FUNCTIONAL TEST
Party filling out this form and witnessing testing ______________________________ Date of test ______________________
2. Prerequisite Checklist
a. The following have been started up and startup reports and prefunctional checklists submitted and approved ready for functional testing: __ ACCU-1-7; FCU-1-7 b. __ All control system functions for this and all interlocking systems are programmed and operable per contract documents, including final setpoints and schedules with debugging, loop tuning and sensor calibrations completed. __________________________________ Controls Contractor Signature or Verbal _________________________ Date
c. d. e. f. g. h. i. j. k.
__ Test and balance (TAB) completed and approved for the hydronic systems and terminal units connected. __ All A/E punchlist items for this equipment corrected. __ These functional test procedures reviewed and approved by installing contractor. __ Safeties and operating ranges reviewed. __ Test requirements and sequences of operation attached. __ Have all energy savings control strategies, setpoints and schedules been incorporated that this equipment and control system are capable of? If not, list recommendations below. __ BAS Program Review. Review the BAS software control program(s) for this equipment. Parameters, setpoints and logic sequences appear to follow the specified written sequences. __ Packaged Control Program Review. Review the packaged control program(s) for this equipment. Parameters, setpoints and logic sequences appear to follow the specified written sequences. __ Record of All Values for Current Setpoints changed to Accommodate Testing:
Pre-Test Values
Pre-Test Values
Location OK1
1st Gage or Pkg & BAS Values Stat: Stat: Stat: Stat: Stat: Stat: Stat:
Final Gage or Pkg & BAS Values Stat: Stat: Stat: Stat: Stat: Stat: Stat:
Pass Y/N?
FCU-1 stat temp. FCU-2 stat temp. FCU-3 stat temp. FCU-4 stat temp. FCU-5 stat temp. FCU-6 stat temp. FCU-7 stat temp.
appendix 3 101
6.
Proced. No.
1
Seq. ID1
ACCU Failure. With the units running in normal mode, shut off power to the ACCU. Low Temp. Operation. During outdoor weather between 20F and 30F, verify that the unit functions and does not shut down on safeties. TREND LOG 1. For 3 of the units, during near design conditions in summer, trend the OSAT and the space temp, in 15 min. intervals for 3 days. -Return all changed control parameters 4 and conditions to their pre-test values
Verify that the unit keeps the space within +/- 3F of setpoint.
MONITORING AND TREND LOGGING. Five monitoring via BAS trend logs are required per test Procedure 4. Trend logs none shall be provided in electronic continuous columnar spreadsheet compatible format. Trends all shall be provided in hard tabular format (continuous columnar with time in left column and at least four columns of point values in adjacent columns). All points for a given trend will begin at exactly the same time. Provide a key to all abbreviations. Attach representative graphs or columnar data and explanatory analysis to this test report.
1 2 3 4
Sequences of operation specified in Contract Documents (attached). Step-by-step procedures for manual testing, trend logging or data-logger monitoring. Include tolerances for a passing condition. Record any permanently changed parameter values and submit to Owner.
FCU / ACCU ID # Procedure 1a. Lower space setpoint. FCU starts and then ACCU starts (Y/N) 1a. ~ 55F air delivered (record air temp) 1a. No excessive evap or cond. Noise (Y/N) 1b.Raise space setpoint to meet space. FCU and ACCU shut OFF, (Y/N) 2. Lower setpoint till running. Shut off power to ACCU. FCU shuts down. (Y/N) 3. Observe operation during 20-30F. Units run OK. (Y/N). 4. Trend 3 of the units. Maintain setpoint? (Y/N) 5. Return setpoints to original? (Y/N) 1 2 3 4 5 6 7
-- END OF TEST --