Documente Academic
Documente Profesional
Documente Cultură
A monthly saving of Rs. 16,66,900 /- in chemical consumption in all the three plants of the water system while maintaining the target Key Performance Indicators (KPI) within limit. Introduction of PID control system for effective control of supplied demineralised water, led to reduced consumption of Mono Ethanol Amine (MEA). Modification of acid dosing line led to effective pH control and reduced consumption of acid (HCl). Modification of alum dosing lines resulted in reduced consumption of alum.
Utilisation of 48% w/w caustic lye in place of flakes in the water treatment plant reduced chemical cost and avoids preparation of hazardous caustic solution from flakes. Implementation of a new treatment programme has reduced cooling tower blow down, system loss, and cold water sump level to save chemicals. Optimum utilisation of ion exchangers in water treatment plant to obtain maximum throughput with reduced quantity of chemicals like HCl and NaOH.
Alkali Waste
PUMP
ethanol amine) dosing system were installed, which gave the desired output. It also increased the CRM produce sheet quality and reduced the coolant consumption (because previously, due to low pH <4 and high pH >10, emulsion quality deteriorated). On-off controller pH range variation:
On-Off controller pH
14 12 10 pH 8 6 4 2 0 1 3 5 7 9 11 13 15 17 19 21 23 25 No of sample Series1
Process modification: After the above process the outlet quality of the HRSCC water is suitable for the fire water makeup only the TSS was slightly high. One multi grade filter (capacity 35 m3/h) as installed after the HRSCC and the filter water sent directly to the fire well as makeup.
Oily sludge
11
6 7
8 5 1. Oily waste from CGL#2 SPM Collection tank-1 2. Oily waste from PLTCM Collection tank-2 3. Continuous Tank 1 4. Continuous Tank 2 5. Feed Pump 6. CAF 1 7. CAF 2 8. Aeration Tank 9. Surface Aerators 10. Clarifier 11. MGF/ACF Feed Tank 12. MGF 13. ACF 14. Final Effluent Tank
Problems Faced & Root Cause Analysis: The problems faced during operation in the oily waste section of CRM waste water systems were as follows: The colour of the ATL started changing to black from normal brown.
Intense smell of rotten egg (i.e. H2S) was polluting the surrounding area. Sludge bulking (huge sludge formation) was found in secondary clarifier, which led to high turbidity of the final effluent. The colour of clarifier effluent was blackish. Both these were unacceptable environmental conditions. Sludge volume index, which is an indication of the settling characteristic of the sludge, of the secondary clarifier was calculated to be 90.5 i.e. high normal (normal range is 40 to 100). The O2 uptake test (Fig.2) conducted showed a flat response, signifying that the bacteria were no longer active.
Dissolved oxygen test result 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 T1 T2 T3 T4 T5 T6 T7 T8 T9 T10
(i) Accessibility to aeration tank top was improved for observation and two extra circular air spurges were provided to reduce H2S exposure. (ii) Extra nutrients were tried and the aeration tank was also loaded with a wide range of micro-organisms from cow dung as well as the BOD plant. Draining out the aeration tank to develop new bacteria was not considered due to environmental concerns of 400 cu.m of liquor from the aeration tank. (iii) Since procurement of a pure culture of thiobacillus ferro-oxidan is timeconsuming, it was decided to carry out the treatment of oily waste in laboratory scale with different soil samples collected from the premises of Tata Steel works. Lab studies on the use of soil samples in the treatment of oily waste had encouraging results. The intermittent enhancement of dissolved oxygen (DO) was taken as a positive indication of growth of the micro organism. The dip in DO may be interpreted as consumption of O2 not only for biochemical reaction but also for some other consumption by other interfering radicals i.e. chemical oxidation. However no tangible colour change was observed at the time of performing the O2 uptake test. The experiment could not be continued beyond D-2 (second day) due to stoppage of airing on D-2 night for some unavoidable reasons.
DO mg/l
Conclusion: It was the first time soil has been used directly in running any biological treatment process, creating a medium required for micro organism growth. Normally in activated sludge process, bacteria culture is made by addition of cow-dung or sludge brought from other BOD removal plant. However it was established in this study that soil micro organisms could have a vital role in biological treatment process because they serve as biochemical agents for the conversion of complex organic compounds into simple inorganic compounds or into their constituent elements. Consequently one could use this material as an inexpensive source of desirable micro organisms in biological treatment processes.
Troubleshooting
Apart from the benefits that have accrued to Tata Steel as detailed above, having a fully experienced team at site specialised in water management has helped Tata Steel maximize uptime of their plants. The teams involvement in trouble shooting in various areas is illustrated below: Water Treatment Plant PROBLEMS Slime gel deposition was detected in DM water supply line. REMEDIAL ACTION a) A sample of slime gel was sent for lab analysis. It was found that slime gel formation took place due to micro-biological growth b) DM water supply line flushing was done during annual shutdown. PLC logic was developed which allowed both pumps to be started in manual-remote mode so that desired flow and pressure could be maintained effectively. Acid soaking was done for SAC. Alkali brine treatment was done for SBA. Mono Ethanol Amine dosing prohibition was provided with PID control for maintaining pH of DM water supply effectively. Powder alum was replaced by liquid alum. Practice has been developed to mix SPM waste
DM water supply pumps often tripped due to high consumption of DM water. Throughput of SAC and SBA reduced. Low pH in DM water supply circuit. Waste Water Treatment Plant Frequent choking of alum dosing pump strainer Oily waste from SPM used to
contain high COD load (1000012000 mg/l) which was beyond our design (600 mg/l). As a result, aeration system was frequently disturbed. Due to increased load and higher volume of oily waste received, sludge generation increased considerably which created disposal problems. Oily waste from SPM contained foaming like surfactants, which caused a lot of foam in the aeration tank resulting in reduction of dissolved oxygen content. Removal of oil scum from continuous tank Higher incoming alkaline waste from continuous galvanizing line than its design, which affects the final effluent quality. Underground pipe line leakage from alkaline waste pipe line from CGL # 1 & CGL # 2. Section 500 filter press not able to form cake. TSS of final effluent high due to section 300.
A spare filter press for section 500 was reinstalled in section 300, which considerably reduced the volume of sludge generation. Proper sprinkling system was developed which reduced the foam and thus helped in maintaining the dissolved oxygen content.
Permanent arrangement (by rotor pump) was made for removal of oil scum. Treatment flow was increased from 14m3/h to 20 m3/h Polymer 441 dosing line made to T- 203 & alum dosing is done through directly from the tank. Overhead line provided for incoming alkaline waste from CGL #2 and CGL #1 to avoid frequent leakages Scrape the deposit mud & continuous airing in sludge sump of section 500. Complete overhauling was done in multi grade and activated carbon filters.
Recirculation Pump House (RCPH) Make-up water could not be FT-01 of RCPH has been replaced at the top of properly monitored as it was not the pipeline to get the correct reading & to possible to calculate the total measure the make-up water during gravity flow. volume of the water that was provided to cold sump for makeup by gravity. Fire fighting line pressure not up Jockey pump: 1 in RCPH has been replaced with to the demand. vertical multistage pump. As is evident from this case study, outsourcing O&M has delivered single-point specialist responsibility for every aspect of the water circuit with manifold benefit. It has resulted in suggestions & implementation of measures to enhance efficiency, save on capital costs & reduce operating costs. Troubleshooting problems and effective tackling of emergencies eliminated downtime and production losses.