-Interface & Boundary meteringResource person: M.V.Prakash, AEE, EBC, KPTCL. August 25, 2010 Bengaluru
Contents
What is interface metering?
KERC Observations
Issues addressed
Status of IF Metering
The metering boundary may differ from the geographic as well as the
ownership boundaries
From the current year KERC has moved from energy based transmission tariff to capacity based tariff
GENERATION
11/15 KV
TRANSMISSION
11 KV SUB TRANSMISSION
33 KV
11 KV
11 KV DISTRIBUTION
0.415/0.23 KV
gantry onwards.
Distribution & Retail Supply Licensee. Metering point for the sale of power to the bulk consumers and CPPs shall be at the point of connection with their systems.
KERC Observations
Observations of KERC at the time of assignment of licenses to DISCOMs 29th May 2002
Several commercial and operational matters that need to be
KERC Observations
It has been mentioned that as per the survey conducted in December 01, there were 85 un-metered interface points and that metering of the same
Educating the station staff on the IF-Metering related aspects and its importance
Issues relating to Auxiliary consumption Calibration of meters Joint meter readings management Issues relating to Inter-DISCOM energy flow
BDISCOM
MDISCOM
GDISCOM
HDISCOM
CESC
HUKKERI
TOTAL
11 33
464 4
81 27
116 46
159 101
148 5
4 3
972 186
EHT
66
110 220
32
0 6 5
0
6 1 2
2
9 2 4
1
2 1 1
14
0 0 10
0
0 0 0
49
17 10 22
11
33
0
511 267
0
117 56
9
188 69
10
275 108
0
177 89
1
8 3
20
1276 592
11 KV 33 KV
741 1 48 0 7
281 11 21 0 0
113 24 0 7 3
189 62 3 16 5
283 114 1 7 4
8 3 0 0 0
1615 215 73 30 19
EHT
66 KV
110 KV 220 KV
IPP 11 KV 33 KV Total No. of Interface points Auxiliary
8
0 805 405
12
0 325 168
2
6 155 71
4
15 294 113
3
24 436 161
0
1 12 4
29
46 2027 922
Ring fencing is required for measuring the net input energy (difference of energy entering into and leaving) of the DISCOM through installation
of :
Import/export meters at the boundary of those lines that are feeding outside as well as inside area of operation so that import
This is the current focus of all DISCOMs and most of the companies in Karnataka have already ensured this
feeding more than one DISCOM the meter at the sending end shall be
considered as main meter and the other at receiving end as
complement meter
action accordingly.
Regarding metering of EHT/open access consumers including captive users, same shall be taken up by respective DISCOM