LEWIS BUILDS CORP. – TRUMP INTERNATIONAL HOTEL & TOWER

Lewis Builds enlisted approximately 50


trades to work on Trump Toronto, and
even went overseas to hire several
NICE FORM
standout specialty subcontractors. Trump Toronto is a reinforced con-
crete structure. Lewis Builds is using
a PERI automatic climbing system that
operates on hydraulic jacks to run up
the elevator cores.
“For the perimeter of the building,
we’re using a PERI rail climbing sys-
tem,” Mark Garland explains.
“This consists of three levels of ply-
wood sheathing that act as a good
wind screen for construction work-
ers and prevent the concrete and
other work materials from blowing
off the building.”
In addition, 50 West Street will fea-
ture a sophisticated design with a warm
color palette, as well as the use of high-
end woods and European-designed fur-
nishings.

Garland says. Lewis Builds is utilizing


approximately 50 trades, a few of which
were recruited specifically for Trump
Toronto. “Suncoast Post-Tension and King
Rebar from Houston and Denver, respec-
tively, will furnish and install all of the post
tension and rebar,” he notes.
The company even went overseas in
search of the best trades. Garland says that
when Lewis Builds was soliciting bids for a
curtainwall contractor, “all of the local com-
panies were busy.
“So, we ended up going to China and
considered three different firms there. We
hired Far East Aluminum, headquartered
in Hong Kong, who is the same curtainwall
through seven above grade. “We will not performed at night, he adds. contractor for the Burj Dubai – the tallest
be cladding those levels until late in the job “After the concrete structure is topped building in the world.”
so we can use those parking levels for stag- out, we have to demolish the temporary Far East Aluminum is expected to
ing material,” Garland says. “The cur- flat floor plate and construct the ramps begin work on the curtainwall installa-
tainwall will start on floor eight rather that go up and down into the basement tion in May.
than down at ground level. Then, we’ll and level two parking area,” Garland con- Garland says the key to Lewis Builds’
come back and fill that in later.” tinues. “This means we’re only construct- success on Trump Toronto is open com-
Another construction logistics concept ing a third of the ramp widths initially so munication with all trades.
is the use of temporary iron grate in the we can drive fork trucks up and down. “We have a standard practice of hold-
ground floor slab. “We’re organizing it so The permanent ramp won’t be completed ing preinstallation conferences for every
the concrete mixer trucks will drive right until after the concrete work is finished.” new element of work that commences,”
through the martini bar into the building For worker and public safety, Lewis he explains. “Typically, we’ll have one of
lobby and discharge their concrete into a Builds installed an overhead protection sys- our project coordinators lead a weekly pre-
concrete pump that sits in the basement,” tem designed for 150-pound-per-square- installation conference that includes the
Garland says. foot live loads and a 5,000-pound punching subcontractor on the new element of work
“We’re able to fit four mixer trucks sheer around the perimeter of the building. along with the relevant design engineer
into the lobby so the concrete deliveries that’s been involved in that part of the
can continue uninterrupted.” Hand-Picked Trades building’s design. We find that this sys-
Because of the project’s urban loca- Selecting the right subcontractors is criti- tem helps us avoid rework and gets it
tion, most of the concrete work will be cal when working on high-profile projects, built right the first time.” ■

74 ■ WWW.CONSTRUCTION-TODAY.COM ■ FEBRUARY 2009