Inspection and Test Plan (I. T. P.

)
I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 1 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

1.0
1.1

Materials
Conduits Each conduit Visual Category A orange heavy Field checklist duty rigid UPVC Comply with AS 2053. Type P2 Vipit at lighting column plinths & Type P4 Vipit at all other locations. Supplied as per the drawings. Moulded case de-ion circuit breakers for protection of all circuits. Three single phase circuit breakers used on three phase street lighting circuits. Generally comply with AS 3000 and RTA R151 unless noted otherwise. Bolts screws hinges etc to be hot dip galvinised & comply with AS 1214 & AS 1650. All labels to be screw fixed. Metal framed holder with perspex cover to be mounted on rear door of cabinet with circuit breakers. Field checklist

1.2

Cable Pits

Each pit

Visual

1.3

Switchboard and Electrical Details

Each

Visual

Field checklist

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 2 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

1.4

Cabling

All cables

Visual

0.6/1Kv P.V.C type V75 or Checklist V90 insulation and sheathed copper core cables, ends fitted with crimp lugs and colour coded when ever they are required. 3 phase: active = red, white/blue; Neutral = black. Single phase circuits: active = red; neutral = black; switchwires = white. Earth conductors = green & yellow.

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 3 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

1.5

Lighting Columns

All lighting columns Visual

Columns to BMES/E0149; Luminaries BMES/E0058; Lamp Control Gear Units to comply with BMES/E0057; Disconnect plug receptacles as shown on the drgs; Plug and Flex Assemblies as shown on drawing EM083; Lamps to be high pressure sodium vapour discharge lamps of wattage on drgs; Anchor Bolts to AS 1554.1 Category GP, AS1627.1-4 base plate to AS1650 & Bolts/nuts/washers to AS 1214.

2.0

Plinths for Control Cabinets & Light Columns


Excavation Each plinth Survey, visual. To dimensions on the Field check list drawings and adjacent to suitable material. Fill areas widened to suit. Unsuitable material to be removed at the Superintendent Representatives direction.

2.1

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 4 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

2.2

Concrete

HP

Prior to each concrete pour

Visual

N20/80/20 concrete Field checklist & HPRF inspected prior to pouring concrete. Finish concrete with wooden float. Comply with AS 1379.

3.0
3.1

Erection and Installation


Wiring Each lot Visual Comply with AS 3000 Wiring rules and the Service and Installation Rules of the local power supply Authority.. Field checklist

3.1

Power Supply

Each Lot 3 months prior to requirement for power.

Visual & written request

Submit written request for Field Checklist & Written power supply to notice Letter. Superindents Representative. Supply sufficient length of cable to the power pole from the power cabinet (10m). Electrodes made of solid Field checklist hard drawn copper > 12mm diameter. All exposed metal associated with electrical installation to be earthed.

3.2

Earthing

Each lot

Visual

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 5 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

3.3

Laying conduit

Each Lot

Visual

Comply with the drawings; Field checklist Min 500mm cover in a trench <300mm wide, laid square to the centre line at a straight grade on min 50mm compacted sand. Provide draw wire in all conduits. Fill compacted to min 100% - relative compaction. Consist of waterproof bituministic sealant or approved equivalent. Placed on 150mm thick drainage layer of 5mm aggregate. Set on concrete plinths. Located as per drawing EM804. Field checklist

RTA T166

3.4

Cable Jointing Pits

Installed each end of Visual conduit crossing, changes of direction and straight runs exceeding 95m.

3.5

Control Cabinets

At power supply points shown on the drawings

Visual

Field checklist

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 6 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

3.6

Cabling

Each lot

Visual

Bound together neatly without twists, kinks, knots or crossing over. Provide adequate slack for maintenance, min 450mm loop at each cable pit. Scotchcast Electrical Jointing Kits or equivalent to be used in accordance with manufacturers recommendations.

Field checklist

3.7

Lighting Columns

Each column

Field measurement Placed & bolted onto Field checklists concrete plinths, +/- 0.5 degree vertical alignment. Provide 20mm dia plastic drainage tube under mounting base. Mounting base to be completely filled with cement mortar and edge neatly chamfered. Visual Lamp control gear unit securely fastened to mounting straps. Comply with RTA R151.

3.8

Lighting Column Fixing

Each column

ITP056

REV: 0.0

22 March, 2010

Inspection and Test Plan (I. T. P.)


I.T.P. # : 056 Project : ELH Master Copy
Rev. Draft Date 19/4/01 18/6/01 Issued for review Issued for construction Reason For Revision Prepared By P.Stathis P. Stathis

Page 7 of 7
Approved For Use I.Karaban S. Glover

ITP Description :

Street Lighting RTA R151

0.0

Item No.

Inspection/Test Activity (Spec./Dwg. Refs.)


Q&E Eng

Responsibility PE/ PES/ S/C Fore RTA man

Frequency

Inspn/Test Method

Acceptance Criteria

Record

Notes

3.9

Luminiaire

Each Luminaire

Visual

Connected to lamp control Field checklist gear unit by 2.5 mm2 twin and earth TPS cable through column. End mounted to lighting spigot and weather proofed and earthed at this point & aligned parallel to the grade of the road. 1. 2. 3. Test all lighting; Close out all NCRs; Inspection and approval by local power Authority; Inspection and approval by Superintendents Representative. Field checklist and approval to commission all lighting work.

3.10

Commissioning and testing

On completion of all Visual Inspection Street lighting work

4.

ITP056

REV: 0.0