Ref No. NS1-MCS (ARV)-EVN-S(DRI)-0804 Date: 18 October 2012 To: Attn to: CC: From: Vietnam Electricity Group Thermal Power Project Management Board No.2 Mr. Nguyen Xo Viet, Director of PMB2 Mr. Nguyen Tien Khoa, Vice Director of PMB2 J-Power/AF-Consult Switzerland Consortium Mr. Kiichiro Onoyama Marubeni Corporation Nghi Son 1 Site Office Tel : +84-37-8711501/502 Fax: +84-37-8711500 Tel : +84-38-3-240-051 Fax: +84-38-3-523-299
__________________________________________________________
Page(s): 1 + 21 Project: Nghi Son 1 Thermal Power Plant Construction Project
Subject: Documents Required for Inspection at site (MC Invoice No. 2PN07638)Steel Conduit Accessories
Dear Sirs, As the delivery inspection for following items are planned on: 20 October 2012, we are pleased to submit the documents required for inspection as attached. No. 1 Transmittal No. (Date)
Please find as attached.
Drawing No.
Hence, we would like to request to dispatch your examining staffs to attend the Inspection. Your attention would be highly appreciated.
c.c.
Fuji Electric Marubeni Tokyo (B715) Marubeni HAN (HAMPOWR) Marubeni HCM (HCMPOWR) Marubeni NS1 Site
Nghi Son 1 TPP Construction Project (on behalf of Mr. Yasushi Matsumura, Project Manager)
Attachment:
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT, VIETNAM CONTRACT NO.: 010610/NS1-EVN-MC
Issue Status A: For Approval I: For Information AB: As Built Drawing C: Internal Design
Return Status A: Approved AC: Approved with Correction Indicated I: Information Only X: Returned for Correction
Drawing Title
Due Date
Return Letter No
Return Date
Return Status
CaRs
18B-E-ARV-5021
NS1-AR-3346PX0935021
EVN-D-2953
04 Jul 12
MC-5535
27 Jul 12
AC
3457
Printed: 10/18/2012
ARV 1 of 1
VIETNAM ELECTRICITY THERMAL POWER PROJECT MANAGEMENT BOARD NO. 2 Address: No.2 Duy Tan Street, Hung Phuc Ward, Vinh City, Nghe An Province, Vietnam; Tel: +84 38 2 240 051; Fax: +84 38 3 523 299;
ORIGINAL
: : : :
NS1-MCS(ARV)-EVN-S(DRI)-0804 30- October -2012 Marubeni Corporation Mr. Yasushi Matsumura, Project Manager
Certificate of Arrival
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT THE DELIVERIES AT SITE IN JULY 2012
: : : : :
Nghi Son Thermal Power Plant Construction Project (I) Marubeni Corporation 010610/NS1-EVN-MC June 01, 2010
In accordance with conditions of the Contract, we, the undersigned, on behalf of EVN hereby certify the oversea manufactured equipment, and material has been delivered at site on July 2012 and confirmed with the relevant conditions of the Contract. The details of the delivered cargoes are described in the Attachment CONFIRMATION OF EQUIPMENT/ MATERIAL DELIVERED AT SITE This Certificate is used only for the purpose of calculating, invoicing, making payment under L/C in accordance with the payment terms stipulated in the above Contract. Best Regards,
_______________________
VIETNAM ELECTRICITY THERMAL POWER PROJECT MANAGEMENT BOARD NO. 2 Address: No.2 Duy Tan Street, Hung Phuc Ward, Vinh City, Nghe An Province, Vietnam; Tel: +84 38 2 240 051; Fax: +84 38 3 523 299;
: : :
NS1-MCS(ARV)-EVN-S(DRI)- 0804 Nghi Son Thermal Power Plant Construction Project (I) Marubeni Corp oration
Refer to Attached
Confirmed by : Contractor: Marubeni Corporation Consultant: JPOWER/ AF Switzerland (Consortium) Owner: EVN/ Thermal Power Project Management Board No.2
Consult
Name: Date:
Name Date:
Name Date:
Name: Date:
Name Date:
Name Date:
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT Attachment 1 COMMENT SHEET ON EQUIPMENT/ MATERIAL INSPECTION Equipment/Material Description Invoice No. Confirmation on Delivery to Site Ref. Letter No. No.
No.
MC Reply / Explanation
Conclusion
Consult
Name: Date:
Name Date:
Name Date:
MARUBENI CORPORATION Marubeni Corporation Site Office Nghi Son 1 Thermal Power Plant Construction Project
Attachment 2 Inspection Attendees Sheet
No 1 2 3
NAME
COMPANY