Documente Academic
Documente Profesional
Documente Cultură
December 2012 | 11
Incident
Naptha/ hydrogen feed Reactor effluent feed Reactor outlet ~630F710F E-6600A
December 2012
Expansion bellows Cooled reactor effluent to E-6600F shell side Naptha feed from E-6600F tube side
reactor effluent passing into the shell. The effluent, conversely, was cooled by the feed. The heat exchangers were first installed in 1971 and rated at 24,800 bpd. Subsequently, this was uprated to 42,000 bpd, the current capacity. At the time of the incident on E-6600E (Figure 2), exchangers E-6600A/B/C were in the final stages of being brought back on line after cleaning.
after cleaning. The seven people were two operators required for this job, their supervisor and four men being trained.
100 900 TemperatureF 800 700 600 500 400 300 0 500 1000 1500 2000 2500 3000
satisfactory performance no internal decarburation or fissuring internal decarburation and fissuring present
The incident
Heat exchanger E-6600E ruptured, releasing a mixture of hydrogen and naphtha which auto-ignited, causing an explosion and fire that fatally injured seven employees who were in the area. The failed heat exchanger is shown in Figure 4, which illustrates the massive nature of the rupture. Exchangers E-6600A/B/C were being brought back on line
December 2012 | 13
b) After Tesoro acquired the refinery in 1998, an in-depth corrosion review was carried out in 1999 and updated in 2003. c) The most recent study took place in 2008. All of these identified that HTHA was a concern in the two hottest heat exchangers, E-6600A and D but not in E-6600B or E. Thus, no prior-to-incident HTHA susceptibility was identified for E-6600E. Figure 4: The failed section (No. 3) of heat exchanger E-6600E bending and tensile strength tests all confirmed consistency with specified design materials. A second exchanger, E-6600B, was tested and inspected by the same means as E-6600E. The two exchangers had a very similar construction and service history and E-6600B had been exposed to the fire from the E-6600E rupture although it had remained intact. The results indicated that E-6600B was in a similar microstructural condition to E-6600E particularly with regard to HTHA in the heat affected zones of the weld seams.
Temperature measurement
There was no intermediate temperature instrumentation between individual heat exchangers, so very limited data existed on actual operating temperatures of E-6600E. Reactor outlet temperatures were reviewed and shown to be as per design except for very short periods, so it could be deduced that temperatures between heat exchangers had been similarly in line with design specification. One very high reactor temperature excursion to 620oC was noted in 1998, though it was likely to have been of very short duration. At the combined E-6600 shell outlet, there was a thermometer in a thermal well. This showed temperatures in the range 120150oC which was consistent with design specification. Absolute temperatures for the E-6600s would have varied during operations depending on many factors, including exchanger fouling but lacking actual process data, it was not possible to draw definitive conclusions about the temperature profile within the heat exchanger train.
The post-incident design (2010) specified a value of 1960 kPa. H2pp is known to vary with hydrogen makeup, system pressure, intermediate exchanger pressures and operation of the recycle compressor, so this disparity of readings was not surprising and the investigation could draw no firm conclusions from them. Operating conditions for H2pp and temperature could not be determined with certainty.
Corrosion reviews
Types of corrosion that could be expected in the heat exchangers had been reviewed before the incident occurred. Thus: a) The first review was completed in 1990 and updated in 1993. At the time, Shell Oil owned the refinery.
December 2012
Conclusion
The rupture occurred because the strength of E-6600E shell had been reduced by HTHA to the extent that the total stress that existed could not be withstood. This was primarily due to lack of post-weld heat treatment. Other factors which might have caused stress such as very high temperatures or pressures, did not exist. The potential for HTHA had not been detected before the incident.
(vii) To establish suitable training in corrosion mechanisms for operational and technical staff. (viii) To fabricate replacement heat exchangers that are not vulnerable to HTHA and to identify, inspect, protect and, if necessary, replace other non post-welded equipment in hydrogen service. (ix) To review and update the corrosion studies, to develop a guidance document for calculating hydrogen partial pressure and to revalidate the standard hydrogen partial pressures in all hydrogen processing plant.
Recommendations
The investigation team made a range of recommendations in the form of corrective actions in accordance with their terms of reference. Thus: (i) In relation to the fatalities, to re-design the heat exchanger train so as to eliminate the need for on-line exchanger cleaning and to develop policies to control the number of people present in potentially hazardous areas at plant start-ups and shutdowns. Minimising the number of people in the vicinity of such operations, as far as is reasonably practicable, is very important. (ii) To install temperature and pressure instrumentation on the inlet and outlet of each reactor feed/effluent heat exchanger. (iii) To review similar hydroprocess units to determine any need for additional instrumentation to manage HTHA. (iv) To establish the safe operating limits (integrity operating window) for hydrogen partial pressure and temperature in hydroprocessing units fabricated of carbon steel and C-Mn-0.5Mo alloys. (v) To install adequate control instrumentation to manage and indicate these parameters (iv above) and to provide a means of alerting operators to significant deviations. (vi) To increase the standard safe operating margin for equipment in hydrogen service below the Nelson Curve in accordance with evidence of occasional failure below thecurve.
References
1. Naphtha Hydroheater E-6600E Failure, April 2, 2010; Anacortes Refinery, Washington; TOP Investigation Team Report 100402OPR038, July 21, 2010. 2. American Petroleum Institute Recommended Practice 941, 7th Edition, August 2008. 3. Cracking of Non-PWHT Carbon Steel at Conditions below The Nelson Curve, ASME Conference, July 2010.