Sunteți pe pagina 1din 4

Version: 1.0.

1 Ref: Solution\INP\Interface Addition

Solution Document for Interface (A, A-ter, Pb, Gb, A-bis, POI) addition of Pirganj BKB_RBM14_additional Plan

1 Prepared by: Mohammad Nurul Momin Verified By: Masudur Rahman, VP, INP

Version: 1.0.1 Ref: Solution\INP\Interface Addition

Executive Summary:. How many interface need to increase and total volume of increment. Location Pirganj BKB Background: Reason for this increase. Existing corresponding node Utilization and Capacity: Provide existing network capacity and utilization report. Forecasted corresponding node utilization and capacity: Provide forecasted report. Hardware change Information (If required) for this addition: Does any hardware need to upgrade or replace or add to increase the interface? Location Pirganj BKB Node name BSC RBM14 Hardware name A-Ter & A Interface Hardware functionality Node Name RBM14 No. of interfaces

Check list for Interface addition: 1. Corresponding Node Hardware and software capacity check 2. Transmission availability check Interface configuration information:

RBM14
Ater-BSC side SubrackSlot-Port 0-16-12 0-16-25 1-16-0 to 1-16-3 Ater-TC side SubrackSlot-Port 6-14-12 6-14-25 6-16-0 to 6-16-3

A Interface SubrackSlot-Port 6-19-20 6-19-27 6-19-28 to 6-19-43 CIC value ---Plan for 6 Ater & 24 A interface expansion MGW Port Remarks

2 Prepared by: Mohammad Nurul Momin Verified By: Masudur Rahman, VP, INP

Version: 1.0.1 Ref: Solution\INP\Interface Addition

MGW plan
MSC RM31 BSC MSC port Info Frame 3; Slot 1; Optical Port 0; E1 20 ~ 43

CIC 6688 - 7455

RBM14

Transmission plan
Transmission routs Plan:

BSC RBM14 MSC RM31 Vendor Huawei A-ter No 33 34 35 36 37 Media BSC ET

BSC Site MSC Site Location map BSC END TX

Pirganj BKB Majhira Remote TC END TX Pirganj_RTN_4PD1P01 Pirganj_RTN_4PD1P02 Pirganj_RTN_4PD1P06 Pirganj_RTN_4PD1P07 Pirganj_RTN_4PD1P08 Pirganj_RTN_4PD1P09 TC ET

Ater Count 36

Tx Route Bogra_RTN2_4PD1P01 Bogra_RTN2_4PD1P02 Bogra_RTN2_4PD1P06 Bogra_RTN2_4PD1P07 Bogra_RTN2_4PD1P08 Bogra_RTN2_4PD1P09

End to End configuration complete. RO is requested to cross connect with BSC ports.

Transmission Protection information:

Detail activity plan:


Detail Activity list sequentially with source of Equipment. Activities should be synchronizing with TNP. Risk and Mitigation plan:

3 Prepared by: Mohammad Nurul Momin Verified By: Masudur Rahman, VP, INP

Version: 1.0.1 Ref: Solution\INP\Interface Addition

Risk and mitigation plan for example if there is any dependency on Core or BSC resources. Impact of this increase: Total impact for this increase. Expected Time line: Propose a feasible expected time line to finish these activities.

4 Prepared by: Mohammad Nurul Momin Verified By: Masudur Rahman, VP, INP