Documente Academic
Documente Profesional
Documente Cultură
The following are some samples of the standard reports available in the Oracle Primavera P6 EPPM Reports Tab. This tab is available when P6 is integrated with Oracle Business Intelligence (BI) Publisher.
Ten Six Consulting offer BI Publisher integration services, Bi Publisher training and BI Publisher report development services. Follow these links for more information. Integration Services: http://www.tensixconsulting.com/software-services/primavera-implementation-consulting/primaveraintegration/ BI Publisher Training: http://www.tensixconsulting.com/oracle-business-intelligence-publisher/ BI Publisher Services: http://www.tensixconsulting.com/primavera-p6-bi-publisher-services/
http://www.tensixconsulting.com
Primavera P6 EPPM Reports Tab BI Publisher Samples Sample Primavera P6 EPPM (BI Publisher) Reports included in this document are:
Cross Project Relationships - 3 Activity Look Ahead 4 Duration Analysis 5 Activity Relationships 6 Activity Resource Assignments 7 Schedule Report with Notebooks 8 Resource Role Skill Sets 9 Resource Code Assignments 10 Resource Role Associations 11 Code Assignments 12 Project Portfolio Review 13 Portfolio Counts 16 Document Assignments 17 Risk Scoring Report 18 Project Status Report 19 Qualitative Risk Report 20 Project Hierarchy Including Steps 21 Users 22 Project Template Management 23 Portfolio Privileges 24 Calendar User 27
Copyright Ten Six Consulting, LLC. 2012. All rights reserved. http://www.tensixconsulting.com
8/13/2012 23:04 PM
1 of 1
8/13/2012 23:01 PM
Prepare and Solicit Bids for Flooring(EC1170) Prepare and Solicit Bids for Heat Pump(EC1190) Excavation(EC1230) Review Bids for Heat Pump(EC1240) Review Bids for Flooring(EC1250) Award Contract for Brick(EC1260) Deliver Brick(EC1280)
In Progress In Progress Not Started Not Started Not Started In Progress Not Started
N Y N Y N N N
95 92 0 0 0 8 0
1 of 1
8/13/2012 23:00 PM
Duration Analysis
Activity Planned Duration Actual Duration High Estimate (25%) Low Estimate (20%) Variance %
Set Heat Pump Rough-In Plumbing/Piping Touch-up and Clean-up Fabricate and Deliver Heat Pump and Controls Install Underground Water Lines Form/Pour Concrete Footings Concrete Foundation Walls Erect Structural Frame Floor Decking Concrete First Floor Install AC Grills and Registers Assemble Brick Samples Assemble and Submit Flooring Samples Start Office Building Addition Project Award Contract for Heat Pump Assemble Technical Data for Heat Pump Form and Pour Slab Begin Structural Phase Concrete Second Floor Install Door and Window Frames Install Exterior Doors and Windows Prepare and Solicit Bids for Heat Pump Finish Carpentry and Millwork Building Addition Complete Install Lighting Fixtures Prepare and Solicit Bids for Brick Exterior
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 58 0 0 0 0 0 92 0 0 0 139
120 24 24 4104 120 230 240 472 314 360 50 0 0 0 60 72 110 0 360 24 48 144 120 0 72 144
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 100 0 0 0 0 0 80 0 0 0 121
1 of 3
8/13/2012 23:04 PM
Activity Relationships
Activity Name Design Building Addition Pred Name Start Office Building Addition Project Succ. Name Review and Approve Designs Start Office Building Addition Project FOLEY Completed Responsibility MILLS Activity Status Completed FOLEY Responsibility MILLS 05/01/2011 Responsibility MILLS Completed 05/01/2011 Responsibility MILLS Responsibility NOLAN MILLS HARIS FOLEY Completed MILLS Responsibility NOLAN 05/01/2011 Responsibility MILLS Responsibility MILLS 05/01/2011 Completed
1 of 15
Start 05/01/2011
Finish 05/01/2011 Finish 05/01/2011 Start 05/01/2011 05/01/2011 Start 05/01/2011 05/01/2011 Finish 05/01/2011 Start 05/01/2011 05/01/2011 05/01/2011 05/01/2011
Responsibility
Succ. Name Design Building Addition Review and Approve Designs Pred Name Design Building Addition Succ. Name Assemble Brick Samples Assemble Technical Data for Heat Pump Assemble and Submit Flooring Samples Begin Building Construction Assemble Brick Samples Pred Name Review and Approve Designs Succ. Name Review and Approve Brick Samples Assemble Technical Data for Heat Pump Pred Name Review and Approve Designs Succ. Name Review Technical Data on Heat Pumps Assemble and Submit HARIS MILLS Completed NOLAN MILLS
05/01/2011 05/01/2011 Start 05/01/2011 05/01/2011 Finish 05/01/2011 Start 05/01/2011 05/01/2011
8/14/2012 1:41 AM
Design Building Addition (EC1000) Resource Name Paul Kim Duration 441.6
417.6 Start 11/01/2010 0 172.8 Duration 172.8 0 57.6 Start 02/16/2011 0 240 Start 02/28/2011 224 Duration 224 0 345.6 Duration 345.6 216 Start 02/24/2011 192 1 of 8 Start 02/23/2011 Start 02/25/2011 Start 01/17/2011
11/01/2010 Finish 01/19/2011 11/01/2010 01/17/2011 Finish 02/17/2011 02/17/2011 02/16/2011 Finish 02/25/2011 02/25/2011 02/28/2011 Finish 04/13/2011 02/25/2011 Finish 04/11/2011 02/28/2011 02/23/2011 Finish 04/18/2011 02/24/2011 Finish 04/06/2011 04/04/2011
01/19/2011
Start Office Building Addition Project (EC1010) Review and Approve Designs (EC1030) Resource Name Paul Kim Assemble Brick Samples (EC1040) Assemble Technical Data for Heat Pump (EC1050) Resource Name Paul Kim Duration 57.6
11/01/2010 02/17/2011
02/17/2011 02/25/2011
Assemble and Submit Flooring Samples (EC1060) Review and Approve Brick Samples (EC1070) Resource Name Paul Kim Review and Approve Flooring (EC1080) Resource Name Paul Kim Begin Building Construction (EC1090) Site Preparation (EC1100) Resource Name Excavator Duration 240
02/25/2011 04/13/2011
04/11/2011
02/28/2011 04/18/2011
Review Technical Data on Heat Pumps (EC1160) Resource Name Paul Kim Duration 216
04/06/2011
05/06/2011
8/13/2012 23:05 PM
Notebook Description: Grading and soil conditions will slow this operation. Check estimate. Also, Plumber availability is limited for this work.
Install Underground Electric Conduit(EC1330) Form/Pour Concrete Footings(EC1340) Concrete Foundation Walls(EC1350)
2 of 5
8/14/2012 1:42 AM
8/14/2012 1:42 AM
Classification CONTR Gary Marshall Conveying Subcontractor Roofing Subcontractor Utilities Subcontractor BPM Consultant 1 Millwork Subcontractor Thermal Protection Subcontractor Finishes & Fit-out Subcontractor Fire Suppression Subcontractor IT Consultant Sue Baxter Specialty Metal Fabricator Subcontractor FF&E Specialties BPM Consultant 2 Drywall Subcontractor BPM Consultant 3 Paul Riley Glass & Glazing Subcontractor Paving & Roadways Subcontractor Pool Installation Subcontractor Landscaping Subcontractor Concrete Foundation Subcontractor PTIC Molly Abraham Alice Wynn Lori McNeil FTTrade Operator 1 of 13
8/14/2012 1:46 AM
Process Architect (5) Judy Billings (BillingsJ) Frank Chu (Chuf) Wayne Prescott (PrescottW) Michelle Peterson (PetersonM) Ben Frost (FrostB) Accounting (2) Project Controls (Project Controls) Administrator (Admin) Business Analyst (4) Ian Vincent (VincentI) Jo Wren (WrenJ) IT Consultant (ITCon) Carina Bennett (BennettC) Business Analyst Level 1 (1) Michelle Peterson (PetersonM) Change Management Coordinator (1) Peter Cooper (CooperP) Consultant (4) External Contractors (Contr) BPM Consultant 3 (Bpm003) BPM Consultant 2 (Bpm002) BPM Consultant 1 (Bpm001) Civil/Structural Crews (0) DBA (2) 1 of 6 3 - Skilled 3 - Skilled 3 - Skilled 3 - Skilled Yes Yes Yes Yes 3 - Skilled Yes 3 - Skilled Yes 3 - Skilled 3 - Skilled 3 - Skilled 3 - Skilled No No Yes No 3 - Skilled 3 - Skilled No No 3 - Skilled 2 - Expert 3 - Skilled 4 - Proficient 2 - Expert Yes Yes Yes No No
8/14/2012 1:47 AM
Code Assignments
Location Europe Europe
2 of 3
Construction Projects
8/14/2012 1:49 AM
Haitang Corporate Park(EC00501) ISSUE qsdfsaf City Center Office Building Addition(EC00515) Nesbid Building Expansion(EC00530) Harbour Pointe Assisted Living Center(EC00610) ISSUE Building 2 Subject To Delay
Chen
Development STATUS Closed Design Initiation Development PRIORITY High Normal Normal Top High STATUS Closed Closed Closed Closed Closed STATUS Closed Closed Closed Closed Closed TYPE Threat Threat Threat Threat Threat
09/01/2010
05/01/2011
Finish Date Variance (days) is -21d on WBS: Harbour Pointe.2.4 Finish Date Variance (days) is -6d on WBS: Harbour Pointe.1.2 Forecast Overrun Unit Finishes Experiencing Productivity Delays RISK Concrete supply constrained Site access restricted for 2 weeks Weather delay due to hurricane Poor ground conditions Failed electrical inspection 1 of 3
Construction Projects
8/14/2012 1:49 AM
NOTEBOOK DESCRIPTION
Construction Projects
8/14/2012 1:49 AM
3 of 3
Construction Projects
8/14/2012 1:49 AM
Portfolio Counts
Project Count: 6 Activity Count: 608 Issues Open: 24 Opportunity:1 Threat:10 Risks
9.091%
Open
Opportunity Threat
90.91% 100.0%
1 of 1
8/14/2012 1:52 AM
Document Assignments
Document Category Activity Name
Detailed Design Specifications Assemble Technical Data for Heat Pump Document Title Detailed Design Specification Deliverable N Work Product N WBS Name Design and Engineering
Design Building Addition Document Title Detailed Design Specification Deliverable N Work Product N WBS Name Design and Engineering
Assemble Technical Data for Heat Pump Document Title Design Deliverable N Work Product N WBS Name Design and Engineering
Design Building Addition Document Title Design Deliverable N Work Product N WBS Name Design and Engineering
1 of 3
Risk Scoring Report 8/14/2012 1:53 AM City Center Office Building Addition Project Summary Project ID: EC00515 Project Name: City Center Office Building Addition Total Activities: 71 Completed: 13 In Progress: 3 Data Date: 05/01/2011 Finish: 07/03/2013 At Completion Cost: $745,786 Actual Cost to Date: $124,028 Remaining Total Cost: $621,758 Risk Summary Report Date: Total Risks: Threats: Opportunities: Proposed Risks: Risk by Tolerance Threshold Probability Impacts Schedule Cost Tolerance Open Risks: Active Risks: Rejected (Closed): Managed (Closed): Impacted (Closed):
Probability and Impact Scoring (PID) Risk Score is based on: Highest Impact Impact Severity 1 Severity 2 Severity 3
Key
As of: 05/01/2011
Project Status Report for: City Center Office Building Addition (EC00515)
SPONSOR BUSINESS SEGMENT PROJECT MANAGER CURRENT PHASE LOCATION
Forsyth
DESCRIPTION
1004050
Thomas
Design
Europe
Project is for the addition to the office building in center city. This includes design and construct work.
START FINISH
11/01/2010
APPROVED BUDGET
07/03/2013
COST TO DATE
TARGET FINISH
% COMPLETE
ACTIVITIES COMPLETED
PROJECT SCORE
06/19/2013
AT COMPLETION
14.88%
COST VARIANCE
13 of 71
LABOR TO DATE
80
LABOR VARIANCE
$734,195
PRIORITY ISSUES 0 priority of 0 issues
$124,028
$745,786
-$11,591
OPEN RISKS 0 open of 0 risks
2038 h
-201.4 h
NOTEBOOKS
MILESTONES Date Assemble Brick Samples Assemble and Submit Flooring Samples Begin Building Construction Begin Structural Phase Building Addition Complete 2/15/2011 2/15/2011 2/15/2011 11/10/2011 6/19/2013 Status Completed Completed Completed Not Started Not Started
Qualitative Risk Report 8/14/2012 1:54 AM City Center Office Building Addition Project Summary Project ID Project Name Total Activities Completed In Progress EC00515 City Center Office Building Addition 71 13 3 Data Date Finish At Completion Cost Actual Cost to Date Remaining Total Cost Risk Summary
$124,028
8/14/2012 1:55 AM
8/14/2012 2:05 AM
Users
Login Name admin biadmin user01 user02 Personal Name admin biadmin user01 user02 Resource MathisL Trades Product Dev Global Profile <Admin Superuser> <Admin Superuser> <Admin Superuser> <Admin Superuser>
Page 1 of 1
8/14/2012 2:06 AM
1 of 1
8/14/2012 2:06 AM
Profile Privileges
Profile Scope Security Profile Security Privilege GLOBAL <No Global Privileges> Administrator Add Global Activity Codes Add Global Issue Codes Add Project Codes Add Resource Codes Add Resources Add/Delete Secure Codes Add/Edit/Delete Activity Step Templates Add/Edit/Delete Categories and Overhead Codes Add/Edit/Delete Cost Accounts Add/Edit/Delete Currencies Add/Edit/Delete Financial Period Dates Add/Edit/Delete Funding Sources Add/Edit/Delete Global Activity and Assignment Layouts, Views and Filters Add/Edit/Delete Global Calendars Add/Edit/Delete Global Dashboards Add/Edit/Delete Global Portfolios Add/Edit/Delete Global Project, WBS and Portfolio Layouts, Views and Filters Add/Edit/Delete Global Reports Add/Edit/Delete Global Resource and Role Teams Add/Edit/Delete Global Scenarios Add/Edit/Delete Issue Forms Add/Edit/Delete Microsoft Project Templates Add/Edit/Delete OBS Add/Edit/Delete Project Templates Add/Edit/Delete Rate Types and Units of Measure Add/Edit/Delete Resource Calendars
1 of 14
8/14/2012 2:06 AM
Profile Privileges
Profile Scope Security Profile Security Privilege Add/Edit/Delete Resource Curves Add/Edit/Delete Risk Categories, Matrices, and Thresholds Add/Edit/Delete Roles Add/Edit/Delete Security Profiles Add/Edit/Delete Timesheet Period Dates Add/Edit/Delete User Defined Fields Add/Edit/Delete User Interface Views Add/Edit/Delete Users Administer Global External Applications Administer Scheduled Services Approve Resource Timesheets Assign Secure Codes Delete Global Activity Codes Delete Global Issue Codes Delete Project Codes Delete Resource Codes Delete Resources Edit Application Settings Edit Global Activity Codes Edit Global Change Definitions Edit Global Issue Codes Edit Global Tracking Layouts Edit Project Codes Edit Projects from Scorecards Edit Resource Codes Edit Resources Edit Secure Codes Import Project Management XER, MPP, MPX, and P3 Import XLS Import XML
2 of 14
8/14/2012 2:06 AM
Profile Privileges
Profile Scope Security Profile Security Privilege Provision Users from LDAP View All Global/Project Data via SDK View Resource Role Proficiency View Resource and Role Costs/Financials View Secure Codes
Executive / Stakeholder Add Project Codes Add Resource Codes Add/Delete Secure Codes Add/Edit/Delete Funding Sources Add/Edit/Delete Global Activity and Assignment Layouts, Views and Filters Add/Edit/Delete Global Portfolios Add/Edit/Delete Global Project, WBS and Portfolio Layouts, Views and Filters Add/Edit/Delete Global Resource and Role Teams Add/Edit/Delete Resource Curves Add/Edit/Delete Security Profiles Add/Edit/Delete User Defined Fields Add/Edit/Delete Users Approve Resource Timesheets Assign Secure Codes Delete Project Codes Delete Resource Codes Edit Global Tracking Layouts Edit Project Codes Edit Projects from Scorecards Edit Resource Codes Edit Secure Codes
3 of 14
8/14/2012 2:17 AM
Calendar Use
Calendar Name Corporate - Standard Full Time (Default Calendar) Project ID CORP00591 CORP00424 CORP00307 CORP00103 CORP00768 CORP00118 CORP00712 CORP00595 CORP00852 CORP00384 PROD00914 PROD00414 PROD00111 PROD00228 Project Name Order Management Redesign Lead Qualification Project VincentI Online Invoice Generation Project CharlesM Order Fullfillment Phase II ZhuS Logistics Reengineering Program LaffertyV GIS Interface Project BennettC Cash Flow BI Project PaxsonD Nexus Project SinghD eBusiness Transformation Program SharpeD Alliance Portal Integration Project ITCon Project Nano LiR 4G Tablet Project RiceB Magna Pad Product Test Xstar Release II ChopraA AbrahamM 2 of 10 Barbara Rice, PMO Director Amit Chopra Molly Abraham Roy Li IT Consultant Dan Sharpe Deepak Singh Dan Paxson Carina Bennett Vanessa Lafferty Shannon Zhu Mandy Charles, VP IT Ops Ian Vincent Resource ID AndersonG Resource Name Glen Anderson, VP Development