03 December 2009
Guus Olierook
Characteristics of bridge
- Cable-stayed swing bridge
Characteristics of bridge
Cable-stayed swing bridge Design by Santiago Calatrava Turning machinery: 5 lift cylinders and 2 turn cylinders Length: 123 m, Width: 28 m, Height: 45 m Weight of Steelconstruction: 2350 ton Plates for Pyloon are 120 mm thick Pivotpoint out of centre: 31 m and 92 m Ballastweight 2800 ton (600 ton steel & 2200 ton concrete) 6 back stay cables of 145 mm diameter 25 fore stay cables of 60 mm diameter Location of bridge in center of Dublin across the River Liffey Order value for Hollandia: Eur 24.500.000,-
Project Organisation
Dublin City Council (Client) Contractors combination Hollandia & Graham
Architect - Calatrava Inspectors - F&N Contract mngt - ROD
Project Engineer
Work Preperator
Project Buyer
Fabricatio n Manager
Quality inspector
Site Manage r
Engineering
Fabrication drawings
800 fabrication drawings
3D computer model
Engineering
Fabrication drawings Design Turning machinery
Lift and Turning system
Engineering
Fabrication drawings Design Turning machinery
Lift and Turning system
Engineering
Fabrication drawings Design Turning machinery
Lift and Turning system Locking pins Expansion joints Traffic barriers
Engineering
Fabrication drawings Design Turning machinery
Lift and Turning system Locking pins Expansion joints Traffic barriers
Procurement
Steel - Arcelor en Dillinger Cable stays - Bridon Hydraulic systeem - Hycom Electric systeem - Huisman Corrosion protection - GSB Transport - ALE Heavylift
Section B
S355ML 120 mm
S355ML 120 mm
S690QL 90 mm
Assembly of bridge
Assembly of bridge
15 October 2008
Assembly of bridge
Assembly of bridge
Assembly of bridge
Assembly of bridge
Assembly of bridge
Assembly of bridge
Bridge Load-out
Preparation load-out
Bridge Load-out
Preparation load-out
Bridge Load-out
Load-out at Hollandia
Bridge Load-out
Load-out at Hollandia Seafastening on barge
Transport to Dublin
Pass bridges in Rotterdam
2350 ton steelconstruction 160 ton equipment 250 ton ballast in bridge 2760 ton total weight
Transport to Dublin
Pass bridges in Rotterdam
2250 ton staalconstructie 160 ton equipment 225 ton ballast in brug 2635 ton totaal gewicht
Transport to Dublin
Pass bridges in Rotterdam Transport across the sea
Transport to Dublin
Arrival in Dublin Pass East Link bridge
Transport to Dublin
Arrival in Dublin Pass East Link bridge Mooring along quay
Transport to Dublin
Arrival in Dublin Pass East Link bridge Mooring along quay
Erection
Position central pipe into concrete pier
Erection
Position central pipe into concrete pier
Erection
Position central pipe into concrete pier Ballasting bridge
Erection
Position central pipe into concrete pier Ballasting brug Skidding bridge
Erection
Position central pipe into concrete pier Ballasting brug Skidding bridge Position bridge on concrete pier
Erection
Position central pipe into concrete pier Ballasting bridge Skidding bridge Position bridge on concrete pier Welding bridge to central pipe Connect Turning cylinders
Erection
Close Bridge first time on 18 June 2009 Remaining ballast in bridge (1000 ton) beginning July 2009 Concrete and Asphalt on deck (Aug and Sept 2009) Final tensioning Cable stays beginning October 2009 Commisioning Hydraulic en Electric Systeem Handover bridge to client on 30 November 2009
Questions?