10 Checking BTS3812E Hardware Installation

10
About This Chapter

Checking BTS3812E Hardware Installation

The checklists for the BTS3812E hardware installation refer to the power-on status check of the BTS3812E cabinet, the power-on status check of the BTS3812E boards, the checklist for the BTS3812E cabinet installation, the checklist for the BTS3812E cable installation, and the checklist for the BTS3812E installation environment.

Issue 03 (2008-01-30)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd

10-1

10 Checking BTS3812E Hardware Installation

BTS3812E Installation Guide

10.1 Checking the Power-On Status of the BTS3812E Cabinet


This topic describes how to perform the power-on status check of the BTS3812E cabinet.

Prerequisite
l

As shown in Power Supply Requirements of the BTS3812E, the power supply requirements of the BTS3812E are met. Hardware of the BTS3812E is installed. All the power switches on the BTS3812E busbar are set to OFF. The power supply of the BTS3812E is cut off.

l l l

Procedure
Step 1 Turn on the power switch of the BTS3812E cabinet. Step 2 Check whether the output voltage of the BTS3812E cabinet is proper. If... The output voltage of the BTS3812E is out of the range from -40 V DC to -60 V DC. The output voltage of the BTS3812E is within the range from -40 V DC to -60 V DC. Then... A power failure occurs to the cabinet. Go to Step 3.

The power-on check of the cabinet ends.

Step 3 Turn off the power switch of the BTS3812E cabinet to cut off the power supply. Step 4 Check the output voltage of the power distribution cabinet, the installation of the power cables, and the routing of the BTS3812E power cables. Step 5 Go to Step 2 to check the output voltage again till the output voltage of the BTS3812E becomes proper. ----End

10.2 Checking the Power-On Status of the BTS3812E Board


The EMI signal cable (48 V) is used to supply power to the EMI and to transmit EMI signals.

Prerequisite
l

As shown in Power Supply Requirements of the BTS3812E, the power supply requirements of the BTS3812E are met. Hardware of the BTS3812E is installed. All the power switches on the BTS3812E busbar are set to OFF.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 03 (2008-01-30)

l l

10-2

BTS3812E Installation Guide


l

10 Checking BTS3812E Hardware Installation

The power supply of the BTS3812E is cut off.

Context
The power switches on the busbar are shown in Table 10-1. Table 10-1 Power switches on the busbar Board MAFUs 0 through 5 MTRU0 MTRU1 MTRU2 MTRU3 MTRU4 MTRU5 FAN Boards in the baseband subrack Power Switches on the Busbar AFU TRU0 TRU1 TRU2 TRU3 TRU4 TRU5 FAN NBBU

Procedure
Step 1 Set the power switch of the fan subrack to ON. Step 2 Check whether fans work properly. If... Fans do not work properly, Fans work properly, Then... Power failure occurs to the cabinet. Go to Step 3. Power supplied to the cabinet is operational. Go to Step 4.

Step 3 Set the power switch of the fan subrack to OFF. Ensure that connections of power cables to the boards and the subracks are correct, and then go to Step 1. Step 4 Set the power switch of the baseband subrack to ON. Step 5 Check whether all the LEDs on a baseband board are ON and then OFF. If... All the LEDs on a baseband board are ON and then OFF, All the LEDs on a baseband board are ON,
Issue 03 (2008-01-30)

Then... The board is not securely inserted. Go to Step 6. The board is securely inserted. Go to Step 7.
10-3

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd

10 Checking BTS3812E Hardware Installation

BTS3812E Installation Guide

Step 6 Fasten the captive screws on the filler panel or reinstall the board. After you install the board tightly, all the LEDs will be ON within three seconds and will not be OFF. Step 7 Set power switches for the MTRUs to ON, and check whether the three LEDs on each MTRU are all ON. If... The three LEDs on each MTRU are all ON, The three LEDs on each MTRU are in other states, Then... The MTRU is properly powered on. Go to Step 8. The power cable is not properly connected or other faults occur. Clear the faults and repeat Step 7.

Step 8 Set the power switch for the MAFU subrack to ON. Check whether the three LEDs on each MAFU are all ON at the beginning and then the PWR LEDs are ON while the ALM LED and the VSWR LED are OFF. If... The three LEDs on each MAFU are ON at the beginning and then the PWR LED is ON while the ALM LED and the VSWR LED are OFF, The three LEDs are all ON steady, The three LEDs are all OFF steady, The three LEDs on the MAFU are in other states, Then... Power and communication cables are operational. The power-on check ends.

The communication between the MTRU and the MAFU is faulty. Go to Step 9. Power failure occurs to the MAFU. Go to Step 10. Go to Step 11.

Step 9 Reinstall the cable between the MAFU and the serial port on the MTRU. Check whether the ALM LED and the VSWR LED are OFF. If... The ALM LED and the VSWR LED are OFF, The ALM LED and the VSWR LED are ON steady, Then... The MAFU is properly powered on. The poweron check ends. Go to Step 11.

Step 10 Reinstall the power cable from busbar to MAFU. Check whether the LEDs on the MAFU are ON at the beginning and then the PWR LED is ON steady while the ALM LED and the VSWR LED are OFF.
10-4 Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 03 (2008-01-30)

BTS3812E Installation Guide

10 Checking BTS3812E Hardware Installation

If... The ALM LED and the VSWR LED are OFF, The ALM LED and the VSWR LED are ON steady,

Then... The MAFU is properly powered on. The poweron check ends. Go to Step 11.

Step 11 Clear the faults and go to Step 8. ----End

10.3 Checklist for BTS3812E Cabinet Installation


This topic describes the checklist for installation of the BTS3812E cabinet. Check the BTS3812E cabinet according to the checklist. Table 10-2 lists the check items. Table 10-2 Checklist for installation of the BTS3812E cabinet SN 1 2 Item The cabinet layout complies with the engineering design. If the equipment room is not equipped with ESD floor, you need to install only the base before installing the cabinet. If the equipment room is equipped with ESD floor, you need to install both the support and the base before installing the cabinet. In addition, you also need to install supporting steels in the case of insufficient load capacity of the ground. 3 4 5 6 7 8 9 10 11 There are insulating pads on the four fixing holes of each base. The base (anchor) fits properly to the expansion bolt holes. The cabinet is securely connected to the base. The cabinet should stand steadily after it is installed. Both the horizontal error and the vertical error should be smaller than 3 mm. Space between the upper frame and the lower one of the base should not be more than 3 mm. The upper surface of the ESD floor should not be higher than the lower surface of the base lest that the ESD floor affect heat dissipation around the base. All screws are fastened. Check that flat washers and spring washers are mounted and the spring washer is installed on the flat washer. No parts on the cabinets are damaged or detached. No cables are scratched or broken. Dust should be cleaned from the cabinet and subracks.

Issue 03 (2008-01-30)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd

10-5

10 Checking BTS3812E Hardware Installation

BTS3812E Installation Guide

SN 12

Item The cabinet should be in clean and neat appearance. External paint should be intact and satisfactory. All labels, tags, and nameplates are correct, legible, and complete. The front door of the cabinet can be easily opened or closed. The DC surge protector for each cabinet should be correctly installed. When you adjust bolts to level the base, add spacers to the base to avoid deformation. The cover plate should be installed on the holes in the cabinet.

13 14 15 16

10.4 Checklist for BTS3812E Cable Installation


This topc describes the check items for installation of signal cables, power cables, and PGND cables after the BTS3812E is installed.

Checklist for Installation of Signal Cables


Table 10-3 shows the check items for installation of the BTS3812E signal cables. Table 10-3 Checklist for installation of the BTS3812E signal cables SN 1 2 3 4 5 6 7 8 9 10 11 12
10-6

Item Connectors on the trunk cables are securely fixed. Connectors on the trunk cables are intact. No trunk cables or RF cables are scratched or broken. Connectors on RF cables are fixed in position lest that possible false connection should cause abnormal voltage standing wave ratio. RF cables routed in the horizontal plane are clamped into cable troughs. Cables of extra length are reserved at the connectors. The cables are neatly bound. The cable ties are installed at even intervals, to a proper tightness, and in one direction. Extra cable ties are truncated. All cuts are smooth without sharp thrum. The cable layout allows easy maintenance and future expansion. All labels and tags at both ends of the cables are legible. The ports not in use on the top of the cabinet are installed with dust-proof covers. RF jumpers are distributed by layer and by sector.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 03 (2008-01-30)

BTS3812E Installation Guide

10 Checking BTS3812E Hardware Installation

SN 13 14

Item RF jumpers keep straight at their joints with the cabinets and the feeders. RF ports not in use should be installed with matched loads.

Checklist for Installation of Power Cables and PGND Cables


Table 10-4 lists the check items for installation of the BTS3812E power cables and PGND cables. Table 10-4 Checklist for installation of the BTS3812E power cables and PGND cables SN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Item The color of the PGND cables complies with the local standards and can be shared with the BTS3812AE. All the power cables and PGND cables should be copper-based. The cable diameter should meet the requirements. No power cables or PGND cables are short-circuited or reversely connected. Power cables and PGND cables are bound separately from other cables. Labels are attached to both ends of each power cable and PGND cable. No power cables or PGND cables are scratched or broken. No connectors are used to join power cables or PGND cables. No devices such as switches and fuses are applied to electric connection of the grounding system. Power cables and PGND cables of extra length are truncated. These cables cannot be coiled. Lugs at both ends of power cables or PGND cables are securely soldered or crimped. Bare wires and lug handles at the wiring terminals are tightly wrapped by insulating tapes or heat-shrinkable tubes. Flat washers and spring washers are securely and closely mounted on wiring terminals. The positive pole of the primary power cable should be properly grounded. Working ground and protection ground of the NodeB and lightning protection ground of the building share one group of grounding conductors. Grounding grids of the tower, equipment room, and transformer (if the distance between the transformer and the equipment room is shorter than 30 m) should be inter-connected.

Issue 03 (2008-01-30)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd

10-7

10 Checking BTS3812E Hardware Installation

BTS3812E Installation Guide

10.5 Checklist for Field Cleanliness of BTS3812E Installation


You need to clean the site after the installation and check the field cleanliness. Table 10-5 lists the items to be checked for field cleanliness of BTS3812E installation. Table 10-5 Checklist for field cleanliness of BTS3812E installation SN 1 2 3 Item No packing boxes or boards are placed at random in the equipment room. No cable ties or other sundries are left on the floor or in the cabinets. There are no fingerprints or other smudges on the cabinet surfaces.