dec-12

47

ECI-1200 Civil GA - Pipe Supports


Location Plan
ECI-1210 Pipe Supports - Sleepers

47

21-Aug-12

24-Oct-12

17-Sep-12

21-Nov-12

20

47

09-Jul-12

11-Sep-12

05-Sep-12

11-Nov-12

43

ECI-1080
ECI-1090
ECI-1095
ECI-1096
ECI-1110
ECI-1120
ECI-1130
ECI-1150
ECI-1160

General Notes, Abbreviations &


Symbols
Typical & Standard Detail
Drawings
Typical Steel Platform Layout &
Details
Structural Calculation For Steel
Platform
Typical Structural Calculation
For Light Pole Foundation
Typical Structural Calculation
For Anchor Block
Typical Structural Calculation
For Concrete Protection Slab
Typical Structural Calculation
For Pipeline Sleeper
Typical Structural Calculation
For Culverts

Drawings & Calculations

QP Refinery

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 44 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

ECI-1220 Pipe Supports - T Posts

47

09-Jul-12

11-Sep-12

10-Sep-12

14-Nov-12

46

ECI-1230 Pipe Supports - Portal Supports

45

14-Aug-12

15-Oct-12

10-Sep-12

12-Nov-12

20

ECI-1240 Pipe Rack Details

45

22-Aug-12

23-Oct-12

18-Sep-12

20-Nov-12

20

ECI-1250 Pipe Rack Foundation Details

45

22-Aug-12

23-Oct-12

18-Sep-12

20-Nov-12

20

ECI-1260 Pig Launcher Foundation


Details
ECI-1270 Pig Trap & Jib Crane
Foundation Details
ECI-1280 Impact Wall Details

44

13-Aug-12

11-Oct-12

13-Sep-12

14-Nov-12

24

44

13-Aug-12

11-Oct-12

13-Sep-12

14-Nov-12

24

44

19-Aug-12

17-Oct-12

19-Sep-12

20-Nov-12

24

ECI-1290 Pump Shed - Architectural


Details
ECI-1300 Pump Shed - Structural Details

72

22-Jul-12

29-Oct-12

02-Aug-12

12-Nov-12

10

78

22-Jul-12

06-Nov-12

02-Aug-12

20-Nov-12

10

ECI-1310 Structural Calculation For Pipe


Supports
ECI-1320 Calculation For French Drain Refinery Area
ECI-1380 SER12 - Demolition Details

44

14-Aug-12

14-Oct-12

10-Sep-12

11-Nov-12

20

46

31-Jul-12

02-Oct-12

17-Sep-12

20-Nov-12

35

48

10-Jul-12

13-Sep-12

26-Aug-12

31-Oct-12

34

ECI-1390 SER12 - Architectural Details

48

10-Jul-12

13-Sep-12

26-Aug-12

31-Oct-12

34

ECI-1400 SER12 - Foundation Details

44

22-Jul-12

19-Sep-12

03-Oct-12

04-Dec-12

54

ECI-1410 SER12 - Structural Details

44

22-Jul-12

19-Sep-12

03-Oct-12

04-Dec-12

54

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 45 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

54

17-Jul-12

30-Sep-12

13-Sep-12

20-Dec-12

59

ECI-1330 Civil GA (BSV-3)

44

23-Jul-12

20-Sep-12

19-Sep-12

20-Nov-12

43

ECI-1360 Pipe Supports - Sleepers


(BSV-3)
ECI-1370 Pipe Supports - T Posts (BSV-3)

44

17-Jul-12

16-Sep-12

13-Sep-12

14-Nov-12

43

44

23-Jul-12

20-Sep-12

19-Sep-12

20-Nov-12

43

ECI-1470 Structural Calculation For Pipe


supports

47

26-Jul-12

30-Sep-12

17-Oct-12

20-Dec-12

59

50

08-Aug-12

16-Oct-12

11-Sep-12

20-Nov-12

25

45

08-Aug-12

09-Oct-12

11-Sep-12

13-Nov-12

25

45

15-Aug-12

16-Oct-12

18-Sep-12

20-Nov-12

25

BSV-3

Elevated Transformer near BSV-3 (Option-1)

ECI-1480 Foundation Details of


Transformer
ECI-1490 Calculations For Foundation
Details of Transformer
Kahramaa Substation near BSV-3 (Option-2)

Early Finish

Late Start

Late Finish

Total
Float 2012

78

12-Jun-12

27-Sep-12

25-Jul-12

20-Nov-12

38

Specification

42

18-Jun-12

14-Aug-12

25-Jul-12

23-Sep-12

28

42

18-Jun-12

14-Aug-12

25-Jul-12

23-Sep-12

28

40

20-Jun-12

14-Aug-12

29-Jul-12

23-Sep-12

28

40

20-Jun-12

14-Aug-12

29-Jul-12

23-Sep-12

28

44

12-Jun-12

12-Aug-12

02-Aug-12

03-Oct-12

38

Material Requisition

EBS-1100 MR for HVAC Equipments for


SER-12 Building Extension
Calculation

Actual Work

Critical Re...

Remaining Work

Milestone

2014

Building Services

EBS-1000 Building Services Specification

2013
J

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 46 of 266

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

44

12-Jun-12

12-Aug-12

02-Aug-12

03-Oct-12

38

74

18-Jun-12

27-Sep-12

08-Aug-12

20-Nov-12

38

EBS-1020 SER-12 Building Extension


HVAC Layout
EBS-1030 SER-12 Building Extension
HVAC Section and
Miscellaneous
Details
EBS-1040 SER-12 Building
Extension
HVAC Schematic and Control
Diagram
EBS-1050 Flow
SER-12
Building Extension
Water Supply and Drainage
EBS-1060 Layout
Plumbing Notes and Symbols

44

18-Jun-12

16-Aug-12

08-Aug-12

09-Oct-12

38

44

18-Jun-12

16-Aug-12

08-Aug-12

09-Oct-12

38

44

18-Jun-12

16-Aug-12

08-Aug-12

09-Oct-12

38

42

24-Jun-12

20-Aug-12

14-Aug-12

11-Oct-12

38

41

30-Jul-12

24-Sep-12

19-Sep-12

15-Nov-12

38

EBS-1070 Miscellaneous Plumbing Details

41

02-Aug-12

27-Sep-12

24-Sep-12

20-Nov-12

38

43

24-Jun-12

21-Aug-12

20-Sep-12

20-Nov-12

65

19-Aug-12

21-Aug-12

15-Nov-12

20-Nov-12

65

43

24-Jun-12

21-Aug-12

20-Sep-12

20-Nov-12

65

149

01-Apr-12

24-Oct-12

26-Jun-12

20-Nov-12

19

134

01-Apr-12

03-Oct-12

26-Jun-12

30-Oct-12

19

60

01-Apr-12

21-Jun-12

26-Jun-12

18-Sep-12

63

50

26-Jul-12

03-Oct-12

21-Aug-12

30-Oct-12

19

EBS-1010 HVAC Load Calculation


Drawings

Schedules / Lists

EBS-1080 SER-12 Building Extension


HVAC MTO
EBS-1090 SER-12 Building Extension
HVAC Equipment Schedule
Cathodic Protection

Reports/Calculations/Schedule

ECP-1000 Site Survey and Soil Resistivity


Measurement
ECP-1005 CP Design Report (including
Calculations)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 47 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

70

10-Jul-12

15-Oct-12

08-Aug-12

13-Nov-12

21

ECP-1020 CP Material Specification

43

09-Aug-12

08-Oct-12

04-Sep-12

04-Nov-12

19

ECP-1030 CP Installation Specification


(Installation Procedures)
ECP-1040 SOW for CP System

43

16-Aug-12

15-Oct-12

16-Sep-12

13-Nov-12

21

39

10-Jul-12

02-Sep-12

08-Aug-12

01-Oct-12

21

43

14-Aug-12

11-Oct-12

09-Sep-12

07-Nov-12

19

43

14-Aug-12

11-Oct-12

09-Sep-12

07-Nov-12

19

49

19-Aug-12

24-Oct-12

12-Sep-12

20-Nov-12

19

ECP-1045 CP Detail drawings

44

19-Aug-12

17-Oct-12

12-Sep-12

13-Nov-12

19

ECP-1050 CP Schematic Diagram

45

23-Aug-12

24-Oct-12

18-Sep-12

20-Nov-12

19

387

25-Apr-12

17-Oct-13

03-Apr-12

25-Nov-13

26

382

02-May-12

17-Oct-13

05-Jun-12

17-Nov-13

21

29

02-May-12

12-Jun-12

05-Jun-12

16-Jul-12

25

21

02-May-12 31-May-12

05-Jun-12

04-Jul-12

25

03-Jun-12

12-Jun-12

05-Jul-12

16-Jul-12

25

402

23-Jul-12

29-Aug-13

19-Aug-12

17-Nov-13

80

Specifications/SOW

Data Sheets

ECP-1010 CP Material Data sheet


Drawings

Procurement Phase
Long Lead Items (Equipment)
QP Supplied Free Issue Material

PP1100
PP1110

16"- 36 KM Coated Pipes To Be


Checked & Verified ( Abo
Nakhla
16"- 36 )KM Coated Pipes
Ready For Transporting

Mechanical Items

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 48 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

401

24-Jul-12

29-Aug-13

19-Aug-12

17-Nov-13

80

PLPL1100 Pig Launcher MR Approved

24-Jul-12

26-Jul-12

19-Aug-12

21-Aug-12

26

PLPL1110 Pig Launcher RFQ to Vendors


to be Issued
PLPL1120 Pig Launcher Purchase Order

26-Jul-12

02-Aug-12

21-Aug-12

28-Aug-12

26

16-Aug-12

23-Aug-12

11-Sep-12

18-Sep-12

26

30

06-Sep-12

06-Oct-12

02-Oct-12

01-Nov-12

26

60

06-Oct-12

05-Dec-12

01-Nov-12

31-Dec-12

26

200

21-Oct-12

09-May-13

16-Nov-12

04-Jun-13

26

15

09-May-13 24-May-13

04-Jun-13

19-Jun-13

26

45

24-May-13

08-Jul-13

19-Jun-13

03-Aug-13

26

08-Jul-13

15-Jul-13

03-Aug-13

10-Aug-13

26

45

15-Jul-13

29-Aug-13

03-Oct-13

17-Nov-13

80

367

01-Aug-12

03-Aug-13

26-Sep-12

13-Oct-13

71

PLEO1100 EOT Crane MR Approved

01-Aug-12

03-Aug-12

26-Sep-12

28-Sep-12

56

PLEO1110 EOT Crane RFQ to Vendors to


be Issued
PLEO1120 EOT Crane Purchase Order

03-Aug-12

10-Aug-12

28-Sep-12

05-Oct-12

56

24-Aug-12

31-Aug-12

19-Oct-12

26-Oct-12

56

Pig Launcher

PLPL1130 Pig Launcher Vendor Document


Approved
PLPL1140 Pig Launcher Receipt Of Filled
SPIR
PLPL1150 Pig Launcher Inspection
Cleared & Factory Tested
PLPL1160 Pig Launcher Ex. Work Delivery
& FOB Complete
PLPL1170 Pig Launcher Received at Site
PLPL1180 Pig Launcher Inspected by QP
at Site
PLPL1190 Pig Launcher Spare Parts &
SPIR's to be Approved
EOT Crane

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 49 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLEO1130 EOT Crane Vendor Document


Approved
PLEO1140 EOT Crane Receipt Of Filled
SPIR
PLEO1150 EOT Crane Inspection Cleared
& Factory Tested
PLEO1160 EOT Crane Ex. Work Delivery &
FOB Complete
PLEO1170 EOT Crane Material Received at
Site
PLEO1180 EOT Inspected by QP at Site
PLEO1190 EOT Crane Spare Parts &
SPIR's to be Approved
Jib Crane

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

30

31-Aug-12

30-Sep-12

26-Oct-12

25-Nov-12

56

60

30-Sep-12

29-Nov-12

25-Nov-12

24-Jan-13

56

180

15-Oct-12

13-Apr-13

10-Dec-12

08-Jun-13

56

15

13-Apr-13

28-Apr-13

08-Jun-13

23-Jun-13

56

45

28-Apr-13

12-Jun-13

23-Jun-13

07-Aug-13

56

12-Jun-13

19-Jun-13

07-Aug-13

14-Aug-13

56

45

19-Jun-13

03-Aug-13

29-Aug-13

13-Oct-13

71

367

23-Jul-12

25-Jul-13

07-Sep-12

13-Oct-13

80

PLJI1100

Jib Crane MR Approved

23-Jul-12

25-Jul-12

07-Sep-12

09-Sep-12

46

PLJI1110

Jib Crane RFQ to Vendors to be


Issued
Jib Crane Purchase Order

25-Jul-12

01-Aug-12

09-Sep-12

16-Sep-12

46

15-Aug-12

22-Aug-12

30-Sep-12

07-Oct-12

46

Jib Crane Vendor Document


Approved
Jib Crane Receipt Of Filled SPIR

30

22-Aug-12

21-Sep-12

07-Oct-12

06-Nov-12

46

60

21-Sep-12

20-Nov-12

06-Nov-12

05-Jan-13

46

Jib Crane Inspection Cleared &


Factory Tested
Jib Crane Ex. Work Delivery &
FOB Complete

180

06-Oct-12

04-Apr-13

21-Nov-12

20-May-13

46

15

04-Apr-13

19-Apr-13

20-May-13

04-Jun-13

46

PLJI1120
PLJI1130
PLJI1140
PLJI1150
PLJI1160

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 50 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLJI1170

Jib Crane Received at Site

PLJI1180

Jib Crane Inspected by QP at


Site
Jib Crane Spare Parts & SPIR's
to be Approved

PLJI1190
Pumps

Main Transfer Pumps

PLMP1100 Main Transfer Pumps MR


Approved
PLMP1110 Main Transfer Pumps RFQ to
Vendors to be Issued
PLMP1120 Main Transfer Pumps Purchase
Order
PLMP1130 Main Transfer Pumps Vendor
Document Approved
PLMP1140 Main Transfer Pumps Receipt
Of Filled SPIR
PLMP1150 Main Transfer Pumps
Inspection Cleared & Factory
Tested
PLMP1160 Main Transfer Pumps Ex. Work
Delivery & FOB Complete
PLMP1170 Main Transfer Pumps Received
at Site
PLMP1180 Main Transfer Pumps Inspected
by QP at Site
PLMP1190 Main Transfer Pumps Spare
Parts & SPIR's to be Approved

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

Early Finish

45

19-Apr-13

03-Jun-13

04-Jun-13

19-Jul-13

46

03-Jun-13

10-Jun-13

19-Jul-13

26-Jul-13

46

45

10-Jun-13

25-Jul-13

29-Aug-13

13-Oct-13

80

455

19-Jul-12

17-Oct-13

21-Jul-12

23-Oct-13

455

19-Jul-12

17-Oct-13

21-Jul-12

23-Oct-13

19-Jul-12

21-Jul-12

21-Jul-12

23-Jul-12

21-Jul-12

28-Jul-12

23-Jul-12

30-Jul-12

11-Aug-12

18-Aug-12

13-Aug-12

20-Aug-12

30

18-Aug-12

17-Sep-12

20-Aug-12

19-Sep-12

60

17-Sep-12

16-Nov-12

19-Sep-12

18-Nov-12

268

02-Oct-12

27-Jun-13

04-Oct-12

29-Jun-13

15

27-Jun-13

12-Jul-13

29-Jun-13

14-Jul-13

45

12-Jul-13

26-Aug-13

14-Jul-13

28-Aug-13

26-Aug-13

02-Sep-13

28-Aug-13

04-Sep-13

45

02-Sep-13

17-Oct-13

08-Sep-13

23-Oct-13

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 51 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

455

19-Jul-12

17-Oct-13

21-Jul-12

23-Oct-13

PLBP1100 Booster Pumps MR Approved

19-Jul-12

21-Jul-12

21-Jul-12

23-Jul-12

PLBP1110 Booster Pumps RFQ to Vendors


to be Issued
PLBP1120 Booster Pumps Purchase Order

21-Jul-12

28-Jul-12

23-Jul-12

30-Jul-12

11-Aug-12

18-Aug-12

13-Aug-12

20-Aug-12

30

18-Aug-12

17-Sep-12

20-Aug-12

19-Sep-12

60

17-Sep-12

16-Nov-12

19-Sep-12

18-Nov-12

268

02-Oct-12

27-Jun-13

04-Oct-12

29-Jun-13

15

27-Jun-13

12-Jul-13

29-Jun-13

14-Jul-13

45

12-Jul-13

26-Aug-13

14-Jul-13

28-Aug-13

26-Aug-13

02-Sep-13

28-Aug-13

04-Sep-13

45

02-Sep-13

17-Oct-13

08-Sep-13

23-Oct-13

393

31-Jul-12

28-Aug-13

04-Sep-12

13-Oct-13

46

357

31-Jul-12

23-Jul-13

07-Sep-12

13-Oct-13

82

31-Jul-12

02-Aug-12

07-Sep-12

09-Sep-12

38

02-Aug-12

09-Aug-12

09-Sep-12

16-Sep-12

38

Booster Pumps

PLBP1130 Booster Pumps Vendor


Document Approved
PLBP1140 Booster Pumps Receipt Of
Filled SPIR
PLBP1150 Booster Pumps Inspection
Cleared & Factory Tested
PLBP1160 Booster Pumps Ex. Work
Delivery & FOB Complete
PLBP1170 Booster Pumps Received at
Site
PLBP1180 Booster Pumps Inspected by
QP at Site
PLBP1190 Booster Pumps Spare Parts &
SPIR's to be Approved
Electrical

Switchgear Panels

PLES1100 Switchgear Panels MR


Approved
PLES1110 Switchgear Panels RFQ to
Vendors to be Issued

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 52 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLES1120 Switchgear Panels Purchase


Order
PLES1130 Switchgear Panels Vendor
Document Approved
PLES1140 Switchgear Panels Receipt Of
Filled SPIR
PLES1150 Switchgear Panels Inspection
Cleared & Factory Tested
PLES1160 Switchgear Panels Ex. Work
Delivery & FOB Complete
PLES1170 Switchgear Panels Received at
Site
PLES1180 Switchgear Panels Inspected by
QP at Site
PLES1190 Switchgear Panels Spare Parts
& SPIR's to be Approved
Distribution Boards

PLED1100 Distribution Boards MR


Approved
PLED1110 Distribution Boards RFQ to
Vendors to be Issued
PLED1120 Distribution Boards Purchase
Order
PLED1130 Distribution Boards Vendor
Document Approved
PLED1140 Distribution Boards Receipt Of
Filled SPIR
PLED1150 Distribution Boards Inspection
Cleared & Factory Tested

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

Early Finish

23-Aug-12

30-Aug-12

30-Sep-12

07-Oct-12

38

30

30-Aug-12

29-Sep-12

07-Oct-12

06-Nov-12

38

60

29-Sep-12

28-Nov-12

06-Nov-12

05-Jan-13

38

170

14-Oct-12

02-Apr-13

21-Nov-12

10-May-13

38

15

02-Apr-13

17-Apr-13

10-May-13

25-May-13

38

45

17-Apr-13

01-Jun-13

25-May-13

09-Jul-13

38

01-Jun-13

08-Jun-13

09-Jul-13

16-Jul-13

38

45

08-Jun-13

23-Jul-13

29-Aug-13

13-Oct-13

82

357

02-Aug-12

25-Jul-13

07-Sep-12

13-Oct-13

80

02-Aug-12

04-Aug-12

07-Sep-12

09-Sep-12

36

04-Aug-12

11-Aug-12

09-Sep-12

16-Sep-12

36

25-Aug-12

01-Sep-12

30-Sep-12

07-Oct-12

36

30

01-Sep-12

01-Oct-12

07-Oct-12

06-Nov-12

36

60

01-Oct-12

30-Nov-12

06-Nov-12

05-Jan-13

36

170

16-Oct-12

04-Apr-13

21-Nov-12

10-May-13

36

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 53 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

15

04-Apr-13

19-Apr-13

10-May-13

25-May-13

36

45

19-Apr-13

03-Jun-13

25-May-13

09-Jul-13

36

03-Jun-13

10-Jun-13

09-Jul-13

16-Jul-13

36

45

10-Jun-13

25-Jul-13

29-Aug-13

13-Oct-13

80

387

06-Aug-12

28-Aug-13

04-Sep-12

13-Oct-13

46

PLEU1100 UPS System MR Approved

06-Aug-12

08-Aug-12

04-Sep-12

06-Sep-12

29

PLEU1110 UPS System RFQ to Vendors to


be Issued
PLEU1120 UPS System Purchase Order

08-Aug-12

15-Aug-12

06-Sep-12

13-Sep-12

29

29-Aug-12

05-Sep-12

27-Sep-12

04-Oct-12

29

PLEU1130 UPS System Vendor Document


Approved
PLEU1140 UPS System Receipt Of Filled
SPIR
PLEU1150 UPS System Inspection Cleared
& Factory Tested
PLEU1160 UPS System Ex. Work Delivery
& FOB Complete
PLEU1170 UPS System Received at Site

30

05-Sep-12

05-Oct-12

04-Oct-12

03-Nov-12

29

60

05-Oct-12

04-Dec-12

03-Nov-12

02-Jan-13

29

200

20-Oct-12

08-May-13

18-Nov-12

06-Jun-13

29

15

08-May-13 23-May-13

06-Jun-13

21-Jun-13

29

45

23-May-13

07-Jul-13

21-Jun-13

05-Aug-13

29

07-Jul-13

14-Jul-13

05-Aug-13

12-Aug-13

29

45

14-Jul-13

28-Aug-13

29-Aug-13

13-Oct-13

46

PLED1160 Distribution Boards Ex. Work


Delivery & FOB Complete
PLED1170 Distribution Boards Material
Received at Site
PLED1180 Distribution Boards Inspected by
QP at Site
PLED1190 Distribution Boards Spare Parts
& SPIR's to be Approved
UPS System

PLEU1180 UPS System Inspected by QP


at Site
PLEU1190 UPS System Spare Parts &
SPIR's to be Approved

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 54 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

416

22-Jul-12

11-Sep-13

12-Aug-12

13-Oct-13

32

412

26-Jul-12

11-Sep-13

27-Aug-12

13-Oct-13

32

26-Jul-12

28-Jul-12

27-Aug-12

29-Aug-12

32

28-Jul-12

04-Aug-12

29-Aug-12

05-Sep-12

32

18-Aug-12

25-Aug-12

19-Sep-12

26-Sep-12

32

30

25-Aug-12

24-Sep-12

26-Sep-12

26-Oct-12

32

60

24-Sep-12

23-Nov-12

26-Oct-12

25-Dec-12

32

225

09-Oct-12

22-May-13

10-Nov-12

23-Jun-13

32

15

22-May-13

06-Jun-13

23-Jun-13

08-Jul-13

32

45

06-Jun-13

21-Jul-13

08-Jul-13

22-Aug-13

32

21-Jul-13

28-Jul-13

22-Aug-13

29-Aug-13

32

45

28-Jul-13

11-Sep-13

29-Aug-13

13-Oct-13

32

412

22-Jul-12

07-Sep-13

27-Aug-12

13-Oct-13

36

PLVE1100 ESD Valve MR Approved

22-Jul-12

24-Jul-12

27-Aug-12

29-Aug-12

36

PLVE1110 ESD Valve RFQ to Vendors to


be Issued

24-Jul-12

31-Jul-12

29-Aug-12

05-Sep-12

36

Valves

Control Valve & Auto Recirculation Valve

PLVC1100 Control Valve & Auto


Recirculation Valve MR
Approved
PLVC1110 Control Valve & Auto
Recirculation Valve RFQ to
Vendors
to be&Issued
PLVC1120 Control Valve
Auto
Recirculation Valve Purchase
PLVC1130 Order
Control Valve & Auto
Recirculation Valve Vendor
Document
Approved
PLVC1140 Control Valve
& Auto
Recirculation Valve Receipt Of
SPIR
PLVC1150 Filled
Control
Valve & Auto
Recirculation Valve Inspection
Cleared
& Factory
Tested
PLVC1160 Control Valve
& Auto
Recirculation Valve Ex. Work
Delivery
& FOB
Complete
PLVC1170 Control Valve
& Auto
Recirculation Valve Received at
PLVC1180 Site
Control Valve & Auto
Recirculation Valve Inspected by
QP
at Site
PLVC1190 Control
Valve & Auto
Recirculation Valve Spare Parts
& SPIR's to be Approved
ESD Valve With All Accessories

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 55 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

14-Aug-12

21-Aug-12

19-Sep-12

26-Sep-12

36

30

21-Aug-12

20-Sep-12

26-Sep-12

26-Oct-12

36

60

20-Sep-12

19-Nov-12

26-Oct-12

25-Dec-12

36

225

05-Oct-12

18-May-13

10-Nov-12

23-Jun-13

36

15

18-May-13

02-Jun-13

23-Jun-13

08-Jul-13

36

45

02-Jun-13

17-Jul-13

08-Jul-13

22-Aug-13

36

17-Jul-13

24-Jul-13

22-Aug-13

29-Aug-13

36

45

24-Jul-13

07-Sep-13

29-Aug-13

13-Oct-13

36

397

30-Jul-12

31-Aug-13

11-Sep-12

13-Oct-13

43

PLVI1100 Isolation Valves MR Approved

30-Jul-12

01-Aug-12

11-Sep-12

13-Sep-12

43

PLVI1110

01-Aug-12

08-Aug-12

13-Sep-12

20-Sep-12

43

22-Aug-12

29-Aug-12

04-Oct-12

11-Oct-12

43

30

29-Aug-12

28-Sep-12

11-Oct-12

10-Nov-12

43

60

28-Sep-12

27-Nov-12

10-Nov-12

09-Jan-13

43

210

13-Oct-12

11-May-13

25-Nov-12

23-Jun-13

43

PLVE1120 ESD Valve Purchase Order


PLVE1130 ESD Valve Vendor Document
Approved
PLVE1140 ESD Valve Receipt Of Filled
SPIR
PLVE1150 ESD Valve Inspection Cleared &
Factory Tested
PLVE1160 ESD Valve Ex. Work Delivery &
FOB Complete
PLVE1170 ESD Valve Received at Site
PLVE1180 ESD Valve Inspected by QP at
Site
PLVE1190 ESD Valve Spare Parts &
SPIR's to be Approved
Isolation Valves at Refinery

Isolation Valves RFQ to Vendors


to be Issued
PLVI1120 Isolation Valves Purchase Order
PLVI1130 Isolation Valves Vendor
Document Approved
PLVI1140 Isolation Valves Receipt Of
Filled SPIR
PLVI1150 Isolation Valves Inspection
Cleared & Factory Tested

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 56 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

PLVI1160 Isolation Valves Ex. Work


Delivery & FOB Complete
PLVI1170 Isolation Valves Received at Site

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

15

11-May-13 26-May-13

23-Jun-13

08-Jul-13

43

45

26-May-13

10-Jul-13

08-Jul-13

22-Aug-13

43

10-Jul-13

17-Jul-13

22-Aug-13

29-Aug-13

43

45

17-Jul-13

31-Aug-13

29-Aug-13

13-Oct-13

43

397

31-Jul-12

01-Sep-13

12-Aug-12

13-Oct-13

42

PLVM1100 Motor Operated Valves MR


Approved
PLVM1110 MOV RFQ to Vendors to be
Issued
PLVM1120 MOV Purchase Order

31-Jul-12

02-Aug-12

12-Aug-12

14-Aug-12

12

02-Aug-12

09-Aug-12

14-Aug-12

21-Aug-12

12

23-Aug-12

30-Aug-12

04-Sep-12

11-Sep-12

12

PLVM1130 MOV Vendor Document


Approved
PLVM1140 MOV Receipt Of Filled SPIR

30

30-Aug-12

29-Sep-12

11-Sep-12

11-Oct-12

12

60

29-Sep-12

28-Nov-12

11-Oct-12

10-Dec-12

12

PLVM1150 MOV Inspection Cleared &


Factory Tested
PLVM1160 MOV Ex. Work Delivery & FOB
Complete
PLVM1170 MOV Received at Site

210

14-Oct-12

12-May-13

26-Oct-12

24-May-13

12

15

12-May-13 27-May-13

24-May-13

08-Jun-13

12

45

27-May-13

11-Jul-13

08-Jun-13

23-Jul-13

12

PLVM1180 Motor Operated Valves


Inspected by QP at Site
PLVM1190 MOV Spare Parts & SPIR's to
be Approved

11-Jul-13

18-Jul-13

23-Jul-13

30-Jul-13

12

45

18-Jul-13

01-Sep-13

29-Aug-13

13-Oct-13

42

PLVI1180 Isolation Valves Inspected by


QP at Site
PLVI1190 Isolation Valves Spare Parts &
SPIR's to be Approved
MOV (Motor Operated Valves)

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 57 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Misc. Types of Valves

PLVD1100 Misc. Types of Valves MR


Approved
PLVD1110 Misc. Types of Valves RFQ to
Vendors to be Issued
PLVD1120 Misc. Types of Valves Purchase
Order
PLVD1130 Misc. Types of Valves Vendor
Document Approved
PLVD1140 Misc. Types of Valves Receipt
Of Filled SPIR
PLVD1150 Misc. Types of Valves
Inspection Cleared & Factory
Tested
PLVD1160 Misc. Types of Valves Ex. Work
Delivery & FOB Complete
PLVD1170 Misc. Types of Valves Received
at Site
PLVD1180 Misc. Types of Valves Inspected
by QP at Site
PLVD1190 Misc. Types of Valves Spare
Parts & SPIR's to be Approved
Instrumentation

Coriollis Flowmeter

PLIF1100 Coriollis Flowmeter MR


Approved
PLIF1110 Coriollis Flowmeter RFQ to
Vendors to be Issued

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

Early Finish

387

09-Aug-12

31-Aug-13

22-Aug-12

13-Oct-13

43

09-Aug-12

11-Aug-12

22-Aug-12

24-Aug-12

13

11-Aug-12

18-Aug-12

24-Aug-12

31-Aug-12

13

01-Sep-12

08-Sep-12

14-Sep-12

21-Sep-12

13

30

08-Sep-12

08-Oct-12

21-Sep-12

21-Oct-12

13

60

08-Oct-12

07-Dec-12

21-Oct-12

20-Dec-12

13

200

23-Oct-12

11-May-13

05-Nov-12

24-May-13

13

15

11-May-13 26-May-13

24-May-13

08-Jun-13

13

45

26-May-13

10-Jul-13

08-Jun-13

23-Jul-13

13

10-Jul-13

17-Jul-13

23-Jul-13

30-Jul-13

13

45

17-Jul-13

31-Aug-13

29-Aug-13

13-Oct-13

43

423

17-Jul-12

13-Sep-13

09-Sep-12

13-Oct-13

30

382

08-Aug-12

25-Aug-13

19-Sep-12

13-Oct-13

49

08-Aug-12

10-Aug-12

19-Sep-12

21-Sep-12

42

10-Aug-12

17-Aug-12

21-Sep-12

28-Sep-12

42

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 58 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLIF1120 Coriollis Flowmeter Purchase


Order
PLIF1130 Coriollis Flowmeter Vendor
Document Approved
PLIF1140 Coriollis Flowmeter Receipt Of
Filled SPIR
PLIF1150 Coriollis Flowmeter Inspection
Cleared & Factory Tested
PLIF1160 Coriollis Flowmeter Ex. Work
Delivery & FOB Complete
PLIF1170 Coriollis Flowmeter Received at
Site
PLIF1180 Coriollis Flowmeter System
Inspected by QP at Site
PLIF1190 Coriollis Flowmeter Spare Parts
& SPIR's to be Approved
Junction Boxes

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

31-Aug-12

07-Sep-12

12-Oct-12

19-Oct-12

42

30

07-Sep-12

07-Oct-12

19-Oct-12

18-Nov-12

42

60

07-Oct-12

06-Dec-12

18-Nov-12

17-Jan-13

42

210

07-Oct-12

05-May-13

18-Nov-12

16-Jun-13

42

15

05-May-13 20-May-13

16-Jun-13

01-Jul-13

42

45

20-May-13

04-Jul-13

01-Jul-13

15-Aug-13

42

04-Jul-13

11-Jul-13

15-Aug-13

22-Aug-13

42

45

11-Jul-13

25-Aug-13

29-Aug-13

13-Oct-13

49

367

31-Jul-12

02-Aug-13

09-Sep-12

13-Oct-13

72

PLIJ1100

Junction Boxes MR Approved

31-Jul-12

02-Aug-12

09-Sep-12

11-Sep-12

40

PLIJ1110

Junction Boxes RFQ to Vendors


to be Issued
Junction Boxes Purchase Order

02-Aug-12

09-Aug-12

11-Sep-12

18-Sep-12

40

23-Aug-12

30-Aug-12

02-Oct-12

09-Oct-12

40

Junction Boxes Vendor


Document Approved
Junction Boxes Receipt Of Filled
SPIR
Junction Boxes Inspection
Cleared & Factory Tested

30

30-Aug-12

29-Sep-12

09-Oct-12

08-Nov-12

40

60

29-Sep-12

28-Nov-12

08-Nov-12

07-Jan-13

40

180

14-Oct-12

12-Apr-13

23-Nov-12

22-May-13

40

PLIJ1120
PLIJ1130
PLIJ1140
PLIJ1150

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 59 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLIJ1160
PLIJ1170
PLIJ1180
PLIJ1190

Original
Duration

Early Start

Junction Boxes Ex. Work


Delivery & FOB Complete
Junction Boxes Received at Site

15

12-Apr-13

27-Apr-13

22-May-13

06-Jun-13

40

45

27-Apr-13

11-Jun-13

06-Jun-13

21-Jul-13

40

Junction Boxes Junction Boxes


Inspected by QP at Site
Junction Boxes Spare Parts &
SPIR's to be Approved

11-Jun-13

18-Jun-13

21-Jul-13

28-Jul-13

40

45

18-Jun-13

02-Aug-13

29-Aug-13

13-Oct-13

72

357

09-Aug-12

01-Aug-13

03-Oct-12

13-Oct-13

73

09-Aug-12

11-Aug-12

03-Oct-12

05-Oct-12

55

11-Aug-12

18-Aug-12

05-Oct-12

12-Oct-12

55

01-Sep-12

08-Sep-12

26-Oct-12

02-Nov-12

55

30

08-Sep-12

08-Oct-12

02-Nov-12

02-Dec-12

55

60

08-Oct-12

07-Dec-12

02-Dec-12

31-Jan-13

55

170

23-Oct-12

11-Apr-13

17-Dec-12

05-Jun-13

55

15

11-Apr-13

26-Apr-13

05-Jun-13

20-Jun-13

55

45

26-Apr-13

10-Jun-13

20-Jun-13

04-Aug-13

55

10-Jun-13

17-Jun-13

04-Aug-13

11-Aug-13

55

45

17-Jun-13

01-Aug-13

29-Aug-13

13-Oct-13

73

Fire and Smoke Detectors

PLID1100 Fire & Smoke Detectors MR


Approved
PLID1110 Fire & Smoke Detectors RFQ to
Vendors to be Issued
PLID1120 Fire & Smoke Detectors
Purchase Order
PLID1130 Fire & Smoke Detectors Vendor
Document Approved
PLID1140 Fire & Smoke Detectors Receipt
Of Filled SPIR
PLID1150 Fire & Smoke Detectors
Inspection Cleared & Factory
Tested
PLID1160 Fire & Smoke Detectors Ex.
Work Delivery & FOB Complete
PLID1170 Fire & Smoke Detectors
Received at Site
PLID1180 Fire & Smoke Detectors
Inspected by QP at Site
PLID1190 Fire & Smoke Detectors Spare
Parts & SPIR's to be Approved

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 60 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

397

12-Aug-12

13-Sep-13

11-Sep-12

13-Oct-13

30

PLIS1100 SCADA, DCS, ESD and F & G


System MR Approved
PLIS1110 SCADA RFQ to Vendors to be
Issued
PLIS1120 SCADA Purchase Order

12-Aug-12

14-Aug-12

11-Sep-12

13-Sep-12

30

14-Aug-12

21-Aug-12

13-Sep-12

20-Sep-12

30

04-Sep-12

11-Sep-12

04-Oct-12

11-Oct-12

30

PLIS1130 SCADA Vendor Document


Approved
PLIS1140 SCADA Receipt Of Filled SPIR

30

11-Sep-12

11-Oct-12

11-Oct-12

10-Nov-12

30

60

11-Oct-12

10-Dec-12

10-Nov-12

09-Jan-13

30

PLIS1150 SCADA Inspection Cleared &


Factory Tested
PLIS1160 SCADA Ex. Work Delivery &
FOB Complete
PLIS1170 SCADA Material Received at
Site
PLIS1180 SCADA, DCS, ESD and F & G
System Inspected by QP at Site
PLIS1190 SCADA Spare Parts & SPIR's to
be Approved

210

26-Oct-12

24-May-13

25-Nov-12

23-Jun-13

30

15

24-May-13

08-Jun-13

23-Jun-13

08-Jul-13

30

45

08-Jun-13

23-Jul-13

08-Jul-13

22-Aug-13

30

23-Jul-13

30-Jul-13

22-Aug-13

29-Aug-13

30

45

30-Jul-13

13-Sep-13

29-Aug-13

13-Oct-13

30

318

17-Jul-12

31-May-13

11-Sep-12

26-Jul-13

56

17-Jul-12

19-Jul-12

11-Sep-12

13-Sep-12

56

19-Jul-12

26-Jul-12

13-Sep-12

20-Sep-12

56

09-Aug-12

16-Aug-12

04-Oct-12

11-Oct-12

56

SCADA, DCS, ESD and F & G System

Instrumentation & Control Cables

PLIC1200 Instrument & Control Cables MR


Approved
PLIC1210 Instrument & Control Cables
RFQ to Vendors to be Issued
PLIC1220 Instrument & Control Cables
Purchase Order

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 61 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PLIC1230 Instrument & Control Cables


Vendor Document Approved
PLIC1240 Instrument & Control Cables
Receipt Of Filled SPIR
PLIC1250 Instrument & Control Cables
Inspection Cleared & Factory
Tested
PLIC1260 Instrument & Control Cables Ex.
Work Delivery & FOB Complete
PLIC1270 Instrument & Control Cables
Received at Site
PLIC1280 Instrument & Control Cables
Inspected by QP at Site
PLIC1290 Instrument & Control Cables
Spare Parts & SPIR's to be
Approved
Isolation Joints

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

30

16-Aug-12

15-Sep-12

11-Oct-12

10-Nov-12

56

60

15-Sep-12

14-Nov-12

10-Nov-12

09-Jan-13

56

136

25-Sep-12

08-Feb-13

20-Nov-12

05-Apr-13

56

15

08-Feb-13

23-Feb-13

05-Apr-13

20-Apr-13

56

45

23-Feb-13

09-Apr-13

20-Apr-13

04-Jun-13

56

09-Apr-13

16-Apr-13

04-Jun-13

11-Jun-13

56

45

16-Apr-13

31-May-13

11-Jun-13

26-Jul-13

56

324

23-Jul-12

12-Jun-13

20-Sep-12

10-Aug-13

59

PLM1200

Isolation Joints MR Approved

23-Jul-12

25-Jul-12

20-Sep-12

22-Sep-12

59

PLM1210

Isolation Joints to Vendors to be


Issued
Isolation Joints Purchase Order

25-Jul-12

01-Aug-12

22-Sep-12

29-Sep-12

59

15-Aug-12

22-Aug-12

13-Oct-12

20-Oct-12

59

Isolation Joints Vendor


Document Approved
Isolation Joints Receipt Of Filled
SPIR
Isolation Joints Inspection
Cleared & Factory Tested
Isolation Joints Ex. Work
Delivery & FOB Complete

30

22-Aug-12

21-Sep-12

20-Oct-12

19-Nov-12

59

60

21-Sep-12

20-Nov-12

19-Nov-12

18-Jan-13

59

148

25-Sep-12

20-Feb-13

23-Nov-12

20-Apr-13

59

15

20-Feb-13

07-Mar-13

20-Apr-13

05-May-13

59

PLM1220
PLM1230
PLM1240
PLM1250
PLM1260

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 62 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

45

07-Mar-13

21-Apr-13

05-May-13

19-Jun-13

59

21-Apr-13

28-Apr-13

19-Jun-13

26-Jun-13

59

45

28-Apr-13

12-Jun-13

26-Jun-13

10-Aug-13

59

397

31-Jul-12

01-Sep-13

11-Sep-12

13-Oct-13

42

Telecom and Telemetry


Equipments MR Approved
Telecom RFQ to Vendors to be
Issued
Telecom Purchase Order

31-Jul-12

02-Aug-12

11-Sep-12

13-Sep-12

42

02-Aug-12

09-Aug-12

13-Sep-12

20-Sep-12

42

23-Aug-12

30-Aug-12

04-Oct-12

11-Oct-12

42

Telecom Vendor Document


Approved
Telecom Receipt Of Filled SPIR

30

30-Aug-12

29-Sep-12

11-Oct-12

10-Nov-12

42

60

29-Sep-12

28-Nov-12

10-Nov-12

09-Jan-13

42

Telecom Inspection Cleared &


Factory Tested
Telecom Ex. Work Delivery &
FOB Complete
Telecom Received at Site

210

14-Oct-12

12-May-13

25-Nov-12

23-Jun-13

42

15

12-May-13 27-May-13

23-Jun-13

08-Jul-13

42

45

27-May-13

11-Jul-13

08-Jul-13

22-Aug-13

42

11-Jul-13

18-Jul-13

22-Aug-13

29-Aug-13

42

45

18-Jul-13

01-Sep-13

29-Aug-13

13-Oct-13

42

387

08-Aug-12

30-Aug-13

04-Sep-12

13-Oct-13

44

PLM1270

Isolation Joints Received at Site

PLM1280

Isolation Joints Inspected by


QP at Site
Isolation Joints Spare Parts &
SPIR's to be Approved

PLM1290

Telecom and Telemetry Equipments

PLTE1100
PLTE1110
PLTE1120
PLTE1130
PLTE1140
PLTE1150
PLTE1160
PLTE1170
PLTE1180
PLTE1190

Telecom and Telemetry


Equipments Inspected by QP at
Site
Telecom Spare Parts & SPIR's
to be Approved

Leak Detection System

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 63 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

08-Aug-12

10-Aug-12

04-Sep-12

06-Sep-12

27

10-Aug-12

17-Aug-12

06-Sep-12

13-Sep-12

27

31-Aug-12

07-Sep-12

27-Sep-12

04-Oct-12

27

30

07-Sep-12

07-Oct-12

04-Oct-12

03-Nov-12

27

60

07-Oct-12

06-Dec-12

03-Nov-12

02-Jan-13

27

200

22-Oct-12

10-May-13

18-Nov-12

06-Jun-13

27

15

10-May-13 25-May-13

06-Jun-13

21-Jun-13

27

45

25-May-13

09-Jul-13

21-Jun-13

05-Aug-13

27

09-Jul-13

16-Jul-13

05-Aug-13

12-Aug-13

27

45

16-Jul-13

30-Aug-13

29-Aug-13

13-Oct-13

44

353

12-Jul-12

30-Jun-13

01-Sep-12

24-Aug-13

55

351

12-Jul-12

28-Jun-13

03-Sep-12

30-Jul-13

32

330

02-Aug-12

28-Jun-13

03-Sep-12

30-Jul-13

32

POMP1100 Pipes & Fittings MR Approved

02-Aug-12

04-Aug-12

03-Sep-12

05-Sep-12

32

POMP1110 Pipes & Fittings RFQ to Vendors


to be Issued

04-Aug-12

11-Aug-12

05-Sep-12

12-Sep-12

32

PLLD1100
PLLD1110
PLLD1120
PLLD1130
PLLD1140
PLLD1150
PLLD1160
PLLD1170
PLLD1180
PLLD1190

Leak Detection System MR


Approved
Leak Detection System RFQ to
Vendors to be Issued
Leak Detection System
Purchase Order
Leak Detection System Vendor
Document Approved
Leak Detection System Receipt
Of Filled SPIR
Leak Detection System
Inspection Cleared & Factory
Tested
Leak Detection System Ex.
Work Delivery & FOB Complete
Leak Detection System
Received at Site
Leak Detection System
Inspected by QP at Site
Leak Detection System Spare
Parts & SPIR's to be Approved

Other Items (Bulk Material)


Mechanical

Pipes & Fittings

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 64 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

POMP1120 Pipes & Fittings Purchase Order

25-Aug-12

01-Sep-12

26-Sep-12

03-Oct-12

32

POMP1130 Pipes & Fittings Ex. Work (50 %


Delivery)
POMP1140 Pipes & Fittings Ex. Work (90 %
Delivery)
POMP1150 Pipes & Fittings (50 % Received
At Site)
POMP1160 Pipes & Fittings (90 % Received
At Site)
POMP1170 Pipes & Fittings Received and
PO Closed

10

31-Oct-12

10-Nov-12

02-Dec-12

12-Dec-12

32

10

10-Dec-12

20-Dec-12

11-Jan-13

21-Jan-13

32

50

20-Dec-12

08-Feb-13

21-Jan-13

12-Mar-13

32

50

10-Mar-13

29-Apr-13

11-Apr-13

31-May-13

32

30

29-May-13

28-Jun-13

30-Jun-13

30-Jul-13

32

330

12-Jul-12

07-Jun-13

03-Sep-12

30-Jul-13

53

POMB1100 Bulk Items (Stud bolts, Nuts,


Gaskets etc.,) MR Approved
POMB1110 Bulk Items RFQ to Vendors to
be Issued
POMB1120 Bulk Items Purchase Order

12-Jul-12

14-Jul-12

03-Sep-12

05-Sep-12

53

14-Jul-12

21-Jul-12

05-Sep-12

12-Sep-12

53

04-Aug-12

11-Aug-12

26-Sep-12

03-Oct-12

53

POMB1130 Bulk Items Ex. Work (50 %


Delivery)
POMB1140 Bulk Items Ex. Work (90 %
Delivery)
POMB1150 Bulk Items (50 % Received At
Site)
POMB1160 Bulk Items (90 % Received At
Site)
POMB1170 Bulk Items Received and PO
Closed

10

10-Oct-12

20-Oct-12

02-Dec-12

12-Dec-12

53

10

19-Nov-12

29-Nov-12

11-Jan-13

21-Jan-13

53

50

29-Nov-12

18-Jan-13

21-Jan-13

12-Mar-13

53

50

17-Feb-13

08-Apr-13

11-Apr-13

31-May-13

53

30

08-May-13

07-Jun-13

30-Jun-13

30-Jul-13

53

Bulk Items (Stud bolts, Nuts, Gaskets etc.,)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 65 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Electrical

Local Control Panel

POEL1100 Local Control Panel MR


Approved
POEL1110 Local Control Panel RFQ to
Vendors to be Issued
POEL1120 Local Control Panel Purchase
Order
POEL1130 Local Control Panel Ex. Work
(50 % Delivery)
POEL1140 Local Control Panel Ex. Work
(90 % Delivery)
POEL1150 Local Control Panel (50 %
Received At Site)
POEL1160 Local Control Panel (90 %
Received At Site)
POEL1170 Local Control Panel Received
and PO Closed
Lighting Fixtures & Lighting Poles

POEF1100 Lighting Fixtures & Lighting


Poles MR Approved
POEF1110 Lighting Fixtures & Lighting
Poles RFQ to Vendors to be
POEF1120 Issued
Lighting Fixtures & Lighting
Poles Purchase Order
POEF1130 Lighting Fixtures & Lighting
Poles Ex. Work (50 % Delivery)

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

Early Finish

320

14-Aug-12

30-Jun-13

23-Sep-12

09-Aug-13

40

290

14-Aug-12 31-May-13

16-Oct-12

02-Aug-13

63

14-Aug-12

16-Aug-12

16-Oct-12

18-Oct-12

63

16-Aug-12

23-Aug-12

18-Oct-12

25-Oct-12

63

06-Sep-12

13-Sep-12

08-Nov-12

15-Nov-12

63

10

12-Nov-12

22-Nov-12

14-Jan-13

24-Jan-13

63

10

22-Dec-12

01-Jan-13

23-Feb-13

05-Mar-13

63

30

01-Jan-13

31-Jan-13

05-Mar-13

04-Apr-13

63

30

02-Mar-13

01-Apr-13

04-May-13

03-Jun-13

63

30

01-May-13 31-May-13

03-Jul-13

02-Aug-13

63

290

31-Aug-12

17-Jun-13

16-Oct-12

02-Aug-13

46

31-Aug-12

02-Sep-12

16-Oct-12

18-Oct-12

46

02-Sep-12

09-Sep-12

18-Oct-12

25-Oct-12

46

23-Sep-12

30-Sep-12

08-Nov-12

15-Nov-12

46

10

29-Nov-12

09-Dec-12

14-Jan-13

24-Jan-13

46

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 66 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

10

08-Jan-13

18-Jan-13

23-Feb-13

05-Mar-13

46

30

18-Jan-13

17-Feb-13

05-Mar-13

04-Apr-13

46

30

19-Mar-13

18-Apr-13

04-May-13

03-Jun-13

46

30

18-May-13

17-Jun-13

03-Jul-13

02-Aug-13

46

320

14-Aug-12

30-Jun-13

23-Sep-12

09-Aug-13

40

POEC1100 Electrical Cables MR Approved

14-Aug-12

16-Aug-12

23-Sep-12

25-Sep-12

40

POEC1110 Electrical Cables RFQ to


Vendors to be Issued
POEC1120 Electrical Cables Purchase
Order
POEC1130 Electrical Cables Ex. Work (50
% Delivery)
POEC1140 Electrical Cables Ex. Work (90
% Delivery)
POEC1150 Electrical Cables (50 %
Received At Site)
POEC1160 Electrical Cables (90 %
Received At Site)
POEC1170 Electrical Cables Received and
PO Closed

16-Aug-12

23-Aug-12

25-Sep-12

02-Oct-12

40

06-Sep-12

13-Sep-12

16-Oct-12

23-Oct-12

40

10

12-Nov-12

22-Nov-12

22-Dec-12

01-Jan-13

40

10

22-Dec-12

01-Jan-13

31-Jan-13

10-Feb-13

40

45

01-Jan-13

15-Feb-13

10-Feb-13

27-Mar-13

40

45

17-Mar-13

01-May-13

26-Apr-13

10-Jun-13

40

30

31-May-13

30-Jun-13

10-Jul-13

09-Aug-13

40

326

17-Jul-12

08-Jun-13

09-Sep-12

24-Aug-13

77

23-Jul-12

08-Jun-13

08-Oct-12

24-Aug-13

77

POEF1140 Lighting Fixtures & Lighting


Poles Ex. Work (90 % Delivery)
POEF1150 Lighting Fixtures & Lighting
Poles (50 % Received At Site)
POEF1160 Lighting Fixtures & Lighting
Poles (90 % Received At Site)
POEF1170 Lighting Fixtures & Lighting
Poles Received and PO Closed
Electrical Cables

Instrumentation

Pressure Transmitters, Differential Pressure Transmitters, Pressure 320


Gauges

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 67 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

POIP1100 Pressure Transmitters MR


Approved
POIP1110 Pressure Transmitters RFQ to
Vendors to be Issued
POIP1120 Pressure Transmitters Purchase
Order
POIP1130 Pressure Transmitters Ex. Work
(50 % Delivery)
POIP1140 Pressure Transmitters Ex. Work
(90 % Delivery)
POIP1150 Pressure Transmitters (50 %
Received At Site)
POIP1160 Pressure Transmitters (90 %
Received At Site)
POIP1170 Pressure Transmitters Received
and PO Closed
Temperature Elements, Temperature Transmitters, Thermowell

POIT1100 Temperature Transmitters MR


Approved
POIT1110 Temperature Transmitters RFQ
to Vendors to be Issued
POIT1120 Temperature Transmitters
Purchase Order
POIT1130 Temperature Transmitters Ex.
Work (50 % Delivery)
POIT1140 Temperature Transmitters Ex.
Work (90 % Delivery)
POIT1150 Temperature Transmitters (50 %
Received At Site)

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

Early Finish

23-Jul-12

25-Jul-12

08-Oct-12

10-Oct-12

77

25-Jul-12

01-Aug-12

10-Oct-12

17-Oct-12

77

15-Aug-12

22-Aug-12

31-Oct-12

07-Nov-12

77

10

21-Oct-12

31-Oct-12

06-Jan-13

16-Jan-13

77

10

30-Nov-12

10-Dec-12

15-Feb-13

25-Feb-13

77

45

10-Dec-12

24-Jan-13

25-Feb-13

11-Apr-13

77

45

23-Feb-13

09-Apr-13

11-May-13

25-Jun-13

77

30

09-May-13

08-Jun-13

25-Jul-13

24-Aug-13

77

320

23-Jul-12

08-Jun-13

08-Oct-12

24-Aug-13

77

23-Jul-12

25-Jul-12

08-Oct-12

10-Oct-12

77

25-Jul-12

01-Aug-12

10-Oct-12

17-Oct-12

77

15-Aug-12

22-Aug-12

31-Oct-12

07-Nov-12

77

10

21-Oct-12

31-Oct-12

06-Jan-13

16-Jan-13

77

10

30-Nov-12

10-Dec-12

15-Feb-13

25-Feb-13

77

45

10-Dec-12

24-Jan-13

25-Feb-13

11-Apr-13

77

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 68 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

POIT1160 Temperature Transmitters (90 %


Received At Site)
POIT1170 Temperature Transmitters
Received and PO Closed

Original
Duration

Early Start

45

23-Feb-13

09-Apr-13

11-May-13

25-Jun-13

77

30

09-May-13

08-Jun-13

25-Jul-13

24-Aug-13

77

17-Jul-12

02-Jun-13

09-Sep-12

26-Jul-13

54

17-Jul-12

19-Jul-12

09-Sep-12

11-Sep-12

54

19-Jul-12

26-Jul-12

11-Sep-12

18-Sep-12

54

09-Aug-12

16-Aug-12

02-Oct-12

09-Oct-12

54

10

15-Oct-12

25-Oct-12

08-Dec-12

18-Dec-12

54

10

24-Nov-12

04-Dec-12

17-Jan-13

27-Jan-13

54

45

04-Dec-12

18-Jan-13

27-Jan-13

13-Mar-13

54

45

17-Feb-13

03-Apr-13

12-Apr-13

27-May-13

54

30

03-May-13

02-Jun-13

26-Jun-13

26-Jul-13

54

320

09-Aug-12

25-Jun-13

06-Oct-12

22-Aug-13

58

09-Aug-12

11-Aug-12

06-Oct-12

08-Oct-12

58

11-Aug-12

18-Aug-12

08-Oct-12

15-Oct-12

58

01-Sep-12

08-Sep-12

29-Oct-12

05-Nov-12

58

Instrument Cable Accessories, Tubing fittings & Misc. Erection Materials


320

POIA1100 Instrument Cable Accessories


MR Approved
POIA1110 Instrument Cable Accessories
RFQ to Vendors to be Issued
POIA1120 Instrument Cable Accessories
Purchase Order
POIA1130 Instrument Cable Accessories
Ex. Work (50 % Delivery)
POIA1140 Instrument Cable Accessories
Ex. Work (90 % Delivery)
POIA1150 Instrument Cable Accessories
(50 % Received At Site)
POIA1160 Instrument Cable Accessories
(90 % Received At Site)
POIA1170 Instrument Cable Accessories
Received and PO Closed
Corrosion Monitoring and Inhibitor Injection Facilities

POCM1100
POCM1110
POCM1120

Corrosion Monitoring and


Inhibitor Injection Facilities MR
Approved
Corrosion Monitoring RFQ to
Vendors to be Issued
Corrosion Monitoring Purchase
Order

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 69 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

POCM1130

Corrosion Monitoring Ex. Work


10
(50 % Delivery)
POCM1140 Corrosion Monitoring Ex. Work
10
(90 % Delivery)
POCM1150 Corrosion Monitoring and
45
Inhibitor Injection Facilities (50 %
Received
Site)
POCM1160 Corrosion At
Monitoring
and
45
Inhibitor Injection Facilities (90 %
Site)
POCM1170 Received
Corrosion At
Monitoring
and
30
Inhibitor Injection Facilities
Received
and
CP System incl. Anode
Beds, Cables,
TR PO
Units,Closed
Jointing Kits, CP Test 332
Post etc.
Temperory Cathodic Protection

POTC1100 Temporary Cathodic Protection


MR Approved
POTC1110 Temporary Cathodic Protection
RFQ to Vendors to be Issued
POTC1120 Temporary Cathodic Protection
Purchase Order
POTC1130 Temporary Cathodic Protection
Ex. Work (50 % Delivery)
POTC1140 Temporary Cathodic Protection
Ex. Work (90 % Delivery)
POTC1150 Temporary Cathodic Protection
(50 % Received At Site)
POTC1160 Temporary Cathodic Protection
(90 % Received At Site)
POTC1170 Temporary Cathodic Protection
Received and PO Closed

Actual Work

Critical Re...

Remaining Work

Milestone

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

07-Nov-12

17-Nov-12

04-Jan-13

14-Jan-13

58

17-Dec-12

27-Dec-12

13-Feb-13

23-Feb-13

58

27-Dec-12

10-Feb-13

23-Feb-13

09-Apr-13

58

12-Mar-13

26-Apr-13

09-May-13

23-Jun-13

58

26-May-13

25-Jun-13

23-Jul-13

22-Aug-13

58

30-Jul-12

27-Jun-13

01-Sep-12

26-Jul-13

29

120

30-Jul-12

27-Nov-12

01-Sep-12

30-Dec-12

33

30-Jul-12

01-Aug-12

01-Sep-12

03-Sep-12

33

01-Aug-12

08-Aug-12

03-Sep-12

10-Sep-12

33

22-Aug-12

29-Aug-12

24-Sep-12

01-Oct-12

33

10

08-Sep-12

18-Sep-12

11-Oct-12

21-Oct-12

33

10

28-Sep-12

08-Oct-12

31-Oct-12

10-Nov-12

33

10

18-Oct-12

28-Oct-12

20-Nov-12

30-Nov-12

33

10

07-Nov-12

17-Nov-12

10-Dec-12

20-Dec-12

33

10

17-Nov-12

27-Nov-12

20-Dec-12

30-Dec-12

33

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 70 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Permenant Cathodic Protection

POPC1100 Permanent Cathodic Protection


MR Approved
POPC1110 Permanent Cathodic Protection
RFQ to Vendors to be Issued
POPC1120 Permanent Cathodic Protection
Purchase Order
POPC1130 Permanent Cathodic Protection
Ex. Work (50 % Delivery)
POPC1140 Permanent Cathodic Protection
Ex. Work (90 % Delivery)
POPC1150 Permanent Cathodic Protection
(50 % Received At Site)
POPC1160 Permanent Cathodic Protection
(90 % Received At Site)
POPC1170 Permanent Cathodic Protection
Received and PO Closed
Sub-Contractors

PSUB1100
PSUB1110
PSUB1120
PSUB1130
PSUB1140

Eq. And Tools Transportation


Sub-contractor to be Mobilized
Topographic Pre-Survey
Sub-Contractor to be Mobilized
Geotechnical Investigation
Sub-Contractor to be Mobilized
Security Sub-Contractor to be
Mobilized
Line Pipes Transportation
Sub-Contractor to be Mobilized

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

290

10-Sep-12

27-Jun-13

09-Oct-12

26-Jul-13

29

10-Sep-12

12-Sep-12

09-Oct-12

11-Oct-12

29

12-Sep-12

19-Sep-12

11-Oct-12

18-Oct-12

29

03-Oct-12

10-Oct-12

01-Nov-12

08-Nov-12

29

10

09-Dec-12

19-Dec-12

07-Jan-13

17-Jan-13

29

10

18-Jan-13

28-Jan-13

16-Feb-13

26-Feb-13

29

45

28-Jan-13

14-Mar-13

26-Feb-13

12-Apr-13

29

45

29-Mar-13

13-May-13

27-Apr-13

11-Jun-13

29

30

28-May-13

27-Jun-13

26-Jun-13

26-Jul-13

29

355

25-Apr-12

04-Sep-13

03-Apr-12

25-Nov-13

58

25-Apr-12

09-May-12

11

25-Apr-12

03-Apr-12

-15

27-May-12

17-Jul-12

37

0
0

Early Finish

Late Start

21-May-12
27-Jun-12

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 71 of 266

Late Finish

03-Jul-12
11-Jul-12

Total
Float 2012

2013
J

2014

32
11

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

PSUB1150

Earth Work Sub-Contractor to


be Mobilized
PSUB1160
Radiographic Test Works
Sub-Contractor to be Mobilized
PSUB1170
Concrete Works Sub-Contractor
Ready For Mobilization
PSUB1180
TPI to be Ready For
Mobilization
PSUB1190
Painting & FBE Coating
Sub-Contractor Mobilized
Anode Deep Well
PSUB1200
Sub-Contractor Ready For
Mobilization
PSUB1210
SCADA Nominated
Sub-contractor Sub-Contractor
Ready
For
Mobilization
PSUB1220
Drying &
Commissioning
Sub-Contractor Ready For
Mobilization
PSUB1230
Caliper Pig Running
Sub-contractor Ready For
Mobilization
Construction Phase
Main Pipeline
Straight Run Activities

Sec. (1) From KP (0) To KP (3)

Original
Duration

Early Start

18-Jul-12

01-Aug-12

11

08-Aug-12

30-Aug-12

17

08-Aug-12

22-Aug-12

11

22-Aug-12

13-Sep-12

17

03-Oct-12

13-Nov-12

30

26-Dec-12

05-Feb-13

30

Early Finish

Late Start

20-Mar-13

Late Finish

30-Apr-13
23-Jul-13

Total
Float 2012

12-Jun-13

30

04-Sep-13

04-Sep-13

25-Nov-13

25-Nov-13

58

378

02-Sep-12

25-Nov-13

19-Sep-12

27-Nov-13

378

02-Sep-12

25-Nov-13

22-Sep-12

27-Nov-13

237

02-Sep-12

11-Jun-13

22-Sep-12

25-Jul-13

37

72

02-Sep-12

27-Nov-12

22-Sep-12

12-Jan-13

37

Survey and Stacking Works

10

02-Sep-12

15-Sep-12

22-Sep-12

03-Oct-12

16

CPA1110

Right Of Way

15

05-Sep-12

23-Sep-12

24-Sep-12

11-Oct-12

16

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 72 of 266

2014

30

CPA1100

Actual Work

2013
J

Date
19-Jul-12

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPA1120

Trench Excavation

15

11-Sep-12

29-Sep-12

30-Sep-12

17-Oct-12

16

CPA1130

13

19-Sep-12

04-Oct-12

08-Oct-12

23-Oct-12

16

13

25-Sep-12

10-Oct-12

14-Oct-12

29-Oct-12

16

CPA1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

29-Sep-12

16-Oct-12

17-Oct-12

04-Nov-12

16

CPA1160

N.D.T & Welds Repair

15

04-Oct-12

22-Oct-12

17-Nov-12

05-Dec-12

37

CPA1170

FBE External Field Joint Coating

15

10-Oct-12

28-Oct-12

24-Nov-12

11-Dec-12

37

CPA1180

Pre-Padding

15

16-Oct-12

03-Nov-12

29-Nov-12

17-Dec-12

37

CPA1190

Lowering Of Pipeline

15

22-Oct-12

08-Nov-12

05-Dec-12

23-Dec-12

37

CPA1200

Tie-Ins Of Strings

15

28-Oct-12

14-Nov-12

11-Dec-12

30-Dec-12

37

CPA1210

Post Padding

15

03-Nov-12

20-Nov-12

17-Dec-12

06-Jan-13

37

CPA1220

Final Backfilling

15

08-Nov-12

27-Nov-12

23-Dec-12

12-Jan-13

37

76

16-Sep-12

15-Dec-12

11-Oct-12

29-Jan-13

37

CPA1140

Sec. (2) From KP (3) To KP (6)

CPB1100

Survey and Stacking Works

10

16-Sep-12

27-Sep-12

11-Oct-12

23-Oct-12

22

CPB1110

Right Of Way

15

23-Sep-12

10-Oct-12

11-Oct-12

29-Oct-12

16

CPB1120

Trench Excavation

15

29-Sep-12

16-Oct-12

17-Oct-12

04-Nov-12

16

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 73 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

13

07-Oct-12

22-Oct-12

25-Oct-12

10-Nov-12

16

13

13-Oct-12

28-Oct-12

31-Oct-12

15-Nov-12

16

CPB1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

16-Oct-12

03-Nov-12

04-Nov-12

21-Nov-12

16

CPB1160

N.D.T & Welds Repair

15

22-Oct-12

08-Nov-12

05-Dec-12

23-Dec-12

37

CPB1170

FBE External Field Joint Coating

15

28-Oct-12

14-Nov-12

11-Dec-12

30-Dec-12

37

CPB1180

Pre-Padding

15

03-Nov-12

20-Nov-12

17-Dec-12

06-Jan-13

37

CPB1190

Lowering Of Pipeline

15

08-Nov-12

27-Nov-12

23-Dec-12

12-Jan-13

37

CPB1200 Tie-Ins Of Strings

15

14-Nov-12

03-Dec-12

30-Dec-12

17-Jan-13

37

CPB1210 Post Padding

15

20-Nov-12

09-Dec-12

06-Jan-13

23-Jan-13

37

CPB1220 Final Backfilling

15

27-Nov-12

15-Dec-12

12-Jan-13

29-Jan-13

37

80

29-Sep-12

03-Jan-13

29-Oct-12

16-Feb-13

37

CPB1130
CPB1140

Sec. (3) From KP (6) To KP (9)

Early Finish

Late Start

Late Finish

Total
Float 2012

CPC1100

Survey and Stacking Works

10

29-Sep-12

10-Oct-12

29-Oct-12

10-Nov-12

26

CPC1110

Right Of Way

15

10-Oct-12

28-Oct-12

29-Oct-12

15-Nov-12

16

CPC1120

Trench Excavation

15

16-Oct-12

03-Nov-12

04-Nov-12

21-Nov-12

16

CPC1130

Transportation Of Coated Pipes


To Site

13

24-Oct-12

08-Nov-12

12-Nov-12

28-Nov-12

16

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 74 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

13

30-Oct-12

14-Nov-12

18-Nov-12

04-Dec-12

16

CPC1150

Stringing Of Pipes Along The


Route
Welding Of Pipes

15

03-Nov-12

20-Nov-12

21-Nov-12

10-Dec-12

16

CPC1160

N.D.T & Welds Repair

15

08-Nov-12

27-Nov-12

23-Dec-12

12-Jan-13

37

CPC1170

FBE External Field Joint Coating

15

14-Nov-12

03-Dec-12

30-Dec-12

17-Jan-13

37

CPC1180

Pre-Padding

15

20-Nov-12

09-Dec-12

06-Jan-13

23-Jan-13

37

CPC1190

Lowering Of Pipeline

15

27-Nov-12

15-Dec-12

12-Jan-13

29-Jan-13

37

CPC1200 Tie-Ins Of Strings

15

03-Dec-12

20-Dec-12

17-Jan-13

04-Feb-13

37

CPC1210 Post Padding

15

09-Dec-12

27-Dec-12

23-Jan-13

10-Feb-13

37

CPC1220 Final Backfilling

15

15-Dec-12

03-Jan-13

29-Jan-13

16-Feb-13

37

84

11-Oct-12

21-Jan-13

15-Nov-12

05-Mar-13

37

CPC1140

Sec. (4) From KP (9) To KP (12)

Early Finish

Late Start

Late Finish

Total
Float 2012

CPD1100

Survey and Stacking Works

10

11-Oct-12

23-Oct-12

15-Nov-12

28-Nov-12

30

CPD1110

Right Of Way

15

28-Oct-12

14-Nov-12

15-Nov-12

04-Dec-12

16

CPD1120

Trench Excavation

15

03-Nov-12

20-Nov-12

21-Nov-12

10-Dec-12

16

CPD1130

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route

13

11-Nov-12

27-Nov-12

01-Dec-12

16-Dec-12

16

13

17-Nov-12

03-Dec-12

06-Dec-12

22-Dec-12

16

CPD1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 75 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPD1150

Welding Of Pipes

15

20-Nov-12

09-Dec-12

10-Dec-12

29-Dec-12

16

CPD1160

N.D.T & Welds Repair

15

27-Nov-12

15-Dec-12

12-Jan-13

29-Jan-13

37

CPD1170

FBE External Field Joint Coating

15

03-Dec-12

20-Dec-12

17-Jan-13

04-Feb-13

37

CPD1180

Pre-Padding

15

09-Dec-12

27-Dec-12

23-Jan-13

10-Feb-13

37

CPD1190

Lowering Of Pipeline

15

15-Dec-12

03-Jan-13

29-Jan-13

16-Feb-13

37

CPD1200 Tie-Ins Of Strings

15

20-Dec-12

09-Jan-13

04-Feb-13

21-Feb-13

37

CPD1210 Post Padding

15

27-Dec-12

15-Jan-13

10-Feb-13

27-Feb-13

37

CPD1220 Final Backfilling

15

03-Jan-13

21-Jan-13

16-Feb-13

05-Mar-13

37

88

24-Oct-12

07-Feb-13

04-Dec-12

23-Mar-13

37

Sec. (5) From KP (12) To KP (15)

CPE1100

Survey and Stacking Works

10

24-Oct-12

05-Nov-12

04-Dec-12

16-Dec-12

34

CPE1110

Right Of Way

15

14-Nov-12

03-Dec-12

04-Dec-12

22-Dec-12

16

CPE1120

Trench Excavation

15

20-Nov-12

09-Dec-12

10-Dec-12

29-Dec-12

16

CPE1130

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

13

29-Nov-12

15-Dec-12

18-Dec-12

05-Jan-13

16

13

05-Dec-12

20-Dec-12

24-Dec-12

10-Jan-13

16

15

09-Dec-12

27-Dec-12

29-Dec-12

16-Jan-13

16

CPE1140
CPE1150

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 76 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPE1160

N.D.T & Welds Repair

15

15-Dec-12

03-Jan-13

29-Jan-13

16-Feb-13

37

CPE1170

FBE External Field Joint Coating

15

20-Dec-12

09-Jan-13

04-Feb-13

21-Feb-13

37

CPE1180

Pre-Padding

15

27-Dec-12

15-Jan-13

10-Feb-13

27-Feb-13

37

CPE1190

Lowering Of Pipeline

15

03-Jan-13

21-Jan-13

16-Feb-13

05-Mar-13

37

CPE1200 Tie-Ins Of Strings

15

09-Jan-13

27-Jan-13

21-Feb-13

11-Mar-13

37

CPE1210 Post Padding

15

15-Jan-13

02-Feb-13

27-Feb-13

17-Mar-13

37

CPE1220 Final Backfilling

15

21-Jan-13

07-Feb-13

05-Mar-13

23-Mar-13

37

92

06-Nov-12

25-Feb-13

22-Dec-12

09-Apr-13

37

Sec. (6) From KP (15) To KP (18)

CPF1100

Survey and Stacking Works

10

06-Nov-12

18-Nov-12

22-Dec-12

05-Jan-13

38

CPF1110

Right Of Way

15

03-Dec-12

20-Dec-12

22-Dec-12

10-Jan-13

16

CPF1120

Trench Excavation

15

09-Dec-12

27-Dec-12

29-Dec-12

16-Jan-13

16

CPF1130

13

17-Dec-12

03-Jan-13

07-Jan-13

22-Jan-13

16

13

23-Dec-12

09-Jan-13

13-Jan-13

28-Jan-13

16

CPF1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

27-Dec-12

15-Jan-13

16-Jan-13

03-Feb-13

16

CPF1160

N.D.T & Welds Repair

15

03-Jan-13

21-Jan-13

16-Feb-13

05-Mar-13

37

CPF1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 77 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPF1170

FBE External Field Joint Coating

15

09-Jan-13

27-Jan-13

21-Feb-13

11-Mar-13

37

CPF1180

Pre-Padding

15

15-Jan-13

02-Feb-13

27-Feb-13

17-Mar-13

37

CPF1190

Lowering Of Pipeline

15

21-Jan-13

07-Feb-13

05-Mar-13

23-Mar-13

37

CPF1200

Tie-Ins Of Strings

15

27-Jan-13

13-Feb-13

11-Mar-13

28-Mar-13

37

CPF1210

Post Padding

15

02-Feb-13

19-Feb-13

17-Mar-13

03-Apr-13

37

CPF1220

Final Backfilling

15

07-Feb-13

25-Feb-13

23-Mar-13

09-Apr-13

37

96

19-Nov-12

14-Mar-13

10-Jan-13

27-Apr-13

37

CPG1100 Survey and Stacking Works

10

19-Nov-12

02-Dec-12

10-Jan-13

22-Jan-13

42

CPG1110

15

20-Dec-12

09-Jan-13

10-Jan-13

28-Jan-13

16

CPG1120 Trench Excavation

15

27-Dec-12

15-Jan-13

16-Jan-13

03-Feb-13

16

CPG1130 Transportation Of Coated Pipes


To Site
CPG1140 Stringing Of Pipes Along The
Route
CPG1150 Welding Of Pipes

13

06-Jan-13

21-Jan-13

24-Jan-13

09-Feb-13

16

13

12-Jan-13

27-Jan-13

30-Jan-13

14-Feb-13

16

15

15-Jan-13

02-Feb-13

03-Feb-13

20-Feb-13

16

CPG1160 N.D.T & Welds Repair

15

21-Jan-13

07-Feb-13

05-Mar-13

23-Mar-13

37

CPG1170 FBE External Field Joint Coating

15

27-Jan-13

13-Feb-13

11-Mar-13

28-Mar-13

37

Sec. (7) From KP (18) To KP (21)

Right Of Way

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 78 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CPG1180 Pre-Padding

15

02-Feb-13

19-Feb-13

17-Mar-13

03-Apr-13

37

CPG1190 Lowering Of Pipeline

15

07-Feb-13

25-Feb-13

23-Mar-13

09-Apr-13

37

CPG1200 Tie-Ins Of Strings

15

13-Feb-13

03-Mar-13

28-Mar-13

15-Apr-13

37

CPG1210 Post Padding

15

19-Feb-13

09-Mar-13

03-Apr-13

21-Apr-13

37

CPG1220 Final Backfilling

15

25-Feb-13

14-Mar-13

09-Apr-13

27-Apr-13

37

100

03-Dec-12

01-Apr-13

28-Jan-13

14-May-13

37

Sec. (8) From KP (21) To KP (24)

Early Finish

Late Start

Late Finish

Total
Float 2012

CPH1100

Survey and Stacking Works

10

03-Dec-12

15-Dec-12

28-Jan-13

09-Feb-13

46

CPH1110

Right Of Way

15

09-Jan-13

27-Jan-13

28-Jan-13

14-Feb-13

16

CPH1120

Trench Excavation

15

15-Jan-13

02-Feb-13

03-Feb-13

20-Feb-13

16

CPH1130

13

23-Jan-13

07-Feb-13

11-Feb-13

26-Feb-13

16

13

29-Jan-13

13-Feb-13

17-Feb-13

04-Mar-13

16

CPH1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

02-Feb-13

19-Feb-13

20-Feb-13

10-Mar-13

16

CPH1160

N.D.T & Welds Repair

15

07-Feb-13

25-Feb-13

23-Mar-13

09-Apr-13

37

CPH1170

FBE External Field Joint Coating

15

13-Feb-13

03-Mar-13

28-Mar-13

15-Apr-13

37

CPH1180

Pre-Padding

15

19-Feb-13

09-Mar-13

03-Apr-13

21-Apr-13

37

CPH1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 79 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

15

25-Feb-13

14-Mar-13

09-Apr-13

27-Apr-13

37

CPH1200 Tie-Ins Of Strings

15

03-Mar-13

20-Mar-13

15-Apr-13

02-May-13

37

CPH1210 Post Padding

15

09-Mar-13

26-Mar-13

21-Apr-13

08-May-13

37

CPH1220 Final Backfilling

15

14-Mar-13

01-Apr-13

27-Apr-13

14-May-13

37

104

16-Dec-12

18-Apr-13

14-Feb-13

02-Jun-13

37

CPH1190

Lowering Of Pipeline

Sec. (9) From KP (24) To KP (27)

Early Finish

Late Start

Late Finish

Total
Float 2012

CPI1100

Survey and Stacking Works

10

16-Dec-12

29-Dec-12

14-Feb-13

26-Feb-13

50

CPI1110

Right Of Way

15

27-Jan-13

13-Feb-13

14-Feb-13

04-Mar-13

16

CPI1120

Trench Excavation

15

02-Feb-13

19-Feb-13

20-Feb-13

10-Mar-13

16

CPI1130

13

10-Feb-13

25-Feb-13

28-Feb-13

16-Mar-13

16

13

16-Feb-13

03-Mar-13

06-Mar-13

21-Mar-13

16

CPI1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

19-Feb-13

09-Mar-13

10-Mar-13

27-Mar-13

16

CPI1160

N.D.T & Welds Repair

15

25-Feb-13

14-Mar-13

09-Apr-13

27-Apr-13

37

CPI1170

FBE External Field Joint Coating

15

03-Mar-13

20-Mar-13

15-Apr-13

02-May-13

37

CPI1180

Pre-Padding

15

09-Mar-13

26-Mar-13

21-Apr-13

08-May-13

37

CPI1190

Lowering Of Pipeline

15

14-Mar-13

01-Apr-13

27-Apr-13

14-May-13

37

CPI1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 80 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPI1200

Tie-Ins Of Strings

15

20-Mar-13

07-Apr-13

02-May-13

20-May-13

37

CPI1210

Post Padding

15

26-Mar-13

13-Apr-13

08-May-13

26-May-13

37

CPI1220

Final Backfilling

15

01-Apr-13

18-Apr-13

14-May-13

02-Jun-13

37

108

30-Dec-12 06-May-13

04-Mar-13

19-Jun-13

37

Sec. (10) From KP (27) To KP (30)

CPJ1100

Survey and Stacking Works

10

30-Dec-12

12-Jan-13

04-Mar-13

16-Mar-13

54

CPJ1110

Right Of Way

15

13-Feb-13

03-Mar-13

04-Mar-13

21-Mar-13

16

CPJ1120

Trench Excavation

15

19-Feb-13

09-Mar-13

10-Mar-13

27-Mar-13

16

CPJ1130

13

27-Feb-13

14-Mar-13

18-Mar-13

02-Apr-13

16

13

05-Mar-13

20-Mar-13

24-Mar-13

08-Apr-13

16

CPJ1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

09-Mar-13

26-Mar-13

27-Mar-13

14-Apr-13

16

CPJ1160

N.D.T & Welds Repair

15

14-Mar-13

01-Apr-13

27-Apr-13

14-May-13

37

CPJ1170

FBE External Field Joint Coating

15

20-Mar-13

07-Apr-13

02-May-13

20-May-13

37

CPJ1180

Pre-Padding

15

26-Mar-13

13-Apr-13

08-May-13

26-May-13

37

CPJ1190

Lowering Of Pipeline

15

01-Apr-13

18-Apr-13

14-May-13

02-Jun-13

37

CPJ1200

Tie-Ins Of Strings

15

07-Apr-13

24-Apr-13

20-May-13

08-Jun-13

37

CPJ1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 81 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

CPJ1210

Post Padding

15

13-Apr-13

30-Apr-13

26-May-13

13-Jun-13

37

CPJ1220

Final Backfilling

15

18-Apr-13

06-May-13

02-Jun-13

19-Jun-13

37

112

13-Jan-13

23-May-13

25-Mar-13

08-Jul-13

37

Sec. (11) From KP (30) To KP (33)

CPK1100

Survey and Stacking Works

10

13-Jan-13

24-Jan-13

25-Mar-13

06-Apr-13

61

CPK1110

Right Of Way

15

03-Mar-13

20-Mar-13

25-Mar-13

11-Apr-13

19

CPK1120

Trench Excavation

15

09-Mar-13

26-Mar-13

31-Mar-13

17-Apr-13

19

CPK1130

13

14-Mar-13

30-Mar-13

04-Apr-13

20-Apr-13

18

13

20-Mar-13

04-Apr-13

10-Apr-13

25-Apr-13

18

CPK1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

26-Mar-13

13-Apr-13

14-Apr-13

01-May-13

16

CPK1160

N.D.T & Welds Repair

15

01-Apr-13

18-Apr-13

14-May-13

02-Jun-13

37

CPK1170

FBE External Field Joint Coating

15

07-Apr-13

24-Apr-13

20-May-13

08-Jun-13

37

CPK1180

Pre-Padding

15

13-Apr-13

30-Apr-13

26-May-13

13-Jun-13

37

CPK1190

Lowering Of Pipeline

15

18-Apr-13

06-May-13

02-Jun-13

19-Jun-13

37

CPK1200 Tie-Ins Of Strings

15

24-Apr-13

12-May-13

08-Jun-13

25-Jun-13

37

CPK1210 Post Padding

15

30-Apr-13

18-May-13

13-Jun-13

01-Jul-13

37

CPK1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 82 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

CPK1220 Final Backfilling


Sec. (12) From KP (33) To KP (36)

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

15

06-May-13 23-May-13

19-Jun-13

08-Jul-13

37

116

26-Jan-13

11-Jun-13

11-Apr-13

25-Jul-13

37

CPL1100

Survey and Stacking Works

10

26-Jan-13

06-Feb-13

11-Apr-13

23-Apr-13

65

CPL1110

Right Of Way

15

20-Mar-13

07-Apr-13

11-Apr-13

29-Apr-13

19

CPL1120

Trench Excavation

15

26-Mar-13

13-Apr-13

17-Apr-13

05-May-13

19

CPL1130

13

31-Mar-13

15-Apr-13

22-Apr-13

07-May-13

19

13

06-Apr-13

21-Apr-13

28-Apr-13

13-May-13

19

CPL1150

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
Route
Welding Of Pipes

15

13-Apr-13

30-Apr-13

01-May-13

19-May-13

16

CPL1160

N.D.T & Welds Repair

15

18-Apr-13

06-May-13

02-Jun-13

19-Jun-13

37

CPL1170

FBE External Field Joint Coating

15

24-Apr-13

12-May-13

08-Jun-13

25-Jun-13

37

CPL1180

Pre-Padding

15

30-Apr-13

18-May-13

13-Jun-13

01-Jul-13

37

CPL1190

Lowering Of Pipeline

15

06-May-13 23-May-13

19-Jun-13

08-Jul-13

37

CPL1200

Tie-Ins Of Strings

15

12-May-13 30-May-13

25-Jun-13

14-Jul-13

37

CPL1210

Post Padding

15

18-May-13

05-Jun-13

01-Jul-13

20-Jul-13

37

CPL1220

Final Backfilling

15

23-May-13

11-Jun-13

08-Jul-13

25-Jul-13

37

CPL1140

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 83 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Open Cut Crossing (no. off 84)

CPCR100

Open Cut Crossings

HDD Crossing (no. off 3)

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

164

15-Nov-12 30-May-13

20-Jan-13

01-Aug-13

53

164

15-Nov-12 30-May-13

20-Jan-13

01-Aug-13

53

144

20-Dec-12

10-Jun-13

24-Feb-13

13-Aug-13

54

CPCR1110

HDD Crossing No. (1)

46

20-Dec-12

14-Feb-13

24-Feb-13

18-Apr-13

54

CPCR1120

HDD Crossing No. (2)

46

18-Feb-13

13-Apr-13

22-Apr-13

16-Jun-13

54

CPCR1130

HDD Crossing No. (3)

46

16-Apr-13

10-Jun-13

19-Jun-13

13-Aug-13

54

287

29-Oct-12

06-Oct-13

17-Dec-12

03-Nov-13

24

204

29-Oct-12

29-Jun-13

17-Dec-12

31-Jul-13

27

180

29-Oct-12

01-Jun-13

17-Dec-12

20-Jul-13

41

180

27-Nov-12

29-Jun-13

30-Dec-12

31-Jul-13

27

80

02-Jul-13

06-Oct-13

31-Jul-13

03-Nov-13

24

CPCP1100 Test Post Distribution & Erection

20

02-Jul-13

27-Jul-13

31-Jul-13

24-Aug-13

24

CPCP1110 Deep Well (25 M)

20

09-Jul-13

01-Aug-13

06-Aug-13

29-Aug-13

24

CPCP1120 Anode For Permanent CP

20

15-Jul-13

07-Aug-13

12-Aug-13

05-Sep-13

24

CPCP1130 Rectifier To Be Installed

10

07-Aug-13

19-Aug-13

05-Sep-13

17-Sep-13

24

Cathodic Protection System

Temporary Cathodic Protection

CPCT1100 Cables To Be Welded By


Thermite
CPCT1110 Anodes For Temperory CP
Permanent Cathodic Protection

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 84 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

CPCP1140 Junction Box & Cables To Be


Connected
CPCP1150 CP System to Be Checked &
Tested
Anchor Blocks

Anchor Block At QP Refinery

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

20

19-Aug-13

12-Sep-13

17-Sep-13

10-Oct-13

24

20

12-Sep-13

06-Oct-13

10-Oct-13

03-Nov-13

24

34

23-May-13

03-Jul-13

21-Jul-13

29-Aug-13

48

22

23-May-13

19-Jun-13

21-Jul-13

27-Aug-13

58

CPAB1100 Anchor Flange To Be Welded

23-May-13 26-May-13

21-Jul-13

23-Jul-13

48

CPAB1110 Excavation For Anchor Block At


QP Refinery
CPAB1120 PC For Anchor Block At QP
Refinery
CPAB1130 RC For Anchor Block At QP
Refinery
CPAB1140 Backfilling For Anchor Block At
QP Refinery

28-May-13

03-Jun-13

24-Jul-13

30-Jul-13

48

03-Jun-13

08-Jun-13

30-Jul-13

04-Aug-13

48

08-Jun-13

17-Jun-13

08-Aug-13

18-Aug-13

52

17-Jun-13

19-Jun-13

25-Aug-13

27-Aug-13

58

22

08-Jun-13

03-Jul-13

04-Aug-13

29-Aug-13

48

CPAB2100 Anchor Flange To Be Welded

08-Jun-13

10-Jun-13

04-Aug-13

06-Aug-13

48

CPAB2110 Excavation For Anchor Block At


BSV-3
CPAB2120 PC For Anchor Block At BSV-3

11-Jun-13

17-Jun-13

07-Aug-13

13-Aug-13

48

17-Jun-13

22-Jun-13

13-Aug-13

18-Aug-13

48

CPAB2130 RC For Anchor Block At BSV-3

22-Jun-13

01-Jul-13

18-Aug-13

27-Aug-13

48

CPAB2140 Backfilling For Anchor Block At


BSV-3

01-Jul-13

03-Jul-13

27-Aug-13

29-Aug-13

48

Anchor Block At BSV-3

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 85 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Hydraulic Test

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

113

17-Jun-13

29-Oct-13

13-Aug-13

21-Nov-13

20

CPHT1100

Pipeline Cleaning & Gauging

14

17-Jun-13

03-Jul-13

13-Aug-13

29-Aug-13

48

CPHT1110

Pipeline Water Filling

45

06-Aug-13

29-Sep-13

29-Aug-13

22-Oct-13

20

CPHT1120

Pipeline Pressurizing

10

29-Sep-13

10-Oct-13

22-Oct-13

03-Nov-13

20

CPHT1130

Pipeline Dewatering & Flushing

15

12-Oct-13

29-Oct-13

04-Nov-13

21-Nov-13

20

141

11-Jun-13

25-Nov-13

25-Jul-13

27-Nov-13

Common Activities

CPCA1100

Pipeline Post Markers

30

11-Jun-13

17-Jul-13

25-Jul-13

29-Aug-13

37

CPCA1110

ROW Re-Instatement

60

04-Aug-13

14-Oct-13

17-Sep-13

26-Nov-13

37

CPCA1120

Punch List & Achieve


Mechanical Completion For PL
and All Facilities

30

21-Oct-13

25-Nov-13

23-Oct-13

27-Nov-13

360

05-Sep-12

05-Nov-13

19-Sep-12

27-Nov-13

19

354

05-Sep-12

29-Oct-13

19-Sep-12

27-Nov-13

25

No. Off (7) Culverts

183

05-Sep-12

10-Apr-13

19-Sep-12

19-May-13

34

Culvert No. (1)

39

05-Sep-12

21-Oct-12

19-Sep-12

12-Jan-13

69

CRCU1100
Excavation For Culvert No. (1)

05-Sep-12

11-Sep-12

19-Sep-12

25-Sep-12

13

CRCU1110PC For Culvert No. (1)

11-Sep-12

20-Sep-12

25-Sep-12

04-Oct-12

13

QP Refinery
Civil Work

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 86 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CRCU1120
RC For Culvert No. (1)

16

20-Sep-12

09-Oct-12

04-Oct-12

23-Oct-12

13

CRCU1130
Backfilling For Culvert No. (1)

10

09-Oct-12

21-Oct-12

30-Dec-12

12-Jan-13

69

39

03-Oct-12

18-Nov-12

17-Oct-12

23-Jan-13

55

CRCU1200
Excavation For Culvert No. (2)

03-Oct-12

09-Oct-12

17-Oct-12

23-Oct-12

13

CRCU1210
PC For Culvert No. (2)

09-Oct-12

18-Oct-12

23-Oct-12

01-Nov-12

13

CRCU1220
RC For Culvert No. (2)

16

18-Oct-12

06-Nov-12

01-Nov-12

20-Nov-12

13

CRCU1230
Backfilling For Culvert No. (2)

10

06-Nov-12

18-Nov-12

12-Jan-13

23-Jan-13

55

39

31-Oct-12

17-Dec-12

14-Nov-12

04-Feb-13

41

CRCU1300
Excavation For Culvert No. (3)

31-Oct-12

06-Nov-12

14-Nov-12

20-Nov-12

13

CRCU1310
PC For Culvert No. (3)

06-Nov-12

15-Nov-12

20-Nov-12

01-Dec-12

13

CRCU1320
RC For Culvert No. (3)

16

15-Nov-12

05-Dec-12

01-Dec-12

19-Dec-12

13

CRCU1330
Backfilling For Culvert No. (3)

10

05-Dec-12

17-Dec-12

23-Jan-13

04-Feb-13

41

39

29-Nov-12

16-Jan-13

13-Dec-12

16-Feb-13

27

CRCU1400
Excavation For Culvert No. (4)

29-Nov-12

05-Dec-12

13-Dec-12

19-Dec-12

13

CRCU1410
PC For Culvert No. (4)

05-Dec-12

15-Dec-12

19-Dec-12

30-Dec-12

13

Culvert No. (2)

Culvert No. (3)

Culvert No. (4)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 87 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CRCU1420
RC For Culvert No. (4)

16

15-Dec-12

05-Jan-13

30-Dec-12

19-Jan-13

13

CRCU1430
Backfilling For Culvert No. (4)

10

05-Jan-13

16-Jan-13

04-Feb-13

16-Feb-13

27

39

29-Dec-12

13-Feb-13

13-Jan-13

27-Feb-13

13

CRCU1500
Excavation For Culvert No. (5)

29-Dec-12

05-Jan-13

13-Jan-13

19-Jan-13

13

CRCU1510
PC For Culvert No. (5)

05-Jan-13

14-Jan-13

19-Jan-13

28-Jan-13

13

CRCU1520
RC For Culvert No. (5)

16

14-Jan-13

02-Feb-13

28-Jan-13

16-Feb-13

13

CRCU1530
Backfilling For Culvert No. (5)

10

02-Feb-13

13-Feb-13

16-Feb-13

27-Feb-13

13

39

27-Jan-13

13-Mar-13

06-Mar-13

07-May-13

48

CRCU1600
Excavation For Culvert No. (6)

27-Jan-13

02-Feb-13

06-Mar-13

12-Mar-13

34

CRCU1610
PC For Culvert No. (6)

02-Feb-13

11-Feb-13

12-Mar-13

21-Mar-13

34

CRCU1620
RC For Culvert No. (6)

16

11-Feb-13

02-Mar-13

21-Mar-13

09-Apr-13

34

CRCU1630
Backfilling For Culvert No. (6)

10

02-Mar-13

13-Mar-13

25-Apr-13

07-May-13

48

39

24-Feb-13

10-Apr-13

03-Apr-13

19-May-13

34

CRCU1700
Excavation For Culvert No. (7)

24-Feb-13

02-Mar-13

03-Apr-13

09-Apr-13

34

CRCU1710
PC For Culvert No. (7)

02-Mar-13

11-Mar-13

09-Apr-13

18-Apr-13

34

Culvert No. (5)

Culvert No. (6)

Culvert No. (7)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 88 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CRCU1720
RC For Culvert No. (7)

16

11-Mar-13

30-Mar-13

18-Apr-13

07-May-13

34

CRCU1730
Backfilling For Culvert No. (7)

10

30-Mar-13

10-Apr-13

07-May-13

19-May-13

34

120

06-Nov-12

30-Mar-13

16-Dec-12

07-May-13

34

CRCS1100 Pre-Cast (220) Sleepers

75

06-Nov-12

05-Feb-13

16-Dec-12

16-Mar-13

34

CRCS1110 Erection Of (220) Sleepers

75

31-Dec-12

30-Mar-13

09-Feb-13

07-May-13

34

157

13-Feb-13

18-Aug-13

27-Feb-13

01-Sep-13

12

14

13-Feb-13

02-Mar-13

27-Feb-13

16-Mar-13

12

CRCE1110 P.C (Foundation)

02-Mar-13

07-Mar-13

16-Mar-13

21-Mar-13

12

CRCE1120 R.C (Foundation)

16

07-Mar-13

26-Mar-13

21-Mar-13

09-Apr-13

12

CRCE1130 Insulation (Foundation)

26-Mar-13

01-Apr-13

09-Apr-13

15-Apr-13

12

CRCE1140 BackFilling (Foundation)

01-Apr-13

04-Apr-13

15-Apr-13

18-Apr-13

12

CRCE1150 R.C (Columns)

04-Apr-13

14-Apr-13

18-Apr-13

28-Apr-13

12

CRCE1160 R.C (Slab& Beams)

28

14-Apr-13

16-May-13

28-Apr-13

01-Jun-13

12

CRCE1170 External Finishing

60

25-May-13 05-Aug-13

18-Jun-13

28-Aug-13

20

CRCE1180 Internal Finishing

60

08-Jun-13

22-Jun-13

01-Sep-13

12

No. Off (220) Seepers

SER12 Extension

CRCE1100 Demolition & Excavation

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

18-Aug-13

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 89 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Pump House

E&I Duct Bank

Original
Duration

Early Start

Early Finish

Late Start

Late Finish

Total
Float 2012

204

02-Mar-13

29-Oct-13

17-Mar-13

27-Nov-13

25

22

22-May-13

18-Jun-13

08-Jun-13

28-Jul-13

33

CRCP1700
Excavation For E&I Duct Bank

22-May-13 29-May-13

08-Jun-13

13-Jun-13

13

CRCP1710
PC For E&I Duct Bank

29-May-13

04-Jun-13

13-Jun-13

19-Jun-13

13

CRCP1720
RC For E&I Duct Bank

10

04-Jun-13

16-Jun-13

19-Jun-13

01-Jul-13

13

16-Jun-13

18-Jun-13

25-Jul-13

28-Jul-13

33

72

02-Mar-13

25-May-13

17-Mar-13

13-Jul-13

40

22

02-Mar-13

27-Mar-13

17-Mar-13

30-Jun-13

80

02-Mar-13

07-Mar-13

17-Mar-13

23-Mar-13

13

07-Mar-13

13-Mar-13

23-Mar-13

28-Mar-13

13

10

13-Mar-13

25-Mar-13

28-Mar-13

09-Apr-13

13

25-Mar-13

27-Mar-13

27-Jun-13

30-Jun-13

80

22

13-Mar-13

08-Apr-13

28-Mar-13

02-Jul-13

72

13-Mar-13

19-Mar-13

28-Mar-13

03-Apr-13

13

19-Mar-13

25-Mar-13

03-Apr-13

09-Apr-13

13

CRCP1730
Backfilling For E&I Duct Bank
Pump Foundations

Main Pump No. (1)

CRCP1100
Excavation For Main Pump No.
(1)
CRCP1110
PC For Main Pump No. (1)
CRCP1120
RC For Main Pump No. (1)
CRCP1130
Backfilling For Main Pump No.
(1)
Main Pump No. (2)

CRCP1200
Excavation For Main Pump No.
(2)
CRCP1210
PC For Main Pump No. (2)

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 90 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

10

25-Mar-13

06-Apr-13

09-Apr-13

21-Apr-13

13

06-Apr-13

08-Apr-13

30-Jun-13

02-Jul-13

72

22

25-Mar-13

20-Apr-13

09-Apr-13

06-Jul-13

64

25-Mar-13

31-Mar-13

09-Apr-13

15-Apr-13

13

31-Mar-13

06-Apr-13

15-Apr-13

21-Apr-13

13

10

06-Apr-13

17-Apr-13

21-Apr-13

02-May-13

13

17-Apr-13

20-Apr-13

02-Jul-13

06-Jul-13

64

22

06-Apr-13

01-May-13

21-Apr-13

08-Jul-13

56

CRCP1400
Excavation For Booster Pump
No. (1)
CRCP1410
PC For Booster Pump No. (1)

06-Apr-13

11-Apr-13

21-Apr-13

27-Apr-13

13

11-Apr-13

17-Apr-13

27-Apr-13

02-May-13

13

CRCP1420
RC For Booster Pump No. (1)

10

17-Apr-13

29-Apr-13

02-May-13

14-May-13

13

CRCP1430
Backfilling For Booster Pump
No. (1)

29-Apr-13

01-May-13

06-Jul-13

08-Jul-13

56

22

17-Apr-13

13-May-13

02-May-13

10-Jul-13

48

17-Apr-13

23-Apr-13

02-May-13

08-May-13

13

23-Apr-13

29-Apr-13

08-May-13

14-May-13

13

CRCP1220
RC For Main Pump No. (2)
CRCP1230
Backfilling For Main Pump No.
(2)
Main Pump No. (3)

CRCP1300
Excavation For Main Pump No.
(3)
CRCP1310
PC For Main Pump No. (3)
CRCP1320
RC For Main Pump No. (3)
CRCP1330
Backfilling For Main Pump No.
(3)
Booster Pump No. (1)

Booster Pump No. (2)

CRCP1500
Excavation For Booster Pump
No. (2)
CRCP1510
PC For Booster Pump No. (2)

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 91 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CRCP1520
RC For Booster Pump No. (2)

10

29-Apr-13

CRCP1530
Backfilling For Booster Pump
No. (2)

Booster Pump No. (3)

Early Finish

11-May-13

11-May-13 13-May-13

Late Start

Late Finish

Total
Float 2012

14-May-13

26-May-13

13

08-Jul-13

10-Jul-13

48

22

29-Apr-13

25-May-13

14-May-13

13-Jul-13

40

CRCP1600
Excavation For Booster Pump
No. (3)
CRCP1610
PC For Booster Pump No. (3)

29-Apr-13

05-May-13

14-May-13

20-May-13

13

05-May-13 11-May-13

20-May-13

26-May-13

13

CRCP1620
RC For Booster Pump No. (3)

10

11-May-13 22-May-13

26-May-13

08-Jun-13

13

CRCP1630
Backfilling For Booster Pump
No. (3)

22-May-13 25-May-13

10-Jul-13

13-Jul-13

40

169

11-Apr-13

29-Oct-13

03-Jun-13

27-Nov-13

25

CRCD1100
Steel Structure Fabrication For
The Pump Shed
CRCD1110Excavation For For The Pump
Shed
CRCD1120
PC For For The Pump Shed

60

11-Apr-13

22-Jun-13

03-Jun-13

13-Aug-13

44

10

22-May-13

04-Jun-13

08-Jun-13

19-Jun-13

13

10

04-Jun-13

16-Jun-13

19-Jun-13

01-Jul-13

13

CRCD1130
RC For For The Pump Shed

20

16-Jun-13

10-Jul-13

01-Jul-13

25-Jul-13

13

CRCD1140
Backfilling For The Pump Shed

10-Jul-13

15-Jul-13

28-Jul-13

01-Aug-13

15

CRCD1150
Steel Structure Erection For The
Pump Shed
CRCD1160
Corrugated Sheets Cladding For
The Pump Shed

30

15-Jul-13

19-Aug-13

13-Aug-13

18-Sep-13

25

15

19-Aug-13

07-Sep-13

18-Sep-13

06-Oct-13

25

The Pump Shed

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 92 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

CRCD1170
Paving For The Pump Shed

15

07-Sep-13

24-Sep-13

06-Oct-13

23-Oct-13

25

CRCD1180
Insulation & Fireproofing

30

24-Sep-13

29-Oct-13

23-Oct-13

27-Nov-13

25

81

22-May-13 27-Aug-13

15-Jun-13

12-Sep-13

13

22-May-13 30-May-13

15-Jun-13

22-Jun-13

19

Launcher Station

Early Finish

Late Start

Late Finish

Total
Float 2012

CRCL1100 Excavation For Launcher


Station
CRCL1110 PC For Launcher Station

10

30-May-13

11-Jun-13

22-Jun-13

03-Jul-13

19

CRCL1120 RC For Launcher Station

18

18-Jun-13

10-Jul-13

03-Jul-13

25-Jul-13

13

10-Jul-13

17-Jul-13

25-Jul-13

01-Aug-13

13

CRCL1140 Fence For Launcher Station

20

17-Jul-13

10-Aug-13

01-Aug-13

25-Aug-13

13

CRCL1150 Paving For Launcher Station

15

10-Aug-13

27-Aug-13

25-Aug-13

12-Sep-13

13

45

15-Aug-13

08-Oct-13

31-Aug-13

23-Oct-13

13

CRCR1100 Roads For Launcher Area

25

15-Aug-13

15-Sep-13

31-Aug-13

30-Sep-13

13

CRCR1110 Roads For Pump Area

10

15-Sep-13

26-Sep-13

30-Sep-13

12-Oct-13

13

CRCR1120 Roads For SER 12

10

26-Sep-13

08-Oct-13

12-Oct-13

23-Oct-13

13

159

30-Apr-13

05-Nov-13

19-May-13

07-Nov-13

40

30-Apr-13

17-Jun-13

19-May-13

13-Aug-13

48

CRCL1130 Backfilling For Launcher Station

Roads

Mechanical Work

General

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 93 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

30

30-Apr-13

05-Jun-13

19-May-13

24-Jun-13

16

06-Jun-13

17-Jun-13

03-Aug-13

13-Aug-13

48

159

30-Apr-13

05-Nov-13

19-May-13

07-Nov-13

CRMP1100 Piping Fabrication

60

30-Apr-13

11-Jul-13

19-May-13

30-Jul-13

16

CRMP1110 Sand Blasting & Panting

48

22-May-13

20-Jul-13

02-Jul-13

28-Aug-13

34

CRMP1120 Piping & Pumps Erection

60

28-Jul-13

07-Oct-13

30-Jul-13

09-Oct-13

CRMP1130 Loops to be Water Filled

15

07-Oct-13

24-Oct-13

09-Oct-13

27-Oct-13

CRMP1140 Loops to be Pressurized

15

13-Oct-13

30-Oct-13

15-Oct-13

02-Nov-13

CRMP1150 Loops to be Dewatered &


Flushed
CRMP1160 Tie in at Refinary

15

19-Oct-13

05-Nov-13

21-Oct-13

07-Nov-13

12

23-Sep-13

07-Oct-13

25-Sep-13

09-Oct-13

32

17-Jul-13

24-Aug-13

10-Aug-13

17-Sep-13

20

CRM1160 Piping Fabrication

15

17-Jul-13

04-Aug-13

10-Aug-13

27-Aug-13

20

CRM1170 Sand Blasting & Panting

15

25-Jul-13

12-Aug-13

18-Aug-13

05-Sep-13

20

CRM1180 Launcher & Piping & Supports


Erection

15

06-Aug-13

24-Aug-13

29-Aug-13

17-Sep-13

20

119

10-Jun-13

29-Oct-13

16-Jul-13

16-Nov-13

15

CRMG1100 A/G Delivery Pipeline From The


Pumps To The Launcher
CRMG1110 A/G Suction Pipeline From The
Header To The Pumps
Pump House

Launcher Station

E&I Work

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 94 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

119

10-Jun-13

29-Oct-13

16-Jul-13

16-Nov-13

15

59

10-Jun-13

19-Aug-13

16-Jul-13

24-Sep-13

30

30

10-Jun-13

16-Jul-13

16-Jul-13

20-Aug-13

30

30

22-Jun-13

28-Jul-13

28-Jul-13

01-Sep-13

30

30

15-Jul-13

19-Aug-13

19-Aug-13

24-Sep-13

30

20

18-Aug-13

11-Sep-13

01-Sep-13

25-Sep-13

12

CREE1100
Lighting Fixtures, Sockets For
Rooms
CREE1110Low Voltage Cables

18-Aug-13

25-Aug-13

01-Sep-13

09-Sep-13

12

24-Aug-13

31-Aug-13

08-Sep-13

15-Sep-13

12

CREE1120
Termination

04-Sep-13

11-Sep-13

18-Sep-13

25-Sep-13

12

CREE1130
UPS System 110 V, 1 ph, 7 KVA

27-Aug-13

04-Sep-13

11-Sep-13

18-Sep-13

12

34

19-Sep-13

29-Oct-13

07-Oct-13

16-Nov-13

15

CREP1100
Lighting System For Pump Area

19-Sep-13

29-Sep-13

07-Oct-13

16-Oct-13

15

CREP1110Power Socket For Pump Area

25-Sep-13

05-Oct-13

13-Oct-13

22-Oct-13

15

CREP1120
Low Voltage Cable Laying For
Pump Area
CREP1130
High Voltage Cable Laying For
Pump Area

29-Sep-13

08-Oct-13

16-Oct-13

26-Oct-13

15

02-Oct-13

12-Oct-13

20-Oct-13

29-Oct-13

15

Electrical

Substation 6003

CRES1100
Modification Of Existing 11 KV
Switchgear
CRES1110Modification Of Existing 3.3 KV
Switchgear
CRES1120
Modification Of Existing 415 V
Switchgear
Extension Of SER 12

Pump Area

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 95 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

06-Oct-13

15-Oct-13

23-Oct-13

02-Nov-13

15

12

15-Oct-13

29-Oct-13

02-Nov-13

16-Nov-13

15

31

22-Sep-13

28-Oct-13

09-Oct-13

16-Nov-13

16

22-Sep-13

29-Sep-13

09-Oct-13

16-Oct-13

15

28-Sep-13

05-Oct-13

15-Oct-13

22-Oct-13

15

03-Oct-13

10-Oct-13

22-Oct-13

29-Oct-13

16

09-Oct-13

16-Oct-13

28-Oct-13

04-Nov-13

16

15-Oct-13

22-Oct-13

03-Nov-13

10-Nov-13

16

10

16-Oct-13

28-Oct-13

04-Nov-13

16-Nov-13

16

60

19-Aug-13

29-Oct-13

24-Sep-13

16-Nov-13

15

24

11-Sep-13

09-Oct-13

25-Sep-13

23-Oct-13

12

CRIE1100Laying of Cables

11-Sep-13

18-Sep-13

25-Sep-13

02-Oct-13

12

CRIE1120DCS System Cabinet to be


Modified
CRIE1130DCS Marchaling Cabinet to be
Modified
CRIE1140ESD System Cabinet to be
Modified

18-Sep-13

25-Sep-13

02-Oct-13

09-Oct-13

12

21-Sep-13

28-Sep-13

05-Oct-13

12-Oct-13

12

23-Sep-13

30-Sep-13

07-Oct-13

14-Oct-13

12

CREP1140
Installation Of Distribution
Boards For Pump Area
CREP1150
Termination For Pump Area
Launcher Area

CREL1100Lighting System For The


Launcher Area
CREL1110Power Socket For The
Launcher Area
CREL1120Low Voltage Cable Laying For
The Launcher Area
CREL1130High Voltage Cable Laying For
The Launcher Area
CREL1140Installation Of Distribution
Boards For The Launcher Area
CREL1150Termination For The Launcher
Area
Instrumentation

Extension Of SER 12

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 96 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

25-Sep-13

02-Oct-13

09-Oct-13

16-Oct-13

12

02-Oct-13

09-Oct-13

16-Oct-13

23-Oct-13

12

29

25-Sep-13

29-Oct-13

13-Oct-13

16-Nov-13

15

CRIP1100Laying Of Cables

25-Sep-13

05-Oct-13

13-Oct-13

22-Oct-13

15

CRIP1110Installation Of Flow Transmitter

29-Sep-13

08-Oct-13

16-Oct-13

26-Oct-13

15

CRIP1120Installation Of Pressure Gauges


With Fittings
CRIP1130Installation Of Pressure
Transmitters With Tubes &
Fittings
CRIP1140Installation Of Junction Boxes
For Pump Area
CRIP1150Installation Of Gas Detectors For
Pump Area
CRIP1160Installation Of Manual Call Point
For Pump Area
CRIP1170Termination For Pump Area

02-Oct-13

12-Oct-13

20-Oct-13

29-Oct-13

15

06-Oct-13

15-Oct-13

23-Oct-13

02-Nov-13

15

09-Oct-13

19-Oct-13

27-Oct-13

05-Nov-13

15

13-Oct-13

22-Oct-13

30-Oct-13

09-Nov-13

15

16-Oct-13

26-Oct-13

03-Nov-13

12-Nov-13

15

20-Oct-13

29-Oct-13

06-Nov-13

16-Nov-13

15

27

28-Sep-13

29-Oct-13

15-Oct-13

16-Nov-13

15

CRIL1110 Laying Of Cables

28-Sep-13

05-Oct-13

15-Oct-13

22-Oct-13

15

CRIL1120Installation Of Pig Signaller

01-Oct-13

08-Oct-13

19-Oct-13

26-Oct-13

15

CRIL1130Installation Of Pressure Gauges


With Fittings

05-Oct-13

12-Oct-13

22-Oct-13

29-Oct-13

15

CRIE1150F&G System Cabinet to be


Modified
CRIE1160Termination For SER-12
Pump Area

Launcher Area

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 97 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

08-Oct-13

15-Oct-13

26-Oct-13

02-Nov-13

15

12-Oct-13

19-Oct-13

29-Oct-13

05-Nov-13

15

15-Oct-13

22-Oct-13

02-Nov-13

09-Nov-13

15

19-Oct-13

26-Oct-13

05-Nov-13

12-Nov-13

15

22-Oct-13

29-Oct-13

09-Nov-13

16-Nov-13

15

25

19-Aug-13

18-Sep-13

24-Sep-13

23-Oct-13

30

CRIS1100Laying of Cables

10

19-Aug-13

31-Aug-13

24-Sep-13

06-Oct-13

30

CRIS1110Installation Of Junction Boxes

10

31-Aug-13

12-Sep-13

06-Oct-13

17-Oct-13

30

CRIS1120Termination For Substation


6003

10

07-Sep-13

18-Sep-13

12-Oct-13

23-Oct-13

30

92

18-Jul-13

04-Nov-13

01-Aug-13

27-Nov-13

20

25

08-Aug-13

08-Sep-13

12-Oct-13

10-Nov-13

54

CRIL1140Installation Of Pressure
Transmitters With Tubes &
Fittings
CRIL1150Installation Of Junction Boxes
For Launcher
CRIL1160Installation Of Gas Detectors For
Launcher
CRIL1170Installation Of Manual Call Point
For Launcher
CRIL1180Termination For Launcher
Substation 6003

BSV (3)
Civil Works

Early Finish

Late Start

Late Finish

Total
Float 2012

CBSC1100

Excavation In BSV-3

10

08-Aug-13

20-Aug-13

12-Oct-13

23-Oct-13

54

CBSC1110

Plain Concrete In BSV-3

10

14-Aug-13

26-Aug-13

17-Oct-13

29-Oct-13

54

CBSC1120

Re-Inforced Concrete In BSV-3

10

20-Aug-13

01-Sep-13

23-Oct-13

04-Nov-13

54

CBSC1130

Fence In BSV-3

10

26-Aug-13

08-Sep-13

29-Oct-13

10-Nov-13

54

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 98 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

Original
Duration

Early Start

64

20-Aug-13

04-Nov-13

23-Oct-13

27-Nov-13

20

15

20-Aug-13

08-Sep-13

23-Oct-13

10-Nov-13

54

29-Oct-13

04-Nov-13

21-Nov-13

27-Nov-13

20

90

18-Jul-13

02-Nov-13

01-Aug-13

27-Nov-13

22

90

18-Jul-13

02-Nov-13

01-Aug-13

27-Nov-13

22

CBSE1100 Installation of Electrical


Permanent Source
CBSE1110 Electrical Connection To MOV

10

18-Jul-13

30-Jul-13

01-Aug-13

13-Aug-13

12

10

04-Sep-13

16-Sep-13

18-Sep-13

30-Sep-13

12

CBSE1120 Diesel Generator to be


Removed

10

21-Oct-13

02-Nov-13

16-Nov-13

27-Nov-13

22

30

04-Sep-13

09-Oct-13

18-Sep-13

23-Oct-13

12

CBSI1100 Laying Of Cables

10

04-Sep-13

16-Sep-13

18-Sep-13

30-Sep-13

12

CBSI1110 Installation Of Pressure


Transmitters With Tubes &
Fittings
CBSI1120 Termination

10

16-Sep-13

28-Sep-13

30-Sep-13

12-Oct-13

12

10

28-Sep-13

09-Oct-13

12-Oct-13

23-Oct-13

12

151

24-Nov-13 21-May-14

26-Nov-13

24-May-14

60

24-Nov-13

04-Feb-14

26-Nov-13

06-Feb-14

60

07-Dec-13

16-Feb-14

09-Dec-13

18-Feb-14

Mechanical Works

CBSM1100
CBSM1120

Installation of Motor Operated


Valve
Tie-In To The Existing Inside
BSV-3

E&I Works

Electrical

Instrumentation

Pre-Commissioning/Commissioning

FCOM1100
FCOM1110

Precomm & Comm For Main


Pipeline
Precomm & Comm For Pumps

Actual Work

Critical Re...

Remaining Work

Milestone

Early Finish

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 99 of 266

Late Start

Late Finish

Date
19-Jul-12

Total
Float 2012

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

FCOM1120
FCOM1130
FCOM1140
FCOM1150
FCOM1160
FCOM1170
FCOM1180
FCOM1190

Original
Duration

Early Start

Precomm & Comm For SCADA


& PLC System
Precomm & Comm For
Telecommunication & FOC
System
Precomm & Comm For Security
System
Precomm & Comm For
Cathodic Protection System
Precomm & Comm For
Electrical & Instrumentation
System
72 Hrs Performance Test

60

18-Dec-13

27-Feb-14

21-Dec-13

02-Mar-14

60

31-Dec-13

11-Mar-14

02-Jan-14

13-Mar-14

60

12-Jan-14

23-Mar-14

14-Jan-14

25-Mar-14

60

23-Jan-14

03-Apr-14

26-Jan-14

06-Apr-14

60

04-Feb-14

15-Apr-14

06-Feb-14

17-Apr-14

15-Apr-14

19-Apr-14

17-Apr-14

21-Apr-14

System Readiness To Be
Operated
Jet A1 Fuel Ready To Be Taken
- In

16

19-Apr-14

07-May-14

21-Apr-14

10-May-14

10

10-May-14 21-May-14

12-May-14

24-May-14

447

05-Nov-12

24-Dec-12

28-Jul-14

150

05-Nov-12 31-May-13

24-Dec-12

19-Jul-13

35

10

20-May-13 31-May-13

01-Aug-13

15-Aug-13

54

36

11-Jun-14

16-Jun-14

28-Jul-14

74

31-May-14 25-Aug-14

18-Jun-14

25-Aug-14

Optional Items

OPT1100
OPT1110
OPT1120

Laying Of New FOC From QP


Refinery to BSV-3
Kahramaa Option (1) / Pole
Mounted Transformer At BSV-3
Baseline Survey

Project Close Out

Early Finish

23-Jul-14

23-Jul-14

Late Start

Late Finish

Total
Float 2012

FPCO1100

As-Built Drawings

50

31-May-14

28-Jul-14

18-Jun-14

16-Aug-14

16

FPCO1110

Asset Capitalization Schedule


(ACS)

40

01-Jun-14

17-Jul-14

30-Jun-14

16-Aug-14

25

Actual Work

Critical Re...

Remaining Work

Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 100 of 266

Date
19-Jul-12

Revision
Rev(5)

2013
J

Checked
Y.Abdalshaf...

2014

Approved

21-Jul-12 22:12

EPIC For 16" - 36 Km Jet A1 Fuel


Activity ID

Activity Name

FPCO1120

Project Handover

Actual Work

Critical Re...

Remaining Work

Milestone

Original
Duration

Early Start

50

28-Jun-14

Early Finish

25-Aug-14

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 101 of 266

Late Start

28-Jun-14

Late Finish

25-Aug-14

Date
19-Jul-12

Total
Float 2012

2013
J

2014

Revision
Rev(5)

Checked
Y.Abdalshaf...

Approved

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
MANPOWER SCHEDULE AND HISTOGRAM
______________________________________

Page 102 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3

Direct Labour list

July-12

August-12

September-12

October-12

November-12

December-12

January-13

February-13

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

February-14

March-14

April-14

12

12

16

16

16

16

16

16

16

16

16

16

16

Pipe Fitter

12

12

12

16

16

16

16

16

16

16

16

16

16

16

15

15

15

20

20

20

20

20

20

20

20

20

20

20

10

Blasting Technician

Coating Technician

August-14

June-12

July-14

May-12

June-14

April-12

May-14

March-12

Rigger

Direct Labour

Mechanical Labour

Welder

Grinder

N.D.T Technician

Hydro-test Technician

Civil Labour

Carpenter

12

12

12

12

12

12

12

12

12

Carpenter Assistant

Steel Fixer

Page 103 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3

Direct Labour list

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

February-14

Scafolder

Insulation Technician

Steel Welder

Erection Fitter

Electrician Technician

Instrument Technician

termination Technician

Pump Technician

August-14

February-13

July-14

January-13

June-14

December-12

May-14

November-12

April-14

October-12

Steel Fixer Assistant

March-14

September-12

August-12

July-12

June-12

May-12

April-12

March-12

Direct Labour

E&I Labour

Cathodic Protection
Technican

General Labour

Survyor

Page 104 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3

Direct Labour list

June-12

July-12

August-12

September-12

October-12

November-12

December-12

January-13

February-13

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

February-14

March-14

April-14

May-14

June-14

July-14

August-14

Surveyor Assistant

May-12

April-12

March-12

Direct Labour

Skilled Labor

10

10

10

10

10

10

10

10

10

10

10

10

10

Un Skilled Labor

10

10

10

15

15

15

15

15

15

15

15

15

15

15

15

10

Maintenance Labor

Safety Officers

Drivers & Operators

Dozer Operator

Grader Operator

Loader Operator

Dump Truck Driver

Excavator / Rock Breaker


Operator

Concrete Pump Operator

Aspalt Finisher Operator

Page 105 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3

Direct Labour list

June-13

July-13

August-13

September-13

October-13

November-13

December-13

August-14

May-13

July-14

April-13

June-14

March-13

May-14

February-13

April-14

January-13

March-14

December-12

February-14

November-12

January-14

October-12

Trailer Driver

September-12

August-12

July-12

June-12

May-12

April-12

Tractor Driver

March-12

Direct Labour

Fork Lift Operator

Side Boom Operator

Water Tanker Driver

Crane up to 60 ton Operator

Total Direct Labour

10

11

43

113

136

171

189

188

189

190

195

195

201

199

192

187

175

124

60

43

34

28

25

25

14

12

Page 106 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3


In-Direct Labour list

August-13

September-13

October-13

November-13

December-13

January-14

February-14

March-14

April-14

May-14

June-14

July-14

August-14

November-12

July-13

October-12

June-13

September-12

May-13

August-12

April-13

July-12

March-13

June-12

February-13

May-12

January-13

April-12

December-12

March-12

General Project Maneger

Project Maneger (Engineering)

Civil Engineer (Design)

Mechanical Engineer (Design)

E&I Engineer (Design)

Mechanical Site Maneger

Civil Site Maneger

In-Direct Labour

Engineeres Staff

E&I Site Maneger

Mechanical Engineer

Civil Engineer

E&I Engineer

Technical office Engineer

Planning Engineer

Custom Clearance Specialist

Inspection Engineer

H.S.E Engineer

Purchasing Engineer

Page 107 of 266

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3


In-Direct Labour list
October-12

November-12

December-12

January-13

February-13

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

February-14

March-14

April-14

May-14

Welder Supervisor

Civil Supervisor

Fitting-Up Supervisor

E&I Supervisor

Coating Supervisor

Rigger Supervisor

H.S.E Supervisor

Equipment Supervisor

Maintenance Supervisor

Fitting-Up Supervisor

E&I Supervisor

Coating Supervisor

Rigger Supervisor

Supervisor Staff For The Main Pipeline

Supervisor Staff For QP Refinery & BSV-3

Welder Supervisor

Civil Supervisor

Page 108 of 266

August-14

September-12

July-14

August-12

June-14

July-12

June-12

May-12

April-12

Maintenance Engineer

March-12

In-Direct Labour

EPIC For 16"-36 Km Jet A1 Fuel PL From QP Refinery to BSV-3


In-Direct Labour list
November-12

December-12

January-13

February-13

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

February-14

March-14

April-14

May-14

Equipment Supervisor

Maintenance Supervisor

Accountant

Purchasing Executive

Security Executive

Guardman

Doctor

35

53

62

63

65

65

65

67

68

79

83

83

83

80

77

76

74

46

46

45

45

44

44

13

11

11

July-12

June-12

May-12

April-12

Administrator

March-12

August-14

October-12

July-14

September-12

June-14

August-12

H.S.E Supervisor

In-Direct Labour

Others

Total

16

19

19

Page 109 of 266

EPIC Of 16" Jet Pipeline From QP Refinery To BSV (3)


Direct Labour
250

200

Number

150

100

50

0
Series1

1
0

2
0

3
4

4
10

5
11

6
43

7
113

8
136

9
171

10
189

11
188

12
189

13
190

14
195

15
195

Page 110 of 266

16
201

17
199

18
192

19
187

20
175

21
124

22
60

23
43

24
34

25
28

26
25

27
25

28
14

29
12

30
8

EPIC Of 16" Jet Pipeline From QP Refinery To BSV (3)


In-Direct Labour

90

80

70

Number

60

50

40

30

20

10

0
In-Direct Labour

1
7

2
16

3
19

4
19

5
35

6
53

7
62

8
63

9
65

10
65

11
65

12
67

13
68

14
79

15
83

Page 111 of 266

16
83

17
83

18
80

19
77

20
76

21
74

22
46

23
46

24
45

25
45

26
44

27
44

28
13

29
11

30
11

EPIC Of 16" Jet Pipeline From QP Refinery To BSV (3)


Direct Labour
250

200

Number

150

100

50

0
Series1

1
0

2
0

3
4

4
10

5
11

6
43

7
113

8
136

9
171

10
189

11
188

12
189

13
190

14
195

15
195

Page 112 of 266

16
201

17
199

18
192

19
187

20
175

21
124

22
60

23
43

24
34

25
28

26
25

27
25

28
14

29
12

30
8

EPIC Of 16"Jet Fuel Pipeline From QP Refinery To BSV(3)


Total Direct + Indirect Labour
300

250

Number

200

150

100

50

0
Total Labour

1
7

2
16

3
23

4
29

5
46

6
7
8
9
10 11 12 13 14 15 16 17 18 19 20 21 22 23
96 175 199 236 254 253 256 258 274 278 284 282 272 264 251 198 106 89

Page 113 of 266

24
79

25
73

26
69

27
69

28
27

29
23

30
19

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
EQUIPMENT DEPLOYMENT
______________________________________

Page 114 of 266

16"-36 Km Jet Fuel Pipline from QP Refinery to BSV-3


Construction Equipment list

March-13

April-13

May-13

June-13

July-13

August-13

September-13

October-13

November-13

December-13

January-14

Grader

Loader

Truck

Trailer

July-12

June-12

May-12

April-12

March-12

Tractor

Excavator / Rock breaker

Concrete Pump

Aspalt Finisher

Fork Lift

Side Boom

Water Tank

12

16

20

20

20

20

20

20

20

20

12

12

12

16

Crane up to 60 ton

Welding Machine

Flat bed

Page 115 of 266

August-14

February-13

July-14

January-13

June-14

December-12

May-14

November-12

April-14

October-12

March-14

September-12

February-14

August-12

Dozer

Equipment

16"-36 Km Jet Fuel Pipline from QP Refinery to BSV-3


Construction Equipment list

August-13

September-13

October-13

November-13

Hydro test Compressor

Filling Pump

Handling Pump

Pressurizing Pump

Generator

Page 116 of 266

August-14

July-13

July-14

June-13

June-14

May-13

Blasting Compressor

May-14

April-13

April-14

March-13

March-14

February-13

February-14

January-13

January-14

December-12

Sand Blasting Machine

December-13

November-12

October-12

September-12

August-12

July-12

June-12

May-12

April-12

March-12

Equipment

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROGRESS MEASUREMENT SYSTEM (PMS)
INCLUDING EDR & PSR
______________________________________

Page 117 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
ENGINEERING DOCUMENT REGISTER
(EDR)
______________________________________

Page 118 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM

February 26, 2012

SUBJECT : ENGINEERING PHASE PROGRESS MEASUREMENT


PREVIOUS WEEK
SER.

DESCRIPTION

THIS WEEK

UP TO DATE

REL. WT. %

PLANNED %

ACTUAL %

DEV. %

PLANNED %

ACTUAL %

DEV. %

PLANNED %

ACTUAL %

DEV. %

GENERAL

4.59

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

PROCESS

6.34

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

LOSS PREVENTION

2.37

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

FIRE & GAS

4.26

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

PIPELINE

8.85

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

MECHANICAL/PIPING

10.51

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

INSTRUMENTATION

9.96

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

TELECOMMUNICATION

1.05

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

ELECTRICAL

15.73

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

10

CIVIL & STRUCTURAL

27.38

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

11

BUILDING SERVICES

2.08

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

12

CATHODIC PROTECTION

1.88

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

95.00

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

THE TOTAL OF ENGINEERING PHASE

Page 119 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

5.0%

5.0%

40.0%

29Apr12

1May12

1May12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

WTD
WTG

85.0%

95.0%

1Jul12

1Jul12

PRG

Remarks

Planned

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00000
0.00%

0.00
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

DETAILED DESIGN ENGINEERING SERVICES


GENERAL
GENERAL
3392-32-69-03-0001 Site Visit Report

3392-32-69-03-0002 FEED Design Review Report

3392-32-69-03-0003 Design Basis Memorandum

3392-32-69-03-0004 Tie-in and Commissioning Philosophy

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

10May12

11Jun12

24Jun12

0.00%
1.149

8Apr12

10Apr12

10Apr12

8May12

14May12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
2.455

16Apr12

18Apr12

18Apr12

3May12

27Jun12

18Jul12

25Jul12

0.00%
0.00%

25Jul12
0.833

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.158

0.00%
4.595

PROCESS
REPORTS/CALCULATIONS
3392-32-00-36-0001 Steady State Hydraulic Analysis/Report

3392-32-00-36-0002 Transient/Surge Analysis Report

3392-32-00-36-0003 Operating Control and Safeguarding Philosophy

3392-32-00-36-0005 Hazop & SIL Closeout Report

3392-32-00-36-0006 Instrument Air consumption Calculation

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

29May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

4Jun12

31May12

31May12

20Jun12

15Jul12

5Aug12

12Aug12

12Aug12

0.00%
0.526

10Jun12

18Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.789

21Jun12

28Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.395

25Jun12

1Jul12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.316

27Jun12

1Jul12

4Jul12

25Jul12

1Aug12

22Aug12

29Aug12

0.00%
0.00%

29Aug12
0.105

0.00%

DRAWINGS
3392-32-00-41-0001 Schematic Flow Diagrams

3392-32-00-31-0001 PFDs

3392-32-00-30-0001 P&ID : Legends and Symbols

3392-32-00-30-0002 P&ID : Tie in at QP Refinery

3392-32-00-30-0003 P&ID : Booster Pumps

3392-32-00-30-0004 P&ID : Main Pumps

3392-32-00-30-0005 P&ID : Pig Launcher

3392-33-00-30-0006 P&ID - Tie-in at BSV 3

3392-32-00-30-0007 P&ID - Tie-in for drains from new pump house

3392-32-00-30-0008 P&ID - Tie-in for drains from pig launcher area

3392-32-00-30-0009

P&ID - Utility Tie-ins to pump house and pig launcher


area

3392-32-00-30-0010 P&ID - Fire water system for pump house (new)

3392-32-00-30-0011 P&ID - Fire water system for pig launcher (new)

3392-32-00-30-0012 P&IDs - Demolition (5 Nos.)

6Jun12

7Jun12

28Jun12

5Jul12

26Jul12

2Aug12

2Aug12

0.00%
0.158

3Jun12

6Jun12

7Jun12

28Jun12

5Jul12

26Jul12

2Aug12

0.00%
0.00%

2Aug12
0.210

4Jun12

6Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.552

3Jun12

4Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

6/32012

4Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

3Jun12

4Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

4Jun12

6Jun12

7Jun12

24Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

12Jun12

14Jun12

19Jun12

9Jul12

30Jul12

20Aug12

27Aug12

0.00%
0.00%

27Aug12
0.263

3Jun12

4Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

4Jun12

6Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

4Jun12

6Jun12

7Jun12

28Jun12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

28Jun12

4Jul12

8Jul12

29Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

28Jun12

4Jul12

8Jul12

15Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.263

14Jun12

18Jun12

20Jun12

8Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.658

0.00%
6.340

LOSS PREVENTION
PHILOSOPHIES / SCHEDULES
3392-32-19-53-0001 Fire Protection and Safety Philosophy

3392-32-19-53-0002 Hazardous Area Schedule

3392-32-19-53-0003 Safety Equipment List

P
F
F
A
P
F
F
A
P
F
F
A

1Aug12

5Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

2Oct12

0.00%
0.158

25Jul12

29Jul12

31Jul12

21Aug12

28Aug12

18Sep12

25Sep12

0.00%
0.00%

25Sep12
0.079

4Jul12

5Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.079

0.00%

Page 120 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A
P
F
F
A

17Jun12

19Jun12

1Jul12

P
F
F
A
P
F
F
A

1Aug12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

WTD
WTG

85.0%

95.0%

26Aug12

26Aug12

PRG

Remarks

Planned

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

SPECIFICATIONS
3392-32-19-17-0001

Specs - Fire Protection, Safety Equipment, Hydrants &


Accessories

3392-32-19-17-0004 Specs/Data sheet - Deluge System

3392-32-19-17-0005 Specs - F&G Detection System

22Jul12

29Jul12

19Aug12

0.00%
0.237

17Jun12

19Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.079

10Jul12

11Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.158

0.00%

Area Classification Drawings


3392-32-16-63-0001 Hazardous Area Classifications - QP Refinery

3392-33-16-63-0002 Hazardous Area Classifications - BSV-3

5Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

2Oct12

0.00%
0.474

1Aug12

6Aug12

6Aug12

27Aug12

3Sep12

24Sep12

1Oct12

0.00%
0.00%

1Oct12
0.395

0.00%

DRAWINGS
3392-32-19-21-0001

3392-32-19-21-0002

Fire Protection and Safety Equipment Layout - Pump


House
Fire Protection and Safety Equipment Layout - Pig
Launcher Area

3392-32-19-21-0005 Safety Equipment Layout - SER12 Building

3392-32-19-21-0003 Escape Evacuation Route - Pump House

3392-32-19-21-0004 Escape Evacuation Route - Pig Launcher Area

12Aug12

14Aug12

4Sep12

11Sep12

2Oct12

9Oct12

9Oct12

0.00%
0.158

5Aug12

12Aug12

14Aug12

4Sep12

11Sep12

2Oct12

9Oct12

0.00%
0.00%

9Oct12
0.158

19Jul12

29Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

0.00%
0.00%

24Sep12
0.079

5Aug12

7Aug12

8Aug12

29Aug12

5Sep12

26Sep12

3Oct12

0.00%
0.00%

3Oct12
0.158

5Aug12

12Aug12

12Aug12

2Sep12

9Sep12

30Sep12

7Oct12

0.00%
0.00%

7Oct12
0.158

0.00%
2.368

FIRE & GAS


SPECIFICATIONS
3392-32-15-17-0019

Specification for F & G Devices (Detectors & Alarm


Devices)

3392-32-15-17-0020 Specifications for F&G System ( Modfication)

3392-32-15-17-0021

Specifications for FIRE Supression System (


Modfication)

3392-32-15-17-0022 Specifications for HSSD system

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

12Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

14Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

13Jun12

P
F
F
A

9Sep12

13Jun12

20Jun12

11Jul12

18Jul12

8Aug12

15Aug12

15Aug12

0.00%
0.088

3Jul12

10Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.039

5Aug12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.039

5Aug12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.079

0.00%

DATA SHEETS
3392-32-15-12-0027 Data Sheet for Flame Detectors

3392-32-15-12-0028 Data Sheet for Manual Call Points

3392-32-15-12-0029 Data Sheet for Smoke Detectors

3392-32-15-12-0030 Data Sheet for Heat Detectors

3392-32-15-12-0031 Data Sheet for HSSD System

3392-32-15-12-0032 Data Sheet for Hydrogen Detectors

3392-32-15-12-0033 Data Sheet for Beacons/Warning lights

3392-32-15-12-0034 Data Sheet for Horns

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

21Aug12

0.00%
0.053

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.035

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.044

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.053

22Jul12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

0.00%
0.00%

19Sep12
0.061

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.053

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.044

14Jun12

24Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

0.00%
0.00%

21Aug12
0.035

0.00%

MATERIAL REQUISITIONS
3392-RQ-32-15-0020 MRs for F&G Devices (Detectors & Alarm Devices)

3392-RQ-32-15-0021 MRs for F&G System ( Modfication)

3392-RQ-32-15-0022 MRs for HSSD system

3392-RQ-32-15-0023 MRs for FIRE Supression System ( Modfication)

13Jun12

14Jun12

5Jul12

12Jul12

2Aug12

9Aug12

9Aug12

0.00%
0.035

27Jun12

27Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.022

27Jun12

27Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.044

27Jun12

27Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.022

0.00%

DOCUMENTS / DRAWINGS
Common
3392-32-15-39-0001 F&G devices typical installation details

10Sep12

10Sep12

1Oct12

8Oct12

29Oct12

5Nov12

5Nov12

0.00%
0.281
0.00%

Page 121 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-15-39-0002 F&G cable schedule

3392-32-15-39-0003 F&G JB schedule

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A

15Aug12

21Aug12

21Aug12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

1Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

11Sep12

18Sep12

9Oct12

WTD
WTG

85.0%

95.0%

16Oct12

16Oct12

PRG

27Aug12

27Aug12

17Sep12

24Sep12

15Oct12

22Oct12

Remarks

Planned

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.403

21Aug12

0.00%
0.00%

22Oct12
0.403

0.00%

QP Refinery
3392-32-15-39-0004 F&G Cause and Effect

3392-32-15-39-0005 F&G I/O schedule

3392-32-15-39-0006 Cable Block Diagrams

3392-32-15-39-0007 F&G Interconnection & Termination Diagrams

3392-32-15-39-0008 F & G Loop Diagrams

3392-32-15-66-0003 F & G Devices Layout (Detectors & Alarm Devices)

3392-32-15-66-0004 F & G Cable Routing Layout Drawing

2Jul12

20Aug12

10Sep12

17Sep12

8Oct12

15Oct12

15Oct12

0.00%
0.237

22Jul12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

0.00%
0.00%

23Sep12
0.386

22Jul12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

0.00%
0.00%

23Sep12
0.351

24Jul12

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

0.00%
0.00%

24Sep12
0.368

7Aug12

12Aug12

12Aug12

2Sep12

9Sep12

30Sep12

7Oct12

0.00%
0.00%

7Oct12
0.447

30Jul12

31Jul12

1Aug12

22Aug12

29Aug12

19Sep12

26Sep12

0.00%
0.00%

26Sep12
0.316

2Aug12

5Aug12

6Aug12

27Aug12

3Sep12

24Sep12

1Oct12

0.00%
0.00%

1Oct12
0.324

0.00%
4.262

PIPELINE
SPECIFICATIONS
3392-33-13-17-3001 Specifications for Hot Induction Bends

3392-33-13-17-3002 Specifications for Pipeline Valves

3392-33-13-17-3003 Specifications for Electrical Isolation joints

3392-33-13-17-3004 Specifications for Pipeline Barred Tees

3392-33-13-17-3005 Specification for Pipeline Fittings and Flanges

3392-33-13-17-3006 Specification for Pig Signaller

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

29Apr12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

9May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5Jun12

P
F
F
A

10Jul12

30Apr12

1May12

20May12

23May12

8Jul12

15Jul12

15Jul12

0.00%
0.070

29Apr12

30Apr12

1May12

20May12

23May12

8Jul12

15Jul12

0.00%
0.00%

15Jul12
0.070

30Apr12

2May12

2May12

20May12

23May12

8Jul12

15Jul12

0.00%
0.00%

15Jul12
0.070

30Apr12

2May12

2May12

20May12

23May12

8Jul12

15Jul12

0.00%
0.00%

15Jul12
0.070

6May12

7May12

7May12

27May12

19Jun12

10Jul12

17Jul12

0.00%
0.00%

17Jul12
0.070

7May12

13May12

14May12

28May12

4Jun12

25Jun12

2Jul12

0.00%
0.00%

2Jul12
0.070

0.00%

DATA SHEETS
3392-33-13-12-3001 Data Sheet for Hot Induction Bends

3392-33-13-12-3002 Data Sheet for Isolation Joints

3392-33-13-12-3003 Data Sheet for Pipeline Barred Tees

3392-33-13-12-3004 Data Sheet for Pipeline Anchor Flanges

9May12

9May12

30May12

5Jun12

26Jun12

2Jul12

2Jul12

0.00%
0.053

9May12

9May12

9May12

21May12

0.00%
0.00%

14Jun12
0.053

9May12

10May12

13May12

28May12

0.00%
0.00%

14Jun12
0.053

9May12

10May12

13May12

28May12

0.00%
0.00%

14Jun12
0.053

0.00%

MATERIAL REQUISITIONS
3392-RQ-33-13-3001 MR for Isolation Joints

3392-RQ-33-13-3002 MR for Pipeline Barred Tees

3392-RQ-33-13-3003 MR for Pipeline Anchor Flanges

3392-RQ-33-13-3004 MR for Pipeline Hot Bends

3392-RQ-33-13-3005 MR for Coating of Fittings

3392-RQ-33-13-3006 MR for Field Joint Coating

3392-RQ-33-13-3007 MR for Pipeline Flanges/Fittings/Gaskets/StudBolts

5Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

23Jul12

0.00%
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

5Jun12

3Jun12

10Jun12

17Jun12

25Jun12

16Jul12

23Jul12

0.00%
0.00%

23Jul12
0.044

0.00%

MTOs
3392-33-13-91-3001 Pipeline Material Take-Off

22Jul12

23Jul12

23Jul12

23Jul12

23Jul12

23Jul12

23Jul12

0.00%
0.263
0.00%

Page 122 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

5.0%

5.0%

40.0%

9May12

28May12

5Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

WTD
WTG

85.0%

95.0%

27Jun12

PRG

Remarks

Planned

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

CALCULATIONS
3392-33-13-20-3050 Pipeline Wall Thickness Calculation

3392-33-13-20-3054 Pipeline Crossing Design Report

3392-33-13-20-3051 Upheaval Buckling Calculations

3392-33-13-20-3052 Elastic Bend Radius & Combined Stress

3392-33-13-20-3053 Pipeline Anchor Force Calculation

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

24Jun12

0.00%
0.079

14May12

28May12

5Jun12

24Jun12

0.00%
0.00%

27Jun12
0.079

16May12

28May12

5Jun12

24Jun12

27Jun12

18Jul12

25Jul12

0.00%
0.00%

25Jul12
0.132

17May12

28May12

5Jun12

24Jun12

27Jun12

18Jul12

25Jul12

0.00%
0.00%

25Jul12
0.105

17May12

28May12

5Jun12

24Jun12

27Jun12

18Jul12

25Jul12

0.00%
0.00%

25Jul12
0.105

0.00%

REPORTS
3392-33-13-17-3007 Pipeline Pigging Philosophy

P
F
F
A

25Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

12Jun12

27Jun12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

0.00%
0.158
0.00%

TYPICAL DETAIL DRAWINGS


3392-33-13-21-3001 Pipeline Overall Route Map

3392-33-13-21-3002 Key Plan Pipeline Route Map

3392-33-13-21-3003 Pipeline Route Map - 1

3392-33-13-21-3004 Pipeline Route Map - 2

3392-33-13-21-3005 Pipeline Route Map - 3

3392-33-13-21-3006 Pipeline Route Map - 4

3392-33-13-21-3007 Pipeline Route Map - 5

3392-33-13-21-3008 Pipeline Route Map - 6

3392-33-13-21-3009 Pipeline Route Map - 7

3392-33-13-21-3010 Pipeline Route Map - 8

3392-33-13-21-3011 Pipeline Route Map - 9

3392-33-13-21-3012 Pipeline Route Map - 10

3392-33-13-21-3013 Pipeline Route Map - 11

3392-33-13-21-3014 Pipeline Route Map - 12

3392-33-13-21-3015 Pipeline Route Map - 13

3392-33-13-20-3001 Keyplan Pipeline Alignment Sheets

3392-33-13-20-3002 Pipeline Alignment Sheet KM 0+000 to KM 1+000

3392-33-13-20-3003 Pipeline Alignment Sheet KM 1+000 to KM 2+000

3392-33-13-20-3004 Pipeline Alignment Sheet KM 2+000 to KM 3+000

3392-33-13-20-3005 Pipeline Alignment Sheet KM 3+000 to KM 4+000

3392-33-13-20-3006 Pipeline Alignment Sheet KM 4+000 to KM 5+000

3392-33-13-20-3007 Pipeline Alignment Sheet KM 5+000 to KM 6+000

3392-33-13-20-3008 Pipeline Alignment Sheet KM 6+000 to KM 7+000

17Jun12

19Jun12

10Jul12

18Jul12

8Aug12

15Aug12

15Aug12

0.00%
0.175

18Jun12

1Jul12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.088

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.114

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.053

18Jun12

21Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.00%
0.00%

26Aug12
0.061

3Jul12

5Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.088

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

0.00%

Page 123 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-33-13-20-3009 Pipeline Alignment Sheet KM 7+000 to KM 8+000

3392-33-13-20-3010 Pipeline Alignment Sheet KM 8+000 to KM 9+000

3392-33-13-20-3011 Pipeline Alignment Sheet KM 9+000 to KM 10+000

3392-33-13-20-3012 Pipeline Alignment Sheet KM 10+000 to KM 11+000

3392-33-13-20-3013 Pipeline Alignment Sheet KM 11+000 to KM 12+000

3392-33-13-20-3014 Pipeline Alignment Sheet KM 12+000 to KM 13+000

3392-33-13-20-3015 Pipeline Alignment Sheet KM 13+000 to KM 14+000

3392-33-13-20-3016 Pipeline Alignment Sheet KM 14+000 to KM 15+000

3392-33-13-20-3017 Pipeline Alignment Sheet KM 15+000 to KM 16+000

3392-33-13-20-3018 Pipeline Alignment Sheet KM 16+000 to KM 17+000

3392-33-13-20-3019 Pipeline Alignment Sheet KM 17+000 to KM 18+000

3392-33-13-20-3020 Pipeline Alignment Sheet KM 18+000 to KM 19+000

3392-33-13-20-3021 Pipeline Alignment Sheet KM 19+000 to KM 20+000

3392-33-13-20-3022 Pipeline Alignment Sheet KM 20+000 to KM 21+000

3392-33-13-20-3023 Pipeline Alignment Sheet KM 21+000 to KM 22+000

3392-33-13-20-3024 Pipeline Alignment Sheet KM 22+000 to KM 23+000

3392-33-13-20-3025 Pipeline Alignment Sheet KM 23+000 to KM 24+000

3392-33-13-20-3026 Pipeline Alignment Sheet KM 24+000 to KM 25+000

3392-33-13-20-3027 Pipeline Alignment Sheet KM 25+000 to KM 26+000

3392-33-13-20-3028 Pipeline Alignment Sheet KM 26+000 to KM 27+000

3392-33-13-20-3029 Pipeline Alignment Sheet KM 27+000 to KM 28+000

3392-33-13-20-3030 Pipeline Alignment Sheet KM 28+000 to KM 29+000

3392-33-13-20-3031 Pipeline Alignment Sheet KM 29+000 to KM 30+000

3392-33-13-20-3032 Pipeline Alignment Sheet KM 30+000 to KM 31+000

3392-33-13-20-3033 Pipeline Alignment Sheet KM 31+000 to KM 32+000

3392-33-13-20-3034 Pipeline Alignment Sheet KM 32+000 to KM 33+000

3392-33-13-20-3035 Pipeline Alignment Sheet KM 33+000 to KM 34+000

3392-33-13-20-3036 Pipeline Alignment Sheet KM 34+000 to KM 35+000

3392-33-13-20-3037 Pipeline Alignment Sheet KM 35+000 to KM 35+719.8

3392-32-13-20-3038 Pipeline Station Approach Drawing - QP Refinery

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

5Jul12

8Jul12

8Jul12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

29Jul12

5Aug12

26Aug12

WTD
WTG

85.0%

95.0%

2Sep12

2Sep12

PRG

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Sep12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

2Sep12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

23Sep12
0.184

0.00%

Page 124 of 266

0.0000

0.00%
0.00%
0.105

23Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

0.0000

0.00%
0.00%
0.105

5Jul12

Actual

0.00%
0.00%
0.105

5Jul12

Planned

0.00%
0.00%
0.105

5Jul12

Remarks

0.00%
0.105

5Jul12

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

3392-33-13-20-3039

DOC / DWG DESCRIPTION

Pipeline Station Approach Drawing - Block


Sectionalizing Valve Station (BSV3)

3392-33-13-50-3001 Typical Details -A/G Pipeline Crossing

3392-33-13-50-3002 Typical Details - Track Crossing

3392-33-13-50-3003 Typical Details -Buried Utility Crossing

3392-33-13-50-3004 Typical Details -Secondary Road Crossing

3392-33-13-50-3005 Typical Details -Overhead Power line Crossing

3392-33-13-50-3006 Typical Details -Marker Posts

3392-33-13-50-3007 Typical Details -Pipeline in Sabkha Area

3392-33-13-50-3008

Typical ROW Cross Section including Trench & Bund


Details

3392-33-13-50-3009 Typical Details - U/G Pipeline Crossing

3392-33-13-20-3040 Crossing Matrix - Roads & 3rd Party Services

3392-33-13-20-3041 Road Crossing Detail Drawings

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

10Jul12

15Jul12

15Jul12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

5Aug12

12Aug12

2Sep12

WTD
WTG

85.0%

95.0%

9Sep12

9Sep12

PRG

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

19Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

11Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

19Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

8Jul12

9Jul12

30Jul12

6Aug12

27Aug12

3Sep12

20Aug12

8Jul12

9Jul12

30Jul12

6Aug12

27Aug12

3Sep12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

3Sep12
0.193

5Jul12

0.0000

0.00%
0.00%
0.044

5Jul12

0.0000

0.00%
0.00%
0.044

19Jun12

0.0000

0.00%
0.00%
0.044

10Jun12

0.0000

0.00%
0.00%
0.044

10Jun12

0.0000

0.00%
0.00%
0.044

10Jun12

0.0000

0.00%
0.00%
0.044

10Jun12

0.0000

0.00%
0.00%
0.044

19Jun12

Actual

0.00%
0.00%
0.044

10Jun12

Planned

0.00%
0.00%
0.044

10Jun12

Remarks

0.00%
0.184

10Jun12

0.00%
0.00%

3Sep12
0.526

0.00%
8.848

MECHANICAL/PIPING
MECHANICAL
SCHEDULES / LISTS
3392-32-13-10-0002 Equipment Schedule

P
F
F
A

13Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

24May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

10Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

21May12

P
F
F
A

10Jul12

25Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

0.00%
0.105
0.00%

SPECIFICATIONS
3392-32-13-17-0010 Specs - Pumps

3392-32-13-17-0011 Specs - Pig Launcher

3392-32-13-17-0013 Specs for Equipment Handling (EOT Cranes)

3392-32-13-17-0014

Spec for Mechanical Interlocking of valves around the


PIG trap

4Jun12

6Jun12

27Jun12

4Jul12

25Jul12

1Aug12

1Aug12

0.00%
0.079

5Jun12

10Jun12

10Jun12

1Jul12

8Jul12

29Jul12

5Aug12

0.00%
0.00%

5Aug12
0.053

17Jun12

19Jun12

20Jun12

8Jul12

16Jul12

6Aug12

13Aug12

0.00%
0.00%

13Aug12
0.000

17Jun12

19Jun12

20Jun12

9Jul12

16Jul12

6Aug12

13Aug12

0.00%
0.00%

13Aug12
0.000

0.00%

DATA SHEETS
3392-32-00-12-0007 Datasheet for Main Transfer Pumps

3392-32-00-12-0008 Datasheet for Booster Pumps

3392-32-00-12-0009 Datasheet for Pig Launcher with Jib Crane

3392-32-00-12-0010 Data sheet for EOT Crane

3392-32-00-12-0012 Corrosion Fitting

7Jun12

11Jun12

1Jul12

5Jul12

26Jul12

2Aug12

2Aug12

0.00%
0.079

11Jun12

7Jun12

14Jun12

4Jul12

8Jul12

29Jul12

5Aug12

0.00%
0.00%

5Aug12
0.079

5Jun12

13Jun12

13Jun12

4Jul12

11Jul12

1Aug12

8Aug12

0.00%
0.00%

8Aug12
0.079

17Jun12

27Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

0.00%
0.00%

22Aug12
0.079

18Jun12

19Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.079

0.00%

TECHNICAL REQUISITIONS
3392-RQ-32-13-0009 MR for Main Transfer Pumps

3392-RQ-32-13-0010 MR for Booster Pumps

3392-RQ-32-13-0011 MR for Pig Launcher with Jib Crane

3392-RQ-32-13-0012 MR for EOT Crane

24May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

19Jul12

0.00%
0.079

21May12

24May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

0.00%
0.00%

19Jul12
0.079

21May12

27May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
0.053

21May12

27May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
0.053

0.00%

PIPING
SCHEDULES / LISTS
3392-32-13-10-0001 Line Schedule

15Jul12

15Jul12

5Aug12

12Aug12

2Sep12

9Sep12

9Sep12

0.00%
0.114
0.00%

Page 125 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-13-10-0003 Valve Schedule

3392-32-13-10-0004 Tie-In Schedule

3392-32-13-63-0001 Pipe Support Schedule

3392-32-13-91-0001 Piping Bulk MTO

3392-32-13-92-0002 Valve MTO

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

12Jul12

15Jul12

17Jul12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

7Aug12

14Aug12

4Sep12

WTD
WTG

85.0%

95.0%

11Sep12

11Sep12

PRG

7Jun12

13Jun12

4Jul12

11Jul12

1Aug12

8Aug12

25Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

8Aug12

24Jul12

24Jul12

24Jul12

24Jul12

24Jul12

24Jul12

20Aug12

25Jul12

25Jul12

25Jul12

25Jul12

25Jul12

25Jul12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

24Jul12
0.368

23Jul12

Actual

0.00%
0.00%
0.237

19Jul12

Planned

0.00%
0.00%
0.105

14Jun12

Remarks

0.00%
0.132

7Jun12

0.00%
0.00%

25Jul12
0.132

0.00%

CALCULATIIONS / REPORTS
3392-32-13-20-0001 Pipe Wall thickness Calculation

3392-32-13-71-0001 Stress Analysis Report - System1

3392-32-13-71-0002 Stress Analysis Report - System2

3392-32-13-71-0003 Stress Analysis Report - System3

3392-32-13-71-0004 Material Handling Study Report

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

30May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

3Jun12

30May12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

13Aug12

0.00%
0.079

8Aug12

12Aug12

13Aug12

3Sep12

10Sep12

1Oct12

8Oct12

0.00%
0.00%

8Oct12
0.316

8Aug12

12Aug12

13Aug12

3Sep12

10Sep12

1Oct12

8Oct12

0.00%
0.00%

8Oct12
0.316

8Aug12

12Aug12

13Aug12

3Sep12

10Sep12

1Oct12

8Oct12

0.00%
0.00%

8Oct12
0.316

28Jun12

10Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.079

0.00%

SPECIFICATIONS
3392-32-13-17-0001 Piping Material Specifications

3392-32-13-17-0002 Specs - Gate Valves

3392-32-13-17-0003 Specs - Ball Valves

3392-32-13-17-0004 Specs - Globe Valves

3392-32-13-17-0005 Specs - Check Valves

3392-32-13-17-0006 Specs- Station CS Pipes

3392-32-13-17-0007 Specs- CS Fittings and Flanges

3392-32-13-17-0008 Specs- Nuts and Bolts

3392-32-13-17-0009 Specs-Gaskets

3Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

13Aug12

0.00%
0.158

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.070

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.070

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.070

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.070

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.053

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.053

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.035

29May12

29May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.035

0.00%

DATA SHEETS
3392-32-00-12-0001 Data Sheet for Gate valves

3392-32-00-12-0002 Data Sheet for Ball Valves

3392-32-00-12-0003 Data Sheet for Globe Valves

3392-32-00-12-0004 Data Sheet for Check valves

3392-32-00-12-0005 Data Sheet for Strainers

3392-32-00-12-0006 Data Sheet for Special Items (If Required)

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

7Jun12

10Jun12

12Jun12

1Jul12

8Jul12

29Jul12

5Aug12

5Aug12

0.00%
0.079

3Jun12

3Jun12

4Jun12

25Jun12

2Jul12

23Jul12

30Jul12

0.00%
0.00%

30Jul12
0.079

7Jun12

10Jun12

12Jun12

1Jul12

8Jul12

29Jul12

5Aug12

0.00%
0.00%

5Aug12
0.079

7Jun12

10Jun12

12Jun12

1Jul12

8Jul12

29Jul12

5Aug12

0.00%
0.00%

5Aug12
0.079

7Jun12

10Jun12

12Jun12

1Jul12

8Jul12

29Jul12

5Aug12

0.00%
0.00%

5Aug12
0.079

9Aug12

12Aug12

14Aug12

4Sep12

11Sep12

2Oct12

9Oct12

0.00%
0.00%

9Oct12
0.079

0.00%

TECHNICAL REQUISITIONS
3392-RQ-32-13-0001 MR for Gate valves

3392-RQ-32-13-0002 MR for Ball Valves

3392-RQ-32-13-0003 MR for Globe Valves

3392-RQ-32-13-0004 MR for Check valves

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

20May12

30May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

19Jul12

0.00%
0.035

20May12

30May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

0.00%
0.00%

19Jul12
0.035

20May12

30May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

0.00%
0.00%

19Jul12
0.035

20May12

30May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

0.00%
0.00%

19Jul12
0.035

0.00%

Page 126 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-RQ-32-13-0005 MR for Strainers

3392-RQ-32-13-0006 MR for Special Items (If required)

3392-RQ-32-13-0007 MR for CS station Pipes, Fittings & Flanges

3392-RQ-32-13-0008 MR for Bolts, Nuts and Gaskets

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

20May12

30May12

24May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

9May12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

14Jun12

21Jun12

12Jul12

WTD
WTG

85.0%

95.0%

19Jul12

19Jul12

PRG

15Aug12

16Aug12

6Sep12

13Sep12

4Oct12

11Oct12

30May12

15May12

5Jun12

12Jun12

3Jul12

10Jul12

11Oct12

30May12

15May12

5Jun12

12Jun12

3Jul12

10Jul12

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.00%
0.00%

10Jul12
0.035

15May12

Planned

0.00%
0.00%
0.035

15May12

Remarks

0.00%
0.035

13Aug12

0.00%
0.00%

10Jul12
0.035

0.00%

DRAWINGS
3392-32-13-22-0001 Overall Plot plan - QP Refinery

3392-33-13-22-0002 Overall Plot plan BSV-3

3392-32-13-22-0003 Plot Plan - Jet A1 Pump House

3392-33-13-22-0004 Plot Plan - BSV-3

3392-32-13-22-0005 Plot Plan - Pig Launcher Area

3392-32-13-31-0001 Piping Key Plan QP Refinery

3392-32-13-31-0002 Piping GA Jet A1 Pumps area- QP Refinery

3392-32-13-31-0003 Piping GA Pig Launcher area - QP Refinery

3392-33-13-31-0004 Piping GA BSV-3

3392-32-13-31-0005 Piping GA Unit 32 Sector 31 QP Refinery

3392-32-13-31-0006 Piping GA Unit 32 Sector 32 QP Refinery

3392-32-13-31-0007 Piping GA Unit 32 Sector 39 QP Refinery

3392-32-13-31-0008 Piping GA Unit 32 Sector 40 QP Refinery

3392-32-13-31-0009 Piping GA Unit 32 Sector 41 QP Refinery

3392-32-13-31-0010 Piping GA Unit 32 Sector 42 QP Refinery

3392-32-13-31-0011 Piping GA Unit 32 Sector 20 QP Refinery

3392-32-13-31-0012 Piping GA Unit 32 Sector 20 QP Refinery (Demolition)

3392-32-13-31-0013 Piping GA - Deluge Piping System 1

3392-32-13-31-0014 Piping GA - Deluge Piping System 2

3392-32-13-31-0015 Piping GA - Deluge Piping System 3

3392-32-13-31-0016 Piping GA - Deluge Piping System 4

Isometrics for above ground Piping

Isometrics for underground Piping

3392-32-31-63-0001 Standard Pipe Support Details

10May12

17May12

4Jun12

20Jun12

8Jul12

16Jul12

16Jul12

0.00%
0.132

9May12

10May12

17May12

4Jun12

20Jun12

8Jul12

16Jul12

0.00%
0.00%

16Jul12
0.132

9May12

10May12

17May12

4Jun12

20Jun12

8Jul12

16Jul12

0.00%
0.00%

16Jul12
0.210

9May12

10May12

17May12

4Jun12

20Jun12

8Jul12

16Jul12

0.00%
0.00%

16Jul12
0.210

21Jun12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.210

14Jun12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.114

10Jul12

22Jul12

23Jul12

13Aug12

20Aug12

10Sep12

17Sep12

0.00%
0.00%

17Sep12
0.158

10Jul12

22Jul12

23Jul12

13Aug12

20Aug12

10Sep12

17Sep12

0.00%
0.00%

17Sep12
0.158

5Jul12

8Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

10Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.158

29Jul12

6Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

0.00%
0.00%

2Oct12
0.158

29Jul12

6Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

0.00%
0.00%

2Oct12
0.158

29Jul12

5Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

0.00%
0.00%

2Oct12
0.158

29Jul12

5Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

0.00%
0.00%

2Oct12
0.158

19Jul12

13Aug12

15Aug12

5Sep12

12Sep12

3Oct12

10Oct12

0.00%
0.00%

10Oct12
1.508

16Aug12

19Aug12

21Aug12

11Sep12

18Sep12

9Oct12

16Oct12

0.00%
0.00%

16Oct12
1.008

14May12

14May12

24May12

14Jun12

21Jun12

12Jul12

19Jul12

0.00%
0.00%

19Jul12
0.158

0.00%
10.505

INSTRUMENTATION
SPECIFICATIONS
3392-32-15-17-0001

Modification to PMS/UPS for Data Transfer to


DCS/SCADA

P
F
F
A

20Jun12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

0.00%
0.088
0.00%

Page 127 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

3392-33-15-17-0002

DOC / DWG DESCRIPTION

Specification for PLC/RTU System @ BSV-3 for 16"


Jet A1 Fuel P/L.

3392-32-15-17-0003 Specification for Pressure Gauges

3392-32-15-17-0004 Specification for Pressure & DP Transmitters

3392-32-15-17-0006 Specification for Tempertaure Element & Transmitters

3392-32-15-17-0007 Specification for ESD & On-Off Valves

3392-32-15-17-0008 Specification for Electric Motor Operated Valves

3392-32-15-17-0009 Specification for Mass Flow Meter & Flow Computer

3392-32-15-17-0010 Specification for Safety Relief Valves

3392-32-15-17-0011 Specification for Control Valves

3392-32-15-17-0013

3392-32-15-17-0014

Specification for Instrument,F&G,Control &


Telecommunication Cables
Specifications for conditioning monitoring system ( new
UCP) interface ( as per design)

3392-32-15-17-0015 Specifications for Leak Detection System

3392-32-15-17-0016 Specification for DCS

3392-32-15-17-0017 Specification for ESD

3392-32-15-17-0018 Specification for SCADA-RTU


Specification for Instrument / Mech
3392-32-15-17-0023 / Pneumatic hook ups and Mech/Pneumatic Bulk materi
al
3392-32-15-17-0024

Specification for Electrical hook up and electrical bulk M


aterial (Junction boxes and cable glands )

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

14Jun12

28Jun12

28Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

19Jul12

26Jul12

16Aug12

WTD
WTG

85.0%

95.0%

23Aug12

23Aug12

PRG

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

26Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

3Jun12

4Jun12

25Jun12

2Jul12

23Jul12

30Jul12

23Aug12

3Jun12

4Jun12

25Jun12

2Jul12

23Jul12

30Jul12

30Jul12

6Jun12

14Jun12

5Jul12

12Jul12

2Aug12

9Aug12

30Jul12

5Jun12

14Jun12

5Jul12

12Jul12

2Aug12

9Aug12

9Aug12

12Jun12

26Jun12

17Jul12

24Jul12

14Aug12

21Aug12

9Aug12

4Jul12

2Jul12

23Jul12

30Jul12

20Aug12

27Aug12

21Aug12

4Jul12

2Jul12

23Jul12

30Jul12

20Aug12

27Aug12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

27Aug12
0.044

17Jun12

0.0000

0.00%
0.00%
0.053

17Jun12

0.0000

0.00%
0.00%
0.061

12Jun12

0.0000

0.00%
0.00%
0.061

5Jun12

0.0000

0.00%
0.00%
0.088

6Jun12

0.0000

0.00%
0.00%
0.123

24May12

0.0000

0.00%
0.00%
0.053

24May12

0.0000

0.00%
0.00%
0.070

20Jun12

0.0000

0.00%
0.00%
0.061

20Jun12

0.0000

0.00%
0.00%
0.079

20Jun12

0.0000

0.00%
0.00%
0.079

20Jun12

0.0000

0.00%
0.00%
0.079

20Jun12

0.0000

0.00%
0.00%
0.053

20Jun12

Actual

0.00%
0.00%
0.053

20Jun12

Planned

0.00%
0.00%
0.053

20Jun12

Remarks

0.00%
0.088

20Jun12

0.00%
0.00%

27Aug12
0.044

0.00%

DATA SHEETS
3392-32-15-12-0001 Data Sheet for Pressure & DP Gauges

3392-32-15-12-0002 Data Sheet for Pressure & DP Transmitters

3392-32-15-12-0003 Data Sheet for Temperature Element & Transmitters

3392-32-15-12-0005 Data Sheet for ESD Valves

3392-32-15-12-0006 Data Sheet for Electric Motor Operated Valves

3392-32-15-12-0007 Data Sheet for Mass Flow meter & Flow Computer

3392-32-15-12-0008 Data Sheet for Safety Relief Valves

3392-32-15-12-0010 Data Sheet for Control Valves

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

28May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

24May12

28May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

31Jul12

0.00%
0.053

28May12

28May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.053

28May12

28May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

0.00%
0.00%

31Jul12
0.053

10Jun12

11Jun12

11Jun12

1Jul12

5Jul12

26Jul12

31Jul12

0.00%
0.00%

31Jul12
0.070

10Jun12

10Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.061

10Jun12

10Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.061

10Jun12

10Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.044

10Jun12

10Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.070

0.00%

TECHNICAL REQUISITIONS
3392-RQ-32-15-0001 MR for Pressure Gauges

3392-RQ-32-15-0002 MR for Pressure & DP Transmitters

3392-RQ-32-15-0003 MR for Temperature Element & Transmitters

3392-RQ-32-15-0005 MR for ESD & On-Off Valves

3392-RQ-32-15-0006 MR for Electric Motor Operated Valves

24May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

22Jul12

0.00%
0.026

20May12

24May12

22May12

12Jun12

18Jun12

9Jul12

16Jul12

0.00%
0.00%

16Jul12
0.026

24May12

24May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
0.026

24May12

24May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
0.044

24May12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

0.00%
0.00%

26Jul12
0.044

0.00%

Page 128 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-RQ-32-15-0007 MR for Mass Flow meter & Flow Computer

3392-RQ-32-15-0008 MR for Safety Relief Valves

3392-RQ-32-15-0009 MR for Control Valves

3392-RQ-32-15-0010 MR for Pig Signallers

3392-RQ-32-15-0011

3392-RQ-32-15-0012

3392-RQ-32-15-0013

MR for Instrument,F&G,Control & Telecommunication


Cables
MR for Instrument / Mech
/ Pneumatic hook ups and Mech/Pneumatic Bulk material

MR for Electrical hook up and electrical bulk Material


(Junction boxes and cable glands

3392-RQ-32-15-0014 MR for Leak Detection System

3392-RQ-32-15-0015 MR for DCS

3392-RQ-32-15-0016 MR for ESD

3392-RQ-32-15-0017 MR for SCADA-RTU

3392-RQ-32-15-0018

3392-RQ-32-15-0019

MR for modification to PMS/UPS for Data Transfer to


DCS/SCADA
MR for PLC/RTU System at BSV-3 for 16" Jet A1 Fuel
Pipeline

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

24May12

24May12

31May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

18Jul12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

13Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

21Jun12

28Jun12

19Jul12

WTD
WTG

85.0%

95.0%

26Jul12

26Jul12

PRG

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

29May12

19Jun12

26Jun12

17Jul12

24Jul12

26Jul12

24May12

24May12

12Jun12

19Jun12

10Jul12

17Jul12

24Jul12

24May12

9Aug12

30Aug12

6Sep12

27Sep12

4Oct12

17Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

4Oct12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

26Jul12

24May12

31May12

21Jun12

28Jun12

19Jul12

26Jul12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

26Jul12
0.044

24May12

0.0000

0.00%
0.00%
0.026

24May12

0.0000

0.00%
0.00%
0.026

24May12

0.0000

0.00%
0.00%
0.026

24May12

0.0000

0.00%
0.00%
0.035

24May12

0.0000

0.00%
0.00%
0.018

24May12

0.0000

0.00%
0.00%
0.018

24May12

0.0000

0.00%
0.00%
0.035

2Aug12

0.0000

0.00%
0.00%
0.044

24May12

Actual

0.00%
0.00%
0.035

24May12

Planned

0.00%
0.00%
0.035

24May12

Remarks

0.00%
0.044

24May12

0.00%
0.00%

26Jul12
0.044

0.00%

DOCUMENTS/DRAWINGS
COMMON
3392-32-15-31-0001 Instrument process hook-up Diagrams

3392-32-15-32-0001 Instrument Installation details

3392-32-15-53-0001

Interface Block Diagrams

3392-32-15-20-0001 Instrument Cable schedule

3392-32-15-20-0002 Instrument JB Schedule

3392-32-15-20-0003 Instrument and Instrument signal earthing

3392-32-15-90-0001 Instrument Bulk MTO

3392-32-15-53-0002

3392-32-15-53-0003

Overall Control System Architecture Diagram


(Modification)

JB Connection Diagram

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

16Sep12

0.00%
0.096

23Jul12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

0.00%
0.00%

19Sep12
0.096

9Aug12

12Aug12

12Aug12

2Sep12

9Sep12

30Sep12

7Oct12

0.00%
0.00%

7Oct12
0.096

24Jul12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

0.00%
0.00%

23Sep12
0.342

30Jul12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.175

5Aug12

6Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

0.00%
0.00%

2Oct12
0.070

30Jul12

1Aug12

2Aug12

2Aug12

2Aug12

2Aug12

2Aug12

0.00%
0.00%

2Aug12
0.307

1Jul12

3Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.105

5Aug12

8Aug12

9Aug12

30Aug12

6Sep12

27Sep12

4Oct12

0.00%
0.00%

4Oct12
0.167

0.00%

QP Refinery
3392-32-15-54-0001 Cause and Effect Diagrams (As per SOW)

3392-32-15-21-0001 Alarm & Trip Schedule

3392-32-15-21-0002 Instrument Schedule

3392-32-15-21-0003 I/O Schedule DCS

3392-32-15-21-0004 I/O Schedule ESD

3392-32-15-21-0005 I/O Schedule SCADA-RTU

3392-32-15-54-0002 Instrumentation Cable Block Diagrams

20Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

22Aug12

0.00%
0.281

18Jul12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

0.00%
0.00%

23Sep12
0.237

26Jun12

26Jun12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.368

1Jul12

15Jul12

16Jul12

6Aug12

13Aug12

3Sep12

10Sep12

0.00%
0.00%

10Sep12
0.079

18Jul12

29Jul12

29Jul12

19Aug12

26Aug12

16Sep12

23Sep12

0.00%
0.00%

23Sep12
0.079

23Jul12

26Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

0.00%
0.00%

20Sep12
0.079

23Jul12

25Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

0.00%
0.00%

20Sep12
0.368

0.00%

Page 129 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-15-54-0003 Instrument Interconnection Wiring Diagram

3392-32-15-54-0004 Instrument Loop Diagrams

3392-32-15-66-0001 Instrument Location Layout

3392-32-15-33-0001 Instrument Cable Routing/Cable tray Layouts

3392-32-15-66-0002

Instrument Equipment Room Layouts (Modification


Scope)

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

16Aug12

19Aug12

19Aug12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

13Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

9Sep12

16Sep12

7Oct12

WTD
WTG

85.0%

95.0%

14Oct12

14Oct12

PRG

19Aug12

19Aug12

9Sep12

16Sep12

7Oct12

14Oct12

25Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

14Oct12

21Aug12

22Aug12

12Sep12

19Sep12

10Oct12

17Oct12

20Sep12

21Aug12

22Aug12

12Sep12

19Sep12

10Oct12

17Oct12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

17Oct12
0.316

20Aug12

Actual

0.00%
0.00%
0.289

20Aug12

Planned

0.00%
0.00%
0.447

24Jul12

Remarks

0.00%
0.368

15Aug12

0.00%
0.00%

17Oct12
0.298

0.00%

BSV-3
3392-33-15-61-0001 Cause and Effect Diagrams (As per SOW)

3392-33-15-22-0001 Alarm & Trip Schedule

3392-33-15-22-0002 Instrument Schedule

3392-33-15-22-0005 I/O Schedule SCADA-RTU

3392-33-15-61-0002 Instrumentation Cable Block Diagrams

3392-33-15-61-0003 Instrument Interconnection Wiring Diagram

3392-33-15-61-0004 Instrument Loop Diagrams

3392-33-15-66-0003 Instrument Location Layout

3392-33-15-33-0002 Instrument Cable Routing/Cable tray Layouts

3392-33-15-66-0004

Instrument Equipment Room Layouts (Modification


Scope)

18Jun12

18Jun12

9Jul12

16Jul12

6Aug12

13Aug12

13Aug12

0.00%
0.219

18Jul12

24Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

0.00%
0.00%

20Sep12
0.237

24Jun12

26Jun12

4Jul12

25Jul12

1Aug12

22Aug12

29Aug12

0.00%
0.00%

29Aug12
0.368

23Jul12

3Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

0.00%
0.00%

20Sep12
0.173

23Jul12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

0.00%
0.00%

19Sep12
0.342

30Jul12

31Jul12

1Aug12

22Aug12

29Aug12

19Sep12

26Sep12

0.00%
0.00%

26Sep12
0.342

1Aug12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.447

9Aug12

13Aug12

13Aug12

3Sep12

10Sep12

1Oct12

8Oct12

0.00%
0.00%

8Oct12
0.289

20Aug12

20Aug12

21Aug12

11Sep12

18Sep12

9Oct12

16Oct12

0.00%
0.00%

16Oct12
0.289

20Aug12

20Aug12

21Aug12

11Sep12

18Sep12

9Oct12

16Oct12

0.00%
0.00%

16Oct12
0.298

0.00%
9.959

TELECOMMUNICATION
SPECIFICATIONS
3392-32-16-51-0001

3392-32-16-51-0002

3392-32-16-51-0004

Specifications for Existing TELECOM systems


modifications
Specifications for Existing PA/GA systems
modifications
Specifications for BMS, Access Control System and
CCTV

P
F
F
A
P
F
F
A
P
F
F
A

15Jul12

P
F
F
A
P
F
F
A

3Jun12

P
F
F
A
P
F
F
A

29Jul12

18Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

0.00%
0.123

15Jul12

18Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

0.00%
0.00%

13Sep12
0.123

15Jul12

18Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

0.00%
0.00%

13Sep12
0.158

0.00%

MATERIAL REQUISITIONS
3392-RQ-32-16-0001

MRs for Existing TELECOM systems/Network


modifications

3392-RQ-32-16-0002 MRs for Existing PA/GA systems modifications

3Jun12

4Jun12

25Jun12

2Jul12

23Jul12

30Jul12

30Jul12

0.00%
0.053

3Jun12

3Jun12

4Jun12

25Jun12

2Jul12

23Jul12

30Jul12

0.00%
0.00%

30Jul12
0.053

0.00%

DRAWINGS
3392-32-16-53-0001 Overall TELECOM system cable block diagram

3392-33-16-53-0002 BSV-3 PA/GA (Telephone) system modification

30Jul12

31Jul12

21Aug12

28Aug12

18Sep12

25Sep12

25Sep12

0.00%
0.289

1Aug12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.254

0.00%
1.052

ELECTRICAL
SPECIFICATIONS
COMMON
3392-32-16-17-0001 Specification for Electrical Bulk Materials

3392-32-16-17-0002 Specification for Distribution Boards

3392-32-16-17-0003

Specification for Electrical Power, Control & Earthing


Cables

P
F
F
A
P
F
F
A
P
F
F
A

15May12

P
F
F
A

15May12

15May12

20May12

10Jun12

17Jun12

8Jul12

15Jul12

15Jul12

0.00%
0.053

15May12

15May12

20May12

10Jun12

17Jun12

8Jul12

15Jul12

0.00%
0.00%

15Jul12
0.053

15May12

15May12

20May12

10Jun12

17Jun12

8Jul12

15Jul12

0.00%
0.00%

15Jul12
0.053

0.00%

QP Refinery
3392-32-16-17-0004

Specification for 11KV & 3.3KV Switchboard


Modifications

15May12

28May12

18Jun12

25Jun12

16Jul12

23Jul12

23Jul12

0.00%
0.079
0.00%

Page 130 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-16-17-0005 Specification for 415V Switchboard Modifications

3392-32-16-17-0007 Specification for Interposing relay panel

3392-32-16-17-0008 Specification for 110V AC UPS

3392-32-16-17-0009 Specification for HV Motors

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

14Jun12

18Jun12

20Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

8Jul12

15Jul12

5Aug12

WTD
WTG

85.0%

95.0%

12Aug12

12Aug12

PRG

18Jun12

20Jun12

8Jul12

15Jul12

5Aug12

12Aug12

22May12

22May12

5Jun12

7Jun12

28Jun12

5Jul12

12Aug12

13May12

13May12

3Jun12

10Jun12

1Jul12

8Jul12

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

5Jul12
0.053

13May12

Planned

0.00%
0.00%
0.053

10May12

Remarks

0.00%
0.079

14Jun12

0.00%
0.00%

8Jul12
0.079

0.00%

BSV-3
3392-33-16-17-0010 Specification for 415V Switchboard modificaion

P
F
F
A

21Jun12

P
F
F
A
P
F
F
A

21May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

15May12

P
F
F
A

23May12

P
F
F
A
P
F
F
A

22May12

P
F
F
A
P
F
F
A

26Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

26Jun12

24Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

0.00%
0.079
0.00%

DATA SHEETS
COMMON
3392-32-16-12-0001 Data Sheet for Distribution Boards

3392-32-16-12-0002 Data Sheet for Power, Control and Earthing Cable

21May12

22May12

12Jun12

19Jun12

10Jul12

17Jul12

17Jul12

0.00%
0.079

21May12

21May12

22May12

12Jun12

19Jun12

10Jul12

17Jul12

0.00%
0.00%

17Jul12
0.053

0.00%

QP Refinery
3392-32-16-12-0003 Data Sheet for 11 & 3.3 KV Switchgear Modification

3392-32-16-12-0004 Data Sheet for 415V Switchboard Modifications

3392-32-16-12-0005 Data Sheet for 110V AC UPS

3392-32-16-12-0006 Data Sheet for 11KV Motors

3392-32-16-12-0007 Data Sheet for 3.3KV Motors

5Jun12

21May12

11Jun12

18Jun12

9Jul12

16Jul12

16Jul12

0.00%
0.079

14Jun12

18Jun12

20Jun12

8Jul12

16Jul12

6Aug12

13Aug12

0.00%
0.00%

13Aug12
0.079

13May12

14May12

15May12

5Jun12

12Jun12

3Jul12

10Jul12

0.00%
0.00%

10Jul12
0.079

8May12

9May12

10May12

31May12

7Jun12

28Jun12

5Jul12

0.00%
0.00%

5Jul12
0.079

8May12

9May12

10May12

31May12

7Jun12

28Jun12

5Jul12

0.00%
0.00%

5Jul12
0.079

0.00%

MATERIAL REQUISITIONS
COMMON
3392-RQ-32-16-0011 MR for Distribution Boards

29May12

28May12

18Jun12

25Jun12

16Jul12

23Jul12

23Jul12

0.00%
0.079
0.00%

QP Refinery
3392-RQ-32-16-0012 MR for 11KV, 3.3KV & 415V Switchboard Modifications

3392-RQ-32-16-0013 MR for 110V AC UPS

29May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

22Jul12

0.00%
0.079

16May12

31May12

21May12

11Jun12

18Jun12

9Jul12

16Jul12

0.00%
0.00%

16Jul12
0.053

0.00%

BSV-3
3392-RQ-33-16-0014 MR for 415V Switchboard modificaion

3392-RQ-32-16-0015

MR for 415KV Switchboard modificaion (SUBSTATION


6003)

28Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

22Aug12

0.00%
0.079

26Jun12

28Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

0.00%
0.00%

22Aug12
0.000

0.00%

REPORTS / CALCULATIONS
QP Refinery
3392-32-16-30-0001 Cable Sizing Calculation

3392-32-16-30-0002 Lighting Calculation

3392-32-16-30-0003 UPS/Battery Sizing Calculations

3392-32-16-30-0004 Power System Study

3392-32-16-30-0005 Protection co-ordination study

1Jul12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

0.00%
0.237

22Jul12

24Jul12

24Jul12

14Aug12

21Aug12

11Sep12

18Sep12

0.00%
0.00%

18Sep12
0.395

15May12

16May12

17May12

7Jun12

14Jun12

5Jul12

12Jul12

0.00%
0.00%

12Jul12
0.158

30Jul12

31Jul12

1Aug12

22Aug12

29Aug12

19Sep12

26Sep12

0.00%
0.00%

26Sep12
0.789

20May12

16May12

30May12

20Jun12

27Jun12

18Jul12

25Jul12

0.00%
0.00%

25Jul12
0.789

0.00%

BSV-3
3392-33-16-30-0006 Cable Sizing Calculation

3392-33-16-30-0007 Lighting Calculation

P
F
F
A
P
F
F
A

12Jun12

P
F
F
A
P
F
F
A

27Jun12

14Jun12

18Jun12

9Jul12

16Jul12

6Aug12

13Aug12

13Aug12

0.00%
0.158

2Jul12

11Jun12

4Jul12

25Jul12

2Aug12

23Aug12

30Aug12

0.00%
0.00%

30Aug12
0.316

0.00%

LISTS / SCHEDULES
QP Refinery
3392-32-16-31-0001 Electrical load list

3392-32-16-41-0011 DB Schedules

27Jun12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

26Aug12

0.00%
0.079

8Jul12

11Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.263

0.00%

Page 131 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-16-31-0005 Electrical Tie-in Schedule

3392-32-16-31-0011 Electrical Cable Schedule

3392-32-16-43-0001 Electrical Bulk MTO

3392-32-16-31-0021 Electrical Equipment list

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

2Jul12

4Jul12

5Jul12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

26Jul12

2Aug12

23Aug12

WTD
WTG

85.0%

95.0%

30Aug12

30Aug12

PRG

11Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

30Jul12

30Jul12

30Jul12

30Jul12

30Jul12

30Jul12

6Sep12

1Jul12

5Jul12

26Jul12

2Aug12

23Aug12

30Aug12

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

30Jul12
0.474

2Jul12

Planned

0.00%
0.00%
0.395

25Jul12

Remarks

0.00%
0.079

8Jul12

0.00%
0.00%

30Aug12
0.079

0.00%

BSV-3
3392-33-16-30-0031 Electrical load list

3392-33-16-41-0021 DB Schedules

3392-33-16-31-0035 Electrical Tie-in Schedule

3392-33-16-31-0012 Electrical Cable Schedule

3392-33-16-43-0002 Electrical Bulk MTO

3392-33-16-31-0022 Electrical Equipment list

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

24May12

P
F
F
A
P
F
F
A
P
F
F
A

21Jun12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

23Jul12

31May12

29May12

19Jun12

26Jun12

17Jul12

24Jul12

24Jul12

0.00%
0.079

24Jun12

19Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.105

17Jun12

19Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.079

16Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.210

23Jul12

29Jul12

29Jul12

29Jul12

29Jul12

29Jul12

29Jul12

0.00%
0.00%

29Jul12
0.210

19Jun12

19Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

0.00%
0.00%

20Aug12
0.079

0.00%

DRAWINGS
3392-32-16-21-0001 Typical EARTHING INSTALLATION DETAILS

3392-32-16-41-0001 Typical LIGHTING INSTALLATION DETAILS

3392-32-16-31-0031 Typical POWER INSTALLATION DETAILS

25Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

23Aug12

0.00%
0.105

21Jun12

25Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.105

21Jun12

25Jun12

28Jun12

19Jul12

26Jul12

16Aug12

23Aug12

0.00%
0.00%

23Aug12
0.105

0.00%

SINGLE LINE DIAGRAMS


QP Refinery
3392-32-16-32-0001 11KV SLD

3392-32-16-32-0002 3.3KV SLD

3392-32-16-32-0003 415V SLD

3392-32-16-32-0004 110V AC UPS SLD

3392-32-16-32-0005 MOV DB SLD-Pump House

3392-32-16-32-0006 LPN SLD - SER 12 Extension

3392-32-16-32-0007 MOV DB-Pig Launcher area

3392-32-16-32-0008 LPN - Pig Launcher area

3392-32-16-32-0009 LPN SLD - Pump house

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

0.00%
0.316

26Jul12

29Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

0.00%
0.00%

24Sep12
0.316

31Jul12

8Jul12

2Aug12

23Aug12

30Aug12

20Sep12

27Sep12

0.00%
0.00%

27Sep12
0.316

15May12

27May12

27May12

17Jun12

24Jun12

15Jul12

22Jul12

0.00%
0.00%

22Jul12
0.237

28May12

5Jun12

3Jun12

24Jun12

1Jul12

22Jul12

29Jul12

0.00%
0.00%

29Jul12
0.210

10Jul12

11Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.237

3Jun12

4Jun12

7Jun12

28Jun12

5Jul12

26Jul12

2Aug12

0.00%
0.00%

2Aug12
0.210

15Jul12

16Jul12

17Jul12

7Aug12

14Aug12

4Sep12

11Sep12

0.00%
0.00%

11Sep12
0.237

18Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.237

0.00%

BSV-3
3392-33-16-32-0010 415V SLD

3392-33-16-32-0011 LPN SLD - Plant area

P
F
F
A
P
F
F
A

5Jul12

P
F
F
A

15Jul12

P
F
F
A
P
F
F
A
P
F
F
A

24Jul12

8Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

6Sep12

0.00%
0.395

5Jul12

8Jul12

12Jul12

2Aug12

9Aug12

30Aug12

6Sep12

0.00%
0.00%

6Sep12
0.210

0.00%

STATION - T1
3392-33-16-32-0013 DB SLD modification

17Jul12

18Jul12

8Aug12

15Aug12

5Sep12

12Sep12

12Sep12

0.00%
0.210
0.00%

LAYOUTS
QP Refinery
3392-32-16-11-0001 Cable Routing Layout - Pump House/SS/SER-12

3392-32-16-11-0002 Cable Routing Layout - Pig Launcher area

3392-32-16-11-0003 Earthing Layout - Plump House/SS/SER-12

29Jul12

31Jul12

21Aug12

28Aug12

18Sep12

25Sep12

25Sep12

0.00%
0.552

24Jul12

29Jul12

31Jul12

21Aug12

28Aug12

18Sep12

25Sep12

0.00%
0.00%

25Sep12
0.395

1Aug12

6Aug12

6Aug12

27Aug12

3Sep12

24Sep12

1Oct12

0.00%
0.00%

1Oct12
0.500

0.00%

Page 132 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-16-11-0004 Earthing Layout - Pig Launcher area

3392-32-16-11-0005 Lighting Layout - Pump House

3392-32-16-11-0006 Lighting Layout - Pig Launcher area

3392-32-16-11-0007 Lighting Layout-SER 12 Extension

3392-32-16-11-0008 Lightning Protection Layout-SER 12 Extension

3392-32-16-11-0009 Equipment Layout modification-S/S 6003

3392-32-16-11-0010 Equipment Layout-SER 12 Extension

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

30Jul12

1Aug12

2Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

23Aug12

30Aug12

20Sep12

WTD
WTG

85.0%

95.0%

27Sep12

27Sep12

PRG

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

24Sep12

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

24Sep12

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

24Sep12

18Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

24Sep12

1Jul12

1Jul12

22Jul12

29Jul12

19Aug12

26Aug12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

13Sep12
0.395

25Jun12

0.0000

0.00%
0.00%
0.237

15Jul12

0.0000

0.00%
0.00%
0.474

25Jul12

Actual

0.00%
0.00%
0.289

25Jul12

Planned

0.00%
0.00%
0.421

25Jul12

Remarks

0.00%
0.368

25Jul12

0.00%
0.00%

26Aug12
0.316

0.00%

BSV-3
3392-33-16-11-0011 Cable Routing Layout

3392-33-16-11-0012 Earthing Layout

3392-33-16-11-0013 Lighting Layout

P
F
F
A
P
F
F
A
P
F
F
A

15Jul12

P
F
F
A

21Jun12

P
F
F
A

22Jul12

18Jul12

18Jul12

8Aug12

15Aug12

5Sep12

12Sep12

12Sep12

0.00%
0.395

15Jul12

19Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

0.00%
0.00%

13Sep12
0.447

4Jul12

5Jul12

5Jul12

26Jul12

2Aug12

23Aug12

30Aug12

0.00%
0.00%

30Aug12
0.368

0.00%

STATION - T1
3392-33-16-11-0014 Cable Routing Layout (Station T1)

24Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

20Aug12

0.00%
0.289
0.00%

Protection & Control Schematics


3392-32-16-32-0001 Scheme for HV motors

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

0.00%
0.474
0.00%
15.731

CIVIL & STRUCTURAL


SPECIFICATIONS
3392-32-18-17-0001 Specifications for Structural Steel

3392-32-18-17-0002 Specifications for Earth Works

3392-33-18-17-0003 Specifications for Fencing

3392-32-18-17-0004 Specifications for Concrete Works

3392-32-18-17-0005 Specificaitons for Building & Architectural Works

3392-32-18-17-0006 Specifications for Road and Paving Works

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

6May12

8May12

7May12

28May12

4Jun12

25Jun12

2Jul12

2Jul12

0.00%
0.061

8May12

8May12

13May12

3Jun12

10Jun12

1Jul12

8Jul12

0.00%
0.00%

8Jul12
0.061

8May12

8May12

13May12

3Jun12

10Jun12

1Jul12

8Jul12

0.00%
0.00%

8Jul12
0.061

8May12

8May12

13May12

3Jun12

10Jun12

1Jul12

8Jul12

0.00%
0.00%

8Jul12
0.061

16May12

20May12

21May12

11Jun12

18Jun12

9Jul12

16Jul12

0.00%
0.00%

16Jul12
0.158

16May12

20May12

21May12

11Jun12

18Jun12

9Jul12

16Jul12

0.00%
0.00%

16Jul12
0.061

0.00%

SCOPE OF WORKS / REPORTS


3392-32-14-17-0002

Scope Of Work For Geotechnical Survey And


Investigation

3392-33-14-17-0001 SOW - Topographical Survey

P
F
F
A
P
F
F
A

28Mar12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

27May12

28Mar12

1Apr12

22Apr12

29Apr12

20May12

27May12

27May12

0.00%
0.210

25Mar12

28Mar12

28Mar12

29Apr12

2May12

0.00%
0.00%

2May12
0.132

0.00%

TYPICAL DETAILS / DRAWINGS


3392-32-14-12-0001 General Notes, Abbreviations & Symbols

3392-32-14-40-0071 Standard Road Details

3392-32-14-40-0072 Typical Safety Barrier Details

3392-32-14-40-0073 Typical Bollard Details

3392-32-14-40-0074 Typical Fence And Gate Details

3392-32-14-40-0075 Standard Grade Slab, Paving And Wall Details

3392-32-14-40-0076 Typical Concrete Protection Details

29May12

29May12

19Jun12

26Jun12

17Jul12

24Jul12

24Jul12

0.00%
0.096

5Jun12

7Jun12

11Jun12

2Jul12

9Jul12

30Jul12

6Aug12

0.00%
0.00%

6Aug12
0.167

5Jun12

7Jun12

11Jun12

27Jun12

4Jul12

25Jul12

1Aug12

0.00%
0.00%

1Aug12
0.096

18Jun12

20Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

0.00%
0.00%

22Aug12
0.105

5Jun12

7Jun12

11Jun12

27Jun12

4Jul12

25Jul12

1Aug12

0.00%
0.00%

1Aug12
0.114

10Jun12

10Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

0.00%
0.00%

13Aug12
0.114

6Jun12

7Jun12

11Jun12

27Jun12

5Jul12

26Jul12

2Aug12

0.00%
0.00%

2Aug12
0.140

0.00%

Page 133 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-14-40-0077 Typical Roof Details

3392-32-14-40-0078 Typical Concrete Protection Slab Details

3392-32-14-40-0079 Typical Storm Water Manhole Details

3392-32-14-40-0081 Typical Oily Water Sewer Manhole Details

3392-32-14-40-0082 Typical Culvert Details

3392-32-14-40-0083 Typical Light Pole Foundation Details

3392-32-14-40-0084 Typical Pipeline Sleeper Details

3392-32-14-40-0085 Typical Pipeline Anchor Block Details

3392-32-18-21-0001 Typical Details For Steel Ladders

3392-32-18-21-0002 Typical Nosing & Bearing Member Details

3392-32-18-21-0003 Steel Works Details - Staircase & Handrail

3392-32-18-21-0004 Standard Steel Flooring Details

3392-32-18-31-0001 Typical Steel Platform Connection Details

3392-32-18-31-0002 Typical Steel Platform Layout & Details

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

6Jun12

7Jun12

11Jun12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

27Jun12

5Jul12

26Jul12

WTD
WTG

85.0%

95.0%

2Aug12

2Aug12

PRG

10Jun12

11Jun12

8Jul12

16Jul12

6Aug12

13Aug12

7Jun12

11Jun12

27Jun12

5Jul12

26Jul12

2Aug12

13Aug12

7Jun12

11Jun12

27Jun12

5Jul12

26Jul12

2Aug12

2Aug12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

2Aug12

21Jun12

3Jul12

24Jul12

31Jul12

21Aug12

28Aug12

2Sep12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

28Aug12

5Aug12

7Aug12

28Aug12

4Sep12

25Sep12

2Oct12

30Sep12

7Jun12

13Jun12

27Jun12

4Jul12

25Jul12

1Aug12

2Oct12

10Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

1Aug12

10Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

13Aug12

10Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

13Aug12

10Jun12

13Jun12

8Jul12

16Jul12

6Aug12

13Aug12

13Aug12

18Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

13Aug12
0.298

17Jul12

0.0000

0.00%
0.00%
0.123

10Jun12

0.0000

0.00%
0.00%
0.123

10Jun12

0.0000

0.00%
0.00%
0.123

10Jun12

0.0000

0.00%
0.00%
0.123

10Jun12

0.0000

0.00%
0.00%
0.386

6Jun12

0.0000

0.00%
0.00%
0.193

2Aug12

0.0000

0.00%
0.00%
0.193

1Aug12

0.0000

0.00%
0.00%
0.552

21Jun12

0.0000

0.00%
0.00%
0.193

1Jul12

Actual

0.00%
0.00%
0.193

6Jun12

Planned

0.00%
0.00%
0.140

6Jun12

Remarks

0.00%
0.114

10Jun12

0.00%
0.00%

13Sep12
1.079

0.00%

TYPICAL CALCULATIONS
3392-32-17-22-0001

Typical Structural Calculation For Concrete Protection


Slab

3392-32-17-22-0002 Typical Structural Calculation For Light Pole Foundation

3392-32-17-22-0003 Typical Structural Calculation For Anchor Block

3392-32-17-22-0004 Typical Structural Calculation For Pipeline Sleeper

3392-32-17-22-0005 Typical Structural Calculation For Culverts

3392-32-18-32-0001 Structural Calculation For Steel Platform

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

31May12

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

21Aug12

31May12

5Jun12

26Jun12

3Jul12

24Jul12

31Jul12

31Jul12

0.00%
0.316

19Jun12

21Jun12

24Jun12

15Jul12

22Jul12

12Aug12

19Aug12

0.00%
0.00%

19Aug12
0.210

2Jul12

9Jul12

9Jul12

30Jul12

6Aug12

27Aug12

3Sep12

0.00%
0.00%

3Sep12
0.342

2Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.237

2Jul12

8Jul12

8Jul12

29Jul12

5Aug12

26Aug12

2Sep12

0.00%
0.00%

2Sep12
0.474

13Aug12

20Aug12

20Aug12

10Sep12

17Sep12

8Oct12

15Oct12

0.00%
0.00%

15Oct12
0.395

0.00%

DRAWINGS & CALCULATIONS


QP Refinery
3392-32-14-20-0001 Civil GA - Pump Area

3392-32-14-20-0002 Civil GA - Pig Launcher Area

3392-32-14-20-0003 Civil GA - Pipe Supports Location Plan

3392-32-14-40-0001 Pipe Supports - Sleepers

3392-32-14-40-0002 Pipe Supports - T Posts

3392-32-14-40-0003 Pipe Supports - Portal Supports

3392-32-14-40-0004 Pipe Rack Details

3392-32-14-40-0005 Pipe Rack Foundation Details

3392-32-14-40-0006 Pig Launcher Foundation Details

27Aug12

29Aug12

19Sep12

26Sep12

17Oct12

24Oct12

24Oct12

0.00%
0.649

20Aug12

26Aug12

28Aug12

18Sep12

25Sep12

16Oct12

23Oct12

0.00%
0.00%

23Oct12
0.649

21Aug12

27Aug12

29Aug12

19Sep12

26Sep12

17Oct12

24Oct12

0.00%
0.00%

24Oct12
0.649

9Jul12

15Jul12

17Jul12

7Aug12

14Aug12

4Sep12

11Sep12

0.00%
0.00%

11Sep12
0.535

9Jul12

15Jul12

17Jul12

7Aug12

14Aug12

4Sep12

11Sep12

0.00%
0.00%

11Sep12
0.535

14Aug12

20Aug12

20Aug12

10Sep12

17Sep12

8Oct12

15Oct12

0.00%
0.00%

15Oct12
0.535

22Aug12

28Aug12

28Aug12

18Sep12

25Sep12

16Oct12

23Oct12

0.00%
0.00%

23Oct12
0.535

22Aug12

26Aug12

28Aug12

18Sep12

25Sep12

16Oct12

23Oct12

0.00%
0.00%

23Oct12
0.403

13Aug12

15Aug12

16Aug12

6Sep12

13Sep12

4Oct12

11Oct12

0.00%
0.00%

11Oct12
0.403

0.00%

Page 134 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-14-40-0007 Pig Trap & Jib Crane Foundation Details

3392-32-14-40-0008 Impact Wall Details

3392-32-14-40-0009 Pump Shed - Architectural Ground Floor Plan

3392-32-14-40-0010 Pump Shed - Architectural Plan At Crane Beam Level

3392-32-14-40-0011 Pump Shed - Architectural Roof Plan

3392-32-14-40-0012 Pump Shed - Architectural Elevations

3392-32-14-40-0013 Pump Shed - Architectural Sections

3392-32-14-40-0014 Pump Shed - Miscellaneous Details

3392-32-14-40-0015 Pump Shed - Structural Plan At Base Level

3392-32-14-40-0016 Pump Shed - Structural Plan At Crane Beam Level

3392-32-14-40-0017 Pump Shed - Structural Roof Plan

3392-32-14-40-0018 Pump Shed - Structural Elevations

3392-32-14-40-0019 Pump Shed - Structural Sections

3392-32-14-40-0020 Pump Shed - Sturctural Miscellaneous Details

3392-32-14-40-0021 Pump Shed - Sturctural Connection Details

3392-32-14-40-0022 Structural Calculation For Pipe Supports

3392-32-14-40-0026 SER12 - Demolition Details

3392-32-14-40-0027 SER12 Extension - Architectural Ground Floor Plan

3392-32-14-40-0028 SER12 Extension - Architectural Roof Plan

3392-32-14-40-0029 SER12 Extension - Architectural Elevations

3392-32-14-40-0030 SER12 Extension - Architectural Sections

3392-32-14-40-0031

SER12 Extension - Doors, Windows & Finishes


Schedule

3392-32-14-40-0032 SER12 Extension - Miscellaneous Details

3392-32-14-40-0033

SER12 Extension - Foundation/Column Layout &


Reinf. Details

3392-32-14-40-0034 SER12 Extension - Grade Slab Ga & Reinf. Details

3392-32-14-40-0035

SER12 Extension - Grade Beam Layout & Reinf.


Details

3392-32-14-40-0036 SER12 Extension - Roof Beam Layout & Reinf. Details

3392-32-14-40-0037 SER12 Extension - Roof Slab Layout & Reinf. Details

3392-32-14-40-0038 SER12 Extension - Miscellaneous Reinf. Details

3392-32-14-40-0041 Pump Shed - Pump Foundation Details

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

13Aug12

15Aug12

16Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

6Sep12

13Sep12

4Oct12

WTD
WTG

85.0%

95.0%

11Oct12

11Oct12

PRG

21Aug12

22Aug12

12Sep12

19Sep12

10Oct12

17Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

17Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

28Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

28Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

28Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

28Oct12

2Sep12

2Sep12

23Sep12

30Sep12

21Oct12

28Oct12

28Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

28Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

3Sep12

3Sep12

24Sep12

1Oct12

22Oct12

29Oct12

29Oct12

19Aug12

19Aug12

9Sep12

16Sep12

7Oct12

14Oct12

29Oct12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

14Oct12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

17Jul12

19Jul12

9Aug12

16Aug12

6Sep12

13Sep12

13Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

13Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

24Jul12

25Jul12

15Aug12

22Aug12

12Sep12

19Sep12

19Sep12

9Sep12

11Sep12

2Oct12

9Oct12

30Oct12

6Nov12

19Sep12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

6Nov12
0.258

0.00%

Page 135 of 266

0.0000

0.00%
0.00%
0.204

5Sep12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.205

22Jul12

0.0000

0.00%
0.00%
0.487

10Jul12

0.0000

0.00%
0.00%
0.487

10Jul12

0.0000

0.00%
0.00%
0.492

10Jul12

0.0000

0.00%
0.00%
0.342

10Jul12

0.0000

0.00%
0.00%
0.342

10Jul12

0.0000

0.00%
0.00%
0.316

10Jul12

0.0000

0.00%
0.00%
0.921

10Jul12

0.0000

0.00%
0.00%
0.456

14Aug12

0.0000

0.00%
0.00%
0.456

25Jul12

0.0000

0.00%
0.00%
0.456

25Jul12

0.0000

0.00%
0.00%
0.456

25Jul12

0.0000

0.00%
0.00%
0.535

25Jul12

0.0000

0.00%
0.00%
0.456

25Jul12

0.0000

0.00%
0.00%
0.456

25Jul12

0.0000

0.00%
0.00%
0.482

25Jul12

0.0000

0.00%
0.00%
0.482

22Jul12

0.0000

0.00%
0.00%
0.482

22Jul12

0.0000

0.00%
0.00%
0.456

22Jul12

0.0000

0.00%
0.00%
0.456

22Jul12

Actual

0.00%
0.00%
0.535

22Jul12

Planned

0.00%
0.00%
0.403

22Jul12

Remarks

0.00%
0.403

19Aug12

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-14-40-0042 Structural Calculation For Pump House

3392-32-14-40-0043 Structural Calculation For Pump Foundation

3392-32-14-40-0044 Structural Calculation For SER12 Extension

3392-32-14-40-0045 Structural Calculation For Impact Wall

3392-32-14-40-0046 Structural Calculation For Pig Launcher Foundation

3392-32-14-40-0047 Structural Calculation For Jib Crane Foundation

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

5.0%

5.0%

40.0%

22Jul12

5Aug12

5Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

26Aug12

2Sep12

23Sep12

WTD
WTG

85.0%

95.0%

30Sep12

30Sep12

PRG

9Sep12

11Sep12

2Oct12

9Oct12

30Oct12

6Nov12

4Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

6Nov12

19Aug12

20Aug12

10Sep12

17Sep12

8Oct12

15Oct12

30Sep12

8Aug12

9Aug12

30Aug12

6Sep12

27Sep12

4Oct12

15Oct12

13Aug12

14Aug12

4Sep12

11Sep12

2Oct12

9Oct12

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.0000

0.0000

0.0000

0.0000

0.00%
0.00%

4Oct12
0.158

13Aug12

0.0000

0.00%
0.00%
0.158

8Aug12

Actual

0.00%
0.00%
0.241

19Aug12

Planned

0.00%
0.00%
0.241

22Jul12

Remarks

0.00%
0.444

5Sep12

0.00%
0.00%

9Oct12
0.158

0.00%

BSV-3
3392-33-14-20-0004 Civil GA (BSV-3)

3392-33-14-40-0024 Pipe Supports - Sleepers (BSV-3)

3392-33-14-40-0025 Pipe Supports - T Posts (BSV-3)

3392-33-14-40-0040 Structural Calculation For Pipe Supports

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

23Jul12

P
F
F
A
P
F
F
A

8Aug12

26Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

20Sep12

0.00%
0.241

17Jul12

22Jul12

22Jul12

12Aug12

19Aug12

9Sep12

16Sep12

0.00%
0.00%

16Sep12
0.241

23Jul12

26Jul12

26Jul12

16Aug12

23Aug12

13Sep12

20Sep12

0.00%
0.00%

20Sep12
0.241

26Jul12

5Aug12

5Aug12

26Aug12

2Sep12

23Sep12

30Sep12

0.00%
0.00%

30Sep12
0.296

0.00%

ELEVATED TRANFORMER NEAR BSV-03 (OPTION 1)


3392-33-17-21-0001 Foundation Details of Transformer

3392-33-17-21-0002 Calculations For Foundation Details of Transformer

12Aug12

14Aug12

4Sep12

11Sep12

2Oct12

9Oct12

9Oct12

0.00%
0.235

15Aug12

19Aug12

21Aug12

11Sep12

18Sep12

9Oct12

16Oct12

0.00%
0.00%

16Oct12
0.342

0.00%
27.382

BUILDING SERVICES
CALCULATION / SCHEDULES / MTO
3392-32-34-17-0001 HVAC Load Calculation

3392-32-34-17-0002 SER-12 Building Extension HVAC MTO

3392-32-34-17-0003 SER-12 Building Extension HVAC Equipment Schedule

P
F
F
A
P
F
F
A
P
F
F
A

12Jun12

P
F
F
A

20May12

P
F
F
A
P
F
F
A

20Jun12

17Jun12

17Jun12

8Jul12

15Jul12

5Aug12

12Aug12

12Aug12

0.00%
0.158

18Jun12

21Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.070

18Jun12

21Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.175

0.00%

SPECIFICATIONS
3392-32-34-17-0004 HVAC Specification

20May12

19Jun12

8Jul12

15Jul12

5Aug12

12Aug12

12Aug12

0.00%
0.105
0.00%

TECHNICAL REQUISITIONS
3392-RQ-32-34-0001

MR for HVAC Equipments for SER-12 Building


Extension

3392-RQ-32-34-0002 MRs for BMS, Access Control System and CCTV

7Jun12

27Jun12

18Jul12

25Jul12

15Aug12

22Aug12

22Aug12

0.00%
0.053

21May12

7Jun12

7Jun12

28Jun12

5Jul12

26Jul12

2Aug12

0.00%
0.00%

2Aug12
0.053

0.00%

DRAWINGS
3392-32-34-20-0001 SER-12 Building Extension HVAC Layout

3392-32-34-20-0002

3392-32-34-20-0003

3392-32-34-20-0004

SER-12 Building Extension HVAC Miscellaneous


Details
SER-12 Building Extension HVAC Schematic and
Control Flow Diagram
SER-12 Building Extension Water Supply and
Drainage Layout

3392-32-34-20-0005 Plumbing Notes and Symbols

3392-32-34-20-0006 Miscellaneous Plumbing Details

P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A

18Jun12

21Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

16Aug12

0.00%
0.333

18Jun12

21Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.333

18Jun12

21Jun12

21Jun12

12Jul12

19Jul12

9Aug12

16Aug12

0.00%
0.00%

16Aug12
0.333

24Jun12

24Jun12

25Jun12

16Jul12

23Jul12

13Aug12

20Aug12

0.00%
0.00%

20Aug12
0.289

30Jul12

30Jul12

30Jul12

20Aug12

27Aug12

17Sep12

24Sep12

0.00%
0.00%

24Sep12
0.088

2Aug12

2Aug12

2Aug12

23Aug12

30Aug12

20Sep12

27Sep12

0.00%
0.00%

27Sep12
0.088

0.00%
2.078

CATHODIC PROTECTION
REPORTS
3392-32-64-81-0005 CP Design Report (including Calculations)

P
F
F
A

26Jul12

P
F
F
A

9Aug12

6Aug12

8Aug12

29Aug12

5Sep12

26Sep12

3Oct12

3Oct12

0.00%
0.474
0.00%

SPECIFICATIONS / SOW
3392-32-64-81-0001 CP Material Specification

12Aug12

13Aug12

3Sep12

10Sep12

1Oct12

8Oct12

8Oct12

0.00%
0.158
0.00%

Page 136 of 266

DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet

ENGG. CONSULTANT : PENSPEN International LTD.


Penspen Project No : 11440

DOCUMENTS CONTROL REGISTER

Cut off Date: 26-Feb-12

CLIENT

Start

Draft

Issued

DOC / DWG NO.

Date

Completion

for QP

Receiving

Review

Comments

DOC / DWG DESCRIPTION

3392-32-64-81-0002 CP Installation Specification

3392-32-64-81-0003 SOW for CP system

5.0%

5.0%

40.0%

P
F
F
A
P
F
F
A

16Aug12

19Aug12

20Aug12

P
F
F
A

14Aug12

P
F
F
A
P
F
F
A

19Aug12

Issued for
QP Approval

Issue as

Final

Receiving

AFC with

AFC Issue

Comments

Hold

65.0%

10Sep12

17Sep12

8Oct12

WTD
WTG

85.0%

95.0%

15Oct12

15Oct12

PRG

10Jul12

10Jul12

31Jul12

7Aug12

28Aug12

2Sep12

Remarks

Planned

Actual

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.000
0.00%

0.000
0.00%

0.00%
0.158

10Jul12

0.00%
0.00%

2Sep12
0.237

0.00%

DATA SHEETS
3392-32-64-81-0004 CP Material Data Sheet

16Aug12

16Aug12

6Sep12

13Sep12

4Oct12

11Oct12

11Oct12

0.00%
0.158
0.00%

DRAWINGS
3392-32-64-81-0008 CP Detail Drawings

3392-32-64-81-0009 CP Schematic Diagram

21Aug12

22Aug12

12Sep12

19Sep12

10Oct12

17Oct12

17Oct12

0.00%
0.298

23Aug12

27Aug12

29Aug12

19Sep12

26Sep12

17Oct12

24Oct12

0.00%
0.00%

24Oct12
0.395

0.00%
1.877

Page 137 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROCUREMENT STATUS REGISTER (PSR)
______________________________________

Page 138 of 266

CONTRACT NO. : GC 11106200

JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY

CLIENT :QATAR PETROLEUM

SUBJECT : MATERIALS PROCUREMENT STATUS REPORT

26-Feb-12

Description

% Weight
Q.ty

SNO

Val ue

WT% Overall
Value of
Procurement

37535313.00

80.92%

Progress Scale

Sec.

(As 100%
Phase)

1.0 LONG LEAD ITEMS

OVERALL PROCUREMENT PROGRESS


(LONG LEAD + BULK MATERIALS)

8,850,035.00

19.08%

% WT respect
to Overall

0.00%

0.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%

100.00%

0.00%
A

Page 139 of 266

% Variance
Respect to
Overall

0.00%

100%
A
P

46,385,348.00

% Phy

100%
A
P

2.0 OTHER ITEMS

% PROGRESS

0.00%

LONG LEAD - EQUIPMENT / MATERIALS PROCUREMENT STATUS REPORT


CONTRACT NO. : GC 11106200

ETROJE
As Of : 26-Feb-12
T

EPIC OF 16" JET A1 PIPELINE FROM QP REFINERY TO BSV-3


Description
Q.ty

SNO

Val ue

WT% Overall
Value of
Procurement

Progress Scale

WT%Long
Lead
Phase

Sec.

MR

RFQ to
Vendors

Purchase
Order

Issued
5%

Issued
10%

Order
15%

Vendor
Filled SPIR
Document
Approved
30%

Receipt
40%

FAT

Ex-works

Compl'n
60%

Delivery
70%

Material at site
Received
85%

QP
Inspected
90%

Spare
Parts
At Site

SPIR's

Completed (As 100%


100%
Phase)

1.0 LONG LEAD ITEMS

517,498

1.12%

1.38%

Pig Launcher at QP Refinery

26-Jul-12

02-Aug-12 23-Aug-12 06-Oct-12 05-Dec-12 09-May-13 24-May-13

08-Jul-13

15-Jul-13

15-Jul-13

29-Aug-13

1.76%

2.17%

EOT Crane

03-Aug-12 10-Aug-12 31-Aug-12 30-Sep-12 29-Nov-12 13-Apr-13

28-Apr-13

12-Jun-13 19-Jun-13 19-Jun-13 03-Aug-13

100,000

0.22%

0.27%

Isolation Joints

25-Jul-12

01-Aug-12 22-Aug-12 21-Sep-12 20-Nov-12 20-Feb-13 07-Mar-13

21-Apr-13

28-Apr-13

28-Apr-13

12-Jun-13

221,785

0.48%

0.59%

Jib Cranes

25-Jul-12

01-Aug-12 22-Aug-12 21-Sep-12 20-Nov-12 04-Apr-13

19-Apr-13

03-Jun-13 10-Jun-13 10-Jun-13

25-Jul-13

P
F
A

B PUMPS
10,150,000

21.88%

27.04%

Mainline Pumps

28-Jul-12

18-Aug-12 17-Sep-12 16-Nov-12 27-Jun-13

12-Jul-13

26-Aug-13 02-Sep-13 02-Sep-13 17-Oct-13

5,645,000

12.17%

15.04%

Booster Pumps

21-Jul-12

28-Jul-12

18-Aug-12 17-Sep-12 16-Nov-12 27-Jun-13

12-Jul-13

26-Aug-13 02-Sep-13 02-Sep-13 17-Oct-13

A
P
F
A

4,340,841
C1

9.36%

11.56%

Switchgear Panels

02-Aug-12 09-Aug-12 30-Aug-12 29-Sep-12 28-Nov-12 02-Apr-13

17-Apr-13

01-Jun-13 08-Jun-13 08-Jun-13

23-Jul-13

C2

0.24%

0.30%

04-Aug-12 11-Aug-12 01-Sep-12 01-Oct-12 30-Nov-12 04-Apr-13

19-Apr-13

03-Jun-13 10-Jun-13 10-Jun-13

25-Jul-13

C3

0.91%

1.13%

UPS System

08-Aug-12 15-Aug-12 05-Sep-12 05-Oct-12 04-Dec-12 08-May-13 23-May-13

07-Jul-13

14-Jul-13

14-Jul-13

28-Aug-13

D1

Control Valve & Auto


Recirculation Valve

P
F
A

977,651

2.11%

2.60%

28-Jul-12

04-Aug-12 25-Aug-12 24-Sep-12 23-Nov-12 22-May-13 06-Jun-13

21-Jul-13

28-Jul-13

28-Jul-13

11-Sep-13

D2

ESD Valve with All Accessories

0.55%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0.00%

0.00%

24-Jul-12

31-Jul-12

21-Aug-12 20-Sep-12 19-Nov-12 18-May-13 02-Jun-13

17-Jul-13

24-Jul-13

24-Jul-13

07-Sep-13

0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0.00%

0.00%

0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0.00%

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%
0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

Page 140 of 266

0.00%

0.00%

0.55%

Shipment
Type

0.00%

2.60%

0.44%

0%

11.56%

205,000

0.00%

1.13%

D VALVES

0%

0.30%

422,708

0.00%

11.56%

111,086

0%

12.99%

Distribution Boards and Local


Control Panels

0.00%

15.04%

C ELECTRICAL

0.00%

27.04%

Vendor
Name

0.00%

42.08%
21-Jul-12

PO #

0.00%

0.59%

F
A

B2

0.00%
0.00%

0.27%

F
A

B1

0.00%
0.00%

2.17%

F
A

A4

0.00%

1.38%

815,000

A3

0.00%

4.41%

A2

% Phy

% Equiv
% Variance
to Phase

100.00%
A
P
F
A

A MECHANICAL ITEMS

A1

% PROGRESS

% Weight

0.00%

0.00%

By Sea

0.00%

By Sea

Remarks

LONG LEAD - EQUIPMENT / MATERIALS PROCUREMENT STATUS REPORT


CONTRACT NO. : GC 11106200

ETROJE
As Of : 26-Feb-12
T

EPIC OF 16" JET A1 PIPELINE FROM QP REFINERY TO BSV-3


Description
Q.ty

SNO

Val ue

WT% Overall
Value of
Procurement

Progress Scale

170,000
D3

0.37%

WT%Long
Lead
Phase

0.45%

Isolation Valves at Refinery

Sec.

MR

RFQ to
Vendors

Purchase
Order

Issued
5%

Issued
10%

Order
15%

Vendor
Filled SPIR
Document
Approved
30%

Receipt
40%

FAT

Ex-works

Compl'n
60%

Delivery
70%

01-Aug-12 08-Aug-12 29-Aug-12 28-Sep-12 27-Nov-12 11-May-13 26-May-13

Material at site
Received
85%

QP
Inspected
90%

10-Jul-13

17-Jul-13

Spare
Parts
At Site
17-Jul-13

SPIR's

Completed (As 100%


100%
Phase)
31-Aug-13

0%

D4

4.24%

5.24%

MOV (Motor Operated Valves)

02-Aug-12 09-Aug-12 30-Aug-12 29-Sep-12 28-Nov-12 12-May-13 27-May-13

11-Jul-13

18-Jul-13

18-Jul-13

01-Sep-13

D5

2.20%

2.72%

All Other Misc. Types of Valves

11-Aug-12 18-Aug-12 08-Sep-12 08-Oct-12 07-Dec-12 11-May-13 26-May-13

10-Jul-13

17-Jul-13

17-Jul-13

31-Aug-13

A
P
F
A

E INSTRUMENTATION WORKS,DCS,ESD
AND F&G SYSTEMS

E1

Coriollis Flowmeter, Hand held


communicator etc.

1,155,406

2.49%

3.08%

10-Aug-12 17-Aug-12 07-Sep-12 07-Oct-12 06-Dec-12 05-May-13 20-May-13

04-Jul-13

11-Jul-13

11-Jul-13

25-Aug-13

E2

1.23%

Junction Boxes

02-Aug-12 09-Aug-12 30-Aug-12 29-Sep-12 28-Nov-12 12-Apr-13

27-Apr-13

11-Jun-13 18-Jun-13 18-Jun-13 02-Aug-13

E3

0.72%

0.88%

Fire and Smoke Detectors

25-Aug-12 01-Sep-12 22-Sep-12 22-Oct-12 21-Dec-12 25-Apr-13 10-May-13 24-Jun-13

01-Jul-13

01-Jul-13

15-Aug-13

E4

3.46%

4.27%

Instrument & Control Cables

21-Jul-12

28-Jul-12

18-Aug-12 17-Sep-12 16-Nov-12 10-Feb-13 25-Feb-13 11-Apr-13

18-Apr-13

18-Apr-13

02-Jun-13

E5

6,014,629

12.97%

16.02%

14-Aug-12 21-Aug-12 11-Sep-12 11-Oct-12 10-Dec-12 24-May-13 08-Jun-13

23-Jul-13

30-Jul-13

30-Jul-13

13-Sep-13

A
P
F
A

118,503
F1

0.26%

0.32%

Telecom and Telemetry


Equipments

02-Aug-12 09-Aug-12 30-Aug-12 29-Sep-12 28-Nov-12 12-May-13 27-May-13

11-Jul-13

18-Jul-13

18-Jul-13

01-Sep-13

P
F
A

I1

Leak Detection System

2.55%

3.16%

0%

0.00%

0.00%

0.00%

0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0.00%

0.00%

09-Jul-13

16-Jul-13

16-Jul-13

30-Aug-13

0.00%

0.00%

0%

0.00%

0%

0.00%

0.00%

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

0.00%

By Sea

By Sea

0.00%
0.00%

0.00%

0%

0.00%
0.00%

0%

Page 141 of 266

0.00%

0.00%

3.16%

Shipment
Type

0.00%

3.16%
10-Aug-12 17-Aug-12 07-Sep-12 07-Oct-12 06-Dec-12 10-May-13 25-May-13

Vendor
Name

0.00%

0.32%

1,185,032

0.00%

0.32%

I LEAK DETECTION SYSTEM

0%

16.02%

F TELECOM AND TELEMETRY EQUIPMENT

0.00%

4.27%

F
A

SCADA, DCS, ESD and F & G


System

0%

0.88%

1,603,703

0.00%

1.23%

331,809

0%

3.08%

1.00%

0.00%

25.49%

462,162

0%

2.72%

PO #

0.00%

5.24%

1,020,000

% Phy

% Equiv
% Variance
to Phase

0.45%

1,967,500

% PROGRESS

% Weight

0.00%

By Sea

Remarks

OTHER ITEMS PROCUREMENT STATUS REPORT


CONTRACT NO. : GC 11106200

ETROJET

EPIC OF 16" JET A1 PIPELINE FROM QP REFINERY TO BSV-3

As Of : 26-Feb-12
Description
Q.ty

Sl NO

Value

WT% Overall
Value of
Procurement

Progress Scale

WT% for
Other
Items

Sec.

RFQ to
Vendors

Purchase
Order

Issued
5%

Order
15%

Ex-works
50% OF Est
Qty
30%

90% OF Est
Qty
40%

Material at site
50% OF Est
Qty
50%

90% OF Est
Qty
80%

All Material
received and
PO Closed
100%

% Weight

% PROGRESS

(As 100%
Phase)

% Phy

% Equiv to
Phase

0.0%

0.00%

2.0 OTHER ITEMS

100.00%

2.1 MECHANICAL

0.0%

0.00%

0%

0.00%

56.36%

A
1 Lot

4,950,000.00

10.67%

55.93%

2.1.1 Pipes & Fittings

11-Aug-12

01-Sep-12

10-Nov-12

20-Dec-12

08-Feb-13

29-Apr-13

28-Jun-13

A
1 Lot

2.1.2

38,000.00

0.08%

0.43%

Bulk Items
Stud bolts, Nuts, Gaskets etc.,

21-Jul-12

11-Aug-12

20-Oct-12

29-Nov-12

18-Jan-13

08-Apr-13

07-Jun-13

2.2 ELECTRICAL

0.22%

1.13%

2.2.1 Local Control Panel

0.44%

2.30%

2.2.2 Lighting Fixtures & Lighting Poles

1.10%

5.78%

2.2.3 Electrical Cables

23-Aug-12

13-Sep-12

22-Nov-12

01-Jan-13

31-Jan-13

01-Apr-13

31-May-13

09-Sep-12

30-Sep-12

09-Dec-12

18-Jan-13

17-Feb-13

18-Apr-13

17-Jun-13

13-Sep-12

22-Nov-12

01-Jan-13

15-Feb-13

01-May-13

30-Jun-13

Temperature Elements,
2.3.2 Temperature Transmitters,
Thermowell

275,520.00

0.59%

3.11%

0.08%

0.40%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

24.50%

01-Aug-12

22-Aug-12

31-Oct-12

10-Dec-12

24-Jan-13

09-Apr-13

08-Jun-13

01-Aug-12

22-Aug-12

31-Oct-12

10-Dec-12

24-Jan-13
-

09-Apr-13

08-Jun-13

0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

0.40%
0%

Page 142 of 266

By Sea

0.00%

By Sea

0.00%

Local

0.00%

Terrestrial

0.00%

Terrestrial

0.00%

3.11%

34,958.00

0%

Item

0.00%

5.78%

Item

0.00%

2.30%

23-Aug-12

0.00%

0.00%

1.13%

Pressure Transmitters,
2.3.1 Differential Pressure
Transmitters, Pressure Gauges

0.00%

9.21%

2.3 INSTRUMENTATION

0%

0.00%

511,515.00

0.00%

0%

Item

0%

203,462.00

0.00%

0.00%

Item

0%

0%

100,379.00

0.00%

Item

0%

0.43%

Shipment
Type

0.00%

55.93%

10-Jun-10

Vendor
Name

0.00%

% Variance

PO #

0.00%

0.00%

Air Freight

0.00%

Air Freight

Remarks

OTHER ITEMS PROCUREMENT STATUS REPORT


CONTRACT NO. : GC 11106200

ETROJET

EPIC OF 16" JET A1 PIPELINE FROM QP REFINERY TO BSV-3

As Of : 26-Feb-12
Description
Sl NO

Q.ty

Value

Lot

1,858,213.00

WT% Overall
Value of
Procurement

WT% for
Other
Items

Sec.

4.01%

21.00%

Progress Scale

Instrument Cable Accessories,


Tubing fittings & Misc. Erection
2.3.3
Materials
(Gas / Flame / Heat / Smoke)

RFQ to
Vendors

Purchase
Order

Issued
5%

Order
15%

50% OF Est
Qty
30%

90% OF Est
Qty
40%

50% OF Est
Qty
50%

90% OF Est
Qty
80%

26-Jul-12

16-Aug-12

25-Oct-12

04-Dec-12

18-Jan-13

03-Apr-13

Ex-works

Material at site

All Material
received and
PO Closed
100%

% PROGRESS

(As 100%
Phase)

% Phy

% Equiv to
Phase

0%

0.00%

02-Jun-13
21.00%

G CORROSION MONITORING AND


INHIBITOR INJECTION FACILITIES

% Weight

0%

0.00%

0%

0.00%

0.86%

A
Item

76,000.00

0.16%

0.86%

Corrosion monitoring and


inhibitor injection facilities

18-Aug-12

08-Sep-12

17-Nov-12

27-Dec-12

10-Feb-13

26-Apr-13

25-Jun-13

H.1

200,497.00

0.43%

2.27%

Temporary Cathodic Protection

H.2

Permanent Cathodic Protection

1.30%

6.80%

0.00%
0.00%

0%

0.00%

9.06%

10-Aug-12

31-Aug-12

20-Sep-12

10-Oct-12

30-Oct-12

19-Nov-12

29-Nov-12

19-Sep-12

10-Oct-12

19-Dec-12

28-Jan-13

14-Mar-13
-

13-May-13

27-Jun-13

0.00%

0.00%

0%

0.00%

0%

0.00%

0%

0.00%

6.80%
0%

Page 143 of 266

Shipment
Type

By Sea

By Sea

0.00%

2.27%

601,491.00

0%

0.00%

Item

0.00%

0%

A
Item

0.00%

Vendor
Name

0.00%

0.86%

H CATHODIC PROTECTION SYSTEM

0.00%

% Variance

PO #

0.00%

0.00%

Terrestrial

0.00%

By Sea

Remarks

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
CONSTRUCTION PROGRESS
MEASUREMENT
______________________________________

Page 144 of 266

CONTRACT NO. : GC 11106200

JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY

February 26, 2012

CLIENT :QATAR PETROLEUM

SUBJECT : CONSTRUCTION PHASE PROGRESS MEASUREMENT

PREVIOUS WEEK

SER.

DESCRIPTION

THIS WEEK

UP TO DATE

MAN HOURS

REL. WT. %

PLANNED

ACTUAL

DEV.

PLANNED

ACTUAL

DEV.

PLANNED

ACTUAL

DEV.

16" - 36 KM MAIN PIPELINE

498424

47.36%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

ALL WORKS INSIDE QP


REFINERY

489518

46.51%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

ALL WORKS INSIDE BSV-3

56000

5.32%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

CLOSE OUT REPORT

8460

0.80%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

1052402

100.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF CONSTRUCTION
PHASE

Page 145 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

16"-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3


MAIN PIPELINE
STRAIGHT RUN ACTIVITIES
SEC (1) FROM KP (0) TO KP (3)
CPA1100 Survey and Stacking Works

2-Sep-12

15-Sep-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1110 Right Of Way

5-Sep-12

23-Sep-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1120 Trench Excavation

11-Sep-12

29-Sep-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

19-Sep-12

4-Oct-12

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

25-Sep-12

10-Oct-12

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1150 Welding Of Pipes

29-Sep-12

16-Oct-12

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1160 N.D.T & Welds Repair

4-Oct-12

22-Oct-12

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1170 FBE External Field Joint Coating

10-Oct-12

28-Oct-12

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1180 Pre-Padding

16-Oct-12

3-Nov-12

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1190 Lowering Of Pipeline

22-Oct-12

8-Nov-12

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1200 Tie-Ins Of Strings

28-Oct-12

14-Nov-12

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1210 Post Padding

3-Nov-12

20-Nov-12

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPA1220 Final Backfilling

8-Nov-12

27-Nov-12

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPA1140
Route
CPA1130

TOTAL OF SEC (1) FROM KP (0) TO KP (3)


SEC (2) FROM KP (3) TO KP (6)
Page 146 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

CPB1100 Survey and Stacking Works

16-Sep-12

27-Sep-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1110 Right Of Way

23-Sep-12

10-Oct-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1120 Trench Excavation

29-Sep-12

16-Oct-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

7-Oct-12

22-Oct-12

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

13-Oct-12

28-Oct-12

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1150 Welding Of Pipes

16-Oct-12

3-Nov-12

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1160 N.D.T & Welds Repair

22-Oct-12

8-Nov-12

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1170 FBE External Field Joint Coating

28-Oct-12

14-Nov-12

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1180 Pre-Padding

3-Nov-12

20-Nov-12

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1190 Lowering Of Pipeline

8-Nov-12

27-Nov-12

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1200 Tie-Ins Of Strings

14-Nov-12

3-Dec-12

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1210 Post Padding

20-Nov-12

9-Dec-12

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPB1220 Final Backfilling

27-Nov-12

15-Dec-12

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPB1140
Route
CPB1130

TOTAL OF SEC (2) FROM KP (3) TO KP (6)


SEC (3) FROM KP (6) TO KP (9)
CPC1100 Survey and Stacking Works

29-Sep-12

10-Oct-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1110 Right Of Way

10-Oct-12

28-Oct-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1120 Trench Excavation

16-Oct-12

3-Nov-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

24-Oct-12

8-Nov-12

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1130

Transportation Of Coated Pipes


To Site

Page 147 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

CPC1140

Stringing Of Pipes Along The


Route

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

30-Oct-12

14-Nov-12

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1150 Welding Of Pipes

3-Nov-12

20-Nov-12

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1160 N.D.T & Welds Repair

8-Nov-12

27-Nov-12

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1170 FBE External Field Joint Coating

14-Nov-12

3-Dec-12

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1180 Pre-Padding

20-Nov-12

9-Dec-12

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1190 Lowering Of Pipeline

27-Nov-12

15-Dec-12

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1200 Tie-Ins Of Strings

3-Dec-12

20-Dec-12

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1210 Post Padding

9-Dec-12

27-Dec-12

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPC1220 Final Backfilling

15-Dec-12

3-Jan-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

TOTAL OF SEC (3) FROM KP (6) TO KP (9)


SEC (4) FROM KP (9) TO KP (12)
CPD1100 Survey and Stacking Works

11-Oct-12

23-Oct-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1110 Right Of Way

28-Oct-12

14-Nov-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1120 Trench Excavation

3-Nov-12

20-Nov-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

11-Nov-12

27-Nov-12

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

17-Nov-12

3-Dec-12

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1150 Welding Of Pipes

20-Nov-12

9-Dec-12

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1160 N.D.T & Welds Repair

27-Nov-12

15-Dec-12

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

3-Dec-12

20-Dec-12

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPD1140
Route
CPD1130

CPD1170 FBE External Field Joint Coating

Page 148 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

CPD1180 Pre-Padding

9-Dec-12

27-Dec-12

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1190 Lowering Of Pipeline

15-Dec-12

3-Jan-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1200 Tie-Ins Of Strings

20-Dec-12

9-Jan-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1210 Post Padding

27-Dec-12

15-Jan-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPD1220 Final Backfilling

3-Jan-13

21-Jan-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

TOTAL OF SEC (4) FROM KP (9) TO KP (12)


SEC (5) FROM KP (12) TO KP (15)
CPE1100 Survey and Stacking Works

24-Oct-12

5-Nov-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1110 Right Of Way

14-Nov-12

3-Dec-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1120 Trench Excavation

20-Nov-12

9-Dec-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

29-Nov-12

15-Dec-12

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

5-Dec-12

20-Dec-12

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1150 Welding Of Pipes

9-Dec-12

27-Dec-12

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1160 N.D.T & Welds Repair

15-Dec-12

3-Jan-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1170 FBE External Field Joint Coating

20-Dec-12

9-Jan-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1180 Pre-Padding

27-Dec-12

15-Jan-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1190 Lowering Of Pipeline

3-Jan-13

21-Jan-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1200 Tie-Ins Of Strings

9-Jan-13

27-Jan-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPE1210 Post Padding

15-Jan-13

2-Feb-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPE1140
Route
CPE1130

Page 149 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

CPE1220 Final Backfilling

EARLY START EARLY FINISH

21-Jan-13

7-Feb-13

DUR.

QUAN.

UNIT

15

3000

M/L

TOTAL OF SEC (5) FROM KP (12) TO KP (15)

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

480

1.8%

26520

100.0%

0.00%

0.00%

DEV %

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (6) FROM KP (15) TO KP (18)


CPF1100 Survey and Stacking Works

6-Nov-12

18-Nov-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1110 Right Of Way

3-Dec-12

20-Dec-12

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1120 Trench Excavation

9-Dec-12

27-Dec-12

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

17-Dec-12

3-Jan-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

23-Dec-12

9-Jan-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1150 Welding Of Pipes

27-Dec-12

15-Jan-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1160 N.D.T & Welds Repair

3-Jan-13

21-Jan-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1170 FBE External Field Joint Coating

9-Jan-13

27-Jan-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1180 Pre-Padding

15-Jan-13

2-Feb-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1190 Lowering Of Pipeline

21-Jan-13

7-Feb-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1200 Tie-Ins Of Strings

27-Jan-13

13-Feb-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1210 Post Padding

2-Feb-13

19-Feb-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPF1220 Final Backfilling

7-Feb-13

25-Feb-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

480

1.8%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPF1140
Route
CPF1130

TOTAL OF SEC (6) FROM KP (15) TO KP (18)


SEC (7) FROM KP (18) TO KP (21)
CPG1100 Survey and Stacking Works

19-Nov-12

2-Dec-12

10

3000

M/L
Page 150 of 266

0.00%

0.00%

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

CPG1110 Right Of Way

20-Dec-12

9-Jan-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1120 Trench Excavation

27-Dec-12

15-Jan-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Jan-13

21-Jan-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

12-Jan-13

27-Jan-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1150 Welding Of Pipes

15-Jan-13

2-Feb-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1160 N.D.T & Welds Repair

21-Jan-13

7-Feb-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1170 FBE External Field Joint Coating

27-Jan-13

13-Feb-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1180 Pre-Padding

2-Feb-13

19-Feb-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1190 Lowering Of Pipeline

7-Feb-13

25-Feb-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1200 Tie-Ins Of Strings

13-Feb-13

3-Mar-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1210 Post Padding

19-Feb-13

9-Mar-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPG1220 Final Backfilling

25-Feb-13

14-Mar-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPG1140
Route
CPG1130

TOTAL OF SEC (7) FROM KP (18) TO KP (21)


SEC (8) FROM KP (21) TO KP (24)
CPH1100 Survey and Stacking Works

3-Dec-12

15-Dec-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1110 Right Of Way

9-Jan-13

27-Jan-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1120 Trench Excavation

15-Jan-13

2-Feb-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

23-Jan-13

7-Feb-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

29-Jan-13

13-Feb-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPH1140
Route
CPH1130

Page 151 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

CPH1150 Welding Of Pipes

2-Feb-13

19-Feb-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1160 N.D.T & Welds Repair

7-Feb-13

25-Feb-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1170 FBE External Field Joint Coating

13-Feb-13

3-Mar-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1180 Pre-Padding

19-Feb-13

9-Mar-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1190 Lowering Of Pipeline

25-Feb-13

14-Mar-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1200 Tie-Ins Of Strings

3-Mar-13

20-Mar-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1210 Post Padding

9-Mar-13

26-Mar-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPH1220 Final Backfilling

14-Mar-13

1-Apr-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

TOTAL OF SEC (8) FROM KP (21) TO KP (24)


SEC (9) FROM KP (24) TO KP (27)
CPI1100 Survey and Stacking Works

16-Dec-12

29-Dec-12

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1110 Right Of Way

27-Jan-13

13-Feb-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1120 Trench Excavation

2-Feb-13

19-Feb-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

10-Feb-13

25-Feb-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

16-Feb-13

3-Mar-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1150 Welding Of Pipes

19-Feb-13

9-Mar-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1160 N.D.T & Welds Repair

25-Feb-13

14-Mar-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1170 FBE External Field Joint Coating

3-Mar-13

20-Mar-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1180 Pre-Padding

9-Mar-13

26-Mar-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPI1140
Route
CPI1130

Page 152 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

CPI1190 Lowering Of Pipeline

14-Mar-13

1-Apr-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1200 Tie-Ins Of Strings

20-Mar-13

7-Apr-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPI1210 Post Padding

26-Mar-13

13-Apr-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

1-Apr-13

18-Apr-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

CPI1220 Final Backfilling

TOTAL OF SEC (9) FROM KP (24) TO KP (27)


SEC (10) FROM KP (27) TO KP (30)
CPJ1100 Survey and Stacking Works

30-Dec-12

12-Jan-13

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1110 Right Of Way

13-Feb-13

3-Mar-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1120 Trench Excavation

19-Feb-13

9-Mar-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

27-Feb-13

14-Mar-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

5-Mar-13

20-Mar-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1150 Welding Of Pipes

9-Mar-13

26-Mar-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1160 N.D.T & Welds Repair

14-Mar-13

1-Apr-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1170 FBE External Field Joint Coating

20-Mar-13

7-Apr-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1180 Pre-Padding

26-Mar-13

13-Apr-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1190 Lowering Of Pipeline

1-Apr-13

18-Apr-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1200 Tie-Ins Of Strings

7-Apr-13

24-Apr-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1210 Post Padding

13-Apr-13

30-Apr-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPJ1220 Final Backfilling

18-Apr-13

6-May-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPJ1140
Route
CPJ1130

Page 153 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

TOTAL OF SEC (10) FROM KP (27) TO KP (30)

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

26520

100.0%

DEV %

0.00%

0.00%

0.00%

SEC (11) FROM KP (30) TO KP (33)


CPK1100 Survey and Stacking Works

13-Jan-13

24-Jan-13

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1110 Right Of Way

3-Mar-13

20-Mar-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1120 Trench Excavation

9-Mar-13

26-Mar-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

14-Mar-13

30-Mar-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

20-Mar-13

4-Apr-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

26-Mar-13

13-Apr-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1160 N.D.T & Welds Repair

1-Apr-13

18-Apr-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1170 FBE External Field Joint Coating

7-Apr-13

24-Apr-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1180 Pre-Padding

13-Apr-13

30-Apr-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1190 Lowering Of Pipeline

18-Apr-13

6-May-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1200 Tie-Ins Of Strings

24-Apr-13

12-May-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1210 Post Padding

30-Apr-13

18-May-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPK1220 Final Backfilling

6-May-13

23-May-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPK1140
Route
CPK1130

CPK1150 Welding Of Pipes

TOTAL OF SEC (11) FROM KP (30) TO KP (33)


SEC (12) FROM KP (33) TO KP (36)
CPL1100 Survey and Stacking Works

26-Jan-13

6-Feb-13

10

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1110 Right Of Way

20-Mar-13

7-Apr-13

15

3000

M/L

600

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 154 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

CPL1120 Trench Excavation

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

26-Mar-13

13-Apr-13

15

3000

M/L

3240

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

31-Mar-13

15-Apr-13

13

3000

M/L

1920

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Apr-13

21-Apr-13

13

3000

M/L

840

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1150 Welding Of Pipes

13-Apr-13

30-Apr-13

15

250

Each

7800

29.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1160 N.D.T & Welds Repair

18-Apr-13

6-May-13

15

250

Each

2040

7.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1170 FBE External Field Joint Coating

24-Apr-13

12-May-13

15

250

Each

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1180 Pre-Padding

30-Apr-13

18-May-13

15

3000

M/L

1680

6.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1190 Lowering Of Pipeline

6-May-13

23-May-13

15

3000

M/L

2520

9.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1200 Tie-Ins Of Strings

12-May-13

30-May-13

15

100

1800

6.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1210 Post Padding

18-May-13

5-Jun-13

15

3000

M/L

1320

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPL1220 Final Backfilling

23-May-13

11-Jun-13

15

3000

M/L

480

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

26520

100.0%

0.00%

0.00%

0.00%

Transportation Of Coated Pipes


To Site
Stringing Of Pipes Along The
CPL1140
Route
CPL1130

TOTAL OF SEC (12) FROM KP (33) TO KP (36)

( SUMMARY OF ALL STRAIGHT RUN SECTIONS )


SER.

ITEM

M/H

WEIGHT%

PLAN

ACTUAL WT. PL % WT. ACT%

DEV

SEC (1) FROM KP (0) TO KP (3)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (2) FROM KP (3) TO KP (6)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (3) FROM KP (6) TO KP (9)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (4) FROM KP (9) TO KP (12)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (5) FROM KP (12) TO KP (15)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 155 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

SEC (6) FROM KP (15) TO KP (18)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (7) FROM KP (18) TO KP (21)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (8) FROM KP (21) TO KP (24)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

SEC (9) FROM KP (24) TO KP (27)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

10

SEC (10) FROM KP (27) TO KP (30)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

11

SEC (11) FROM KP (30) TO KP (33)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

12

SEC (12) FROM KP (33) TO KP (36)

26520

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

318240

100%

0.00%

0.00%

0.00%

42000

100.0%

0.00%

0.00%

0.00%

42000

100.0%

0.00%

0.00%

0.00%

TOTAL OF ALL STRAIGHT RUN SECTIONS


ALL TYPES CROSSINGS
OPEN CUT CROSSINGS (NO. OFF 84)
CPCR100 Open Cut Crossings

15-Nov-12

30-May-13

164

84

Each

TOTAL OF OPEN CUT CROSSINGS

0.00%

0.00%

HDD CROSSINGS (NO. OFF 3)


CPCR1110 HDD Crossing No. (1)

20-Dec-12

14-Feb-13

46

Each

22080

33.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCR1120 HDD Crossing No. (2)

18-Feb-13

13-Apr-13

46

Each

22080

33.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCR1130 HDD Crossing No. (3)

16-Apr-13

10-Jun-13

46

Each

22080

33.3%

0.00%

0.00%

0.00%

0.00%

0.00%

66240

100.0%

0.00%

0.00%

0.00%

TOTAL OF HDD CROSSINGS


CATHODIC PROTECTION SYSTEM
TEMPORARY CATHODIC PROTECTION
Page 156 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

CPCT1100

Cables To Be Welded By
Thermite

CPCT1110 Anodes For Temperory CP

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

29-Oct-12

1-Jun-13

180

100

7200

50.0%

0.00%

0.00%

0.00%

0.00%

0.00%

29-Nov-12

1-Jul-13

180

100

7200

50.0%

0.00%

0.00%

0.00%

0.00%

0.00%

14400

100.0%

0.00%

0.00%

0.00%

TOTAL OF TEMPORARY CATHODIC PROTECTION


PERMANENT CATHODIC PROTECTION
CPCP1100 Test Post Distribution & Erection

2-Jul-13

27-Jul-13

20

100

800

12.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCP1110 Deep Well (25 M)

9-Jul-13

1-Aug-13

20

100

2240

33.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCP1120 Anode For Permanent CP

15-Jul-13

7-Aug-13

20

100

800

12.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCP1130 Rectifier To Be Installed

7-Aug-13

19-Aug-13

10

100

560

8.4%

0.00%

0.00%

0.00%

0.00%

0.00%

19-Aug-13

12-Sep-13

20

100

1120

16.9%

0.00%

0.00%

0.00%

0.00%

0.00%

12-Sep-13

6-Oct-13

20

100

1120

16.9%

0.00%

0.00%

0.00%

0.00%

0.00%

6640

100.0%

0.00%

0.00%

0.00%

Junction Box & Cables To Be


Connected
CP System to Be Checked &
CPCP1150
Tested
CPCP1140

TOTAL OF PERMANENT CATHODIC PROTECTION


ANCHOR BLOCKS
ANCHOR BLOCK AT QP REFINERY
CPAB1100 Anchor Flange To Be Welded
Excavation For Anchor Block At
QP Refinery
PC For Anchor Block At QP
CPAB1120
Refinery
RC For Anchor Block At QP
CPAB1130
Refinery
Backfilling For Anchor Block At
CPAB1140
QP Refinery
CPAB1110

23-May-13

26-May-13

100

288

6.1%

0.00%

0.00%

0.00%

0.00%

0.00%

28-May-13

3-Jun-13

100

650

13.7%

0.00%

0.00%

0.00%

0.00%

0.00%

3-Jun-13

8-Jun-13

100

800

16.8%

0.00%

0.00%

0.00%

0.00%

0.00%

8-Jun-13

17-Jun-13

100

2960

62.3%

0.00%

0.00%

0.00%

0.00%

0.00%

17-Jun-13

19-Jun-13

100

54

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

4752

100.0%

0.00%

0.00%

0.00%

TOTAL OF ANCHOR BLOCK AT QP REFINERY


Page 157 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

DEV %

ANCHOR BLOCK AT BSV-3


CPAB2100 Anchor Flange To Be Welded

8-Jun-13

10-Jun-13

100

288

6.1%

0.00%

0.00%

0.00%

0.00%

0.00%

11-Jun-13

17-Jun-13

100

650

13.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CPAB2120 PC For Anchor Block At BSV-3

17-Jun-13

22-Jun-13

100

800

16.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPAB2130 RC For Anchor Block At BSV-3

22-Jun-13

1-Jul-13

100

2960

62.3%

0.00%

0.00%

0.00%

0.00%

0.00%

1-Jul-13

3-Jul-13

100

54

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

4752

100.0%

0.00%

0.00%

0.00%

CPAB2110

CPAB2140

Excavation For Anchor Block At


BSV-3

Backfilling For Anchor Block At


BSV-3

TOTAL OF ANCHOR BLOCK AT BSV-3


HYDRAULIC TEST
CPHT1100 Pipeline Cleaning & Gauging

18-Jun-13

6-Jul-13

14

36000

M/L

3360

14.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CPHT1110 Pipeline Water Filling

6-Aug-13

29-Sep-13

45

36000

M/L

12960

54.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPHT1120 Pipeline Pressurizing

29-Sep-13

10-Oct-13

10

36000

M/L

4080

17.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CPHT1130 Pipeline Dewatering & Flushing

12-Oct-13

29-Oct-13

15

36000

M/L

3240

13.7%

0.00%

0.00%

0.00%

0.00%

0.00%

23640

100.0%

0.00%

0.00%

0.00%

TOTAL OF HYDRAULIC TEST


COMMON ACTIVITIES
CPCA1100
Pipeline Post Markers

11-Jun-13

17-Jul-13

30

100

1920

10.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CPCA1110
ROW Re-Instatement

4-Aug-13

14-Oct-13

60

36000

M/L

7200

40.5%

0.00%

0.00%

0.00%

0.00%

0.00%

30

100

8640

48.6%

0.00%

0.00%

0.00%

0.00%

0.00%

17760

100.0%

0.00%

0.00%

0.00%

Punch List & Achieve


CPCA1120
21-Oct-13
25-Nov-13
Mechanical Completion For PL
and All Facilities
TOTAL OF COMMON ACTIVITIES

( SUMMARY OF THE MAIN PIPELINE )


Page 158 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : MAIN P/L CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:

26-Feb-12

ID

DESCRIPTION

SER.

ITEM

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL% WT. PL % WT. ACT%

M/H

WEIGHT%

PLAN

ACTUAL WT. PL % WT. ACT%

DEV %

DEV

TOTAL OF ALL STRAIGHT RUN SECTIONS

318240

63.85%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF OPEN CUT CROSSINGS

42000

8.43%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF HDD CROSSINGS

66240

13.29%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF TEMPORARY CATHODIC PROTECTION

14400

2.89%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF PERMANENT CATHODIC PROTECTION

6640

1.33%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF ANCHOR BLOCK AT QP REFINERY

4752

0.95%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OFANCHOR BLOCK AT BSV-3

4752

0.95%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF HYDRAULIC TEST

23640

4.74%

0.00%

0.00%

0.00%

0.00%

0.00%

TOTAL OF COMMON ACTIVITIES

17760

3.56%

0.00%

0.00%

0.00%

0.00%

0.00%

498424

100.00%

0.00%

0.00%

0.00%

TOTAL OF THE MAIN PIPELINE

Page 159 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

QP REFINERY
CIVIL WORKS
NO. OFF (7) CULVERTS
CULVERT NO. (1)
CRCU1100

Excavation For Culvert No. (1)

5-Sep-12

11-Sep-12

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1110

PC For Culvert No. (1)

11-Sep-12

20-Sep-12

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1120

RC For Culvert No. (1)

20-Sep-12

9-Oct-12

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1130

Backfilling For Culvert No. (1)

9-Oct-12

21-Oct-12

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (2)


CRCU1200

Excavation For Culvert No. (2)

3-Oct-12

9-Oct-12

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1210

PC For Culvert No. (2)

9-Oct-12

18-Oct-12

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1220

RC For Culvert No. (2)

18-Oct-12

6-Nov-12

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1230

Backfilling For Culvert No. (2)

6-Nov-12

18-Nov-12

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (3)


CRCU1300

Excavation For Culvert No. (3)

31-Oct-12

6-Nov-12

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1310

PC For Culvert No. (3)

6-Nov-12

15-Nov-12

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1320

RC For Culvert No. (3)

15-Nov-12

5-Dec-12

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1330

Backfilling For Culvert No. (3)

5-Dec-12

17-Dec-12

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (4)


Page 160 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

CRCU1400

Excavation For Culvert No. (4)

29-Nov-12

5-Dec-12

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1410

PC For Culvert No. (4)

5-Dec-12

15-Dec-12

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1420

RC For Culvert No. (4)

15-Dec-12

5-Jan-13

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1430

Backfilling For Culvert No. (4)

5-Jan-13

16-Jan-13

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (5)


CRCU1500

Excavation For Culvert No. (5)

29-Dec-12

5-Jan-13

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1510

PC For Culvert No. (5)

5-Jan-13

14-Jan-13

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1520

RC For Culvert No. (5)

14-Jan-13

2-Feb-13

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1530

Backfilling For Culvert No. (5)

2-Feb-13

13-Feb-13

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (6)


CRCU1600

Excavation For Culvert No. (6)

27-Jan-13

2-Feb-13

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1610

PC For Culvert No. (6)

2-Feb-13

11-Feb-13

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1620

RC For Culvert No. (6)

11-Feb-13

2-Mar-13

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1630

Backfilling For Culvert No. (6)

2-Mar-13

13-Mar-13

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CULVERT NO. (7)


CRCU1700

Excavation For Culvert No. (7)

24-Feb-13

2-Mar-13

100

650

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1710

PC For Culvert No. (7)

2-Mar-13

11-Mar-13

100

1600

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1720

RC For Culvert No. (7)

11-Mar-13

30-Mar-13

16

100

5920

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCU1730

Backfilling & Re-Instatement


For Culvert No. (7)

30-Mar-13

10-Apr-13

10

100

400

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 161 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

TOTAL OF (7) CULVERTS

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

59990

100.0%

WT. PL % WT. ACT%

DEV %

0.00%

0.00%

0.00%

NO. OFF (220) SLEEPERS


CRCS1100

Pre-Cast (220) Sleepers

6-Nov-12

5-Feb-13

75

100

15750

65.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCS1110

Erection Of (220) Sleepers

31-Dec-12

30-Mar-13

75

100

8250

34.4%

0.00%

0.00%

0.00%

0.00%

0.00%

24000

100.0%

0.00%

0.00%

0.00%

TOTAL OF (220) SLEEPERS


SER12 EXTENSION
CRCE1100

Demolition & Excavation

13-Feb-13

2-Mar-13

14

100

1120

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1110

P.C (Foundation)

2-Mar-13

7-Mar-13

100

1200

3.3%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1120

R.C (Foundation)

7-Mar-13

26-Mar-13

16

100

2800

7.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1130

Insulation (Foundation)

26-Mar-13

31-Mar-13

100

720

2.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1140

BackFilling (Foundation)

1-Apr-13

4-Apr-13

100

280

0.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1150

R.C (Columns)

4-Apr-13

14-Apr-13

100

2160

5.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1160

R.C (Slab& Beams)

14-Apr-13

16-May-13

28

100

4480

12.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1170

External Finishing

25-May-13

5-Aug-13

60

100

12000

32.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCE1180

Internal Finishing

8-Jun-13

18-Aug-13

60

100

12000

32.6%

0.00%

0.00%

0.00%

0.00%

0.00%

36760

100.0%

0.00%

0.00%

0.00%

TOTAL OF SER12 EXTENSION


PUMP HOUSE
PUMP FOUNDATIONS
MAIN PUMP NO. (1)
Page 162 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

CRCP1100

Excavation For Main Pump


No. (1)

2-Mar-13

7-Mar-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1110

PC For Main Pump No. (1)

7-Mar-13

13-Mar-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1120

RC For Main Pump No. (1)

13-Mar-13

25-Mar-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1130

Backfilling For Main Pump


No. (1)

25-Mar-13

27-Mar-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

MAIN PUMP NO. (2)


CRCP1200

Excavation For Main Pump


No. (2)

13-Mar-13

19-Mar-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1210

PC For Main Pump No. (2)

19-Mar-13

25-Mar-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1220

RC For Main Pump No. (2)

25-Mar-13

6-Apr-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1230

Backfilling For Main Pump


No. (2)

6-Apr-13

8-Apr-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

MAIN PUMP NO. (3)


CRCP1300

Excavation For Main Pump


No. (3)

25-Mar-13

31-Mar-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1310

PC For Main Pump No. (3)

31-Mar-13

6-Apr-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1320

RC For Main Pump No. (3)

6-Apr-13

17-Apr-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1330

Backfilling For Main Pump


No. (3)

17-Apr-13

20-Apr-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

BOOSTER PUMP NO. (1)


CRCP1400

Excavation For Booster Pump


No. (1)

6-Apr-13

11-Apr-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1410

PC For Booster Pump No. (1)

11-Apr-13

17-Apr-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1420

RC For Booster Pump No. (1)

17-Apr-13

29-Apr-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1430

Backfilling For Booster Pump


No. (1)

29-Apr-13

1-May-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 163 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

BOOSTER PUMP NO. (2)


CRCP1500

Excavation For Booster Pump


No. (2)

17-Apr-13

23-Apr-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1510

PC For Booster Pump No. (2)

23-Apr-13

29-Apr-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1520

RC For Booster Pump No. (2)

29-Apr-13

11-May-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1530

Backfilling For Booster Pump


No. (2)

11-May-13

13-May-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

BOOSTER PUMP NO. (3)


CRCP1600

Excavation For Booster Pump


No. (3)

29-Apr-13

5-May-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1610

PC For Booster Pump No. (3)

5-May-13

11-May-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1620

RC For Booster Pump No. (3)

11-May-13

22-May-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1630

Backfilling For Booster Pump


No. (3)

22-May-13

25-May-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

E&I DUCT BANK


CRCP1700

Excavation For E&I Duct Bank

22-May-13

29-May-13

100

650

0.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1710

PC For E&I Duct Bank

29-May-13

4-Jun-13

100

1130

1.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1720

RC For E&I Duct Bank

4-Jun-13

16-Jun-13

10

100

3600

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCP1730

Backfilling For E&I Duct Bank

16-Jun-13

18-Jun-13

100

200

0.2%

0.00%

0.00%

0.00%

0.00%

0.00%

11-Apr-13

22-Jun-13

60

100

19680

19.8%

0.00%

0.00%

0.00%

0.00%

0.00%

22-May-13

4-Jun-13

10

100

1300

1.3%

0.00%

0.00%

0.00%

0.00%

0.00%

4-Jun-13

16-Jun-13

10

100

2260

2.3%

0.00%

0.00%

0.00%

0.00%

0.00%

THE PUMP SHED


CRCD1100
CRCD1110
CRCD1120

Steel Structure Fabrication


For The Pump Shed
Excavation For For The Pump
Shed
PC For For The Pump Shed

Page 164 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

CRCD1130

RC For For The Pump Shed

16-Jun-13

10-Jul-13

20

100

7200

7.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCD1140

Backfilling For The Pump Shed

10-Jul-13

15-Jul-13

100

400

0.4%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Jul-13

19-Aug-13

30

100

9840

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

19-Aug-13

7-Sep-13

15

100

4920

4.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCD1150
CRCD1160

Steel Structure Erection For


The Pump Shed
Corrugated Sheets Cladding
For The Pump Shed

CRCD1170

Paving For The Pump Shed

7-Sep-13

24-Sep-13

15

100

4950

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCD1180

Insulation & Fireproofing

24-Sep-13

29-Oct-13

30

100

9900

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

99510

100.0%

0.00%

0.00%

0.00%

TOTAL OF PUMP HOUSE


LAUNCHER STATION
CRCL1100

Excavation For Launcher


Station

22-May-13

30-May-13

100

780

5.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCL1110

PC For Launcher Station

30-May-13

11-Jun-13

10

100

2000

13.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCL1120

RC For Launcher Station

18-Jun-13

10-Jul-13

18

100

6660

44.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCL1130

Backfilling & Re-Instatement


For Launcher Station

10-Jul-13

17-Jul-13

100

270

1.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCL1140

Fence For Launcher Station

17-Jul-13

10-Aug-13

20

100

4000

26.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCL1150

Paving For Launcher Station

10-Aug-13

27-Aug-13

15

100

1152

7.8%

0.00%

0.00%

0.00%

0.00%

0.00%

14862

100.0%

0.00%

0.00%

0.00%

TOTAL OF LAUNCHER STATION


ROADS
CRCR1100

Roads For Launcher Area

15-Aug-13

15-Sep-13

25

100

4320

55.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCR1110

Roads For Pump Area

15-Sep-13

26-Sep-13

10

100

1728

22.2%

0.00%

0.00%

0.00%

0.00%

0.00%

CRCR1120

Roads For SER 12

26-Sep-13

8-Oct-13

10

100

1728

22.2%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 165 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

TOTAL OF THE ROADS

Q.DONE

M/H

7776

WEIGHT% PLANNED% ACTUAL%

207.8%

WT. PL % WT. ACT%

0.00%

0.00%

DEV %

0.00%

( SUMMARY OF CIVIL WORKS INSIDE QP REFINERY)


SER.

ITEM

M/H

WEIGHT%

PLAN

ACTUAL WT. PL % WT. ACT%

DEV

NO. 0FF (7) CULVERTS

59990

24.7%

0.00%

0.00%

0.00%

0.00%

0.00%

NO. 0FF (220) SLEEPERS

24000

9.9%

0.00%

0.00%

0.00%

0.00%

0.00%

SER12 EXTENSION

36760

15.1%

0.00%

0.00%

0.00%

0.00%

0.00%

PUMP HOUSE

99510

41.0%

0.00%

0.00%

0.00%

0.00%

0.00%

LAUNCHER STATION

14862

6.1%

0.00%

0.00%

0.00%

0.00%

0.00%

THE ROADS

7776

3.2%

0.00%

0.00%

0.00%

0.00%

0.00%

242898

100%

0.00%

0.00%

0.00%

TOTAL OF THE CIVIL WORKS INSIDE QP REFINERY


MECHANICAL WORKS
GENERAL
CRMG1100
CRMG1110

A/G Delivery Pipeline From


The Pumps To The Launcher
A/G Suction Pipeline From
The Header To The Pumps

30-Apr-13

5-Jun-13

30

100

17700

76.1%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Jun-13

18-Jun-13

10

100

5545

23.9%

0.00%

0.00%

0.00%

0.00%

0.00%

23245

100.0%

0.00%

0.00%

0.00%

TOTAL OF MECHANICAL WORKS FOR PUMP HOUSE


PUMP HOUSE
CRMP1100

Piping Fabrication

30-Apr-13

11-Jul-13

60

100

49224

40.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CRMP1110

Sand Blasting & Panting

22-May-13

20-Jul-13

48

100

11040

9.1%

0.00%

0.00%

0.00%

0.00%

0.00%

CRMP1120

Piping & Pumps Erection

28-Jul-13

7-Oct-13

60

100

47327

39.0%

0.00%

0.00%

0.00%

0.00%

0.00%

Page 166 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

CRMP1130

Loops to be Water Filled

7-Oct-13

24-Oct-13

15

100

4320

3.6%

0.00%

0.00%

0.00%

0.00%

0.00%

CRMP1140

Loops to be Pressurized

13-Oct-13

30-Oct-13

15

100

6120

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CRMP1150

Loops to be Dewatered &


Flushed

19-Oct-13

5-Nov-13

15

100

3240

2.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRMP1160

Tie in at Refinary

23-Sep-13

7-Oct-13

12

100

180

0.1%

0.00%

0.00%

0.00%

0.00%

0.00%

121451

100.0%

0.00%

0.00%

0.00%

TOTAL OF MECHANICAL WORKS FOR PUMP HOUSE


LAUNCHER STATION
CRM1160

Piping Fabrication

17-Jul-13

4-Aug-13

15

100

8739

36.9%

0.00%

0.00%

0.00%

0.00%

0.00%

CRM1170

Sand Blasting & Panting

25-Jul-13

12-Aug-13

15

100

3545

15.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CRM1180

Launcher & Piping Erection

6-Aug-13

24-Aug-13

15

100

11400

48.1%

0.00%

0.00%

0.00%

0.00%

0.00%

23684

100.0%

0.00%

0.00%

0.00%

TOTAL OF MECHANICAL WORKS FOR THE LAUNCHER STATION

( SUMMARY OF MECHANICAL WORKS INSIDE QP REFINERY )


SER.

ITEM

M/H

WEIGHT%

PLAN

ACTUAL WT. PL % WT. ACT%

DEV

GENERAL

23245

13.8%

0.00%

0.00%

0.00%

0.00%

0.00%

PUMP HOUSE

121451

72.1%

0.00%

0.00%

0.00%

0.00%

0.00%

LAUNCHER STATION

23684

14.1%

0.00%

0.00%

0.00%

0.00%

0.00%

168380

100%

0.00%

0.00%

0.00%

TOTAL OF THE MECHANICAL WORKS


E&I WORKS
ELECTRICAL WORKS
SUB-STATION 6003
Page 167 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

CRES1100
CRES1110
CRES1120

DESCRIPTION

Modification Of Existing 11
KV Switchgear
Modification Of Existing 3.3
KV Switchgear
Modification Of Existing 415 V
Switchgear

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

10-Jun-13

16-Jul-13

30

100

6300

14.9%

0.00%

0.00%

0.00%

0.00%

0.00%

22-Jun-13

28-Jul-13

30

100

6300

14.9%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Jul-13

19-Aug-13

30

100

6300

14.9%

0.00%

0.00%

0.00%

0.00%

0.00%

EXTENSION OF SER-12
CREE1100

Lighting Fixtures, Sockets For


Rooms

18-Aug-13

25-Aug-13

100

1020

2.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CREE1110

Low Voltage Cables

24-Aug-13

31-Aug-13

100

1020

2.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CREE1130

UPS System 110 V, 1 ph, 7


KVA

27-Aug-13

4-Sep-13

100

1020

2.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CREE1120

Termination

4-Sep-13

11-Sep-13

100

1020

2.4%

0.00%

0.00%

0.00%

0.00%

0.00%

CREP1100

Lighting System For Pump


Area

19-Sep-13

29-Sep-13

100

1680

4.0%

0.00%

0.00%

0.00%

0.00%

0.00%

CREP1110

Power Socket For Pump Area

25-Sep-13

5-Oct-13

100

1680

4.0%

0.00%

0.00%

0.00%

0.00%

0.00%

29-Sep-13

8-Oct-13

100

1680

4.0%

0.00%

0.00%

0.00%

0.00%

0.00%

2-Oct-13

12-Oct-13

100

1680

4.0%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Oct-13

15-Oct-13

100

1680

4.0%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Oct-13

29-Oct-13

12

100

2520

6.0%

0.00%

0.00%

0.00%

0.00%

0.00%

22-Sep-13

29-Sep-13

100

1260

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

28-Sep-13

5-Oct-13

100

1260

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

3-Oct-13

10-Oct-13

100

1260

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

PUMP AREA

CREP1120
CREP1130
CREP1140
CREP1150

Low Voltage Cable Laying For


Pump Area
High Voltage Cable Laying
For Pump Area
Installation Of Junction Boxes
For Pump Area
Termination For Pump Area

LAUNCHER AREA
CREL1100
CREL1110
CREL1120

Lighting System For The


Launcher Area
Power Socket For The
Launcher Area
Low Voltage Cable Laying For
The Launcher Area

Page 168 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

CREL1130
CREL1140
CREL1150

DESCRIPTION

High Voltage Cable Laying


For The Launcher Area
Installation Of Junction Boxes
For The Launcher Area
Termination For The
Launcher Area

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

9-Oct-13

16-Oct-13

100

1260

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Oct-13

22-Oct-13

100

1260

3.0%

0.00%

0.00%

0.00%

0.00%

0.00%

16-Oct-13

28-Oct-13

10

100

2100

5.0%

0.00%

0.00%

0.00%

0.00%

0.00%

42300

100.0%

0.00%

0.00%

0.00%

TOTAL OF ELECTRICAL WORKS

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

INSTRUMENTATION WORKS
SUB-STATION 6003
CRIS1100

Laying of Cables

19-Aug-13

31-Aug-13

10

100

2100

5.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIS1110

Installation Of Junction Boxes

31-Aug-13

12-Sep-13

10

100

2100

5.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIS1120

Termination For Substation


6003

7-Sep-13

18-Sep-13

10

100

2100

5.8%

0.00%

0.00%

0.00%

0.00%

0.00%

11-Sep-13

18-Sep-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

18-Sep-13

25-Sep-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

21-Sep-13

28-Sep-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

23-Sep-13

30-Sep-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

25-Sep-13

2-Oct-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

Termination For SER-12

2-Oct-13

9-Oct-13

100

1020

2.8%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIP1100

Laying Of Cables

25-Sep-13

5-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIP1110

Installation Of Flow
Transmitter

29-Sep-13

8-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

EXTENSION OF SER-12
CRIE1100
CRIE1120
CRIE1130
CRIE1140
CRIE1150
CRIE1160

Laying of Cables
DCS System Cabinet to be
Modified
DCS Marchaling Cabinet to be
Modified
ESD System Cabinet to be
Modified
F&G System Cabinet to be
Modified

PUMP AREA

Page 169 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

CRIP1120
CRIP1130
CRIP1140
CRIP1150
CRIP1160
CRIP1170

DESCRIPTION

Installation Of Pressure
Gauges With Fittings
Installation Of Pressure
Transmitters With Tubes &
Fittings
Installation
Of Junction Boxes
For Pump Area
Installation Of Gas Detectors
For Pump Area
Installation Of Manual Call
Point For Pump Area
Termination For Pump Area

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

2-Oct-13

12-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Oct-13

15-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

9-Oct-13

19-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

13-Oct-13

22-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

16-Oct-13

26-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

20-Oct-13

29-Oct-13

100

1680

4.7%

0.00%

0.00%

0.00%

0.00%

0.00%

LAUNCHER AREA
CRIL1110

Laying Of Cables

28-Sep-13

5-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIL1120

Installation Of Pig Signaller

1-Oct-13

8-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

5-Oct-13

12-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

CRIL1130
CRIL1140
CRIL1150
CRIL1160
CRIL1170
CRIL1180

Installation Of Pressure
Gauges With Fittings
Installation Of Pressure
Transmitters With Tubes &
Fittings
Installation
Of Distribution
Boards For Launcher
Installation Of Gas Detectors
For Launcher
Installation Of Manual Call
Point For Launcher

8-Oct-13

15-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

12-Oct-13

19-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Oct-13

22-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

19-Oct-13

26-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

Termination For Launcher

22-Oct-13

29-Oct-13

100

1260

3.5%

0.00%

0.00%

0.00%

0.00%

0.00%

35940

100.0%

0.00%

0.00%

0.00%

TOTAL OF INSTRUMENTATION WORKS

SUMMARY OF ALL WORKS INSIDE QP REFINERY


SER.

ITEM

M/H
Page 170 of 266

WEIGHT%

PLAN

ACTUAL WT. PL % WT. ACT%

DEV

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : QP REFINERY CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START

EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

CIVIL WORKS

242898

49.62%

0.00%

0.00%

0.00%

0.00%

0.00%

MECHANICAL WORKS

168380

34.40%

0.00%

0.00%

0.00%

0.00%

0.00%

ELECTRICAL WORKS

42300

8.64%

0.00%

0.00%

0.00%

0.00%

0.00%

INSTRUMENTATION WORKS

35940

7.34%

0.00%

0.00%

0.00%

0.00%

0.00%

489518

100.00%

0.00%

0.00%

0.00%

CONSTRUCTION OF ALL WORKS INSIDE QP FEFINERY

Page 171 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : BSV (3) CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

BSV-3
CIVIL WORKS
CBSC1100 Excavation In BSV-3
Plain Concrete In
BSV-3
Re-Inforced Concrete
CBSC1120
In BSV-3
CBSC1110

CBSC1130 Fence In BSV-3

8-Aug-13

20-Aug-13

10

100

1200

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

14-Aug-13

26-Aug-13

10

100

1200

8.3%

0.00%

0.00%

0.00%

0.00%

0.00%

20-Aug-13

1-Sep-13

10

100

6000

41.7%

0.00%

0.00%

0.00%

0.00%

0.00%

26-Aug-13

8-Sep-13

10

100

6000

41.7%

0.00%

0.00%

0.00%

0.00%

0.00%

14400

100.0%

0.00%

0.00%

0.00%

TOTAL OF CIVIL WORKS FOR BSV-3


MECHANICAL WORKS
Installation of Motor
Operated Valve
Tie-In To The Existing
CBSM1120
Inside BSV-3
CBSM1100

20-Aug-13

8-Sep-13

15

100

7800

75.0%

0.00%

0.00%

0.00%

0.00%

0.00%

6-Nov-13

12-Nov-13

100

2600

25.0%

0.00%

0.00%

0.00%

0.00%

0.00%

10400

100.0%

0.00%

0.00%

0.00%

TOTAL OF MECHANICAL WORKS FOR BSV-3


E&I WORKS
ELECTRICAL WORKS
Installation of
Electrical Permanent
Electrical Connection
CBSE1110
To MOV
Diesel Generator to be
CBSE1120
Removed
CBSE1100

18-Jul-13

30-Jul-13

10

100

5100

32.7%

0.00%

0.00%

0.00%

0.00%

0.00%

4-Sep-13

16-Sep-13

10

100

2550

16.3%

0.00%

0.00%

0.00%

0.00%

0.00%

21-Oct-13

2-Nov-13

10

100

7950

51.0%

0.00%

0.00%

0.00%

0.00%

0.00%

15600

100.0%

0.00%

0.00%

0.00%

TOTAL OF ELECTRICAL WORKS FOR BSV-3


INSTRUMENTATION WORKS
Page 172 of 266

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : BSV (3) CONSTRUCTION PHASE PROGRESS MEASUREMENT
DATE:
ID

26-Feb-12
DESCRIPTION

CBSI1100 Laying Of Cables


CBSI1110

Installation Of
Pressure Transmitters

CBSI1120 Termination

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

4-Sep-13

16-Sep-13

10

100

5100

32.7%

0.00%

0.00%

0.00%

0.00%

0.00%

16-Sep-13

28-Sep-13

10

100

2550

16.3%

0.00%

0.00%

0.00%

0.00%

0.00%

28-Sep-13

9-Oct-13

10

100

7950

51.0%

0.00%

0.00%

0.00%

0.00%

0.00%

15600

100.0%

0.00%

0.00%

0.00%

TOTAL OF INSTRUMENTATION WORKS FOR BSV-3

( SUMMARY OF ALL WORKS INSIDE BSV-3)


SER.

ITEM

M/H

WEIGHT%

PLAN

CIVIL WORKS

14400

25.71%

0.00%

0.00%

0.00%

0.00%

0.00%

MECHANICAL WORKS

10400

18.57%

0.00%

0.00%

0.00%

0.00%

0.00%

ELECTRICAL WORKS

15600

27.86%

0.00%

0.00%

0.00%

0.00%

0.00%

INSTRUMENTATION WORKS

15600

27.86%

0.00%

0.00%

0.00%

0.00%

0.00%

56000

100.00%

0.00%

0.00%

0.00%

TOTAL OF ALL WORKS INSIDE BSV-3

Page 173 of 266

ACTUAL WT. PL % WT. ACT%

DEV

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : CLOSE OUT CONSTRUCTION PHASE PROGRESS MEASUREMENT

26-Feb-12

DATE:
ID

DESCRIPTION

EARLY START EARLY FINISH

DUR.

QUAN.

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

WT. PL % WT. ACT%

DEV %

Close Out
Project Close Out
FPCO1100 As-Built Drawings
FPCO1110

Asset Capitalization
Schedule (ACS)

FPCO1120 Project Handover

31-May-14

28-Jul-14

50

100

2700

31.9%

0.00%

0.00%

0.00%

0.00%

0.00%

1-Jun-14

17-Jul-14

40

100

3200

37.8%

0.00%

0.00%

0.00%

0.00%

0.00%

28-Jun-14

25-Aug-14

50

100

2560

30.3%

0.00%

0.00%

0.00%

0.00%

0.00%

8460

100.0%

0.00%

0.00%

0.00%

TOTAL OF CIVIL WORKS FOR BSV-3

( SUMMARY OF ALL WORKS INSIDE BSV-3)


SER.
1

ITEM

Close out
TOTAL OF ALL WORKS INSIDE BSV-3

Page 174 of 266

M/H

WEIGHT%

PLAN

ACTUAL

8460

100.00%

0.00%

0.00%

8460

100.00%

WT. PL % WT. ACT%

DEV

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

CONTRACT NO. : GC 11106200


JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY
CLIENT :QATAR PETROLEUM
SUBJECT : PRE-COMMISSIONING & COMMISSIONING PROGRESS MEASUREMENT
Date :
Act. ID

26-Feb-12
DESCRIPTION

E START

M/H

WEIGHT%

PLANNED
%

ACTUAL
%

WT. PL %

WT. ACT%

DEV %

4,500

6.56%

0.00%

0.00%

0.00%

0.00%

0.00%

E FINISH

DUR.

T. Q.TY

UNIT

24-Nov-13

4-Feb-14

60

100

Q.DONE

PRECOMMISSIONING & COMMISSIONING PHASE


FCOM1100

Precomm & Comm For Main


Pipeline

FCOM1110

Precomm & Comm For Pumps

7-Dec-13

16-Feb-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1120

Precomm & Comm For SCADA &


PLC System

18-Dec-13

27-Feb-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1130

Precomm & Comm For


Telecommunication & FOC System

31-Dec-13

11-Mar-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1140

Precomm & Comm For Security


System

12-Jan-14

23-Mar-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1150

Precomm & Comm For Cathodic


Protection System

23-Jan-14

3-Apr-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1160

Precomm & Comm For Electrical


& Instrumentation System

4-Feb-14

15-Apr-14

60

100

9,000

13.12%

0.00%

0.00%

0.00%

0.00%

0.00%

15-Apr-14

19-Apr-14

100

2,240

3.27%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1170 72 Hrs Performance Test


FCOM1180

System Readiness To Be Operated

19-Apr-14

7-May-14

16

100

5,600

8.17%

0.00%

0.00%

0.00%

0.00%

0.00%

FCOM1190

Jet A1 Fuel Ready To Be Taken In

10-May-14

21-May-14

10

100

2,240

3.27%

0.00%

0.00%

0.00%

0.00%

0.00%

68580

100.0%

0.00%

0.00%

0.00%

TOTAL OF PRE-COMMISSIONING & COMMISSIONING

Page 175 of 266

CONTRACT NO. : GC 11106200

JOB TITLE : EPIC FOR 16" JET A1 FUEL PL FROM QP REFINERY

CLIENT :QATAR PETROLEUM

SUBJECT : THE OPTIONAL ITEMS PROGRESS MEASUREMENT

Date :

26-Feb-12

Act. ID

DESCRIPTION

E START

E FINISH

DUR.

T. Q.TY

UNIT

Q.DONE

M/H

WEIGHT% PLANNED% ACTUAL%

5-Nov-12

31-May-13

150

100

12,000

71.22%

0.00%

WT. PL %

WT. ACT%

DEV %

0.00%

0.00%

0.00%

0.00%

The Optional Items

OPT1100

Laying Of New FOC From QP Refinery


to BSV-3

OPT1110

Kahramaa Option (1) / Pole Mounted


Transformer At BSV-3

20-May-13

31-May-13

10

100

800

4.75%

0.00%

0.00%

0.00%

0.00%

0.00%

OPT1120

Baseline Survey

11-Jun-14

23-Jul-14

36

100

4,050

24.04%

0.00%

0.00%

0.00%

0.00%

0.00%

16850

100.0%

0.00%

0.00%

0.00%

TOTAL OF THE OPTIONAL ITEMS

Page 176 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROGRESS S-CURVES, LATE CURVES AND
TABLES ON WEEKLY AND MONTHLY BASIS
______________________________________

Page 177 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROGRESS S-CURVES
_____________________________________

Page 178 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3


PROJECT OVERALL S-CURVE

100.00

PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00

Planned
Actual
Dev.

20.00
10.00

:
:
:

%
%
%

0.00

DATE
Page 179 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3 PROJECT


ENGINEERING PHASE S-CURVE

100.00

PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00

Planned
Actual
Dev.

20.00
10.00

:
:
:

%
%
%

0.00

DATE
Page 180 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3 PROJECT


PROCUREMENT PHASE S-CURVE

100.00

PROG. %
90.00
80.00

70.00
60.00
50.00
40.00
30.00

Planned
Actual
Dev.

20.00
10.00

:
:
:

%
%
%

0.00

DATE
Page 181 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3 PROJECT


CONSTRUCTION PHASE S-CURVE

100.00

PROG. %
90.00
80.00

70.00
60.00
50.00
40.00
30.00

Planned
Actual
Dev.

20.00
10.00

:
:
:

%
%
%

0.00

DATE
Page 182 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3 PROJECT


PRE-COMM &COMMISSIONING S-CURVE

100.00

PROG. %
90.00
80.00

70.00
60.00
50.00
40.00
30.00
20.00

Planned
Actual
Dev.

10.00

:
:
:

%
%
%

0.00

DATE
Page 183 of 266

16 JET A1 FUEL P/L FROM QP REFINERY TO BSV-3


OPTIONAL ITEM S-CURVE

100.00

PROG. %
90.00
80.00

70.00
60.00
50.00
40.00
30.00
20.00

Planned
Actual
Dev.

10.00

:
:
:

%
%
%

0.00

DATE
Page 184 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROGRESS LATE CURVE
______________________________________

Page 185 of 266

21-Jul-12 22:34

EPIC For 16" - 36 Km Jet A1 Fuel

12500d

187500d

10000d

150000d

7500d

112500d

5000d

75000d

2500d

37500d

Mar

Apr

May

Jun
Jul
2012

Budgeted Units
Remaining Late Units

Limit

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun
Jul
2013

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

PETROJET CO

Page 186 of 266

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Date
19-Jul-12

Mar

Apr
May
2014

Revision
Rev(5)

Jun

Checked
Y.Abdalshaf...

Jul

Aug

Approved

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
PROGRESS TABLES ON WEEKLY AND
MONTHLY BASIS
______________________________________

Page 187 of 266

16" Jet A1 Fuel PL Project Overall Planned (On Monthly Basis)

PLANNED

PLANNED

PLANNED

29-02-2012

31-03-2012

30-04-2012

31-05-2012

30-06-2012

31-07-2012

31-08-2012

30-09-2012

31-10-2012

30-11-2012

31-12-2012

Engineering

0.00

0.07

1.66

5.54

15.30

40.64

65.86

85.47

94.75

95.00

95.00

Procurement

0.00

0.00

0.00

0.00

0.00

4.20

12.38

23.53

27.26

34.92

39.50

Construction

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.22

5.44

11.30

18.17

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

8.60

19.27

Overall

0.00

0.00

0.08

0.28

0.77

3.71

8.25

14.27

18.25

24.31

29.66

31-01-2013

28-02-2013

31-03-2013

30-04-2013

31-05-2013

30-06-2013

31-07-2013

31-08-2013

30-09-2013

31-10-2013

30-11-2013

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

40.27

42.42

42.42

52.59

61.06

76.09

86.47

92.89

96.59

100.00

100.00

Construction

26.15

33.04

42.00

49.91

59.07

67.44

73.79

82.03

89.64

98.15

99.20

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.55

Optional

29.93

39.56

50.23

60.55

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

34.01

38.37

42.88

50.95

59.05

69.08

76.28

82.80

87.93

93.38

93.91

31-12-2013

31-01-2014

28-02-2014

31-03-2014

30-04-2014

31-05-2014

30-06-2014

31-07-2014

25-08-2014

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

97.33

100.00

100.00

Procurement

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Construction

99.20

99.20

99.20

99.20

99.20

99.20

99.53

99.90

100.00

Precomm&Comm

10.20

35.37

63.93

81.93

93.56

100.00

100.00

100.00

100.00

Optional

75.96

75.96

75.96

75.96

75.96

75.96

86.84

100.00

100.00

Overall

94.40

95.65

97.08

97.98

98.56

98.89

99.38

99.95

100.00

Page 188 of 266

16" Jet A1 Fuel PL Project Overall Planned (On Weekly Basis)

26-02-2012 01-03-2012 08-03-2012 15-03-2012 22-03-2012 29-03-2012 05-04-2012 12-04-2012 19-04-2012 26-04-2012 03-05-2012

PLANNED

Engineering

0.00

0.00

0.00

0.00

0.00

0.07

0.14

1.18

1.53

1.53

2.26

Procurement

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Construction

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Overall

0.00

0.00

0.00

0.00

0.00

0.00

0.01

0.06

0.08

0.08

0.11

10

10-05-2012 17-05-2012 24-05-2012 31-05-2012 07-06-2012 14-06-2012 21-06-2012 28-06-2012 05-07-2012 12-07-2012 19-07-2012

PLANNED

Engineering

2.49

3.80

4.43

5.54

7.84

9.99

12.44

15.30

18.76

23.13

28.26

Procurement

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Construction

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Overall

0.12

0.19

0.22

0.28

0.39

0.50

0.62

0.77

0.94

1.16

1.41

11

12

13

14

15

16

17

18

19

20

21

26-07-2012 02-08-2012 09-08-2012 16-08-2012 23-08-2012 30-08-2012 06-09-2012 13-09-2012 20-09-2012 27-09-2012 04-10-2012

PLANNED

Engineering

35.57

42.82

47.93

53.80

59.93

65.86

72.62

76.68

80.72

84.02

87.46

Procurement

2.19

4.90

5.08

8.21

11.35

12.25

13.55

14.73

20.48

20.94

23.57

Construction

0.00

0.00

0.00

0.00

0.00

0.00

0.02

0.19

0.49

0.96

1.69

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Overall

2.65

4.10

4.43

5.97

7.54

8.19

9.06

9.82

12.46

13.04

14.61

22

23

24

25

26

27

28

29

30

31

32

Page 189 of 266

16" Jet A1 Fuel PL Project Overall Planned (On Weekly Basis)

11-10-2012 18-10-2012 25-10-2012 01-11-2012 08-11-2012 15-11-2012 22-11-2012 29-11-2012 06-12-2012 13-12-2012 20-12-2012

PLANNED

Engineering

89.47

91.64

94.75

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

27.14

27.14

27.26

27.26

27.26

28.86

32.90

34.90

36.63

38.32

39.38

Construction

2.58

3.46

4.48

5.62

6.93

8.20

9.67

11.08

12.59

14.03

15.48

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

0.00

0.00

0.00

0.00

1.03

3.44

5.85

8.26

10.67

13.07

15.48

Overall

16.57

17.10

17.79

18.35

19.00

20.30

22.67

24.19

25.66

27.07

28.24

33

34

35

36

37

38

39

40

41

42

43

27-12-2012 03-01-2013 10-01-2013 17-01-2013 24-01-2013 31-01-2013 07-02-2013 14-02-2013 21-02-2013 28-02-2013 07-03-2013

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

39.50

39.83

39.83

39.83

39.94

40.27

40.27

42.03

42.07

42.42

42.44

Construction

17.19

18.95

20.67

22.45

24.27

26.15

27.98

29.65

31.26

33.04

34.92

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

17.89

20.30

22.71

25.12

27.52

29.93

32.34

34.75

37.16

39.56

41.97

Overall

29.16

30.18

31.06

31.96

32.93

34.01

34.94

36.49

37.33

38.37

39.33

44

45

46

47

48

49

50

51

52

53

54

14-03-2013 21-03-2013 28-03-2013 04-04-2013 11-04-2013 18-04-2013 25-04-2013 02-05-2013 09-05-2013 16-05-2013 23-05-2013

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

42.44

42.44

42.44

46.14

46.95

48.79

49.03

53.03

53.93

56.45

57.30

Construction

36.88

39.01

41.16

43.06

44.98

46.83

48.03

50.55

52.77

54.87

56.77

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

44.38

46.79

49.20

51.61

54.01

56.42

58.83

61.24

63.65

66.06

69.76

Overall

40.32

41.39

42.47

44.91

46.20

47.87

48.59

51.45

52.92

54.99

56.31

55

56

57

58

59

60

61

62

63

64

65

Page 190 of 266

16" Jet A1 Fuel PL Project Overall Planned (On Weekly Basis)

30-05-2013 06-06-2013 13-06-2013 20-06-2013 27-06-2013 04-07-2013 11-07-2013 18-07-2013 25-07-2013 01-08-2013 08-08-2013

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

60.96

63.92

66.30

66.53

73.74

76.50

78.37

82.43

85.72

86.47

86.47

Construction

58.79

60.72

62.87

64.83

66.65

68.40

69.90

70.82

72.33

74.02

75.56

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

75.19

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

58.86

60.98

62.97

64.00

67.76

69.70

71.17

73.23

75.28

76.39

77.13

66

67

68

69

70

71

72

73

74

75

76

15-08-2013 22-08-2013 29-08-2013 05-09-2013 12-09-2013 19-09-2013 26-09-2013 03-10-2013 10-10-2013 17-10-2013 24-10-2013

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

86.82

86.82

92.38

95.04

95.30

96.59

96.59

96.59

96.59

100.00

100.00

Construction

77.31

79.26

81.41

83.39

85.35

86.85

88.41

90.72

93.16

94.65

96.59

Precomm&Comm

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Optional

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

78.11

79.04

82.30

84.31

85.36

86.59

87.34

88.45

89.62

91.70

92.63

77

78

79

80

81

82

83

84

85

86

87

31-10-2013 07-11-2013 14-11-2013 21-11-2013 28-11-2013 05-12-2013 12-12-2013 19-12-2013 26-12-2013 02-01-2014 09-01-2014

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Construction

98.15

98.57

98.94

99.10

99.20

99.20

99.20

99.20

99.20

99.20

99.20

Precomm&Comm

0.00

0.00

0.00

0.00

0.36

1.00

2.56

4.56

7.91

11.51

16.05

Optional

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

93.38

93.58

93.76

93.84

93.90

93.94

94.01

94.11

94.28

94.46

94.69

88

89

90

91

92

93

94

95

96

97

98

Page 191 of 266

16" Jet A1 Fuel PL Project Overall Planned (On Weekly Basis)

16-01-2014 23-01-2014 30-01-2014 06-02-2014 13-02-2014 20-02-2014 27-02-2014 06-03-2014 13-03-2014 20-03-2014 27-03-2014

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

Procurement

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Construction

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

Precomm&Comm

21.33

27.18

34.35

41.70

49.54

56.64

63.18

68.43

73.30

77.24

80.43

Optional

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

94.95

95.24

95.60

95.97

96.36

96.72

97.04

97.31

97.55

97.75

97.91

99

100

101

102

103

104

105

106

107

108

109

03-04-2014 10-04-2014 17-04-2014 24-04-2014 01-05-2014 08-05-2014 15-05-2014 22-05-2014 29-05-2014 05-06-2014 12-06-2014

PLANNED

Engineering

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.00

95.63

Procurement

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Construction

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.20

99.24

99.32

Precomm&Comm

83.05

84.36

86.93

90.84

94.01

96.73

98.22

100.00

100.00

100.00

100.00

Optional

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

75.96

Overall

98.04

98.10

98.23

98.43

98.59

98.72

98.80

98.89

98.89

98.90

98.97

110

111

112

113

114

115

116

117

118

119

120

19-06-2014 26-06-2014 03-07-2014 10-07-2014 17-07-2014 24-07-2014 31-07-2014 07-08-2014 14-08-2014 21-08-2014 25-08-2014

PLANNED

Engineering

96.25

96.88

97.50

98.13

98.75

99.38

100.00

100.00

100.00

100.00

100.00

Procurement

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Construction

99.40

99.48

99.57

99.68

99.79

99.85

99.90

99.92

99.95

99.98

100.00

Precomm&Comm

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Optional

80.54

84.55

88.55

92.56

96.57

100.00

100.00

100.00

100.00

100.00

100.00

Overall

99.14

99.29

99.44

99.60

99.77

99.90

99.95

99.96

99.98

99.99

100.00

121

122

123

124

125

126

127

128

129

130

131

Page 192 of 266

16" Jet A1 Fuel PL Project


Overall Planned Per Month
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Month

29-Feb-12

0.00

0.00

31-Mar-12

0.00

0.00

30-Apr-12

0.08

0.08

31-May-12

0.28

0.19

30-Jun-12

0.77

0.49

31-Jul-12

3.71

2.95

31-Aug-12

8.25

4.53

30-Sep-12

14.27

6.03

31-Oct-12

18.25

3.98

30-Nov-12

24.31

6.06

10

31-Dec-12

29.66

5.34

11

31-Jan-13

34.01

4.35

12

28-Feb-13

38.37

4.36

13

31-Mar-13

42.88

4.51

14

30-Apr-13

50.95

8.07

15

31-May-13

59.05

8.09

16

30-Jun-13

69.08

10.03

17

31-Jul-13

76.28

7.20

18

31-Aug-13

82.80

6.52

19

30-Sep-13

87.93

5.13

20

31-Oct-13

93.38

5.45

21

30-Nov-13

93.91

0.53

22

31-Dec-13

94.40

0.48

23

31-Jan-14

95.65

1.26

24

28-Feb-14

97.08

1.43

25

31-Mar-14

97.98

0.90

26

30-Apr-14

98.56

0.58

27

31-May-14

98.89

0.32

28

30-Jun-14

99.38

0.49

29

31-Jul-14

99.95

0.57

30

25-Aug-14

100.00

0.05

Page 193 of 266

16" Jet A1 Fuel PL Project


Overall Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

26-Feb-12

0.00

0.00

1-Mar-12

0.00

0.00

8-Mar-12

0.00

0.00

15-Mar-12

0.00

0.00

22-Mar-12

0.00

0.00

29-Mar-12

0.00

0.00

5-Apr-12

0.01

0.00

12-Apr-12

0.06

0.05

19-Apr-12

0.08

0.02

26-Apr-12

0.08

0.00

10

3-May-12

0.11

0.04

11

10-May-12

0.12

0.01

12

17-May-12

0.19

0.07

13

24-May-12

0.22

0.03

14

31-May-12

0.28

0.06

15

7-Jun-12

0.39

0.12

16

14-Jun-12

0.50

0.11

17

21-Jun-12

0.62

0.12

18

28-Jun-12

0.77

0.14

19

5-Jul-12

0.94

0.17

20

12-Jul-12

1.16

0.22

21

19-Jul-12

1.41

0.26

22

26-Jul-12

2.65

1.24

23

2-Aug-12

4.10

1.45

24

9-Aug-12

4.43

0.33

25

16-Aug-12

5.97

1.55

26

23-Aug-12

7.54

1.56

27

30-Aug-12

8.19

0.66

28

6-Sep-12

9.06

0.87

29

13-Sep-12

9.82

0.76

30

20-Sep-12

12.46

2.65

31

27-Sep-12

13.04

0.57

32

4-Oct-12

14.61

1.57

33

11-Oct-12

16.57

1.96

34

18-Oct-12

17.10

0.53

Page 194 of 266

16" Jet A1 Fuel PL Project


Overall Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

35

25-Oct-12

17.79

0.69

36

1-Nov-12

18.35

0.56

37

8-Nov-12

19.00

0.65

38

15-Nov-12

20.30

1.30

39

22-Nov-12

22.67

2.37

40

29-Nov-12

24.19

1.53

41

6-Dec-12

25.66

1.47

42

13-Dec-12

27.07

1.42

43

20-Dec-12

28.24

1.17

44

27-Dec-12

29.16

0.92

45

3-Jan-13

30.18

1.03

46

10-Jan-13

31.06

0.87

47

17-Jan-13

31.96

0.90

48

24-Jan-13

32.93

0.97

49

31-Jan-13

34.01

1.08

50

7-Feb-13

34.94

0.93

51

14-Feb-13

36.49

1.55

52

21-Feb-13

37.33

0.84

53

28-Feb-13

38.37

1.04

54

7-Mar-13

39.33

0.96

55

14-Mar-13

40.32

0.99

56

21-Mar-13

41.39

1.07

57

28-Mar-13

42.47

1.08

58

4-Apr-13

44.91

2.44

59

11-Apr-13

46.20

1.29

60

18-Apr-13

47.87

1.67

61

25-Apr-13

48.59

0.72

62

2-May-13

51.45

2.86

63

9-May-13

52.92

1.47

64

16-May-13

54.99

2.06

65

23-May-13

56.31

1.33

66

30-May-13

58.86

2.54

67

6-Jun-13

60.98

2.13

68

13-Jun-13

62.97

1.98

69

20-Jun-13

64.00

1.03

Page 195 of 266

16" Jet A1 Fuel PL Project


Overall Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

70

27-Jun-13

67.76

3.76

71

4-Jul-13

69.70

1.94

72

11-Jul-13

71.17

1.47

73

18-Jul-13

73.23

2.07

74

25-Jul-13

75.28

2.04

75

1-Aug-13

76.39

1.11

76

8-Aug-13

77.13

0.74

77

15-Aug-13

78.11

0.98

78

22-Aug-13

79.04

0.94

79

29-Aug-13

82.30

3.26

80

5-Sep-13

84.31

2.01

81

12-Sep-13

85.36

1.04

82

19-Sep-13

86.59

1.24

83

26-Sep-13

87.34

0.75

84

3-Oct-13

88.45

1.11

85

10-Oct-13

89.62

1.17

86

17-Oct-13

91.70

2.08

87

24-Oct-13

92.63

0.93

88

31-Oct-13

93.38

0.75

89

7-Nov-13

93.58

0.20

90

14-Nov-13

93.76

0.18

91

21-Nov-13

93.84

0.08

92

28-Nov-13

93.90

0.07

93

5-Dec-13

93.94

0.03

94

12-Dec-13

94.01

0.08

95

19-Dec-13

94.11

0.10

96

26-Dec-13

94.28

0.17

97

2-Jan-14

94.46

0.18

98

9-Jan-14

94.69

0.23

99

16-Jan-14

94.95

0.26

100

23-Jan-14

95.24

0.29

101

30-Jan-14

95.60

0.36

102

6-Feb-14

95.97

0.37

103

13-Feb-14

96.36

0.39

104

20-Feb-14

96.72

0.35

Page 196 of 266

16" Jet A1 Fuel PL Project


Overall Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

105

27-Feb-14

97.04

0.33

106

6-Mar-14

97.31

0.26

107

13-Mar-14

97.55

0.24

108

20-Mar-14

97.75

0.20

109

27-Mar-14

97.91

0.16

110

3-Apr-14

98.04

0.13

111

10-Apr-14

98.10

0.07

112

17-Apr-14

98.23

0.13

113

24-Apr-14

98.43

0.20

114

1-May-14

98.59

0.16

115

8-May-14

98.72

0.14

116

15-May-14

98.80

0.07

117

22-May-14

98.89

0.09

118

29-May-14

98.89

0.00

119

5-Jun-14

98.90

0.02

120

12-Jun-14

98.97

0.07

121

19-Jun-14

99.14

0.16

122

26-Jun-14

99.29

0.15

123

3-Jul-14

99.44

0.15

124

10-Jul-14

99.60

0.16

125

17-Jul-14

99.77

0.16

126

24-Jul-14

99.90

0.13

127

31-Jul-14

99.95

0.06

128

7-Aug-14

99.96

0.01

129

14-Aug-14

99.98

0.01

130

21-Aug-14

99.99

0.01

131

25-Aug-14

100.00

0.01

Page 197 of 266

16" Jet A1 Fuel PL Project


Construction Phase Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

30-Aug-12

0.00

0.00

6-Sep-12

0.02

0.02

13-Sep-12

0.19

0.17

20-Sep-12

0.49

0.30

27-Sep-12

0.96

0.47

4-Oct-12

1.69

0.73

11-Oct-12

2.58

0.89

18-Oct-12

3.46

0.88

25-Oct-12

4.48

1.02

10

1-Nov-12

5.62

1.14

11

8-Nov-12

6.93

1.31

12

15-Nov-12

8.20

1.27

13

22-Nov-12

9.67

1.47

14

29-Nov-12

11.08

1.41

15

6-Dec-12

12.59

1.51

16

13-Dec-12

14.03

1.44

17

20-Dec-12

15.48

1.45

18

27-Dec-12

17.19

1.71

19

3-Jan-13

18.95

1.76

20

10-Jan-13

20.67

1.72

21

17-Jan-13

22.45

1.78

22

24-Jan-13

24.27

1.82

23

31-Jan-13

26.15

1.88

24

7-Feb-13

27.98

1.83

25

14-Feb-13

29.65

1.67

26

21-Feb-13

31.26

1.61

27

28-Feb-13

33.04

1.78

28

7-Mar-13

34.92

1.88

29

14-Mar-13

36.88

1.96

30

21-Mar-13

39.01

2.13

31

28-Mar-13

41.16

2.15

32

4-Apr-13

43.06

1.90

33

11-Apr-13

44.98

1.92

34

18-Apr-13

46.83

1.85

35

25-Apr-13

48.03

1.20

36

2-May-13

50.55

2.52

37

9-May-13

52.77

2.22

Page 198 of 266

16" Jet A1 Fuel PL Project


Construction Phase Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

38

16-May-13

54.87

2.10

39

23-May-13

56.77

1.90

40

30-May-13

58.79

2.02

41

6-Jun-13

60.72

1.93

42

13-Jun-13

62.87

2.15

43

20-Jun-13

64.83

1.96

44

27-Jun-13

66.65

1.82

45

4-Jul-13

68.40

1.75

46

11-Jul-13

69.90

1.50

47

18-Jul-13

70.82

0.92

48

25-Jul-13

72.33

1.51

49

1-Aug-13

74.02

1.69

50

8-Aug-13

75.56

1.54

51

15-Aug-13

77.31

1.75

52

22-Aug-13

79.26

1.95

53

29-Aug-13

81.41

2.15

54

5-Sep-13

83.39

1.98

55

12-Sep-13

85.35

1.96

56

19-Sep-13

86.85

1.50

57

26-Sep-13

88.41

1.56

58

3-Oct-13

90.72

2.31

59

10-Oct-13

93.16

2.44

60

17-Oct-13

94.65

1.49

61

24-Oct-13

96.59

1.94

62

31-Oct-13

98.15

1.56

63

7-Nov-13

98.57

0.42

64

14-Nov-13

98.94

0.37

65

21-Nov-13

99.10

0.16

66

28-Nov-13

99.20

0.10

67

5-Dec-13

99.20

0.00

68

12-Dec-13

99.20

0.00

69

19-Dec-13

99.20

0.00

70

26-Dec-13

99.20

0.00

71

2-Jan-14

99.20

0.00

72

9-Jan-14

99.20

0.00

73

16-Jan-14

99.20

0.00

74

23-Jan-14

99.20

0.00

Page 199 of 266

16" Jet A1 Fuel PL Project


Construction Phase Planned Per Week
ETROJET

Month No.

Date

Cumulative Planned

Planned Per Week

75

30-Jan-14

99.20

0.00

76

6-Feb-14

99.20

0.00

77

13-Feb-14

99.20

0.00

78

20-Feb-14

99.20

0.00

79

27-Feb-14

99.20

0.00

80

6-Mar-14

99.20

0.00

81

13-Mar-14

99.20

0.00

82

20-Mar-14

99.20

0.00

83

27-Mar-14

99.20

0.00

84

3-Apr-14

99.20

0.00

85

10-Apr-14

99.20

0.00

86

17-Apr-14

99.20

0.00

87

24-Apr-14

99.20

0.00

88

1-May-14

99.20

0.00

89

8-May-14

99.20

0.00

90

15-May-14

99.20

0.00

91

22-May-14

99.20

0.00

92

29-May-14

99.20

0.00

93

5-Jun-14

99.24

0.04

94

12-Jun-14

99.32

0.08

95

19-Jun-14

99.40

0.08

96

26-Jun-14

99.48

0.08

97

3-Jul-14

99.57

0.09

98

10-Jul-14

99.68

0.11

99

17-Jul-14

99.79

0.11

100

24-Jul-14

99.85

0.06

101

31-Jul-14

99.90

0.05

102

7-Aug-14

99.92

0.02

103

14-Aug-14

99.95

0.03

104

21-Aug-14

99.98

0.03

105

25-Aug-14

100.00

0.02

Page 200 of 266

31-Mar-12
30-Apr-12
31-May-12
30-Jun-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12

0
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Series1

Page 201 of 266

Series2
25-Aug-14

31-Jul-14

30-Jun-14

31-May-14

30-Apr-14

31-Mar-14

28-Feb-14

31-Jan-14

31-Dec-13

30-Nov-13

31-Oct-13

30-Sep-13

31-Aug-13

31-Jul-13

30-Jun-13

31-May-13

30-Apr-13

31-Mar-13

28-Feb-13

31-Jan-13

29-Feb-12

Project Overall Planned (Commulative / Per Month)

100.00

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00

10.00

0.00

26-Feb-12
15-Mar-12
5-Apr-12
26-Apr-12
17-May-12
7-Jun-12
28-Jun-12
19-Jul-12
9-Aug-12
30-Aug-12
20-Sep-12
11-Oct-12
1-Nov-12
22-Nov-12
13-Dec-12
3-Jan-13
24-Jan-13
14-Feb-13
7-Mar-13
28-Mar-13
18-Apr-13
9-May-13
30-May-13
20-Jun-13
11-Jul-13
1-Aug-13
22-Aug-13
12-Sep-13
3-Oct-13
24-Oct-13
14-Nov-13
5-Dec-13
26-Dec-13
16-Jan-14
6-Feb-14
27-Feb-14
20-Mar-14
10-Apr-14
1-May-14
22-May-14
12-Jun-14
3-Jul-14
24-Jul-14
14-Aug-14

Project Overall Planned (Commulative / Per Week)

100.00

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00

10.00

0.00

0 2 4 6 8 101214161820222426283032343638404244464850525456586062646668707274767880828486889092949698100
102
104
106
108
110
112
114
116
118
120
122
124
126
128
130

Series1
Series2

Page 202 of 266

Series1

Page 203 of 266

Series2
14-Aug-14

24-Jul-14

3-Jul-14

12-Jun-14

22-May-14

1-May-14

10-Apr-14

20-Mar-14

27-Feb-14

6-Feb-14

16-Jan-14

26-Dec-13

5-Dec-13

14-Nov-13

24-Oct-13

3-Oct-13

12-Sep-13

22-Aug-13

1-Aug-13

11-Jul-13

20-Jun-13

30-May-13

9-May-13

18-Apr-13

28-Mar-13

7-Mar-13

14-Feb-13

24-Jan-13

3-Jan-13

13-Dec-12

22-Nov-12

1-Nov-12

11-Oct-12

20-Sep-12

30-Aug-12

Construction Phase Planned (Commulative / Per Week)

100.00

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00

10.00

0.00

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95 97 99101103105

16" JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3 PROJECT


ENGINEERING PHASE S-CURVE
#REF!
Planned Vs Actual Progress
8.00%

100.00%

90.00%
7.00%

80.00%
6.00%
70.00%

5.00%
60.00%

4.00%

50.00%

40.00%
3.00%

30.00%
2.00%
20.00%

1.00%

29-Mar- 5-Apr-12 12-Apr12


12

19-Apr12

26-Apr- 3-May-12 10-May- 17-May- 24-May- 31-May- 7-Jun-12 14-Jun12


12
12
12
12
12

21-Jun12

Plan Wk %

Plan Cumm. %

21-Oct12

34

33

32

31

30

29

28

27

26

25

24

23

22

21

20

19

18

28-Jun- 5-Jul-12 12-Jul-12 19-Jul-12 26-Jul-12 2-Aug-12 9-Aug-12 16-Aug- 23-Aug- 30-Aug- 6-Sep-12 13-Sep- 20-Sep- 27-Sep- 5-Oct-12 13-Oct12
12
12
12
12
12
12
12

Actual Wk %

Week start
Week End
Week No.

17

16

15

14

13

12

11

10

0.00%

10.00%

0.00%

29-Oct- 6-Nov-12 14-Nov- 22-Nov12


12
12

Actual Cumm %

23-Mar-12
29-Mar-12

30-Mar-12
5-Apr-12

6-Apr-12
12-Apr-12

13-Apr-12
19-Apr-12

20-Apr-12
26-Apr-12

27-Apr-12
3-May-12

4-May-12
10-May-12

11-May-12
17-May-12

18-May-12
24-May-12

25-May-12
31-May-12

1-Jun-12
7-Jun-12

8-Jun-12
14-Jun-12

15-Jun-12
21-Jun-12

22-Jun-12
28-Jun-12

29-Jun-12
5-Jul-12

6-Jul-12
12-Jul-12

13-Jul-12
19-Jul-12

20-Jul-12
26-Jul-12

27-Jul-12
2-Aug-12

3-Aug-12
9-Aug-12

10-Aug-12
16-Aug-12

17-Aug-12
23-Aug-12

24-Aug-12
30-Aug-12

31-Aug-12
6-Sep-12

7-Sep-12
13-Sep-12

14-Sep-12
20-Sep-12

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

0.07%

1.04%

0.35%

0.73%

0.23%

1.31%

0.63%

1.11%

2.30%

2.15%

2.45%

2.86%

3.46%

4.37%

5.13%

7.31%

7.25%

5.11%

5.87%

6.13%

5.93%

6.76%

4.06%

4.04%

3.30%

0.07%

0.14%

1.18%

1.53%

1.53%

2.26%

2.49%

3.80%

4.43%

5.54%

7.84%

9.99%

12.44%

15.30%

18.76%

23.13%

28.26%

35.57%

42.82%

47.93%

53.80%

59.93%

65.86%

72.62%

76.68%

80.72%

84.02%

Week start
Week End
Week No.

28-Sep-12
5-Oct-12

6-Oct-12
13-Oct-12

14-Oct-12
21-Oct-12

22-Oct-12
29-Oct-12

30-Oct-12
6-Nov-12

7-Nov-12
14-Nov-12

15-Nov-12
22-Nov-12

23-Nov-12
30-Nov-12

1-Dec-12
8-Dec-12

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

Plan Wk %

3.44%

2.01%

2.17%

3.11%

0.25%

87.46%

89.47%

91.64%

94.75%

95.00%

95.00%

95.00%

Plan Wk %

21-Sep-12
27-Sep-12

Actual Wk %
Plan Cumm. %
Actual Cumm %

Actual Wk %
Plan Cumm. %
Actual Cumm %

NOTE : 5% is considered for As-Built

Page 204 of 266

16" JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3 PROJECT


PROCUREMENT PHASE S-CURVE

Planned Vs Actual Progress


9.00%

100.00%

90.00%

8.00%

80.00%

7.00%

70.00%

6.00%
60.00%
5.00%

50.00%
4.00%
40.00%
3.00%
30.00%

2.00%

20.00%

1.00%

Actual Bi-Wk %

Bi-Week start
Bi-Week End
Bi-Week No.

20-Jul-12
26-Jul-12
1

Plan Bi-Wk %

Plan Wk %

Plan Cumm. %

3-Aug-12
9-Aug-12
2

17-Aug-12
23-Aug-12
3

31-Aug-12
6-Sep-12
4

14-Sep-12
20-Sep-12
5

28-Sep-12
4-Oct-12
6

12-Oct-12
18-Oct-12
7

26-Oct-12
1-Nov-12
8

9-Nov-12
15-Nov-12
9

23-Nov-12
29-Nov-12
10

7-Dec-12
13-Dec-12
11

21-Dec-12
27-Dec-12
12

4-Jan-13
10-Jan-13
13

18-Jan-13
24-Jan-13
14

1-Feb-13
7-Feb-13
15

15-Feb-13
21-Feb-13
16

1-Mar-13
7-Mar-13
17

2.89%

6.27%

2.20%

6.93%

3.09%

3.57%

0.12%

1.60%

6.04%

3.42%

1.18%

0.33%

0.11%

0.33%

1.80%

0.37%

5.08%

11.35%

13.55%

20.48%

23.57%

27.14%

27.26%

28.86%

34.90%

38.32%

39.50%

39.83%

39.94%

40.27%

42.07%

42.44%

15-Mar-13
21-Mar-13
18

32

33

16-May-13 30-May-13 13-Jun-13

31

2-May-13

30

18-Apr-13

29

4-Apr-13

28

21-Mar-13

27

7-Mar-13

26

21

21-Feb-13

25

20

7-Feb-13

24

19

24-Jan-13

23

18

15-Nov-12 29-Nov-12 13-Dec-12 27-Dec-12 10-Jan-13

22

17

1-Nov-12

16

18-Oct-12

15

4-Oct-12

14

20-Sep-12

13

6-Sep-12

12

23-Aug-12

11

9-Aug-12

10

26-Jul-12

0.00%

10.00%

27-Jun-13

11-Jul-13

25-Jul-13

8-Aug-13

22-Aug-13

5-Sep-13

19-Sep-13

3-Oct-13

17-Oct-13

0.00%

Actual Cumm %

29-Mar-13
4-Apr-13
19

12-Apr-13
18-Apr-13
20

26-Apr-13
2-May-13
21

10-May-13
16-May-13
22

24-May-13
30-May-13
23

7-Jun-13
13-Jun-13
24

21-Jun-13
27-Jun-13
25

5-Jul-13
11-Jul-13
26

19-Jul-13
25-Jul-13
27

2-Aug-13
8-Aug-13
28

16-Aug-13
22-Aug-13
29

30-Aug-13
5-Sep-13
30

13-Sep-13
19-Sep-13
31

3.70%

2.65%

4.24%

3.42%

4.51%

5.34%

7.44%

4.63%

7.35%

0.75%

0.35%

8.22%

1.55%

46.14%

48.79%

53.03%

56.45%

60.96%

66.30%

73.74%

78.37%

85.72%

86.47%

86.82%

95.04%

96.59%

27-Sep-13
3-Oct-13
32

11-Oct-13
17-Oct-13
33

3.41%

Actual Bi-Wk %
Plan Cumm. %

2.19%

Actual Cumm %

Page 205 of 266

42.44%

96.6%

100%

16" JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3 PROJECT


CONSTRUCTION PHASE S-CURVE

Planned Vs Actual Progress


6.00%

100.00%

90.00%

5.00%
80.00%

70.00%
4.00%

60.00%

3.00%

50.00%

40.00%

2.00%
30.00%

20.00%
1.00%

0.00%

33

32

31

30

29

28

27

26

25

24

23

22

21

20

19

18

17

16

15

14

13

12

11

10

0.00%

10.00%

27-Sep-12 11-Oct-12 25-Oct-12 8-Nov-12 22-Nov-12 6-Dec-12 20-Dec-12 3-Jan-13 17-Jan-13 31-Jan-13 14-Feb-13 28-Feb-13 14-Mar-13 28-Mar-13 11-Apr-13 25-Apr-13 9-May-13 23-May-13 6-Jun-13 20-Jun-13 4-Jul-13 18-Jul-13 1-Aug-13 15-Aug-13 29-Aug-13 12-Sep-13 26-Sep-13 10-Oct-13 24-Oct-13 7-Nov-13 21-Nov-13 5-Dec-13 2-Jan-14 13-Feb-14 20-Mar-14 24-Apr-14 29-May-14 3-Jul-14

Actual Bi-Wk %

Bi-Week start
Bi-Week End
Bi-Week No.

Plan Wk %

Plan Cumm. %

Actual Cumm %

22-Sep-12
27-Sep-12

6-Oct-12
11-Oct-12

20-Oct-12
25-Oct-12

3-Nov-12
8-Nov-12

17-Nov-12
22-Nov-12

1-Dec-12
6-Dec-12

15-Dec-12
20-Dec-12

29-Dec-12
3-Jan-13

12-Jan-13
17-Jan-13

26-Jan-13
31-Jan-13

9-Feb-13
14-Feb-13

23-Feb-13
28-Feb-13

9-Mar-13
14-Mar-13

23-Mar-13
28-Mar-13

6-Apr-13
11-Apr-13

20-Apr-13
25-Apr-13

4-May-13
9-May-13

18-May-13
23-May-13

1-Jun-13
6-Jun-13

15-Jun-13
20-Jun-13

29-Jun-13
4-Jul-13

13-Jul-13
18-Jul-13

27-Jul-13
1-Aug-13

10-Aug-13
15-Aug-13

24-Aug-13
29-Aug-13

7-Sep-13
12-Sep-13

21-Sep-13
26-Sep-13

5-Oct-13
10-Oct-13

19-Oct-13
24-Oct-13

2-Nov-13
7-Nov-13

16-Nov-13
21-Nov-13

30-Nov-13
5-Dec-13

28-Dec-13
2-Jan-14

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

1.62%

1.90%

2.45%

2.74%

2.92%

2.89%

3.47%

3.50%

3.70%

3.50%

3.39%

3.84%

4.28%

3.82%

3.05%

4.74%

4.00%

3.95%

4.11%

3.57%

1.50%

4.12%

3.29%

4.10%

3.94%

3.06%

5.19%

1.05%

3.92%

0.53%

0.10%

0.96%

2.58%

4.48%

6.93%

9.67%

12.59%

15.48%

18.95%

22.45%

26.15%

29.65%

33.04%

36.88%

41.16%

44.98%

48.03%

52.77%

56.77%

60.72%

64.83%

68.40%

69.90%

74.02%

77.31%

81.41%

85.35%

88.41%

93.60%

94.65%

98.57%

99.1%

99.2%

8-Feb-14
13-Feb-14

15-Mar-14
20-Mar-14

19-Apr-14
24-Apr-14

24-May-14
29-May-14

28-Jun-14
3-Jul-14

2-Aug-14
7-Aug-14

19-Aug-14
25-Aug-14

0.37%

0.24%

0.19%

99.6%

99.8%

100.0%

Plan Bi-Wk %
Actual Bi-Wk %
Plan Cumm. %
Actual Cumm %
Week start
Week End
Week No.
Plan Wk %
Actual Wk %
Plan Cumm. %

99.2%

99.2%

99.2%

99.2%

Actual Cumm %

Page 206 of 266

99.2%

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
CONSTRUCTION VERIFICATION SHEET
______________________________________

Page 207 of 266

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

4.0

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

Complete Construction and Installation for


the Scope of Work including but not limited
to:

4.A

Pipeline

4.A1

Pipelines including but not limited to


installation, welding, testing, coating etc.

4.A1.1

Transportation of Pipes

23040.0

0.0221

36000

MT

4.A1.2

Pipe Stringing

10080.0

0.0097

36000

MT

4.A1.3

Welding

93600.0

0.0897

3000

J.No

4.A1.4

NDT

24480.0

0.0235

3000

J.No

4.A1.5

FBE External Field Joint Coating

21600.0

0.0207

3000

J.No

4.A1.6

Lowering of pipe

30240.0

0.0290

36000

MT

4.A1.7

Anchor Flange To Be Welded

576.0

0.0006

No.

4.A1.8

Pipeline Cleaning & Gauging

3360.0

0.0032

36000

MT

4.A1.9

Pipeline Water Filling

12960.0

0.0124

36000

MT

4.A1.10

Pipeline Pressurizing

4080.0

0.0039

36000

MT

4.A1.11

Pipeline Dewatering & Flushing

3240.0

0.0031

36000

MT

0.2177

4.A2

Civil Works including but not limited to:

4.A2.1

ROW

4.A2.1a

Survey and Stacking Works

5760.0

0.0055

36000

MT

4.A2.1b

Right Of Way

7200.0

0.0069

36000

MT

4.A2.1c

ROW Re-Instatement

7200.0

0.0069

36000

MT

Sub Total Weightage(ROW)

0.0193

4.A2.2

Trenching

4.A2.2a

Trench Excavation

38880.0

0.0372

36000

MT

4.A2.2b

Open Cut Crossings

42000.0

0.0402

84

No.

4.A2.2c

HDD Crossings (Highway)

66240.0

0.0635

No.

Sub Total Weightage(Trenching)

0.1410

4.A2.3

Sand Bedding, Berm Construction

4.A2.3a

Pre-Padding

20160.0

0.0193

36000

MT

4.A2.3b

Post Padding

15840.0

0.0152

36000

MT

4.A2.3c

Final Backfilling

5760.0

0.0055

36000

MT

Page 208 of 266

WEIGHTAGE ACTUAL

UNIT

Construction and
Installation

Sub Total Weightage(Pipelines including but


not limited to installation, welding, testing,
coating etc. )

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

Excavation For Anchor Blocks At Refinery &


BSV-3

1300.0

0.0012

Each

4.A2.3e

PC For Anchor Blocks At Refinery & BSV-3

1600.0

0.0015

Each

4.A2.3f

RC For Anchor Blocks At Refinery & BSV-3

5920.0

0.0057

Each

4.A2.3g

Backfilling For Anchor Blocks At Refinery &


BSV-3

108.0

0.0001

Each

4.A2.3h

Pipeline Post Markers

1920.0

0.0018

36000

MT

4.A2.3i

Punch List

8640.0

0.0083

Lot

Lot

4.A3

Tie-ins

4.A3.1

Tie-Ins Of Strings

0.0587

21600.0

Sub Total Weightage(Tie-ins)

4.A4

0.0207

0.0207

Cathodic Protection System

4.A4.1 Temporary Cathodic Protection


4.A4.1a

Cables To Be Welded By Thermite

7200.0

0.0069

18

Connections

4.A4.1b

Anode For Temporary CP

7200.0

0.0069

18

No.

4.A4.2 Permanent Cathodic Protection


4.A4.2a

Test Post Distribution & Erection

800.0

0.0008

25

No.

4.A4.2b

Deep Well (25 M)

2240.0

0.0021

No.

4.A4.2c

Anode For Permanent CP

800.0

0.0008

No.

4.A4.2d

Rectifier To Be Installed

560.0

0.0005

No.

4.A4.2e

Cables To Be Connected

1120.0

0.0011

1500

MT

4.A4.2f

CP System to Be Checked & Tested

1120.0

0.0011

Lot

Sub Total Weightage(Cathodic Protection


System)

4.B

Station Works at Refinery and


BSV3

4.B1

Mechanical and Piping

WEIGHTAGE ACTUAL

UNIT

4.A2.3d

Sub Total Weightage(Sand Bedding, Berm


Construction)

ETROJET

0.0202

4.B1.1 General
4.B1.1a

A/G Delivery Pipeline From The Pumps To The


Launcher

17700.0

0.0170

530

M/L

4.B1.1b

A/G Suction Pipeline From The Header To The


Pumps

5545.0

0.0053

170

M/L

4.B1.2 Pumps Area


4.B1.2a

Piping Fabrication

49224.0

0.0472

10800

D.I

4.B1.2b

Sand Blasting & Panting

11040.0

0.0106

4000

M2

4.B1.2c

Piping & Pumps Erection

47327.0

0.0453

7200

D.I

Page 209 of 266

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

Loops to be Water Filled

4320.0

0.0041

Lot

4.B1.2e

Loops to be Pressurized

6120.0

0.0059

Lot

4.B1.2f

Loops to be Dewatered & Flushed

3240.0

0.0031

Lot

4.B1.3 Launcher Area


4.B1.3a

Piping Fabrication

8739.0

0.0084

900

D.I

4.B1.3b

Sand Blasting & Panting

3545.0

0.0034

625

M2

4.B1.3c

Launcher & Piping Erection

11400.0

0.0109

600

D.I

4.B1.4 BSV-3
4.B1.4a

Installation of Motor Operated Valve

7800.0

0.0075

No.

4.B1.4b

Tie-In To The Existing Inside BSV-3

2600.0

0.0025

Lot

4.B2

0.1711

Instrumentation and Control

4.B2.1 Substation 6003


4.B2.1a

Laying of Cables

2100.0

0.0020

2100

4.B2.1b

Installation Of Junction Boxes

2100.0

0.0020

200

4.B2.1c

Termination For Substation 6003

2100.0

0.0020

150

4.B2.2 Pumps Area


4.B2.2a

Laying Of Cables

1680.0

0.0016

5555

M/L

4.B2.2b

Installation Of Flow Transmitter

1680.0

0.0016

No.

4.B2.2c

Installation Of Pressure Gauges With Fittings

1680.0

0.0016

12

No.

4.B2.2d

Installation Of Pressure Transmitters With


Tubes & Fittings

1680.0

0.0016

10

No.

4.B2.2e

Installation Of Junction Boxes For Pump Area

1680.0

0.0016

No.

4.B2.2f

Installation Of Gas Detectors For Pump Area

1680.0

0.0016

No.

4.B2.2g

Installation Of Manual Call Point For Pump Area

1680.0

0.0016

No.

4.B2.2h

Termination For Pump Area

1680.0

0.0016

Lot

4.B2.3 Launcher Area


4.B2.3a

Laying Of Cables

1260.0

0.0012

13775

4.B2.3b

Installation of Pig Signaller

1260.0

0.0012

No.

4.B2.3c

Installation Of Pressure Gauges With Fittings

1260.0

0.0012

No.

4.B2.3d

Installation Of Pressure Transmitters With


Tubes & Fittings

1260.0

0.0012

No.

4.B2.3e

Installation Of Junction Boxes For Launcher

1260.0

0.0012

No.

Page 210 of 266

WEIGHTAGE ACTUAL

UNIT

4.B1.2d

Sub Total Weightage(Mechanical & Piping)

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

Installation Of Gas Detectors For Launcher

1260.0

0.0012

No.

4.B2.3g

Installation Of Manual Call Point For Launcher

1260.0

0.0012

No.

4.B2.3h

Termination For Launcher

1260.0

0.0012

Lot

4.B2.4 BSV-3
4.B2.4a

Laying Of Cables

5100.0

0.0049

Lot

4.B2.4b

Installation Of Pressure Transmitters With


Tubes & Fittings

2550.0

0.0024

Lot

4.B2.4c

Termination

7950.0

0.0076

Lot

4.B3

0.0435

Electrical

4.B3.1 Substation 6003


4.B3.1a

Modification Of Existing 11 KV Switchgear

6300.0

0.0060

No.

4.B3.1b

Modification Of Existing 3.3 KV Switchgear

6300.0

0.0060

No.

4.B3.1c

Modification Of Existing 415 V Switchgear

6300.0

0.0060

No.

4.B3.2 Pumps Area


4.B3.2a

Lighting System For Pump Area

1680.0

0.0016

Lot

4.B3.2b

Power Socket For Pump Area

1680.0

0.0016

Lot

4.B3.2c

Low Voltage Cable Laying For Pump Area

1680.0

0.0016

524

M/L

4.B3.2d

High Voltage Cable Laying For Pump Area

1680.0

0.0016

205

M/L

4.B3.2e

Installation Of Distribution Boards For Pump


Area

1680.0

0.0016

Lot

4.B3.2f

Termination For Pump Area

2520.0

0.0024

Lot

4.B3.3 Launcher Area


4.B3.3a

Lighting System For The Launcher Area

1260.0

0.0012

Lot

4.B3.3b

Power Socket For The Launcher Area

1260.0

0.0012

Lot

4.B3.3c

Low Voltage Cable Laying For The Launcher


Area

1260.0

0.0012

120

M/L

4.B3.3d

High Voltage Cable Laying For The Launcher


Area

1260.0

0.0012

260

M/L

4.B3.3e

Installation Of Distribution Boards For The


Launcher Area

1260.0

0.0012

Lot

4.B3.3f

Termination For The Launcher Area

2100.0

0.0020

Lot

4.B3.4 BSV-3
4.B3.4a

Installation of Electrical Permanent Source

5100.0

0.0049

Lot

4.B3.4b

Electrical Connection To MOV

2550.0

0.0024

125

4.B3.4c

Diesel Generator to be Removed

7950.0

0.0076

No.

Page 211 of 266

WEIGHTAGE ACTUAL

UNIT

4.B2.3f

Sub Total Weightage(Instrumentation &


Control)

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

Sub Total Weightage( Electrical )

4.B5

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

0.0516

Structural and Architectural

4.B5.1a

Excavation For (7) Culverts

4550.0

0.0044

515

Cu.M

4.B5.1b

PC For (7) Culverts

11200.0

0.0107

298

Cu.M

4.B5.1c

RC For (7) Culverts

41440.0

0.0397

210

Cu.M

4.B5.1d

Backfilling For (7) Culverts

2800.0

0.0027

No.

4.B5.2 N0 Off (220) Sleepers


4.B5.2a

Pre-Cast (220) Sleepers

15750.0

0.0151

220

No.

4.B5.2b

Erection Of (220) Sleepers

8250.0

0.0079

220

No.

4.B5.3.1a Excavation For (6) Pump Fondations

3900.0

0.0037

No.

4.B5.3.1b PC For (6) Pump Fondations

6780.0

0.0065

No.

4.B5.3.1c RC For (6) Pump Fondations

21600.0

0.0207

No.

4.B5.3.1d Backfilling For (6) Pump Fondations

1200.0

0.0011

No.

4.B5.3.2a Excavation For E&I Duct Bank

650.0

0.0006

141

Cu.M

4.B5.3.2b PC For E&I Duct Bank

1130.0

0.0011

114

Cu.M

4.B5.3.2c RC For E&I Duct Bank

3600.0

0.0034

62

Cu.M

4.B5.3.2d Backfilling For E&I Duct Bank

200.0

0.0002

Lot

4.B5.3.3a Steel Structure Fabrication For The Pump Shed

19680.0

0.0189

165

Ton

4.B5.3.3b Excavation For For The Pump Shed

1300.0

0.0012

95

Cu.M

4.B5.3.3c PC For For The Pump Shed

2260.0

0.0022

95

Cu.M

4.B5.3.3d RC For For The Pump Shed

7200.0

0.0069

73

Cu.M

4.B5.3.3e Backfilling For The Pump Shed

400.0

0.0004

Lot

4.B5.3.3f Steel Structure Erection For The Pump Shed

9840.0

0.0094

165

Ton

4920.0

0.0047

2850

Sq.M

4950.0

0.0047

188

Cu.M

4.B5.3 Pumps Area


4.B5.3.1 Pump Foundations

4.B5.3.2 E&I Duct Bank In Pump Area

4.B5.3.3 Pump Shed

Corrugated Sheets Cladding For The Pump


Shed

4.B5.3.3h Paving For The Pump Shed

4.B5.4 Launcher Area

Page 212 of 266

WEIGHTAGE ACTUAL

UNIT

4.B5.1 No. OFF (7) Culverts

4.B5.3.3g

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

Excavation For Launcher Station

780.0

0.0007

27

Cu.M

4.B5.4b

PC For Launcher Station

2000.0

0.0019

27

Cu.M

4.B5.4c

RC For Launcher Station

6660.0

0.0064

25

Cu.M

4.B5.4d

Backfilling & Re-Instatement For Launcher


Station

270.0

0.0003

Lot

4.B5.4e

Fence For Launcher Station

4000.0

0.0038

Lot

4.B5.4f

Paving For Launcher Station

1152.0

0.0011

50

Cu.M

4.B5.5 Roads
4.B5.5a

Roads For Launcher Area

4320.0

0.0041

677

Sq.M

4.B5.5b

Roads For Pump Area

1728.0

0.0017

19

Sq.M

4.B5.5b

Roads For SER 12

1728.0

0.0017

67

Sq.M

4.B5.6 BSV-3
4.B5.6a

Excavation In BSV-3

1200.0

0.0011

21

Cu.M

4.B5.6b

Plain Concrete In BSV-3

1200.0

0.0011

21

Cu.M

4.B5.6c

Re-Inforced Concrete In BSV-3

6000.0

0.0057

37

Cu.M

4.B5.6d

Fence In BSV-3

6000.0

0.0057

60

M/L

4.B9

Insulation & Fireproofing

4.B9

Insulation & Fireproofing

4.B11

Extension of SER-12

0.2018

9900.0

0.0095

Lot

4.B11.1a Demolition & Excavation

1120.0

0.0011

28

Cu.M

4.B11.1b P.C (Foundation)

1200.0

0.0011

Sq.M

4.B11.1c R.C (Foundation)

2800.0

0.0027

40

Sq.M

4.B11.1d Insulation (Foundation)

720.0

0.0007

Lot

4.B11.1e BackFilling (Foundation)

280.0

0.0003

Lot

4.B11.1f R.C (Columns)

2160.0

0.0021

Cu.M

4.B11.1g R.C (Slab& Beams)

4480.0

0.0043

40

Cu.M

4.B11.1h External Finishing

12000.0

0.0115

Lot

4.B11.1i Internal Finishing

12000.0

0.0115

Lot

1020.0

0.0010

Lot

4.B11.1 Civil Works

4.B11.2 Electrical Works


4.B11.2a Lighting Fixtures, Sockets For Rooms

Page 213 of 266

WEIGHTAGE ACTUAL

UNIT

4.B5.4a

Sub Total Weightage(Structural and


Architectural )

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

PREVIOUS
MONTH

1020.0

0.0010

Lot

4.B11.2c UPS System 110 V, 1 ph, 7 KVA

1020.0

0.0010

Set

4.B11.2d Termination

1020.0

0.0010

Lot

4.B11.3a Laying of Cables

1020.0

0.0010

250

M/L

4.B11.3b DCS System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3c DCS Marchaling Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3d ESD System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3e F&G System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3f Termination For SER-12

1020.0

0.0010

Lot

4.B11.3 Instrumentation Works

Total Weightage Of The Project

0.0450

1043762.0

1.0000

Page 214 of 266

WEIGHTAGE ACTUAL

UNIT

4.B11.2b Low Voltage Cables

Sub Total Weightage(Extension of SER-12)

ETROJET

THIS MONTH AS ON DATE

PREVIOUS
MONTH

THIS MONTH AS ON DATE

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
MARCHING CHART
______________________________________

Page 215 of 266

Final Backfilling

Cleaning ang Gauging

Water Fill & Stabilize

Dewatering & Flushing


P

A
Page 216 of 266

30.7
31.8
32.9
34.1
35.2
36.0

28.9
30.1
31.2
32.3
33.4
34.6

A
36.0

36.0

34.0

32.9

31.8

30.7

36.0

34.6

33.5

32.4

31.3

30.2

29.1

28.1

27.0

25.9

24.8

23.7

22.6

21.5

20.4

19.3

18.2

17.1

16.1

15.0

13.9

12.8

11.7

10.6

9.5

8.4

7.3

36.0

34.4

33.4

32.3

31.2

30.1

29.0

27.9

26.8

25.7

24.6

23.5

22.4

21.4

20.3

19.2

18.1

17.0

15.9

14.8

13.7

12.6

11.5

10.4

9.4

8.3

7.2

4-Apr-13
11-Apr-13
18-Apr-13
25-Apr-13

32.3 28/Mar/13
33.4 4/Apr/13
34.4 11/Apr/13
36.0 18/Apr/13

27/Jun/13

20/Jun/13

13/Jun/13

6/Jun/13

30/May/13

23/May/13

16/May/13

9/May/13

2/May/13

31-Oct-13

3/Oct/13
10/Oct/13
17/Oct/13
24/Oct/13
31/Oct/13
7/Nov/13

23.4
26.6

18.9
36.0

28/Nov/13

28-Nov-13

21-Nov-13

Review & Approval

21/Nov/13

19-Jul-12

14-Nov-13

Marching Chart

7-Nov-13

GC 11106200

14/Nov/13

24-Oct-13

26/Sep/13
20.1

19-Sep-13

Issued For

36.0

17-Oct-13

19/Sep/13
16.8

12-Sep-13

Date

6.9

10-Oct-13

12/Sep/13
13.6

5-Sep-13

Document Description

29.9

3-Oct-13

5/Sep/13
10.3

29-Aug-13

Contract Number

0.0

26-Sep-13

29/Aug/13
7.0

22-Aug-13

15-Aug-13

22/Aug/13

8-Aug-13

1-Aug-13

3.7

A
15/Aug/13

0.5

1/Aug/13

25-Jul-13

18-Jul-13

11-Jul-13

4-Jul-13

27-Jun-13

20-Jun-13

13-Jun-13

6-Jun-13

30-May-13

23-May-13

16-May-13

9-May-13

2-May-13

28-Mar-13
31.2 21/Mar/13

25/Apr/13

21-Mar-13

14-Mar-13

7-Mar-13

28-Feb-13

21-Feb-13

14-Feb-13

7-Feb-13

31-Jan-13

24-Jan-13

17-Jan-13

10-Jan-13

3-Jan-13

27-Dec-12

20-Dec-12

13-Dec-12

6-Dec-12

29-Nov-12

22-Nov-12

15-Nov-12

8-Nov-12

1-Nov-12

25-Oct-12

30.1 14/Mar/13

29.0 7/Mar/13

27.9 28/Feb/13

26.8 21/Feb/13

25.7 14/Feb/13

24.6 7/Feb/13

23.5 31/Jan/13

22.4 24/Jan/13

21.4 17/Jan/13

20.3 10/Jan/13

19.2 3/Jan/13

18.1 27/Dec/12

17.0 20/Dec/12

15.9 13/Dec/12

14.8 6/Dec/12

13.7 29/Nov/12

12.6 22/Nov/12

11.5 15/Nov/12

10.4 8/Nov/12

9.4 1/Nov/12

8.3 25/Oct/12

7.2 18/Oct/12

6.1 11/Oct/12

25/Jul/13

36.0

A
18/Jul/13

36.0

34.1

20.6

36.0

34.3

33.2

A
11/Jul/13

36.0

34.3

33.2

32.1

34.0

32.9

31.8

30.7

29.6

11.6

36.0

34.6

33.5

32.4

31.3

33.0

31.9

30.9

29.8

28.7

29.6

28.5

27.4

26.3

25.2

24.2

23.1

22.0

20.9

19.8

18.7

17.6

16.5

15.4

14.3

13.2

12.2

11.1

10.0

8.9

7.8

6.7

A
4/Jul/13

36.0

36.0

34.9

33.8

32.6

31.5

32.1

31.0

29.9

28.8

27.7

28.5

27.4

26.3

25.2

24.2

23.1

22.0

20.9

19.8

18.7

17.6

16.5

15.4

14.3

13.2

12.2

11.1

10.0

8.9

7.8

6.7

5.6

6.2

6.1

2.6

36.0

34.0

32.9

31.8

30.7

29.6

31.0

29.9

28.8

27.7

26.6

27.6

26.5

25.4

24.3

23.2

22.1

21.0

19.9

18.9

17.8

16.7

15.6

14.5

13.4

12.3

11.2

10.1

9.0

7.9

6.9

5.8

4.7

5.6

5.1

5.0

18-Oct-12

5.0 4/Oct/12

30.2

29.1

28.1

27.0

25.9

26.6

25.6

24.5

23.4

22.3

21.2

20.1

19.0

17.9

16.8

15.7

14.6

13.6

12.5

11.4

10.3

9.2

8.1

7.0

5.9

4.8

3.7

4.5

4.5

4.1

3.9

11-Oct-12

3.9 27/Sep/12

30.4

29.3

28.1

27.0

25.9

25.6

24.5

23.4

22.3

21.2

20.1

19.0

17.9

16.8

15.7

14.6

13.6

12.5

11.4

10.3

9.2

8.1

7.0

5.9

4.8

3.7

2.6

3.6

3.4

3.4

3.0

2.8

4-Oct-12

2.8 20/Sep/12

12

28.5

27.4

26.3

25.2

24.2

24.8

23.7

22.6

21.5

20.4

19.3

18.2

17.1

16.1

15.0

13.9

12.8

11.7

10.6

9.5

8.4

7.3

6.2

5.1

4.1

3.0

1.9

2.6

2.5

2.3

2.3

1.9

1.7

27-Sep-12

1.7 13/Sep/12

16

8/Aug/13

P
24.8

23.6

22.5

21.4

20.3

19.1

18.0

16.9

15.8

14.6

13.5

12.4

11.3

10.1

9.0

7.9

6.8

5.6

4.5

3.4

2.3

1.1

1.6

1.6

1.4

1.2

1.2

0.8

20-Sep-12

0.6 6/Sep/12

20

0.0

P
23.1

22.0

20.9

19.8

18.7

17.6

16.5

15.4

14.3

13.2

12.2

11.1

10.0

8.9

7.8

6.7

5.6

4.5

3.4

2.3

1.2

0.2

0.8

0.5

0.5

0.3

0.2

0.2

0.6

13-Sep-12

6-Sep-12

24

36.0

29.6

27.8

19.4

17.7

28.4

18.3

16.6

26.7

17.2

15.4

27.3

16.1

14.3

25.6

14.9

13.2

26.2

13.8

12.1

24.4

12.7

10.9

25.1

11.6

9.8

23.3

10.4

8.7

23.9

9.3

7.6

22.2

8.2

6.4

22.8

7.1

5.3

21.1

5.9

4.2

21.7

4.8

3.1

19.9

3.7

1.9

20.6

2.6

0.8

18.8

1.4

0.5

A
0.3

0.0

Post Padding
P

0.0

Tie-Ins of Strings
P

0.0

Lowering
P

0.0

Pre-Padding
P

0.0

FBE Joint Coating


P

0.0

NDT
P

0.0

Welding of Pipes
P

0.0

Pipe Stringing
P

0.0

Pipe Transportation
P

0.0

Trench Excavation
P

0.0

Right Of Way
P

0.0

Survey & Stacking


0.0 30/Aug/12

DESCRIPTION/
DATE

0.0

0
30-Aug-12

EPIC For New 16" - 36 Km Jet A1 Fuel Pipeline From QP Refinery To BSV-3

ETROJET

36

32

28

Survey & Stacking

Right Of Way

Trench Excavation

Pipe Transportation

Pipe Stringing

Welding of Pipes

NDT

FBE Joint Coating

Pre-Padding

Lowering

Tie-Ins of Strings

Post Padding

Final Backfilling

Cleaning ang Gauging

Water Fill & Stabilize

Dewatering & Flushing

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
CASH FLOW CURVE AND TABLE
______________________________________

Page 217 of 266

Cash Flow (Commulative / Per Month)

Page 218 of 266

Cash Flow Per Month (QR)

25-Aug-14

31-Jul-14

30-Jun-14

31-May-14

30-Apr-14

31-Mar-14

28-Feb-14

31-Jan-14

31-Dec-13

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

30-Nov-13

31-Dec-12

31-Oct-13

30-Nov-12

30-Sep-13

31-Oct-12

31-Aug-13

30-Sep-12

31-Jul-13

31-Aug-12

30-Jun-13

31-Jul-12

Cumulative Cash Flow (QR)

31-May-13

30-Jun-12

30-Apr-13

31-May-12

31-Mar-13

30-Apr-12

28-Feb-13

31-Mar-12

31-Jan-13

29-Feb-12

120000000
115000000
110000000
105000000
100000000
95000000
90000000
85000000
80000000
75000000
70000000
65000000
60000000
55000000
50000000
45000000
40000000
35000000
30000000
25000000
20000000
15000000
10000000
5000000
0

16"-36 Km Jet A1 Fuel PL Project


Cumulative / Per Month Cash Flow
ETROJET

Month No.

Date

Cumulative Cash
Flow (QR)

Cash Flow Per


Month (QR)

Percentage Per
Month

29-Feb-12

0.00%

31-Mar-12

2630

2630

0.00%

30-Apr-12

62375

59745

0.05%

31-May-12

208167

145792

0.12%

30-Jun-12

574901

366734

0.31%

31-Jul-12

3503361

2928460

2.50%

31-Aug-12

8300094

4796733

4.10%

30-Sep-12

15012456

6712362

5.74%

31-Oct-12

19637567

4625111

3.95%

30-Nov-12

27040797

7403230

6.33%

10

31-Dec-12

33658179

6617381

5.66%

11

31-Jan-13

39145613

5487434

4.69%

12

28-Feb-13

44596642

5451029

4.66%

13

31-Mar-13

50307596

5710954

4.88%

14

30-Apr-13

60164963

9857367

8.43%

15

31-May-13

70139876

9974913

8.53%

16

30-Jun-13

82212930

12073055

10.32%

17

31-Jul-13

90891072

8678142

7.42%

18

31-Aug-13

98835036

7943964

6.79%

19

30-Sep-13

105122710

6287674

5.37%

20

31-Oct-13

111811637

6688926

5.72%

21

30-Nov-13

112455893

644256

0.55%

22

31-Dec-13

112752876

296983

0.25%

23

31-Jan-14

113527493

774617

0.66%

24

28-Feb-14

114406438

878946

0.75%

25

31-Mar-14

114960396

553957

0.47%

26

30-Apr-14

115318314

357918

0.31%

27

31-May-14

115516507

198194

0.17%

28

30-Jun-14

116166002

649494

0.56%

29

31-Jul-14

116928613

762612

0.65%

30

25-Aug-14

116988359

59746

0.05%

Page 219 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
INVOICING SYSTEM
______________________________________

Page 220 of 266

PETROJET
The Petroleum Projects and
Technical Consultations Co.
One of the Egyptian General Petroleum
Corporation Companies

abcdef

INTERIM INVOICE
Part 1
1.1) Invoice Number :

1.2) Date : May 31,2012

1.3)

Contract Number : GC11106200

1.4)

Period of Work Done / Invoiced : From : Feb 26,2012

1.5)

Title :

To : May 31,2012

EPIC For 16 Jet A1 Fuel Pipeline

_________________________________________________________________________________
Part 2
2.1) Original Contract Value
2.2)

Variations,

2.3)

Current Contract Value

QR

116,988,359,00
0,00
116,988,359,00

_________________________________________________________________________________
Part 3
3.1) Cumulative value of work done

QR

00,00

3.2)

Less : Value of work done up to last invoice

0,00

3.3)

Balance advance to be recovered as of date

00,00

_________________________________________________________________________________
Part 4
4.1) Gross Value of work done as per this invoice

QR

00,00

4.2)

Less : Advance

0,00

4.3)

Less: Retention as per this invoice

00,00

4.4)

Less: Liquidated Damages as per this invoice

00,00

4.5)

Net amount claimed as per this invoice

00,00

4.6)

Amount in Words :

_________________________________________________________________________________
Part 5
5.1) Authorized Signature
5.2)

Name of Authorized Signatory : Hany Badie

5.3)

Designation : General Projects Manager

5.4)

Company Seal

This invoice should be supported by a statement showing progress in work as per schedule of
prices certified by QP representative for the job. Invoice without this certification is liable to be
rejected by Qatar Petroleum.
Page 221 of 266

LUMP SUM PROGRESS BILLING SUMMARY


CONTRACT NO. : GC11106200

REPORT NO. :

JOB TITLE : EPIC FOR 16" JET A1 FUEL PIPELINE

PERIOD :

CURRENCY : QR

PROGRESS CUT OFF DATE :


PERCENT COMPLETE

ITEM NO.

DESCRIPTION OF WORK INCLUDES


TOTAL PROJECT LUMP SUM

LUMP SUM
VALUE

INVOICE AMOUNTS

PERCENTAGE

This Period

Previous

To Date

This Period

Previous

To Date

PRELIMINARY AND GENERAL


MATTERS (SCHEDULE 1)

6912860.00

5.91%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

DESIGN AND ENGINEERING


(SCHEDULE 2)

3757524.00

3.21%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

PROCUREMENT (SCHEDULE 3)

46385347.66

39.65%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

CONSTRUCTION (SCHEDULE 4)

52832810.46

45.16%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

PRE-COMMISSIONING &
COMMISSIONING (SCHEDULE 5)

3077540.58

2.63%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

SPARES (SCHEDULE 6)

669488.81

0.57%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

OPTIONAL ITEMS (SCHEDULE 7)

3202787.00

2.74%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

PROVISIONAL (SCHEDULE 8)

150000.00

0.13%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

116988359

100.00%

0.000000%

0.000000%

0.000000%

0.00

0.00

0.00

TOTAL VALUE FOR OVERALL PROJECT LUMP SUM

PETROJET COMPANY

QATAR PETROLEUM

PRPARED BY : MAMDOUH SALAH

PERCENTAGE PROGRESS AMOUNTS APPROVED AND

REVIEWED BY : MOHAMMED MAMDOUH

REVIEWED BY

APPROVED BY :

APPROVED BY

ARITHMATIC EXTENSIONS CHECKED.

NAME

HANY BADIE

NAME

JOB TITLE

JOB TITLE :

DATE

DATE

COMPANY REVIEW AND APPROVAL OF THE PRODUCT OF AGREED PROGRESS AND LUMPSUM VALUES IN
THIS SUPPORTING DOCUMENTATION DOES NOT SIGNIFY APPROVAL OF THIS INVOICE .

Page 222 of 266

Item

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

PRELIMINARIES

The following costs are for those preliminaries required


for the complete execution of the whole of the WORK

CONTRACT Particulars
For convenience, only those provisions considered to have
an obvious financial effect are set out below and against
each provision, the price is inserted for compliance:

Article 11.7 : Performance Bond

Item

150,011.00

Appendix - C : Insurance Specific to the Contract

Item

341,322.00

Appendix - C : Insurance for Free Issue Materials

Item

162,060.00

QR.

653,393.00

TOTAL OF PRELIMINARIES & CONTRACT


PARTICULARS

Page 223 of 266

Item

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

GENERAL MATTERS

Mobilisation and Demobilisation

Mobilisation of all supervision, labour, plant, materials and


equipment necessary for the proper execution of the WORK.

Item

1,637,958

De-mobilisation of all supervision, labour, plant, materials


and equipment necessary for the proper execution of the
WORK.

Item

691,403

WORKSITE Facilities and Utilities


Provision, maintenance and subsequently removal of all
temporary office, site facilities and utilities at WORKSITE for
CONTRACTOR and SUBCONTRACTOR personnel as
required for the COMPLETION of the WORK.

Item

286,250

Provision of project planning/management, QA/QC activities,


proprietary design softwares, liasion and all office overhead
necessary for the proper execution of the WORK.

Item

1,002,484

Provision of all temporary works as required for the


COMPLETION of the WORK.

Item

806,180

Provision of compliance with CONTRACT terms and


conditions regarding obtaining QP permit to WORK, entry
permit, ID cards, Inductions, Safetywear etc.

Item

398,340

Provision of progress and safety meeting with QP.

Item

317,115

Provision of Asset Capitalization Schedule

Item

33,116

Compilation and entry of required data for all supplied items


in QP's computerised Maintenance Management System
(CMMS)

Item

20,000

Supply and erect 2 Nos. Sign Board as defined in Clause


no.8.18

Item

7,200

Provision of Cost Breakdown details as per Scope of Work


Appendix A and E

Item

24,126

Provision for Digital Data for GIS as described in the


CONTRACT.

Item

30,000

Provision of Project Dossiers includung As-Built Drawings,


Construction Data Books, and start -up, Operation and
Maintenance Manuals as described in the CONTRACT.

Item

50,000

Provision of co-ordination with Vendors and


SUBCONTRACTORS

Item

179,045

Office facilities for QP PERSONNEL as detailed in Clause


3.7.2 of Appendix A

Item

776,250

TOTAL OF GENERAL MATTERS

QR.

6,259,467.00

Page 224 of 266

SCHEDULE OF PRICES 1.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

Collection

Total of Preliminaries & Contract Particulars

Item

653,393.00

Total of General Matters

Item

6,259,467.00

QR.

6,912,860

TOTAL OF SCHEDULE 1.0

Page 225 of 266

SCHEDULE OF PRICES 2.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Carry out detailed site surveys and document retrieval

Item

103,245

Design Basis Memorandum (DBM)

Item

107,938

HAZID Study as per clause 4.2.2 of SOW - App.A.

Item

18,771

HAZOP Study as per clause 4.2.3 of SOW - App.A.

Item

84,473

SIL Study as per clause 4.2.6 of SOW - App.A.

Item

39,890

Carry out Project Risk Assessment as per cl. 3.1.16 of SOW App.A.

Item

9,386

Topographic Survey

Item

9,386

Pipeline Route Surveys

Item

37,544

Geotechnical Investigations

Item

18,771

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

Complete design and detailed engineering for the Scope


of Work including but not limited to:
J

Process

Item

337,893

Mechanical & Piping

Item

478,682

Pipelines

Item

450,524

Instrumentation and Control

Item

455,217

Electrical

Item

375,437

Loss Prevention

Item

103,245

Civil, Structural and Architectural

Item

305,042

Building Services

Item

225,262

Telecommunication

Item

25,077

Coating, Insulation & Fireproofing

Item

46,199

Environmental Control

Item

60,000

Corrosion and Cathodic Protection Design

Item

23,465

Rotating Equipment / Mechanical Handling

Item

277,824

Interfaces with existing facilities/systems

Item

164,253

QR.

3,757,524

TOTAL OF SCHEDULE 2.0

Page 226 of 266

SCHEDULE OF PRICES 3.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

Procurement for the complete Scope of Work including


but not limited to:
A

Mechanical Items

A1

Pig Launcher at QP Refinery

Item

517,498

A2

EOT Crane

Item

815,000

A3

Jib Cranes

Item

221,785

Pumps

B1

Mainline Pumps

Item

10,150,000

B2

Booster Pumps

Item

5,645,000

Electrical

C1

Switchgear Panels

Item

4,340,841

C2

Distribution Boards and Local Control Panels

Item

111,086

C3

UPS System

Item

422,708

C4

Local Control Panel

Item

100,379

C5

Lighting Fixtures & Lighting Poles

Item

203,462

C6

Cables

Item

511,515

Valves

D1

Control Valve & Auto Recirculation Valve

Item

977,651

D2

ESD Valve with all accessories

Item

205,000

D3

Isolation Valves at Refinery

Item

170,000

D4

MOV (Motor operated Valves)

Item

1,967,500

D5

All other misc. types of valves

Item

1,020,000

Items for Instrumentation works, DCS, ESD and F&G


systems

E1

Instruments

E1.1

Coriollis Flowmeter, Hand held communicator etc.

Item

1,155,406

E1.2

Item

275,520

Item

34,958

E2

Pressure Transmitters, Differential Pressure Transmitters,


Pressure Gauges
Temperature Elements, Temperature Transmitters,
Thermowell
Junction Boxes

Item

462,162

E3

Instrument & Control Cables

Item

1,603,703

E4

Fire and Smoke detectors

Item

331,809

E5

SCADA, DCS, ESD and F & G System

Item

6,014,629

E6

Instrument Cable Accessories, Tubing


fittings & Miscellaneous erection materials
Telecom and Telemetry Equipments

Item

1,858,213

Item

118,503

Corrosion monitoring and inhibitor injection facilities

Item

76,000

Item

801,988

CP System incl. Anode Beds, Cables, TR Units, Jointing


Kits CP Test Post etc
Leak Detection System

Item

1,185,032

Any Other Items not specifically mentioned herein above


Item

5,088,000

E1.3

i) Process Piping, fittingetc at Refinary


TOTAL OF SCHEDULE 3.0

QR.

46,385,348

Page 227 of 266

SCHEDULE OF PRICES 4.0

Item

4.0

APPENDIX B PART II

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

Construction and Installation


Complete Construction and Installation for the Scope of
Work including but not limited to:

4.A

Pipeline
Pipelines including but not limited to installation, welding,
testing, coating etc.

Item

9,088,007.00

4.A.2.1 ROW

Item

1,009,779.00

4.A.2.2 Trenching

Item

5,048,893.00

4.A.1

4.2.3

Sand Bedding ,Berm Construction

Item

4,260,490.00

4.A.3

Tie-Ins

Item

1,075,779.00

4.A.4

Cathodic Protection System

Item

1,748,742.00

4.A.5

Pipeline Caliper Survey

Item

540,580.00

4.B

Station Works at Refinery and BSV3

4.B.1

Mechanical & Piping including but not limited to installation,


welding, testing, coating etc.

Item

4,695,500.00

4.B.2

Instrumentation and Control

Item

1,572,285.00

4.B.3

Electrical

Item

1,457,285.00

4.B.4

Loss Prevention

Item

100,000.00

4.B.5

Structural and Architectural

Item

11,423,351.00

4.B.6

Building Services

Item

114,430.00

4.B.7

Telecommunication

Item

1,165,828.00

4.B.8

Coating

Item

850,000.00

4.B.9

Insulation & Fireproofing

Item

4,613,488.00

4.B.10

Security System incl. CCTV Cameras, PA System, ESecurity

Item

203,825.00

Item

318,500.00

Item

3,546,048.00

QR.

52,832,810.00

Extension of SER-12 including installation of Air-coditioning


4.B.11 unit, F&G systems and all other woks in line with existing
SER-12.
4.C

Interfaces with existing facilities/systems

TOTAL OF SCHEDULE 4.0

Page 228 of 266

SCHEDULE OF PRICES 5.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

Pre- Commissioning & Commissioning

Complete Pre-Commissioning & Commissioning for the


scope of work incl. but not limited to:-

A1

Pipeline

Item

1,259,981

A2

Pumps

Item

200,000

A3

SCADA & PLC System

Item

797,000

A4

Telecommunication & FOC System

Item

155,500

A5

Security System

Item

108,000

A6

Cathodic Protection System

Item

170,220

A7

Electrical & Instrumentation System

Item

321,840

72 Hrs Performance Test

Item

65,000

TOTAL OF SCHEDULE 5.0

QR.

3,077,540.58

Page 229 of 266

SCHEDULE OF PRICES 6.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Spare Parts for Pre commissioning and Commissioning

Item

182,429

Spare Parts for First Year Operation

Item

457,286

Provide Completed SPIR Forms including list of spares for


2nd year operation.

Item

29,774

QR.

669,489

TOTAL OF SCHEDULE 6.0

Page 230 of 266

Up to Last
Month Invoice

For This
Invoice

Total Invoice

% of
Invoice

SCHEDULE OF PRICES 7.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

ITEMS SUBJECT TO DELETION AT QP'S DISCRETION

Baseline Survey. Ref clause no. 12 of SOW, App.A

Item

648,696

Item

375,177

Facilities to QP during Detail Design (Outside Qatar)


C
Facilities to QP during Detail Design (Inside Qatar)

All works related to Option I of Cl.6.14.3.6 of App.A for


permanent power supply from Karahmaa to BSV-3 by pole
mounted transformer.

Item

256,550

All works related to Option II of Cl.6.14.3.6 of App.A for


permanent power supply from Karahmaa to BSV-3 by ground
mounted transformer.

Item

905,924

Training to Qatari Engineers as per clause nos. 3.3.12 and


14.2.3 of App. A

Item

75,910

Providing Training for operations & maintenance personnel


separately for each sub-system as per clause nos. 3.3.12
and 14.2.3 of App. A.

Item

227,730

Laying of new FOC from QP Refinery to BSV3 as per clause


6.18.2 of App. A.

Item

712,800

TOTAL OF SCHEDULE 7.0

QR.

3,202,787.00

Page 231 of 266

SCHEDULE OF PRICES 8.0

Item

APPENDIX B PART II

Description

Unit

Amount Q.R

International Telephone and fax charges for calls made by


A TB6 QP employees for official purposes as detailed in clause
3.8.4.5 of Appendix A.

Item

100,000.00

Mail and Courier Service charges such services provided to


B TB6 QP employees for official purposes as detailed in clause
3.8.4.6 of Appendix A.

Item

50,000.00

TOTAL OF SCHEDULE 4.0

QR.

150,000

Page 232 of 266

Up to Last
Month Invoice

For This
Invoice

% of
Invoice

Total Invoice

ITEM NO

2.0

TOTAL
WEIGHTAGE

DESCRIPTION

Engineering
Engineering for the complete Scope of Work including but not
limited to:

Carry out detailed site surveys and document retrieval

0.027

Design Basis Memorandum (DBM)

0.029

HAZID Study as per clause 4.2.2 of SOW - App.A.

0.005

HAZOP Study as per clause 4.2.3 of SOW - App.A.

0.022

SIL Study as per clause 4.2.6 of SOW - App.A.

0.011

Carry out Project Risk Assessment as per cl. 3.1.16 of SOW - App.A.

0.002

Topographic Survey

0.002

Pipeline Route Surveys

0.010

Geotechnical Investigations

0.005

Complete design and detailed engineering for the Scope of Work


including but not limited to:
J

Process

0.090

Mechanical & Piping

0.127

Pipelines

0.120

Instrumentation and Control

0.121

Electrical

0.100

Loss Prevention

0.027

Civil, Structural and Architectural

0.081

Building Services

0.060

Telecommunication

0.007

Coating, Insulation & Fireproofing

0.012

Environmental Control

0.016

Corrosion and Cathodic Protection Design

0.006

Rotating Equipment / Mechanical Handling

0.074

Interfaces with existing facilities/systems

0.044

Total

1.000

Page 233 of 266

CUMMULATIVE
WTG PROGRESS

CUMMLATIVE
PROGRESS %

REMARKS

EPIC For New 16" Jet A1 Fuel Pipeline From QP Refinery


To BSV-3
Contract Number

Document Description

GC 11106200

Engineering Detailed Progress


QUANTITY ACTUAL

ITEM

DESCRIPTION

WEIGHTAGE

QUANTITY

Engineering
Engineering for the complete Scope of Work including but
not limited to:

Carry out detailed site surveys and document retrieval

0.0275

Lot

Design Basis Memorandum (DBM)

0.0287

Lot

HAZID Study as per clause 4.2.2 of SOW - App.A.

0.0050

Lot

HAZOP
per cclause
O Study as pe
ause 4.2.3
3 of
o SOW
SO - App.A.
pp

0.0225

Lot

SIL Study as per clause 4.2.6 of SOW - App.A.

0.0106

Lot

Carry out Project Risk Assessment as per cl. 3.1.16 of SOW - App.A.

0.0025

Lot

Topographic Survey

0.0025

Lot

Pipeline Route Surveys

0.0100

Lot

Geotechnical Investigations

0.0050

Lot

Complete design and detailed engineering for the Scope of


Work including but not limited to:

Process

0.0899

Lot

Mechanical & Piping

0.1274

Lot

Pipelines

0.1199
0 1199

Lot

Instrumentation and Control

0.1211

Lot

Electrical

0.0999

Lot

Loss Prevention

0.0275

Lot

Civil, Structural and Architectural

0.0812

Lot

Building Services

0.0599

Lot

Telecommunication

0.0067

Lot

Coating, Insulation & Fireproofing

0.0123

Lot

Environmental Control

0.0160

Lot

Corrosion and Cathodic Protection Design

0.0062

Lot

Rotating Equipment / Mechanical Handling

0.0739

Lot

Interfaces with existing facilities/systems

0.0437

Lot

Total Weightage

WEIGHTAGE ACTUAL

UNIT
PREVIOUS
THIS MONTH
MONTH

2.0

ETROJET

1.0000

Page 234 of 266

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

ITEM NO

TOTAL
WEIGHTAGE

DESCRIPTION
Procurement for the complete Scope of Work including but not
limited to:

Mechanical Items

A1

Pig Launcher at QP Refinery

0.011

A2

EOT Crane

0.018

A3

Jib Cranes

0.005

Pumps

B1

Mainline Pumps

0.219

B2

Booster Pumps

0.122

Electrical

C1

Switchgear Panels

0.094

C2

Distribution Boards and Local Control Panels

0.002

C3

UPS System

0.009

C4

Local Control Panel

0.002

C5

Lighting Fixtures & Lighting Poles

0.004

C6

Cables

0.011

Valves

D1

Control Valve & Auto Recirculation Valve

0.021

D2

ESD Valve with all accessories

0.004

D3

Isolation Valves at Refinery

0.004

D4

MOV (Motor operated Valves)

0.042

D5

All other misc. types of valves

0.022

E
E1

Items for Instrumentation works, DCS, ESD and F&G systems


Instruments

E1.1

Coriollis Flowmeter, Hand held communicator etc.

0.025

E1.2

Pressure Transmitters, Differential Pressure Transmitters, Pressure


Gauges

0.006

E1.3

Temperature Elements, Temperature Transmitters, Thermowell

0.001

E2

Junction Boxes

0.010

E3

Instrument & Control Cables

0.035

E4

Fire and Smoke detectors

0.007

E5

SCADA, DCS, ESD and F & G System

0.130

E6

Instrument Cable Accessories, Tubing


fittings & Miscellaneous erection materials

0.040

Telecom and Telemetry Equipments

0.003

Corrosion monitoring and inhibitor injection facilities

0.002

CP System incl. Anode Beds, Cables, TR Units, Jointing Kits, CP


Test Post etc.

0.017

Leak Detection System

0.026

Any Other Items not specifically mentioned herein above

i) Process Piping, fittingetc at Refinary

Total

0.110

1.000

Page 235 of 266

CUMMULATIVE
WTG PROGRESS

CUMMLATIVE
PROGRESS %

REMARKS

EPIC For New 16" Jet A1 Fuel Pipeline From QP Refinery


To BSV-3
Contract Number

Document Description

GC 11106200

Procurement Detailed Progress


QUANTITY ACTUAL

ITEM

3.0

DESCRIPTION

QR

WEIGHTAGE

QUANTITY

UNIT

Procurement
Procurement for the complete Scope of Work including but
not limited to:

Mechanical Items

3.A1

Pig Launcher at QP Refinery

517497.7

0.0112

Lot

3.A2

EOT Crane

815000.0

0.0176

Lot

3.A3

Jib Cranes

221784.7

0.0048

Lot

3.B

Pumps

3.B1

Mainline Pumps

10150000.0

0.2188

Lot

3
3.B2

p
Booster Pumps

5645000.0

0.1217

Lot

4340841.0

0.0936

Lot

3.C

Electrical

3.C1

Switchgear Panels

3.C2

Distribution Boards and Local Control Panels

111086.3

0.0024

Lot

3.C3

UPS System

422707.8

0.0091

Lot

3.C4

Local Control Panel

100379.2

0.0022

Lot

3.C5

Lighting Fixtures & Lighting Poles

203461.6

0.0044

Lot

3.C6

Cables

511515.5

0.0110

Lot

3.D

Valves

3.D1

Control Valve & Auto Recirculation Valve

977651.2

0.0211

Lot

3.D2

ESD Valve with all accessories

205000.0

0.0044

Lot

3.D3

Isolation Valves at Refinery

170000.0

0.0037

Lot

3.D4

MOV (Motor operated Valves)

1967500.0

0.0424

Lot

3.D5
3 D5

All other
th misc.
i
ttypes off valves
l

1020000.0
1020000 0

0.0220
0 0220

Lot
L t

3.E

Items for Instrumentation works, DCS, ESD


and F&G systems

3.E1

Instruments

3.E1.1

Coriollis Flowmeter, Hand held communicator etc.

1155405.9

0.0249

Lot

3.E1.2

Pressure Transmitters, Differential Pressure Transmitters,


Pressure Gauges

275519.9

0.0059

Lot

3.E1.3

Temperature Elements, Temperature Transmitters,


Thermowell

34958.4

0.0008

Lot

3.E2

Junction Boxes

462162.4

0.0100

Lot

3.E3

Instrument & Control Cables

1603703.5

0.0346

Lot

3.E4

Fire and Smoke detectors

331808.9

0.0072

Lot

3.E5

SCADA, DCS, ESD and F & G System

6014628.6

0.1297

Lot

3.E6

Instrument Cable Accessories, Tubing


fittings & Miscellaneous erection materials

1858212.7

0.0401

Lot

Telecom and Telemetry Equipments

118503.2

0.0026

Lot

76000.0

0.0016

Lot

F
G
H

Corrosion monitoring and inhibitor injection


facilities
incl Anode Beds,
Beds Cables,
Cables TR Units,
Units
CP System incl.
Jointing Kits, CP Test Post etc.

801987.7

0.0173

Lot

1185031.7

0.0255

Lot

Lot

Leak Detection System

Any Other Items not specifically mentioned


herein above

K.i

Process Piping, fittingetc at Refinary

5088000.0

0.1097

Total Weightage

46385348

1.0000

Page 236 of 266

PREVIOUS
THIS MONTH
MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

Price (QR)

RELATIVE
WEIGHT

Pipelines including but not limited to installation,


welding, testing, coating etc.

9088007.360

0.172

4.A.2.1

ROW

1009778.596

0.019

4.A.2.2

Trenching

5048892.978

0.096

4.A2.3

Sand Bedding ,Berm Construction

4260490.382

0.081

4.A.3

Tie-Ins

1075778.596

0.020

4.A.4

Cathodic Protection System

1748742.205

0.033

4.A.5

Pipeline Caliper Survey

540579.600

0.010

ITEM NO

4.0

DESCRIPTION

Construction and Installation


Complete Construction and Installation for the Scope of
Work including but not limited to:

4.A

4.A.1

4.B

Pipeline

Station Works at Refinery and BSV3

4.B.1

Mechanical & Piping including but not limited to


installation, welding, testing, coating etc.

4695500.000

0.089

4.B.2

Instrumentation and Control

1572285.171

0.030

4.B.3

Electrical

1457285.171

0.028

4.B.4

Loss Prevention

100000.000

0.002

4.B.5

Structural and Architectural

11423351.000

0.216

4.B.6

Building Services

114430.000

0.002

4.B.7

Telecommunication

1165828.137

0.022

4.B.8

Coating

850000.000

0.016

4.B.9

Insulation & Fireproofing

4613488.000

0.087

4.B.10

Security System incl. CCTV Cameras, PA System, ESecurity

203825.459

0.004

4.B.11

Extension of SER-12 including installation of Aircoditioning unit, F&G systems and all other woks in line
with existing SER-12.

318500.000

0.006

Interfaces with existing facilities/systems

3546047.808

0.067

52832810.46

1.000

4.C

Total

Page 237 of 266

CUMMULATIVE
WTG PROGRESS

CUMMLATIVE
PROGRESS %

REMARKS

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

4.0

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

Construction and Installation


Complete Construction and Installation for the
Scope of Work including but not limited to:

4.A

Pipeline

4.A1

Pipelines including but not limited


installation, welding, testing, coating etc.

to

4.A1.1

Transportation of Pipes

23040.0

0.0221

36000

MT

4.A1.2

Pipe Stringing

10080.0

0.0097

36000

MT

4.A1.3

Welding

93600.0

0.0897

3000

J.No

4.A1.4

NDT

24480.0

0.0235

3000

J.No

4.A1.5

FBE External Field Joint Coating

21600.0

0.0207

3000

J.No

4.A1.6

Lowering of pipe

30240.0

0.0290

36000

MT

4.A1.7

Anchor Flange To Be Welded

576.0

0.0006

No.

4 A1 8
4.A1.8

Pipeline Cleaning & Gauging

3360 0
3360.0

0 0032
0.0032

36000

MT

4.A1.9

Pipeline Water Filling

12960.0

0.0124

36000

MT

4.A1.10

Pipeline Pressurizing

4080.0

0.0039

36000

MT

4.A1.11

Pipeline Dewatering & Flushing

3240.0

0.0031

36000

MT

Sub Total Weightage(Pipelines including but not


limited to installation, welding, testing, coating etc. )

4.A2
4.A2.1

0.2177

Civil Works including but not limited to:


ROW

4.A2.1a

Survey and Stacking Works

5760.0

0.0055

36000

MT

4.A2.1b

Right Of Way

7200.0

0.0069

36000

MT

4.A2.1c

ROW Re-Instatement

7200.0

0.0069

36000

MT

Sub Total Weightage(ROW)

4.A2.2

0.0193

Trenching

4.A2.2a

Trench Excavation

38880.0

0.0372

36000

MT

4 A2 2b
4.A2.2b

Open Cut Crossings

42000 0
42000.0

0 0402
0.0402

84

No
No.

4.A2.2c

HDD Crossings (Highway)

66240.0

0.0635

No.

Sub Total Weightage(Trenching)

4.A2.3

0.1410

Sand Bedding, Berm Construction

4.A2.3a

Pre-Padding

20160.0

0.0193

36000

MT

4.A2.3b

Post Padding

15840.0

0.0152

36000

MT

Page 238 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.A2.3c

Final Backfilling

5760.0

0.0055

36000

MT

4.A2.3d

Excavation For Anchor Blocks At Refinery & BSV-3

1300.0

0.0012

Each

4.A2.3e

PC For Anchor Blocks At Refinery & BSV-3

1600.0

0.0015

Each

4.A2.3f

RC For Anchor Blocks At Refinery & BSV-3

5920.0

0.0057

Each

4.A2.3g

Backfilling For Anchor Blocks At Refinery & BSV-3

108.0

0.0001

Each

4.A2.3h

Pipeline Post Markers

1920.0

0.0018

36000

MT

4.A2.3i

Punch List

8640.0

0.0083

Lot

Lot

Sub Total Weightage(Sand Bedding, Berm


Construction)

4.A3
4.A3.1

0.0587

Tie-ins
Tie-Ins Of Strings

21600.0

Sub Total Weightage(Tie-ins)

4 A4
4.A4

0.0207

0.0207

Cathodic Protection System

4.A4.1 Temporary Cathodic Protection


4.A4.1a

Cables To Be Welded By Thermite

7200.0

0.0069

18

Connections

4.A4.1b

Anode For Temporary CP

7200.0

0.0069

18

No.

4.A4.2 Permanent Cathodic Protection


4.A4.2a

Test Post Distribution & Erection

800.0

0.0008

25

No.

4.A4.2b

Deep Well (25 M)

2240.0

0.0021

No.

4.A4.2c

Anode For Permanent CP

800.0

0.0008

No.

4.A4.2d

Rectifier To Be Installed

560.0

0.0005

No.

4.A4.2e

Cables To Be Connected

1120.0

0.0011

1500

MT

1120.0

0.0011

Lot

4.A4.2f

CP System to Be Checked & Tested

Sub Total Weightage(Cathodic Protection System)

4.B

Station Works at Refinery and BSV3

4 B1
4.B1

Mechanical and Piping

0.0202

4.B1.1 General
4.B1.1a

A/G Delivery Pipeline From The Pumps To The Launcher

17700.0

0.0170

530

M/L

4.B1.1b

A/G Suction Pipeline From The Header To The Pumps

5545.0

0.0053

170

M/L

49224.0

0.0472

10800

D.I

4.B1.2 Pumps Area


4.B1.2a

Piping Fabrication

Page 239 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.B1.2b

Sand Blasting & Panting

11040.0

0.0106

4000

M2

4.B1.2c

Piping & Pumps Erection

47327.0

0.0453

7200

D.I

4.B1.2d

Loops to be Water Filled

4320.0

0.0041

Lot

4.B1.2e

Loops to be Pressurized

6120.0

0.0059

Lot

4.B1.2f

Loops to be Dewatered & Flushed

3240.0

0.0031

Lot

4.B1.3 Launcher Area


4.B1.3a

Piping Fabrication

8739.0

0.0084

900

D.I

4.B1.3b

Sand Blasting & Panting

3545.0

0.0034

625

M2

4.B1.3c

Launcher & Piping Erection

11400.0

0.0109

600

D.I

4.B1.4 BSV-3
4.B1.4a

Installation of Motor Operated Valve

7800.0

0.0075

No.

4 B1 4b
4.B1.4b

Tie-In
Tie
In To The Existing Inside BSV-3
BSV 3

2600 0
2600.0

0 0025
0.0025

Lot

Sub Total Weightage(Mechanical & Piping)

4.B2

0.1711

Instrumentation and Control

4.B2.1 Substation 6003


4.B2.1a

Laying of Cables

2100.0

0.0020

2100

4.B2.1b

Installation Of Junction Boxes

2100.0

0.0020

200

4.B2.1c

Termination For Substation 6003

2100.0

0.0020

150

4.B2.2 Pumps Area


4.B2.2a

Laying Of Cables

1680.0

0.0016

5555

M/L

4.B2.2b

Installation Of Flow Transmitter

1680.0

0.0016

No.

4.B2.2c

Installation Of Pressure Gauges With Fittings

1680.0

0.0016

12

No.

4.B2.2d

Installation Of Pressure Transmitters With Tubes &


Fittings

1680.0

0.0016

10

No.

4.B2.2e

Installation Of Junction Boxes For Pump Area

1680.0

0.0016

No.

4 B2 2f
4.B2.2f

Installation Of Gas Detectors For Pump Area

1680 0
1680.0

0 0016
0.0016

No
No.

4.B2.2g

Installation Of Manual Call Point For Pump Area

1680.0

0.0016

No.

4.B2.2h

Termination For Pump Area

1680.0

0.0016

Lot

4.B2.3 Launcher Area


4.B2.3a

Laying Of Cables

1260.0

0.0012

13775

4.B2.3b

Installation of Pig Signaller

1260.0

0.0012

No.

Page 240 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.B2.3c

Installation Of Pressure Gauges With Fittings

1260.0

0.0012

No.

4.B2.3d

Installation Of Pressure Transmitters With Tubes &


Fittings

1260.0

0.0012

No.

4.B2.3e

Installation Of Junction Boxes For Launcher

1260.0

0.0012

No.

4.B2.3f

Installation Of Gas Detectors For Launcher

1260.0

0.0012

No.

4.B2.3g

Installation Of Manual Call Point For Launcher

1260.0

0.0012

No.

4.B2.3h

Termination For Launcher

1260.0

0.0012

Lot

4.B2.4 BSV-3
4.B2.4a

Laying Of Cables

5100.0

0.0049

Lot

4.B2.4b

Installation Of Pressure Transmitters With Tubes &


Fittings

2550.0

0.0024

Lot

4.B2.4c

Termination

7950.0

0.0076

Lot

Sub Total Weightage(Instrumentation & Control)

4 B3
4.B3

0.0435

Electrical

4.B3.1 Substation 6003


4.B3.1a

Modification Of Existing 11 KV Switchgear

6300.0

0.0060

No.

4.B3.1b

Modification Of Existing 3.3 KV Switchgear

6300.0

0.0060

No.

4.B3.1c

Modification Of Existing 415 V Switchgear

6300.0

0.0060

No.

4.B3.2 Pumps Area


4.B3.2a

Lighting System For Pump Area

1680.0

0.0016

Lot

4.B3.2b

Power Socket For Pump Area

1680.0

0.0016

Lot

4.B3.2c

Low Voltage Cable Laying For Pump Area

1680.0

0.0016

524

M/L

4.B3.2d

High Voltage Cable Laying For Pump Area

1680.0

0.0016

205

M/L

4.B3.2e

Installation Of Distribution Boards For Pump Area

1680.0

0.0016

Lot

4.B3.2f

Termination For Pump Area

2520.0

0.0024

Lot

4.B3.3 Launcher Area


4 B3 3a
4.B3.3a

Lighting System For The Launcher Area

1260 0
1260.0

0 0012
0.0012

Lot

4.B3.3b

Power Socket For The Launcher Area

1260.0

0.0012

Lot

4.B3.3c

Low Voltage Cable Laying For The Launcher Area

1260.0

0.0012

120

M/L

4.B3.3d

High Voltage Cable Laying For The Launcher Area

1260.0

0.0012

260

M/L

4.B3.3e

Installation Of Distribution Boards For The Launcher Area

1260.0

0.0012

Lot

4.B3.3f

Termination For The Launcher Area

2100.0

0.0020

Lot

Page 241 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.B3.4 BSV-3
4.B3.4a

Installation of Electrical Permanent Source

5100.0

0.0049

Lot

4.B3.4b

Electrical Connection To MOV

2550.0

0.0024

125

4.B3.4c

Diesel Generator to be Removed

7950.0

0.0076

No.

Sub Total Weightage( Electrical )

4.B5

0.0516

Structural and Architectural

4.B5.1 No. OFF (7) Culverts


4.B5.1a

Excavation For (7) Culverts

4550.0

0.0044

515

Cu.M

4.B5.1b

PC For (7) Culverts

11200.0

0.0107

298

Cu.M

4.B5.1c

RC For (7) Culverts

41440.0

0.0397

210

Cu.M

4.B5.1d

Backfilling For (7) Culverts

2800.0

0.0027

No.

4 B5 2 N0 Off (220) Sleepers


4.B5.2
4.B5.2a

Pre-Cast (220) Sleepers

15750.0

0.0151

220

No.

4.B5.2b

Erection Of (220) Sleepers

8250.0

0.0079

220

No.

4.B5.3 Pumps Area


4.B5.3.1 Pump Foundations
4.B5.3.1a

Excavation For (6) Pump Fondations

3900.0

0.0037

No.

4.B5.3.1b

PC For (6) Pump Fondations

6780.0

0.0065

No.

4.B5.3.1c

RC For (6) Pump Fondations

21600.0

0.0207

No.

4.B5.3.1d

Backfilling For (6) Pump Fondations

1200.0

0.0011

No.

4.B5.3.2 E&I Duct Bank In Pump Area


4.B5.3.2a

Excavation For E&I Duct Bank

650.0

0.0006

141

Cu.M

4.B5.3.2b

PC For E&I Duct Bank

1130.0

0.0011

114

Cu.M

4.B5.3.2c

RC For E&I Duct Bank

3600.0

0.0034

62

Cu.M

4 B5 3 2d
4.B5.3.2d

Backfilling For E&I Duct Bank

200 0
200.0

0 0002
0.0002

Lot

4.B5.3.3 Pump Shed


4.B5.3.3a

Steel Structure Fabrication For The Pump Shed

19680.0

0.0189

165

Ton

4.B5.3.3b

Excavation For For The Pump Shed

1300.0

0.0012

95

Cu.M

4.B5.3.3c

PC For For The Pump Shed

2260.0

0.0022

95

Cu.M

4.B5.3.3d

RC For For The Pump Shed

7200.0

0.0069

73

Cu.M

Page 242 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.B5.3.3e

Backfilling For The Pump Shed

400.0

0.0004

Lot

4.B5.3.3f

Steel Structure Erection For The Pump Shed

9840.0

0.0094

165

Ton

4.B5.3.3g

Corrugated Sheets Cladding For The Pump Shed

4920.0

0.0047

2850

Sq.M

4.B5.3.3h

Paving For The Pump Shed

4950.0

0.0047

188

Cu.M

4.B5.4 Launcher Area


4.B5.4a

Excavation For Launcher Station

780.0

0.0007

27

Cu.M

4.B5.4b

PC For Launcher Station

2000.0

0.0019

27

Cu.M

4.B5.4c

RC For Launcher Station

6660.0

0.0064

25

Cu.M

4.B5.4d

Backfilling & Re-Instatement For Launcher Station

270.0

0.0003

Lot

4.B5.4e

Fence For Launcher Station

4000.0

0.0038

Lot

4.B5.4f

Paving For Launcher Station

1152.0

0.0011

50

Cu.M

4 B5 5 Roads
4.B5.5
4.B5.5a

Roads For Launcher Area

4320.0

0.0041

677

Sq.M

4.B5.5b

Roads For Pump Area

1728.0

0.0017

19

Sq.M

4.B5.5b

Roads For SER 12

1728.0

0.0017

67

Sq.M

4.B5.6 BSV-3
4.B5.6a

Excavation In BSV-3

1200.0

0.0011

21

Cu.M

4.B5.6b

Plain Concrete In BSV-3

1200.0

0.0011

21

Cu.M

4.B5.6c

Re-Inforced Concrete In BSV-3

6000.0

0.0057

37

Cu.M

4.B5.6d

Fence In BSV-3

6000.0

0.0057

60

M/L

Sub Total Weightage(Structural and Architectural )

4.B9

Insulation & Fireproofing

4.B9

Insulation & Fireproofing

4.B11

Extension of SER-12

0.2018

9900.0

0.0095

Lot

4 B11 1 Civil Works


4.B11.1
4.B11.1a

Demolition & Excavation

1120.0

0.0011

28

Cu.M

4.B11.1b

P.C (Foundation)

1200.0

0.0011

Sq.M

4.B11.1c

R.C (Foundation)

2800.0

0.0027

40

Sq.M

4.B11.1d

Insulation (Foundation)

720.0

0.0007

Lot

4.B11.1e

BackFilling (Foundation)

280.0

0.0003

Lot

Page 243 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC For 16"- 36 Km Jet A1 Fuel Pipeline


From QP Refinery To BSV-3
Contract Number

Document Description

GC 11106200

Construction Verification Sheet


QUANTITY ACTUAL

ITEM

DESCRIPTION

MANHOURS

RELATIVE
WEIGHT

QUANTITY

UNIT

4.B11.1f

R.C (Columns)

2160.0

0.0021

Cu.M

4.B11.1g

R.C (Slab& Beams)

4480.0

0.0043

40

Cu.M

4.B11.1h

External Finishing

12000.0

0.0115

Lot

4.B11.1i

Internal Finishing

12000.0

0.0115

Lot

4.B11.2 Electrical Works


4 B11 2a
4.B11.2a

Lighting Fixtures
Fixtures, Sockets For Rooms

1020 0
1020.0

0 0010
0.0010

Lot

4.B11.2b

Low Voltage Cables

1020.0

0.0010

Lot

4.B11.2c

UPS System 110 V, 1 ph, 7 KVA

1020.0

0.0010

Set

4.B11.2d

Termination

1020.0

0.0010

Lot

4.B11.3 Instrumentation Works


4.B11.3a

Laying of Cables

1020.0

0.0010

250

M/L

4.B11.3b

DCS System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3c

DCS Marchaling Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3d

ESD System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3e

F&G System Cabinet to be Modified

1020.0

0.0010

Lot

4.B11.3f

Termination For SER-12

1020.0

0.0010

Lot

Sub Total Weightage(Extension of SER-12)

Total Weightage Of The Project

0.0450

1043762.0

1.0000

Page 244 of 266

PREVIOUS
MONTH

THIS MONTH

ETROJET
WEIGHTAGE ACTUAL

AS ON
DATE

PREVIOUS
MONTH

THIS
MONTH

AS ON
DATE

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
DAILY PROGRESS REPORT
(DPR) FORMAT
______________________________________

Page 245 of 266

CONTRACT NO. : GC11106200


16"-36 KM JET A1 FUEL PL FROM QP REFINERY TO BSV-3

Daily Progress Report For 16"-36 km Jet A1 Fuel Pipeline


As Of : July 19,2012

Daily Progress Report No. : (3392-DPR-0001)

Ser.

Activity

Unit

Total
Q.ty

Target

P 1/1

Actaul Executed Quantities

Q.ty

Previous

Today

Cumu.
Q.ty

Cumu.
%

Variance
%

Survey & Stacking

M/L

36000

0.00%

0.00%

0.00%

Grading For R.O.W

M/L

36000

0.00%

0.00%

0.00%

Trench Excavation

M/L

36000

0.00%

0.00%

0.00%

Pipe Transportation

M/L

36000

0.00%

0.00%

0.00%

Pipe Stringing

M/L

36000

0.00%

0.00%

0.00%

Straight Run Welding

Joint

3000

0.00%

0.00%

0.00%

N.D.T

Joint

3000

0.00%

0.00%

0.00%

External F.J. Coating (FBE)

Joint

3000

0.00%

0.00%

0.00%

Pre-Padding

M/L

36000

0.00%

0.00%

0.00%

10

Lowering

M/L

36000

0.00%

0.00%

0.00%

11

Post Padding

M/L

36000

0.00%

0.00%

0.00%

12

String Tie-Ins (Estimited)

Each

226

0.00%

0.00%

0.00%

13

Final Back-Filling

M/L

36000

0.00%

0.00%

0.00%

14

Cleaning By Pigs

M/L

36000

0.00%

0.00%

0.00%

Planning Engineer

Project Manager

M. Salah

M. Mamdouh
Page 246 of 266

Remarks

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
WEEKLY PROGRESS REPORT
(WPR) FORMAT
______________________________________

Page 247 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

CONTRACT NO: GC11106200


Title : 16 Jet A1 Fuel PL From QP Refinery to BSV-3
(EPIC Project)

WEEKLY PROGRESS REPORT


(Week Ending July 19,2012)

Eng. M. Salah

Eng. M. Mamdouh

Planning Engineer

Project Manager

Page 248 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

WEEKLY PROGRESS REPORT FORMAT

TABLE OF CONTENTS
1. PROJECT KEY EVENTS
2. PHYSICAL PROGRESS
3. QUANTITATIVE PROGRESS
4. WEEKLY HIGHLIGHT
5. SAFETY STATISTICS
6. MOBILIZATION AND DE-MOBILIZATION
7. INTERFACE STATUS
8. SUB-CONTRACTORS LIST / STATUS
9. ACTIVITES PLANNED FOR NEXT WEEK
10. AREA OF CONCERNS
11. ATTACHMENTS
10.1

Manpower Status

10.2

Equipment Status

10.3

Construction Verification Sheet

10.4

Marching Chart

10.5

Project Overall S-Curve

10.6

Engineering Phase S-Curve

10.7

Procurement Phase S-Curve

10.8

Construction Phase S-Curve

10.9

Project Overall Progress Measurement

10.10 Engineering Document Register (EDR)


10.11 Procurement Status Register (PSR)
10.12 Construction Progress Measurement
10.13 Two Weeks Lookahead Schedule

Page 249 of 266

July 19,2012

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

1. PROJECT KEY EVENTS:

S/NO.

Description

Original plan

Forecast*

Actual

Contract Award

Feb 26,2012

Feb 26,2012

Engineering team Mobilization

Mar 7,2012

Mar 17,2012

Construction Start

June 3,2012

Design Review Meeting

June 3,2012

Complete Major Subcontractor Order


Issuance

Jul 15,2012

Complete Placement Of all Long Lead Items

Jul 16,2012

Trench Excavation Start

Jul 30,2012

Transport Start For 16 Coated Pipes To


Site

Welding Activity Start (16 Gas P/L)

Sep 1,2012

10

Start of Construction in QP Refinery

Feb 25,2013

11

Achieve Mechanical Completion of PL

Nov 21,2013

12

Achieve Commissioning of PL and All


Facilities

May 23,2014

13

Complete Baseline Survey

Jul 23,2014

14

Project Close Out & Handover

Aug 25,2014

Aug 13, 2012

* Forecasted dates reflect current work plan & will not impact the date of the Commissioning
achieving of PL and all facilities. (May 25,2014)

Page 250 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

2. PHYSICAL PROGRESS
Progress figures based on the approved project baseline schedule
This Week
Description

WT %

Cumulative

Planned
%

Actual
%

Planned
%

Actual
%

Variance
%

Engineering

5.0 %

0.00 %

0.00 %

0.00 %

0.00 %

0.00 %

Procurement

40.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Construction

48.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Pre-commissioning &
Commissioning

5.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Optional

2.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

100.0 %

0.00 %

0.00 %

0.00 %

0.00 %

0.00 %

Total Project

3. QUANTITATIVE PROGRESS
This Week
Activity

Unit

Cumulative

Quantity
Planned

Actual

Planned

Actual

Survey Work

M/L

36000

0.0

0.0

0.0

0.0

Grading & ROW

M/L

36000

0.0

0.0

0.0

0.0

Trench Excavation

M/L

36000

0.0

0.0

0.0

0.0

Transportation Of Coated Pipes

M/L

36000

0.0

0.0

0.0

0.0

Stringing Along The Route

M/L

36000

0.0

0.0

0.0

0.0

Welding Of Pipes

Joint

3000

0.0

0.0

0.0

0.0

N.D.T & Welding Repair

Joint

3000

0.0

0.0

0.0

0.0

Field Joint Coating (FBE)

Joint

3000

0.0

0.0

0.0

0.0

Sand Pre-Padding

M/L

36000

0.0

0.0

0.0

0.0

Lowering Of Pipeline

M/L

36000

0.0

0.0

0.0

0.0

Sand Padding

M/L

36000

0.0

0.0

0.0

0.0

100

0.0

0.0

0.0

0.0

Open Cut Crossings

Each

84

0.0

0.0

0.0

0.0

HDD Crossings

Each

0.0

0.0

0.0

0.0

Final Backfilling

M/L

36000

0.0

0.0

0.0

0.0

Tie-in Of Sections

Page 251 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010
DOUMENT TITLE

CONTRACT NO: GC11106200

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

4. WEEKLY HIGHLIGHT
4-1 Engineering

4-2 Procurement

Construction
1.

Completion of the grading for the route of 16" Jet A1 Fuel P/L with total length of 0.0 km.

2.

Finalized the trench excavation for 0.0 km out of 36 km.

3.

106.48 Km of 16" coated pipes had been transported from coating plant to the field site,
LSTK Contractor is requested to expedite the delivery of the remaining 16" pipes with
productivity not less than 1.5 km / day to overcome the delay in the pipe transportation
activity.

4.

0.00 Km of 16" coated pipes had been stringed along the route.

5.

Finalized the welding activity for 0.00 Km of 16" pipes out of 36 km.

6.

N.D.T for welded joints is in progress 0.00 %.

7.

Finalized the field joint coating (FBE) with total quantity 0.00 km out of 36 km.

8.

Finalized the lowering activity with total quantity 0.00 km out of 36 km.

9.

Finalized the cleaning by pigs with total quantity 0.0 km out of 36 km .

10.

Finalized the sand padding activity with total quantity 0.0 km out of 36 km.

11.

Finalized the final backfilling activity with total quantity 0.0 km out of 36 km

12.

Finalized the rock cap cover activity with total quantity 0.0 km out of 36 km

Page 252 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

5. SAFETY STATISTICS

Injuries (Major, Minor and Fist-Aid)

Near
Miss

FAI

MTC

FAT

LTI

RDI

MVA's

Fires

Others
*

Manpower

204

Manhours
(This Week)

12240

Year to date
(MH)

12240

Project to date
(MH)

12240

FAI : First Aid Incident / MTC : Medical Treatment Case / FAT : Fatality / LTI : Lost Time Injury-Illness /
RDI : Restricted Duty Incident
* Other Incident (Spill, damage to property, environment, etc)

6. MOBILIZATION AND DE-MOBILIZATION

7. INTERFACE STATUS
Petrojet already attended the meeting with Kahramaa to finalize the necessary permit and
requirements by Kahramaa approved consultant as a first stage to get QP approval to execute the
option # (1) at BSV-3 (Pole mounted Transformer ) .

Page 253 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

8. SUBCONTRACTORS LIST / STATUS

No.

Sub-Contracting Description

Status

Engineering Consultant

The Task already has been started

TCF construction

Petrojet will utilize L&T company offices at


Abo Nakhla area

Trench excavation & Rocks to be


shattered

Material Requisition under Petrojet review

Security sub-contractor

Transportation of the const.


Equipment & tools

Concrete work and General civil

N.D.T

Material Requisition under Petrojet review

3-rd Party (TPI)

Material Requisition under Petrojet review

Garnet-Blasting & FBE for the


filed joint coating

10

Cathodic Protection

11

Drying , Nitrogen Purging

12

Commissioning

Page 254 of 266

Remarks
Already
Awarded

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

9. ACTIVITIES PLANNED FOR NEXT WEEK


(Based On The Project Approved Schedule)
(16- 36 km Jet A1 Fuel Pipeline)
Planned During Next
Week
Activity

Unit

Quantity
Q.ty

Survey Work

M/L

36000

Grading & ROW

M/L

36000

Trench Excavation

M/L

36000

Transportation Of Coated
Pipes

M/L

36000

Stringing Along The


Route

M/L

36000

Welding Of Pipes

Joint

3000

N.D.T & Welding Repair

Joint

3000

Field Joint Coating (FBE)

Joint

3000

Sand Pre-Padding

M/L

36000

Lowering Of Pipeline

M/L

36000

Sand Padding

M/L

36000

100

Open Cut Crossings

Each

84

HDD Crossings

Each

Final Backfilling

M/L

36000

Tie-in Of Sections

Cumulative Planned Up
To End Of Next Week

Page 255 of 266

Q.ty

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-WPR-0010

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

July 19,2012

WEEKLY PROGRESS REPORT FORMAT

10. AREA OF CONCERNS

EPIC Contractor is requested to take the corrective action and maximize the
resources to mitigate the severe delay of the engineering phase .

EPIC Contractor is requested to start the geotechnical investigation A.S.A.P to


avoid any delay .

EPIC Contractor is requested to finalize the material requisition of HAZOP &


HAZID & SIL A.S.A.P .

EPIC Contractor is requested to obtain the governmental permits and the


environmental clearance A.S.A.P .

EPIC Contractor is requested to expedite the finalizing of the (WPS) which will
be followed with the PQR and welders qualifications .

11. ATTACHMENTS

Page 256 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

REV 5

DATE

JULY 19,2012

PLANNING PACKAGE

______________________________________
MONTHLY PROGRESS REPORT
(MPR) FORMAT
______________________________________

Page 257 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

CONTRACT NO: GC11106200


Title : 16 Jet A1 Fuel PL From QP Refinery to BSV-3
(EPIC Project)

MONTHLY PROGRESS REPORT


(June, 2012)

Eng. M. Salah

Eng. M. Mamdouh

Planning Engineer

Project Manager

Page 258 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

MONTHLY PROGRESS REPORT FORMAT

TABLE OF CONTENTS
1. PROJECT KEY EVENTS
2. PHYSICAL PROGRESS
3. QUANTITATIVE PROGRESS
4. EXECUTIVE SUMMARY
5. SAFETY STATISTICS
6. MOBILIZATION AND DE-MOBILIZATION
7. INTERFACE STATUS
8. SUB-CONTRACTORS LIST / STATUS
9. ACTIVITES PLANNED FOR NEXT MONTH
10. AREA OF CONCERNS
11. VARIANCE ANALYSIS AND MITIGATION PLAN
12. ATTACHMENTS
10.1

Manpower Status

10.2

Equipment Status

10.3

Construction Verification Sheet

10.4

Marching Chart

10.5

Project Overall S-Curve

10.6

Engineering Phase S-Curve

10.7

Procurement Phase S-Curve

10.8

Construction Phase S-Curve

10.9

Project Overall Progress Measurement

10.10 Engineering Document Register (EDR)


10.11 Procurement Status Register (PSR)
10.12 Construction Progress Measurement
10.13 Two Months Lookahead Schedule
10.14 Updated Organization Chart
10.15 Pictures

Page 259 of 266

June 28,2012

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

1. PROJECT KEY EVENTS:

S/NO.

Description

Original plan

Forecast*

Actual

Contract Award

Feb 26,2012

Feb 26,2012

Engineering team Mobilization

Mar 7,2012

Mar 17,2012

Construction Start

June 3,2012

Design Review Meeting

June 3,2012

Complete Major Subcontractor Order


Issuance

Jul 15,2012

Complete Placement Of all Long Lead Items

Jul 16,2012

Trench Excavation Start

Jul 30,2012

Transport Start For 16 Coated Pipes To


Site

Welding Activity Start (16 Gas P/L)

Sep 1,2012

10

Start of Construction in QP Refinery

Feb 25,2013

11

Achieve Mechanical Completion of PL

Nov 21,2013

12

Achieve Commissioning of PL and All


Facilities

May 23,2014

13

Complete Baseline Survey

Jul 23,2014

14

Project Close Out & Handover

Aug 25,2014

Aug 13, 2012

* Forecasted dates reflect current work plan & will not impact the date of the Commissioning
achieving of PL and all facilities. (May 25,2014)

Page 260 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

2. PHYSICAL PROGRESS
Progress figures based on the approved project baseline schedule
This Month
Description

WT %

Cumulative

Planned
%

Actual
%

Planned
%

Actual
%

Variance
%

Engineering

5.0 %

0.00 %

0.00 %

0.00 %

0.00 %

0.00 %

Procurement

40.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Construction

48.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Pre-commissioning &
Commissioning

5.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

Optional

2.0 %

00.00 %

00.00 %

00.00 %

00.00 %

00.00 %

100.0 %

0.00 %

0.00 %

0.00 %

0.00 %

0.00 %

Total Project

3. QUANTITATIVE PROGRESS
This Month
Activity

Unit

Cumulative

Quantity
Planned

Actual

Planned

Actual

Survey Work

M/L

36000

0.0

0.0

0.0

0.0

Grading & ROW

M/L

36000

0.0

0.0

0.0

0.0

Trench Excavation

M/L

36000

0.0

0.0

0.0

0.0

Transportation Of Coated Pipes

M/L

36000

0.0

0.0

0.0

0.0

Stringing Along The Route

M/L

36000

0.0

0.0

0.0

0.0

Welding Of Pipes

Joint

3000

0.0

0.0

0.0

0.0

N.D.T & Welding Repair

Joint

3000

0.0

0.0

0.0

0.0

Field Joint Coating (FBE)

Joint

3000

0.0

0.0

0.0

0.0

Sand Pre-Padding

M/L

36000

0.0

0.0

0.0

0.0

Lowering Of Pipeline

M/L

36000

0.0

0.0

0.0

0.0

Sand Padding

M/L

36000

0.0

0.0

0.0

0.0

100

0.0

0.0

0.0

0.0

Open Cut Crossings

Each

84

0.0

0.0

0.0

0.0

HDD Crossings

Each

0.0

0.0

0.0

0.0

Final Backfilling

M/L

36000

0.0

0.0

0.0

0.0

Tie-in Of Sections

Page 261 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003
DOUMENT TITLE

CONTRACT NO: GC11106200

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

4. EXECUTIVE SUMMARY
4-1 Engineering

4-2 Procurement

Construction
1.

Completion of the grading for the route of 16" Jet A1 Fuel P/L with total length of 0.0 km.

2.

Finalized the trench excavation for 0.0 km out of 36 km.

3.

106.48 Km of 16" coated pipes had been transported from coating plant to the field site,
LSTK Contractor is requested to expedite the delivery of the remaining 16" pipes with
productivity not less than 1.5 km / day to overcome the delay in the pipe transportation
activity.

4.

0.00 Km of 16" coated pipes had been stringed along the route.

5.

Finalized the welding activity for 0.00 Km of 16" pipes out of 36 km.

6.

N.D.T for welded joints is in progress 0.00 %.

7.

Finalized the field joint coating (FBE) with total quantity 0.00 km out of 36 km.

8.

Finalized the lowering activity with total quantity 0.00 km out of 36 km.

9.

Finalized the cleaning by pigs with total quantity 0.0 km out of 36 km .

10.

Finalized the sand padding activity with total quantity 0.0 km out of 36 km.

11.

Finalized the final backfilling activity with total quantity 0.0 km out of 36 km

12.

Finalized the rock cap cover activity with total quantity 0.0 km out of 36 km

Page 262 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

5. SAFETY STATISTICS

Injuries (Major, Minor and Fist-Aid)

Near
Miss

FAI

MTC

FAT

LTI

RDI

MVA's

Fires

Others
*

Manpower

204

Manhours
(This Month)

12240

Year to date
(MH)

12240

Project to date
(MH)

12240

FAI : First Aid Incident / MTC : Medical Treatment Case / FAT : Fatality / LTI : Lost Time Injury-Illness /
RDI : Restricted Duty Incident
* Other Incident (Spill, damage to property, environment, etc)

6. MOBILIZATION AND DE-MOBILIZATION

7. INTERFACE STATUS
Petrojet already attended the meeting with Kahramaa to finalize the necessary permit and
requirements by Kahramaa approved consultant as a first stage to get QP approval to execute the
option # (1) at BSV-3 (Pole mounted Transformer ) .

Page 263 of 266

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

8. SUBCONTRACTORS LIST / STATUS

No.

Sub-Contracting Description

Status

Engineering Consultant

The Task already has been started

TCF construction

Petrojet will utilize L&T company offices at


Abo Nakhla area

Trench excavation & Rocks to be


shattered

Material Requisition under Petrojet review

Security sub-contractor

Transportation of the const.


Equipment & tools

Concrete work and General civil

N.D.T

Material Requisition under Petrojet review

3-rd Party (TPI)

Material Requisition under Petrojet review

Garnet-Blasting & FBE for the


filed joint coating

10

Cathodic Protection

11

Drying , Nitrogen Purging

12

Commissioning

Page 264 of 266

Remarks
Already
Awarded

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

9. ACTIVITIES PLANNED FOR NEXT MONTH


(Based On The Project Approved Schedule)
(16- 36 km Jet A1 Fuel Pipeline)
Planned during next
month
Activity

Unit

Quantity
Q.ty

Survey Work

M/L

36000

Grading & ROW

M/L

36000

Trench Excavation

M/L

36000

Transportation Of Coated
Pipes

M/L

36000

Stringing Along The


Route

M/L

36000

Welding Of Pipes

Joint

3000

N.D.T & Welding Repair

Joint

3000

Field Joint Coating (FBE)

Joint

3000

Sand Pre-Padding

M/L

36000

Lowering Of Pipeline

M/L

36000

Sand Padding

M/L

36000

100

Open Cut Crossings

Each

84

HDD Crossings

Each

Final Backfilling

M/L

36000

Tie-in Of Sections

Cumulative Planned up
to end of next month

Page 265 of 266

Q.ty

EPIC FOR 16-36 KM JET A1 FUEL


PIPELINE FROM QP REFINERY TO BSV-3

DOC
NO

3392-MPR-0003

CONTRACT NO: GC11106200

DOUMENT TITLE

DATE

June 28,2012

MONTHLY PROGRESS REPORT FORMAT

10. AREA OF CONCERNS

EPIC Contractor is requested to take the corrective action and maximize the
resources to mitigate the severe delay of the engineering phase .

EPIC Contractor is requested to start the geotechnical investigation A.S.A.P to


avoid any delay .

EPIC Contractor is requested to finalize the material requisition of HAZOP &


HAZID & SIL A.S.A.P .

EPIC Contractor is requested to obtain the governmental permits and the


environmental clearance A.S.A.P , especially the permits will take a long time to
be finalized .

EPIC Contractor is requested to expedite the finalizing of the (WPS) which will
be followed with the PQR and welders qualifications .

11. VARIANCE ANALYSIS AND MITIGATION PLAN

12. ATTACHMENTS

Page 266 of 266