ECONOMIC STIMULUS PROJECT LIST

ROADWAY PROJECTS

1/13/2009 18:05

PROJECT SPONSOR PROJECT NAME CONST COST COMMENTS AND DELIVERY ISSUES

PROJECTS WITH HIGH CONFIDENCE OF READINESS IN 90 - 180 DAYS

US95 Wyoming to Ohio Match Existing federal aid project. City of Hayden offers contribution
ITD/City of Hayden (including signals at Lancaster $ 21,000,000 for corresponding local system improvements. Direct tie to job
and Wyoming) creation and safety for employees at Warren K Industrial Park.

Highway improvement project through the town of Worley.


ITD US95 Worley North $ 15,000,000
Ready to go.

Existing federal aid project. National studies show pathways


City of Coeur d’Alene Atlas Bike Path $ 500,000 are tied to economic benefits for communities. Concept report
is almost complete. Simple project, no right of way required.

New fed-aid project. Improves safety and access to growing


City of Coeur d’Alene Kathleen/Howard Signal $ 300,000
commercial area of Coeur d'Alene.

New federal-aid project. Improves safety and access at busy


City of Post Falls Seltice/Cedar Signal $ 300,000
intersection that meets signal warrants.
Lancaster Overlay from US 95 to New fed-aid project. 3 mile overlay of existing pavemetn at 36-
Lakes Hwy District $ 600,000
Huetter ft width
Ramsey Road Overlay, from New fed-aid project. 2.8 mile overlay of existing pavement at
Lakes Hwy District $ 500,000
Scarcello to Brunner 28-ft width
East Hayden Lake Road
New fed-aid project. 6.75 mile overlay of existing pavement at
Lakes Hwy District Overlay, from Dodd to Mokins $ 1,200,000
28-ft width.
Bay
Watson Road , from Vogul to New fed-aid project. This will be a reconstructed roadway into
Worley Hwy District terminus $ 1,000,000 a primarily summer use community on lake CDA, (recreation).
Safety improvements Benefits tourism and safety.
Conkling Road, US95 to
Heyburn State Park New fed-aid project. Cement recycled asphalt base
Worley Hwy District $ 2,500,000
Cement treated base and pave stabilization is planned. Benefits tourism.
5.76 miles
French Gulch Rd
ESHD Cement-treated base and pave $ 1,400,000 New fed-aid project.
3.5 miles
Yellowstone Trail Rd
ESHD $ 1,800,000 New fed-aid project.
Level and overlay 5.2 miles
Fernan Hill Rd
ESHD Cement treated base and pave 1 $ 400,000 New fed-aid project.
mile
Canyon Rd
ESHD $ 3,100,000 New fed-aid project.
Level and overlay 8.7 miles
Burma Rd
ESHD Cement treated base and pave $ 1,000,000 New fed-aid project. Not part of the current STP Rural project
2.4 miles.
O'Gara Rd
ESHD $ 2,500,000 New fed-aid project.
Level and overlay 7.4 miles
Bell Canyon Rd
ESHD Ballast, base, drainage and pave $ 800,000 New fed-aid project.
1.2 miles
Hells Gulch Rd
ESHD Ballast, base, drainage and pave $ 1,500,000 New fed-aid project.
2.4 miles
Sunnyside Road
ESHD Overlay existing pavement 2 $ 400,000 New fed-aid project.
miles
PROJECT SPONSOR PROJECT NAME CONST COST COMMENTS AND DELIVERY ISSUES

Sunnyside Road
ESHD $ 1,300,000 New fed-aid project.
Ballast, base and pave 1.8 miles

TOTAL "180 DAY" PROJECTS $ 57,100,000

HIGH-RISK PROJECTS POTENTIALLY READY IN 180 DAYS

Construction cost does not include right of way acquisition.

Existing federal-aid project. Environmental Clearance


complete. Final design needs to be funded immediately so
ITD/WSDOT Bridging the Valley that HDR can assess feasibility of immediate possession and
$ 9,000,000
City of Rathdrum Main Street Extension use agreements for right of way. This project would impact a
commercial property that is currently for sale, and several
mobile homes.

Benefits both commerce and safety.

TOTAL "HIGH RISK" PROJECTS $ 9,000,000

TOTAL KMPO ROADWAY PROJECTS $ 66,100,000