Documente Academic
Documente Profesional
Documente Cultură
Mine2-4D Projects
An Introduction to creating projects in Mine2-4D MUG-M24-0006 Datamine Software Limited 2 St Cuthbert Street, Wells Somerset, United Kingdom BA5 2AW Tel: +44 1749 679299 Fax: +44 1749 670290 Grant King
This documentation is confidential and may not be disclosed to third parties without the prior written permission of Datamine Corporate Limited.
Datamine Corporate Limited
Contents
1 Introduction to Mine2-4D Purpose of this document Prerequisites More information 1 1 1 2
2 3
Background Information The User and Design Manager Introduction and Background to task Before you start Exercise 1 Create a new User List Exercise 2 - User Administration Exercise 3 Create a new File Add List Exercise 4 Create a new Attribute List Add a New Attribute Add Values for an Attribute Exercise 5 Starting a new project in Design Manager Exercise 6 Check in / Check Out Exercise 7 Project History Show History Project Setup Introduction and background to task Project Setup Sub-Projects Project Setup dialogs Project Details Design Strings Exercise 1 Mine2-4D Startup Exercise 2 Project Setup Design Strings Options Measurement system Exercise 3 Geology Interrogation Legend to use in Interrogation Exercise 4 General Options Exercise 5 Property Conventions Design and Validation Introduction and background to task Design Tab Tools Tab Data Validation Attributes Invalid Point Strings Cross Over Strings Duplicate Strings Duplicate Checking Precision Resolve Points Endlink Checking Complex Solid Checking Data Deletion Exercise 1 Edit Design Directions Exercise 2 Data Validation
3 4 4 5 8 9 10 10 10 11 13 13 13 15 15 15 16 16 16 17 17 18 19 19 20 21 21 22 23 24 25 25 27 27 27 27 28 28 29 29 29 31 33 4
15
23
Design Definitions
Introduction and background to task Filters and Attributes Buttons Applying Filters Editing Attributes Saving Changes to Attributes Cross Section Tool Segment Length Exercise 1 Design Definitions Cross Sectional Shape Segment Length Preparation Introduction and background to task Design Menu Preparation Menu Exercise 1 Define Attributes Exercise 2 Apply Design Attributes Exercise 3 - Wall & Point Generation Solids and Evaluation Introduction and background to task Preparation Solids and Evaluation Sequencing and Scheduling Reporting Exercise 1 Creating Solids Exercise 2 Evaluating Solids Sequencing Introduction and background to task Automatic Dependency Creation Position Search Origin Predecessor/Successor Position Overrider Position Scenario Link (Delay / Type) Type Examples Limiting the Search Search (Method / Radius / Origin) Exercise 1: Automatic Sequence Generation Sequencing Troubleshooting Exercise 2 Scheduling An Introduction to EPS Introduction and background to task The EPS Interface Resources Project Settings Exercise 1 Viewing your data Exercise 2 Summarising the Project Data Exercise 3 - Setting up the Crosstab Exercise 4 Creating Filters and Sorting Exercise 5 Levelling Resources Reporting
35 35 35 36 36 37 37 38 38 39 41 42 42 43 43 44 47 49 49 49 49 50 50 51 55 55 56 56 56 56 57 57 58 58 58 60 62 64 66 66 67 67 68 68 69 70 71
42
49
55
10
66
11
73
12
Introduction and background to task Evaluation Properties Schedule Exercise 1 Set Schedule Colouring Definitions Exercise 2 - Create 3D Animations Create from Schedule Exercise 3 Check in / Check Out Present Plotting Manually Introduction and background to task What is Earthworks Present? Document Wizard Exercise 1 Data Import (Strings) Exercise 2 Data Import (Wireframes) Exercise 3 Finishing the Import Exercise 4 Setting the Paper Size and Grid Settings Exercise 5 Setting Scales and Clipping Exercise 6 Zooming and Panning Exercise 7 Formatting the Wireframes Display Exercise 8 Adding a title box Present Plotting Automatically Introduction and background to task Exercise 1 Creating a Present template Mine2-4D 660 Level Introduction and background to task Exercise 1 Starting a new project Exercise 2 Project Setup Exercise 3 - Interrogation Exercise 4 Model Splitting Tool Exercise 5 Default Values and External Data External Data Exercise 6 Attribute Convention Exercise 7 Properties Exercise 8 Naming Conventions Exercise 9 Scheduler, General Options Exercise 10 Design Exercise 11 Preparation Exercise 12 Solids and Evaluation Exercise 13 Automatic Sequencing Exercise 14 - Derived Activities Exercise 15 - Reporting Exercise 16 - Colour According to Legend Mine2-4D 680 and 700 Levels Introduction Exercise 1 Exercise 2 Exercise 3 and background to task Create a New Project for the 680 Level Using the Project Cascader Complete 680 and 700 Levels
79 79 79 79 80 82 83 84 85 86 88 88 90 90
73 73 73 73 74 76 77 78
13
90
14
15
92
INTRODUCTION TO MINE2-4D
Prerequisites
To use this tutorial you will need the following components installed on your computer: Mine24D version 11.0.1409.0 or later EPS Scheduler version 1.0.1433 or later Information
To display the installed Mine2-4D version, choose Help | About Mine2-4D. about the installed product is displayed together with its version number.
M24D Manual 2
Mine2-4D Projects
More information
There are many sources of online help - designed to suit the way you work: Mine2-4D Help Contents Choose the Contents command from the Help menu to display the contents page for Datamine help. Context Help Choose the Help button on any command dialog to display help on use of the displayed dialog. Tool Tips Pass the pointer over the toolbar buttons to display tool tips and one line help on the status bar. AutoHelp Check this option on any command dialog to display the AutoHelp window. Online User Guide Comprehensive User Guides and Process Descriptions are provided on the Datamine Website at www.datamine.co.uk and the Mine2-4D website, www.mine24d.com Telephone Support The Datamine support desk is available during normal office hours from your local Datamine office. MSN Messenger Support is also available from MSN messenger. For more details, please contact your local Datamine office.
M24D Manual 2
Mine2-4D Projects
BACKGROUND INFORMATION
Mine2-4D is an Earthworks software product that uses a unique methodology to allow the integrated design and scheduling of both underground and open pit mines. Mine2-4D consists of the following main components: Design Vertical Mine2-4D Menu Adjustable
Design Window
The Vertical menu provides access to the Mine2-4D integrated design and scheduling processes. In this document, we will cover the use of the Design menu as it relates to the training dataset. The Design menu provides access to the standard Design Window and batch (dataprocessing) commands. For more information in the use of this menu, please refer to the Mine2-Design Tool training manuals (Manuals 1A and 1B).
M24D Manual 2
Mine2-4D Projects
The 660, 680 and 700 levels represent the various levels of the mine, while the Future_Infrastructure directory contains the capital development necessary to access and support mining operations from these three levels. The Common Data and Geology directories contain files that are common to all projects and will be referenced using the File Inclusion List.
M24D Manual 2
Mine2-4D Projects
What is the Design Manager? The Design Manager controls the individual Mine2-4D projects and manages the data across the network. Before being able to commence work on a project, the project must be checked out from the server to a working directory. Should the local disk be selected as the working directory, this can dramatically speed up processing. The Mine2-4D Design Manager works in conjunction with the Mine2-4D User Manager to control the use of design files and ensure data integrity. Once a user profile has been setup in the User Manager, the Design Manager controls access to project files from a central file server. The Design Manager ensures that two users cannot work on the same project file at the same time. This is to prevent loss of data when users copy worked projects back to the central file server. The Design Manager also ensures that a single user cannot check out two projects at the same time - this would lead to data being overwritten within the local working directory. Userlists and your Working Directory The Design Manager requires a user-list and working directory to be set so that a user can access and create project files Data Management and Checking Procedures Within the Design Manager, a user has access to several data management and checking procedures. These include: Adding an existing project to the Design Manager Deleting a project from the Design Manager Checking out a project Checking in a project Undoing a check out Retrieving the original data from the server Showing the working history of a project
If this icon is not visible, go to Start | Programs | Earthworks | Mine2-4d Tools | Systray to initialise. Right clicking on the icon in the tooltray should reveal the following menu:
M24D Manual 2
Mine2-4D Projects
Select File | Set Userlist Location, and create a new directory under the C:\Program Files\Earthworks\Mine2-4D directory called UserList. Select this new directory as your user-list location.
M24D Manual 2
Mine2-4D Projects
You will be prompted to enter a password for access to the new user list. Enter admin as the password. This will become the new Administrator password to the Mine2-4D system, including start-up of the software. By default, the list file (M4Duserlist.m1d) will automatically be saved to the current location, either the working directory you are in or the directory you have specified using the Set Userlist Location menu. The location of the user-list will be displayed in the status bar at the base of the dialog.
If this location is incorrect, use the Set Userlist Location option to update the directory location.
M24D Manual 2
Mine2-4D Projects
Select Options | User Administration and then enter the Administrator password admin to continue.
The fields in the User administration window represent the following: Username : the logon name for the user, and must be unique for each user. Note: The admin user-name for the Administrator cannot be deleted or renamed. Password : the password to the user log-in name - shown in an encrypted form in this dialog. The actual password may be altered by the administrator by right clicking on the row and selecting Change Password. The existing password is not required in order to change the password. Privileges : This is broken up into 4 status levels: Administrator status (of which there may only be 1), Power User status (has ability to change everything in Mine2-4D with the exception of usernames and passwords), User status (can alter designs but definition databases cannot be changed) and Read Only status, which does not have the ability to change anything in the system. Password Saves : This option should be toggled ON if remembering of the users password is allowed during user logon. If toggled OFF, the option will be disabled and the user will have to re-type the password each time they logon. Active : The activity status of a user can be toggled OFF and set to Inactive if required - their details can remain on the system, however the ability to logon is removed. If the user
M24D Manual 2 Mine2-4D Projects
attempts to logon while their status is set as inactive, a message box will appear on the machine asking them to contact the system administrator. It is recommended that rather than deleting users, the status should be set to inactive. Stand Alone : This toggle allows the user to access the system when not connected to the network. This option can be toggled OFF for users other than the Administrator. User Types : The user can be allocated a User Type to limit their access to specific areas of the database - All, Engineering, Geology or Survey.
To add and delete records from the User list simply right click on the grid and select the appropriate option. Add yourself to the user list, giving yourself Power User privileges.
Right-click on the Files to Add window, then select Add File Add the model file resmod.dm to the File Add List. This can be found in the sub-directory Geology. Repeat for the file 2dgrid.dm which can be found in the sub-directory Common Data. The File Add List screen should appear as follows :
M24D Manual 2
Mine2-4D Projects
When adding a new attribute it is necessary to specify the type of attribute - Numeric or Alpha-Numeric. If the type is Alpha-numeric, the character length of the attribute (a multiple of 4 to a maximum of 20) must also be specified.
M24D Manual 2
Mine2-4D Projects
10
Next enter the values 680 and 700 in the same way, and, finally, click Exit. The Attribute List dialog should now appear as follows.
Click OK, to return to the User Manager dialog. Select File | Exit to exit from the User Manager.
M24D Manual 2
Mine2-4D Projects
11
First select the sub-directory Working as your working directory using the option File | Set Working Folder.
If the sub-directory Working does not exist under the training directory, create it. Once you have specified your working directory, create a new project file for the Underground directory by clicking New at the bottom of the Design Manager window.
In the Browse For Folder dialog, find and select the folder Underground | Future Infrastructure (within the Database | Training | M24D folder). You will then get the following dialog, but with an empty text box:
M24D Manual 2
Mine2-4D Projects
12
Enter a name for the new project ie: Future_Infrastructure, then click OK. The project should automatically be created and checked out by the system and subsequently executed on your computer. (Warning: you may need to select or enter license details at this stage.)
Undo Check Out If no changes were made, you can undo the check out rather than check the project back in. This will eliminate the need to back-up data. The project will be checked back in and the original data will be restored on the design file server. Note that any changes made since the last check out will be lost.
M24D Manual 2
Mine2-4D Projects
13
Select Exit to return to the Design Manager dialog. In preparation for the next exercise, you will need to check the project back out by rightclicking on the project then selecting Check Out from the menu, followed by Execute. (Located in the lower right-hand corner of the Design Manager).
M24D Manual 2
Mine2-4D Projects
14
PROJECT SETUP
Project Setup
The Project Setup dialog is used to define the initial design information for a project.
Sub-Projects Sub-projects can be used in Mine 2-4D as a means of scenario analysis - each sub-project uses the same .m4d file (containing the tables for the project), but can contain a completely different design or Mine2-4D design parameters.
M24D Manual 2
Mine2-4D Projects
15
Project Setup dialogs Dialog General Conventions Geology Derived Activities Scheduler Description Allows for entry of string files to be included in the design, and basic project options. Setup of attributes, properties and naming convention to be used for the Project. Block Model setup for interrogation and depletion Definition of derived activities, including a derived activity expression builder Allows for entry of EPS Scheduler setup details. (Can also be accessed from EPS).
Project Details
Details for the current project are specified in the Project Set-up | General menu. Design Strings In the Project Setup menu you can specify the design string types to be used within the project and define the files corresponding to each active design string type. There are three design string types that can be used: fixed cross sectionals, outlines and complex solids. Fixed cross sectionals (fxs) are created by applying a fixed cross sectional area to a design string (survey line). Outlines are created by projecting closed strings a set distance perpendicularly, or by projecting them to hanging-wall and foot-wall wireframes. Complex solids (cxs) are created by wireframing two closed strings.
M24D Manual 2
Mine2-4D Projects
16
M24D Manual 2
Mine2-4D Projects
17
Design Strings The Future_Infrastructure project consists of one design file containing centre-lines for the ramp, vent and orepass system for an open stoping operation. The design file is called hwrs.dm and can be found in the Future_Infrastructure folder. 1. To attach this table to your project, select Add File to Project Add Files to Project. (or use File |
2. Next tick the Fixed Cross Sectional checkbox, then select the design string file HWRS by clicking on the browser button . A window will open listing the string files available. Because the table HWRS does not physically reside in the working folder, you will see the following message:
3. Click Yes to confirm this action. 4. Click the view button to view the fxs design strings. The strings will be loaded into the Design Window. (If this window is currently an icon, you will need to Restore it before you can see the strings.) 5. To see the loaded design strings in 3-D, right-click in the Design Window and select Update Visualizer Objects from the menu. Your Visualizer should look similar to the following:
M24D Manual 2
Mine2-4D Projects
18
Options 1. Leave all the options turned off. Measurement system 1. Set the Measurement system to Metric. 2. Check that the Project dialog has the settings shown below:
M24D Manual 2
Mine2-4D Projects
19
2. Next, ensure that the model file RESMOD is part of your project. To do this, select File | Browse Project. If RESMOD does not exist, add it to the project using File | Add Files to Project | Manually. The file you need to add is resmod.dm in the folder Geology. 3. Right-click in the grid (grey area), then select Add from the menu. A default Interrogate action for RESMOD will be added to the list:
4. This will be sufficient for a simple interrogation of all design data against the model. 5. Make sure that the Perform Dilution Calculations checkbox is ticked; this ensures that any voids are treated as waste with no grade.
M24D Manual 2
Mine2-4D Projects
20
6. Set the [Default] value for Density to [4] as shown in the following image:
Legend to use in Interrogation Although we are not using this option for this exercise, it is good to know of its existence. The Legend to use in Interrogation allows the user to specify a Legend that will be used during the interrogation. This Legend needs to have first been defined under the Format | Legend menu. The legend must be set up using a field from the geological model that is NOT going to be interrogated.
2. Ensure the default Measurement system is set to metric and the gradient convention to 1:n and +ve up, the latter meaning that a positive gradient value indicates an upwards gradient and a negative value is downwards.
M24D Manual 2 Mine2-4D Projects
21
3. Select the Scheduler tab and select the default scheduling project as the Earthworks Production Scheduler.
3. Toggle on the Including Depletion fields option. This has the effect of adding a further property: Depleted Volume. 4. Select OK to proceed.
M24D Manual 2
Mine2-4D Projects
22
The main Mine2-4D design dialog consists of the following three steps: Step 1 Design Mine2-4D automates a great deal of the mine design process by using string attributes to define different excavation types. By creating a new string (or group of strings) with a unique colour, line style and symbol, the user can apply unique attributes to the string at a later stage. Step 2 - Design Validation Mine2-4D automatics the string cleaning and checking processes via a Data Validation Wizard. Step 3 - Design Definitions Once the design stage is completed, Mine2-4D applies attributes to the strings. These attributes include description, mining rate and scheduling constraints. There are two tabs that exist under the Design menu: Design and Tools.
M24D Manual 2 Mine2-4D Projects
23
Design Tab
Under the Design tab, the following menus are available:
The Automatic Layout Tool is used to create designs from user-defined rules. Note: Design Definitions must have been run before creating the Automatic Layout rules, as they are based on the Mine2-4D description of Design Types The Design Editor enables referencing of remote files while editing design strings. Editing of Design Directions allows users to reverse the direction of design strings. It is very important to ensure a string is laid out in the correct direction for sequencing and scheduling purposes. In this instance, all of the design work has been carried out already. Therefore, all that is left to do is to edit the design directions. It is very important to ensure that the Fixed Cross-Sectional design strings run in the correct direction, i.e. the direction of mining. If not, problems will occur with the sequence and the scheduling of the design. These problems can be fixed later, but it is much more difficult and time-consuming to do so.
M24D Manual 2
Mine2-4D Projects
24
Tools Tab
Under the tools tab, the following menus are available:
The Design Tools Tab, is activated by pressing the Design icon in the main menu. The Mean Azi and Dip button calculates the mean azimuth and dip of each design string. This information is stored in a duplicate string file, via the newly created attributes AZIMUTH and DIP. The Borehole Warning dialog is used to find boreholes in the vicinity of excavations
Data Validation
The Data Validation Wizard can be used to clean the Mine2-4D design data or the data associated with any other user defined file selected via the browser. During the design process, data may be duplicated, wrongly entered or corrupted. The Data Validation Wizard offers an array of tools for removing any of this erroneous data.
M24D Manual 2
Mine2-4D Projects
25
The wizard investigates the Design Strings in the project. If no Design Strings have been defined the dialog will not operate. The Data Validation Wizard specifically deals with the following: invalid attributes invalid point strings cross over strings removal of duplicate strings and points resolution of points flagging of severe angle changes endlink checking complex solid checking data deletion
M24D Manual 2
Mine2-4D Projects
26
Attributes
This step allows the user to strip attributes from the design strings. Since all design tables in Mine2-4D are database tables, attributes are simply extra fields in these tables. Removing these attributes can reduce file size and processing time as well as keeping the data clean. To remove any unwanted attributes click on the Remove check box next to the attribute. Invalid Point Strings
Duplicate Strings
M24D Manual 2
Mine2-4D Projects
27
Duplicate Checking Precision can be set to check for points which are not exactly the same. A checking precision of 0.1 is recommended. Leaving the precision set at 0 will ensure that only exact duplicate strings are flagged. Compare String Properties can be used to specify whether design definitions are used to define duplicate strings. If the check box is toggled on, Mine2-4D will only flag duplicate strings which do not share the same COLOUR, LSTYLE and SYMBOL combination. Otherwise, all spatial duplicates will be flagged. Flag Partials can be toggled to search for strings which share two or more points. This tool is especially useful for highlighting fixed cross sectional strings that share many points but each have at least one unique point. Duplicate Example 1
The strings shown in the fixed cross sectional example above would generally not be flagged as duplicates. However, if the precision was set to 0.5, points A2 and B1 would be seen as duplicate and points A3 and B2 would also be seen as duplicate. Still, if Flag Partials was not checked, these strings would not be seen as duplicate as points A1 and B3 would both be seen as unique. Hence if the precision was set to 0.5 and the Flag Partials was toggled on for Fixed Cross Sectionals, these strings would be seen as duplicate. If the Check Design Definitions toggle for Fixed Cross Sectionals was also toggled, these strings would not be seen as duplicate as string A has COLOUR 7 while string B has COLOUR 8. Duplicate Example 2
In this second example, running with a precision of 0.5, the Flag Partials check box would not need to be toggled on to find string B as a duplicate. Because all of the points on string B can be found on string A, string B would be flagged as a duplicate. Note: If the Check Design Definition check box was toggled for Fixed Cross Sectionals, string B would not be found as a duplicate, as it does not have the same COLOUR, LSTYLE and SYMBOL combination as string A. Resolve Points
M24D Manual 2
Mine2-4D Projects
28
Endlink Checking
The end link checker will only activate as long as there are outline or complex solid design types. Fixed Cross Sectionals are not subjected to this check. The process cycles through the design and checks each item individually. Complex Solid Checking
As per the endlink check, the complex solid checker is only run on the complex solids design types. Fixed Cross Sectionals and Outlines are not subjected to this check Data Deletion
The dialog shown above is displayed at the conclusion of the data validation process. Suspected problems are highlighted by recolouring the column heading either red or orange.
M24D Manual 2
Mine2-4D Projects
29
The fields of the grid represent the following: Field PVALUE TYPE COLOUR LSTYLE SYMBOL Dupl ID Description unique ID for each string 1, 2 or 3 for each of the design types (FXS, OUT and CXS respectively) Colour of the string Linestyle of the string Symbol used for points on the string Duplicate strings Partial duplicates will be highlighted in Orange, while exact duplicates will be highlighted in Red. By hovering over a duplicate, the PVALUE of the matching duplicate is displayed as shown. Point Number of points in the string. A single point string is not allow anywhere in Mine2-4D. Two and three point strings in CXS and OUT design types are defined as suspect. RSLVE Angles CXS Instances where points along a string are closer than the specified minimum tolerance. Instances where strings contain severe angle changes. Number of strings with the COLOUR, LSTYLE and SYMBOL combination. A CXS MUST contain at least two strings - if it does not it will be flagged. EndLink Endlink problem. If an error in the end-linking process occurred then the suspect string will be flagged. XO XY XO YZ XO XZ Cross over in the XY plane. Cross over in the YZ plane. Cross over in the XZ plane. A cross over string is calculated on view planes. While the system will flag crossovers they MUST be checked by the user. Looping strings will also be reported as crossovers.
M24D Manual 2
Mine2-4D Projects
30
3. Select the strings whose direction you wish to reverse - multiple strings can be selected by holding down the Control key while left-clicking - then click the reverse direction button (rev). . Alternatively you can use the short-cut key
4. You will notice the direction of the arrows on the design string will be reversed. This is a visual representation of the correct direction of mining. 5. Click OK to update the design string files with the altered string directions. Click the Cancel button to discard all changes (design string files will not be updated). 6. You should be required to edit the direction of several of the strings. You may also wish to use the insert-point-at-intersections (ii) and delete-point (dpo) commands to trim the vent raise to the lower access.
M24D Manual 2
Mine2-4D Projects
31
7. Finally, use your knowledge of the Design Window commands to complete the design by adding an Ore Pass vertically connecting the three Orepass Crosscuts. (For more information on these commands, please refer to your Mine2-4D Design Tools Manual 1A).
M24D Manual 2
Mine2-4D Projects
32
2. Select the Data Validation Wizard : The wizard investigates the Design Strings in the project. If no Design Strings have been defined the dialog will not operate. 3. Check the design strings for each of the following, as per the exercises: invalid attributes invalid point strings cross over strings removal of duplicate strings and points resolution of points flag severe angle changes data deletion
4. Upon completion of the wizard, you should see the following form displayed:
M24D Manual 2
Mine2-4D Projects
33
5. Select the red XO XY Heading. You should see that all of the records are sorted according to this column, with any problem records reporting to the top of the form. 6. Check the Show and Auto Zoom options, and Apply Filter. 7. You will notice that it is the ramp string that is highlighted. In this instance the problem of suspected cross-overs has been flagged with the string as the string DOES cross over in the X-Y plane. As this is not an error with the data there is no need to make any adjustments.
M24D Manual 2
Mine2-4D Projects
34
DESIGN DEFINITIONS
The Design Definitions dialog is available from the Connect to Definitions area. This dialog contains up to three tabs, depending on the file types that were previously enabled in the Project Setup. The valid string file types are: Fixed cross sectionals Outline definition Complex solids
M24D Manual 2
Mine2-4D Projects
35
Applying Filters To have access to the above options, you must toggle on View Design strings while editing Design Definitions upon opening of the Design Definitions form. This toggle allows you to subsequently view any strings with an individual design definition on their own by using filters. To view strings of a particular description, click on the description, then click the Apply Button in the Filters area. All other Design Types will be hidden in the Design Window. To view all of the design strings for that design type, click on the Remove Filters button. To change how you view the strings (i.e. to fill the entire Design Window) check the Auto Zoom button before applying the filter. This will automatically zoom to extents when you apply the filter. To remove the filter click on the remove filter button.
Editing Attributes
To edit the attributes of design strings, click on the Edit button in the Attributes area then go to the Design Window and click the string you wish to edit. Four attribute menu buttons will appear at the bottom left of the Design Window:
M24D Manual 2
Mine2-4D Projects
36
Other Attributes
Clicking the Colour, Symbol, or Linestyle menu buttons will bring up the respective lists of those types from which you can choose. To change an attribute of the selected design string, click on the Colour, Symbol or Linestyle that you wish to use. Clicking on the Other Attributes Box will bring up two boxes to the right; one with the Attribute Name and the other with the Attribute Value. Arrows are provided to the right of the Attribute Name Box which allow the user to scroll through the various Attribute Names. To change the Attribute Value click in Attribute Value Box, type in the new value and hit enter. Be aware that Attribute Names and their Values are case sensitive.
On exiting the Design Definition Database, Mine2-4D will prompt whether the user wishes to connect the definition database to the design. Clicking OK will apply all the Properties from the Design Definition Database to the Design String File.
M24D Manual 2
Mine2-4D Projects
37
Segment Length
The segment distance specifies the segment length to which each fxs design string will be cut, for the purposes of sequencing, wireframing, evaluation, and scheduling. Note: It is possible to enter a segment length of -1. This will have the effect of creating NO segments. Similarly, entering -2 will have the effect of breaking the string into 2 equal segment lengths etc The smaller the segment length chosen, the greater the level of detail able to be reported. However, reducing the segment length also has the effect of increasing the number of records in a project. Therefore there typically has to be some compromise between reasonable amount of detail, and reasonable size of project.
3. Check the box to View Design Strings while editing Design Definitions. This will load the design strings into the Design Window for you to view and edit. If you do not
M24D Manual 2 Mine2-4D Projects
38
toggle this option on, you will not have access to the filtering and attribute options discussed in the Background Information. 4. If you have not saved valid changes to the strings in the Design Window, click No at this point. Return and save the changes before continuing. 5. If you are happy that all data is saved, click Yes to Continue. 6. On selecting Yes, the following warning dialog will appear:
7. Click YES and select the M24DESC field. This will select the M4DDESC field as the basis for each string Description. 8. The Design Definition form will then open. Check that you can see the following:
Before continuing you will need to edit the X-Sectional shape, Scheduling Rate and Segment Distance for each design type as follows: Cross Sectional Shape By default, you are able to choose from three standard X-Sectional shapes. These are Standard Rectangular, Standard Circular and ShantyBack. You also have the option to create any user defined shape required. 9. For the Orepass_XCut choose a Standard Rectangular X Section shape and give it the following dimensions: 4mW x 4mH.
M24D Manual 2 Mine2-4D Projects
39
10. For the Ramp, we first need to create a user-defined arched profile. To do this, click the button to bring up the X-Section Tool dialog. Select the Arch option and input a height of 5m, a width of 5m and an arch radius of 1.8m. By selecting the Create button, you should see the following displayed on screen:
` 11. Select the Save Option and you will be prompted to enter a name for your new profile.
12. You will then be prompted to select two outline positions. These positions will be used as the reference points to automatically generate wall strings for you. Therefore it makes sense to select the two points at the left and right hand corner of the arch. You will be prompted to reply if you are happy with the outline points you have selected. Choose Yes and Exit from the X-Sectional Tool. You will now find that you are able to select the 5x5 Arch from the drop down list when nominating your X Sectional Shape. 13. To finish, nominate the following:
Mine2-4D Projects
M24D Manual 2
40
Standard Rectangular 5mW x 5mH Standard Circular 3.5m diameter Standard Rectangular 4mW x 4mH Standard Circular 3.5m diameter
Segment Length By scrolling to the right of the main Design Definition form, you will notice that there is allowance to enter in a scheduling constraint, rate and segment distance.
The default scheduling constraint is ASAP (As Soon As Possible). The option of As Late As Possible (ALAP ) is also available. 14. Change the Description field, so that each different activity type has both a 2-3 character code as well as the description of the activity. (This is important to ensure the naming convention works properly, as will be discussed in more detail later). 15. Enter the Scheduling rates and Segment distances as per the above form. Please note that the Scheduling rate is the nominal rate that will be exported to your scheduling package. Therefore it is a good idea to select a sensible figure for each design type. A segment distance of 10 will cause your design strings to broken into 10m segment intervals for wall and wireframe creation. A segment distance of -1 will cause your design strings to be maintained with no segment distance being used while a segment distance of -2 will cause your design strings to be broken into two halves etc The segment distances you choose will affect the sequencing rules in later chapters. The advanced options are for integration with the Earthworks Rings package. 16. Select Connect to save and continue.
M24D Manual 2
Mine2-4D Projects
41
PREPARATION
Design Menu
M24D Manual 2
Mine2-4D Projects
42
Preparation Menu
The functions available through the vertical Design | Design Definitions | Preparation Menu allow the user to apply the attributes defined in the Project Setup to the design. These functions can also be accessed from the Planning | Preparation Menu. The preparation area is also where the user creates Design, Defined and Derived activities. Design activities are those defined in your Design Definition table, such as ramp development and stoping. Defined Activities are stand-alone occurrences, such as a Crusher Chamber installation, a 3 month exploration drilling program etc Derived activities are activities that can be based on a Base activity. For example, longhole drilling metres can be derived from your base activity of stoping.
43
Attributes can be defined as follows: Visual Manual Attributes: rarely used, except in situations where it is useful to recolour the design items based on the application of the attribute. Non- visual manual attributes: the most common. Attributes are applied to the design item manually. Automatic: attributes are automatically assigned to the design items from 2D string files or 3D wireframe files. Scheduler Entered: attributes are created in EPS and applied to design items after the schedule has been generated. Model Identifier: automatically applied by Mine2-4D, to keep a record of which model was used during the evaluation process.
Return to the Project Setup area and define the following under the Attributes menu:
This ensures that every design string in Mine2-4D has the following attributes associated with it: LEVEL Numeric code field. Once this attribute has been defined, select the Design | Design Definitions | Preparation Menu. You are now able to start defining the attributes.
44
2. Select the 660 level Orebody XCut, Orepass_XCut and Vent_XCut strings. From the drop-down list available in the Set Attribute Value form, select the 660 value (as previously defined in the User Manager | Options | Attribute List). Select the Set Selected button to apply this attribute value to the selected strings in the Design Window. 3. Repeat the process for the 680 and 700 level strings. (Do not apply any value for the decline or ventilation rise). Upon completion, you should see the
M24D Manual 2
Mine2-4D Projects
45
following, the - value indicating absent values for the LEVEL attribute on some of the design strings.
M24D Manual 2
Mine2-4D Projects
46
Wall and point generation occurs under the Design | Design Definitions | Preparation Menu. These functions can also be accessed from the Planning | Preparation Menu. Each activity in Mine24D is in someway represented by a physical location in space and other associated data. Wall and point creation takes the mine design as an input and converts it over to a wall string and point for each activity. During the process the following tables are created: walls_all_[] - a 3D string for each activity
points_all_[] - a 3D point in space for each activity evald[] - dummy evaluation containing "estimated" values for metres and tonnage. .
As the Future_Infrastructure project consists of only a fxs design, it will only be necessary to generate walls and points for this design type.
M24D Manual 2
Mine2-4D Projects
47
1. Toggle ON the option to Create a single outline of each design string if you wish to create an additional output file, outd0.dm, containing one continuous outline for each design string.
2. Select OK. Wall strings will then be generated for each segment (according to the segment size defined in the Design Definitions form) and saved to the wallsd0.dm file:
. You should also note that each segment is represented by a single point (displayed as an arrow). The starting segment for each string is represented by a green point, the middle segment by a yellow point, the end segment by a red point and all other segments as blue points.
M24D Manual 2
Mine2-4D Projects
48
Preparation
This stage can also be accessed from the Design Menu, and has been dealt with in the previous chapter.
49
Reporting
A major aspect of Mine2-4D is its ability to communicate your design and schedule to others. Mine2-4D has a set of reporting tools that enable the user to communicate the design in a range of ways, from detailed costing numbers through to 3D animations.
1. For this exercise, we are only going to be wireframing our fixed cross sectional strings. Therefore select the Fixed Cross Sectional button. At the following dialog, select OK.
M24D Manual 2
Mine2-4D Projects
50
2. Upon completion, the following should be visible from the Visualizer Window:
M24D Manual 2
Mine2-4D Projects
51
1. Select the Evaluate Design button, and OK. As this is the first time you have processed any data using the resmod.dm model, you will be required to first run through the Block Model Validation Wizard.
This wizard helps validate your model, to ensure there are no absent or negative values for any of the model fields. It also allows you to delete any unnecessary fields in an effort to reduce overall file size and processing time. 2. As CU is the only grade field you are interested in evaluating, delete all remaining fields from the model by toggling off the option to include them in the Output Model.
M24D Manual 2
Mine2-4D Projects
52
3. As soon as the model validation has finished, select Finish to allow the evaluation process to begin. Upon completion, an Interrogation Report will be displayed. This report highlights those wireframes that have a large volume discrepancy between the dummy volume (calculated volume) and evaluation volume (evaluated against the block model).
4. If you have toggled on the option to Display the report grid on completion you will have the following Data Reporting screen displayed at the end of the evaluation processing:
M24D Manual 2
Mine2-4D Projects
53
5. This screen can be displayed at all times by selecting the Tools | Reporting | Project option from the menu. 6. Experiment with the group by columns option that is available by dragging the column header to the grey grid area at the top of the form. A variety of actions can also be performed on the data by selecting from the Column | Action options available from the left hand side of the form. For example, in the form below the data has been grouped according to the M4DESC field and the metres have been summed for each different occurrence of M4DDESC.
M24D Manual 2
Mine2-4D Projects
54
SEQUENCING
M24D Manual 2
Mine2-4D Projects
55
Position
Throughout the Automatic Dependency Definitions dialog, the term "Position" is used to represent a location on a design string. Four positions types are available - START, END, MID and ANY. START - start point of a string (denoted as a green point) END - end point of a string (denoted as a red point) MID - approximate middle point of a string (denoted as a yellow point) ANY - includes any point from strings with the specified description, including Start, End and Mid-points (denoted by green, red, yellow or blue point).
Search Origin
Mine2-4D uses the Search Origin to define where to focus a search for Predecessors or Successors. The user must select the description of the string and the position on the string to centre the search radius. Note: at least one of the Predecessor or Successor fields must match the description of the Search Origin. If this is not the case no automatic linking will take place.
Predecessor/Successor
By definition, a successor is dependent upon a predecessor. Mine2-4D will search the Predecessor and Successor fields for a DIFFERENT description to the Search Origin point.
Position Overrider
The Position Overrider is effective when there is ambiguity within the search criteria. The following example illustrates one of these cases.
M24D Manual 2
Mine2-4D Projects
56
Position Scenario Headings "B" and "C" represent two active cut and fill stopes. The distance from the start activity of "A" to the END activity of B is roughly 50m. The distance from the END activity of B to C's END activity is 5 m. The search radius that would need to be created in order to encapsulate B's END point would be so large, that C's END point would most likely be within the sphere'. There could likely be other END points of B or C on a different elevation. The Position Override would allow a much smaller search radius to be used. The ANY position point combined with the END Override Position would first find the nearest (ANY) B point, yet Override to the END point for linking. In addition to the standard type of Overrider it is also legitimate to supply an integer value. This will override the join by that number of segments. This can be particularly useful when trying to ensure that faces are kept a certain distance from each other. If the number of segments goes past the last segment of the parent string, the override will not be performed. Negative values are also supported, however, if the position goes beyond the start of the parent string, no override will be performed.
Link (Delay / Type) Under the LINK feature, two subheadings exist. DELAY is quite obviously a built-in delay. The link simply dictates order of operation', but the delay will provide a time lag where required. There are four choices under TYPE, namely FS, SF, SS, FF (Start and Finish Links 1 through 4 respectively).
M24D Manual 2
Mine2-4D Projects
57
Type Examples The FS option will be the link used most often. The FF is an effective tool, as it will ensure two items complete simultaneously. It is important that this link is only be used with a total understanding of global efforts since it can cause problems if used incorrectly.
M24D Manual 2
58
o o
Constrained (Spherical) - This option provides no limits with respect to azimuth Constrained (+ve Z) - This option allows the user to narrow the defined azimuth to an elevation greater than that of the Search Origin's activity Constrained (-ve Z) - This option allows the user to narrow the defined azimuth to an elevation less than that of the Search Origin's activity
ORIGIN is how the user wants the search to be oriented, and is also subdivided. This option allows the user to be more specific with the desired searching area with different options available when using STANDARD vs. DEFINED AZIMUTH for the METHOD. As the user selects the ORIGIN, the SEARCH AZIMUTH and SEARCH DIP cells will toggle between white and grey. Grey indicates that input is not required. This deals with the four categories classified as: o STANDARD method o USER DEFINED This option should be selected when the user wishes to define the MAIN Azimuth and Dip of the perspective from the Search Origin's activity DESIGN AZIMUTH - This option should be selected when the user wishes to simply define the MAIN Dip, while using the design's existing Azimuth DESIGN DIP - This option should be selected when the user wishes to simply define the MAIN Azimuth, while using the design's existing Dip DESIGN AZIMUTH & DIP This option should be selected when the user is satisfied using the design's existing Azimuth and Dip
DEFINED AZIMUTH method requires the user to input the two azimuths "1" and "2" (in the Automatic Dependency Definitions box), from the Design or MAIN, which are to be searched between. The following schematics clearly show examples of different possibilities. o USER DEFINED This option should be selected when the user wishes to define the MAIN Azimuth and Dip, as well as dictating the search Azimuth DESIGN AZIMUTH - This option should be selected when the user wishes to input only the Dip, while satisfied with using the design Azimuth DESIGN DIP - This option should be selected when the user wishes to input only the Azimuth, while satisfied with using the design Dip DESIGN AZIMUTH & DIP This option should be selected when the user is satisfied using the design's existing Azimuth and Dip
M24D Manual 2
Mine2-4D Projects
59
The SEARCH RADIUS DIVISORS dictate the size and shape of the search extents. The Y-axis will be the Design Azimuth unless otherwise specified by the user. The X and Z-axis units can be manipulated to produce a shape other than a sphere. For example, if the RADIUS is set to 25 and the X, Y, and Z parametres are all set to 1, a sphere with a search radius of 25 would be created. Because of the DIVISOR's nature, the value will be divided by the RADIUS to produce a search radius for that axis. For example, with the RADIUS set to 25, and the X and Y parametres are set to 1 with the Z parametre set to 2, an ellipsoid with a 25m radius for the X and Y axis with a 12.5m (25/2) radius for the Z axis will be created.
By clicking on the activity points will be annotated with the Description given in the Design Definitions. Pressing the Generate button will result in the dependencies being created.
M24D Manual 2
Mine2-4D Projects
60
3. Note that the search radius required will depend heavily on the segment distance used in the Design Definitions form. As the Ramp was originally assigned a segment distance of 10m, this also makes sense for the initial search radius. 4. As soon as you are satisfied with the first automatic Sequence rule you have created, select the Process button. The following screen will then appear:
You will need to toggle Recalculate Sequence if links have been MOVED (as opposed to created).
Link creation button. Select and then snap from and to the points that you want to create the link between. Delay button. Set before creating new link. Select OK to save and exit.
5. Adjust the animation interval to 300 and select the Animate button. Your sequence will be animated in the Design Window. Links will be displayed as bright purple stings that are easily distinguished.
M24D Manual 2
Mine2-4D Projects
61
6. The initial sequence rule should result in three sequence links being generated. 7. Once you are satisfied with the effect of your single rule creation, select OK and return to the Automatic Sequence Generator. Build up the remaining three rules you require to sequence the entire future infrastructure process. If you encounter problems, you may wish to refer to the completed rules overleaf. 8. Select Process and re-run the animation. If your rules are correct, you will have created 11 automatic dependencies. Sequencing Troubleshooting If you are not happy with the sequencing, you can use the Sequence, Filter, AutoLink and Checks menus to help troubleshoot. If the problem is that one of your rules is unsuitable, select OK and return to the Automatic Rule Generator to resolve. You may find that you actually need to return and edit your design string directions or actual design strings in order to streamline the process. If the problem is a single one-off instance that could be fixed by the addition of a small number of manual links, you may prefer to use the Dependencies area to add a manual dependency. You can do this by selecting the button.
M24D Manual 2
Mine2-4D Projects
62
M24D Manual 2
Mine2-4D Projects
63
Exercise 2 Scheduling
Once you are satisfied with the sequencing, you are able to move onto the Scheduling area.
UPDATES Mine2-4D with any changes made in EPS (Links, start dates, finish dates, rates, data values etc). Returns to the manual sequencing form for sequence validation.
The Scheduling tab allows for the export/import of the visual schedule into the Earthworks Production Scheduler (EPS) for further refinement. For this exercise, we will be using a blank EPS template. Therefore select the Sequence Export button, to see the following dialog:
It is possible to select settings for EPS in the Project Setup of Mine2-4D. In this exercise we are simply going to export the raw data. 1. Select OK to start the exporting process. This may take a few minutes. 2. Once complete, select the Open Selected Scheduler button. You should see the following displayed on your screen:
M24D Manual 2 Mine2-4D Projects
64
M24D Manual 2
Mine2-4D Projects
65
10
AN INTRODUCTION TO EPS
Date Bar
The EPS interface consists of a Task Table, Gantt Chart, Crosstab and Date Bar. The Gantt Chart area of the application shows a view of the schedule information contained within the Task Table. When dependencies are created this information is stored in the Task Table. The scheduling engine calculates Start and Finish dates for the activities and the associated Gantt Bars are shown in the Gantt Chart The Crosstab then has the ability to show the information from the Task Table (both custom and fixed fields) in the associated Date Bar column. In addition, filters may be applied to this information for more advanced reporting.
M24D Manual 2
Mine2-4D Projects
66
Resources
EPS contains a number of tools for resource management and levelling. When a resource is defined, it is necessary to apply a default production rate. This can be a single default value or it can refer to a lookup table, allowing the resource different rates based on the characteristics of the activity. It is also possible to apply availabilities to a resource and costs to track economic information.
Project Settings
Each schedule or project can contain large amounts of data. Effective formatting, lookup tables and targets are necessary with complex projects to allow you to effectively schedule. These are defined in the Project Settings as shown below.
Calendars allow you to have specific working periods for different activities and resources to reflect the reality of the project. Filters assist managing the large quantities of data inherent in a complex schedule. The creation of new Production Fields allows you to generate data from existing data using equations (eg weighted grade of a block) and filters. As well as production fields, you can create Text Fields and Code Fields to define lists of possible code categories for the project. Summary Fields can also be created to assist in reporting from the Crosstab. Targets can be set to anticipated values for defined fields to assist in tracking (not optimization). Targets can be projected over time and can be allocated high and low values if fluctuations are expected. Targets are defined to alter the colour of the relevant fields being reported in the Crosstab to indicate whether above or below the target range. Any field can be used to set a target. Production Lookup Tables can be defined to apply changes in resource rates depending on time or values of any fields.
M24D Manual 2
Mine2-4D Projects
67
2. By default the project start date will be set to todays date. To alter to the project start date, go to Project | Settings |Target Start and enter 1 July 2008.
M24D Manual 2
Mine2-4D Projects
68
Note A naming convention is a very useful way of being able to group your data. 3. Select the [Rollup Description] item from the Grouping drop-down list. 4. Highlight all of the data in the Task Table by clicking in the grey header area of the field. 5. Next select the Roll Up Button 6. To view Summary Bars for the entire Task Table, highlight the Description field and click the Hide Subtasks button. This is especially useful for the printing of project data - it can greatly reduce the amount of visible information while still providing an overall duration for the completion of tasks.
2. Select the Chart Options menu. Next select the Blank Page icon to create a new Crosstab. Assign this crosstab the name Summary.
M24D Manual 2 Mine2-4D Projects
69
4. Scroll across, and apply the Crosstab to all Filtered Tasks. You may also want to adjust the decimal spacing reported in the Crosstab.
5. To view the same Crosstab data, but in histogram format, right click in the Crosstab area and select Chart Options | General and toggle on Histogram of totalled fields.
70
2. Assign the filter the name Ramp, and assign the expression Description = Ramp. Toggle ON the Show related Summary Tasks option.
3. Create additional filters for the Orepass, Orebody_XCut, Vent_XCut and Orepass_XCut development. Remember to toggle on the Show Related Summary Tasks option for each filter.
1. To do this, simply type the resource name in o the CrossTab. Double click on the item to open up the Resource Information form.
M24D Manual 2 Mine2-4D Projects
71
2. Enter in 6/d as the Default Production Rate. (The units are automatically taken from the activity to which the resource is applied). 3. To assign the resource to a task, first select the task/s in the task table. Select Edit | Assign Resource or <Cntrl-A> to assign the resource, and Tools | Resource Levelling | Level Now to level the tasks according to the resource. 4. Finally, select File | Save to save the EPS project to the working directory. (This file is copied back into the C:\Database\Training\Future_Infrastructure folder when the Mine2-4D project is checked back in). 5. Select File | Save As to save the file as Template.ext C:\Database\Training\M24D\Underground\CommonData folder. template will be used for data exporting in later exercises. to the This
M24D Manual 2
Mine2-4D Projects
72
11
REPORTING
Evaluation
The first area, Evaluation, is used to create reports on either the actual design or on the project. Reports on the actual design can be conducted by clicking on the Design Stats button, or alternatively on the project by clicking the Project Reporting button.
Properties
The second area, Properties, allows specific colours to be applied to parts of the design. Under Legend Definitions, the user is able to setup legends for colouring the evaluated objects. The Colour Objects button is used to apply the defined legends to actual objects in the schedule.
Schedule
The final part of the form, Schedule, allows specific colours to be applied to different parts of the design schedule and for the final schedule to be viewed in 3D as an animation. The
M24D Manual 2
Mine2-4D Projects
73
colours for the schedule are defined by pressing the button Schedule Colouring Definitions, while the animation can be viewed by pressing the 3D Animation button. Step 3: create animation.
1. Select the Get Schedule Stats button in order to read the schedule file and fill in the Schedule Statistics. This provides feedback on the start and end dates of the schedule and the length of the schedule. 2. To create a new colouring definition, click New and assign a name for the definition. In this instance we will be creating a monthly schedule legend, so name the colour definition MONTH. 3. Right clicking on the grid (grey area), to Add a single record to the definition. (If you make a mistake, the option Delete Current will delete the selected record). 4. Next use the Generate Recurrences button to automatically create recurring intervals. For this exercise, generate monthly intervals until the schedule end.
M24D Manual 2 Mine2-4D Projects
74
5. You can edit the resulting colours by clicking on each colour and selecting an alternative from the drop-down menu. The colours correspond with the standard Mine2-4D Design Window colours.
6. Once you are happy with the schedule legend, colour your solids using the following button:
M24D Manual 2
Mine2-4D Projects
75
7. This step will create the wireframe files schedwall_all_0tr/pt.dm. (You have the provision to rename these files by typing over the default in the Save As dialog). 8. In addition, if you select the Break FXS to Schedule this option will re-generate the wall outlines according to your schedule. This option is invaluable when generating Budget, LoM, Monthly rolling plans etc. 9. You can create a psuedo wall-string or wireframe animation from within this dialog if required. For this exercise, select Exit and we will use the 3D Animation dialog as part of the next exercise.
M24D Manual 2
Mine2-4D Projects
76
Select schedule definition to determine animation speed Choose from schedule colours (as per Step 1) or user colours. User colours will animate the wireframes according to the selected schedule date legend, but the wireframe colours will be taken from the original design or a user defined legend).
Add objects to animation (such as survey as-builts) Handy tool for open-pit animation.
Select OK to continue.
Create from Schedule 1. Select the Animation button from the Reporting Tab, and choose the Create from Schedule option. 2. Select the recently created MONTH Schedule Definition from the drop down menu. 3. Check on the Apply schedule colours to colour the solids according to the date they are scheduled to occur using the legend created by the chosen Schedule Definition. 4. It is important to realize that when an animation is created from a schedule, a solids (wireframe) file called sched_wre_all_*tr is also created. This file contains all the solids to be animated and the animation sequence. It is therefore possible to run an animation from this solids file by specifying it as the Solid Triangles file under the Create from Solid Tab.
M24D Manual 2
Mine2-4D Projects
77
5. To view the animation, right click in the Visualizer Window and select the Start Animation option. 6. To save a copy of your animation, right click in the Design Window and choose Publish Animated Visualizer View. This will save your animation as a .gvp file but without any annotation text. Alternatively, if you choose the Visualisation|Publish Animated Visualizer View option from the Visualisation Menu, your animation will be saved WITH text annotation.
M24D Manual 2
Mine2-4D Projects
78
12
Flexible data model A single Present document contains all section, plan, and 3D plots for each project simplifying the task of project document management. The document records the links to all the imported data tables, parametre surface models and 3D objects without actually copying the original data. This means whenever the document is opened or refreshed, any changes made to the source data are automatically shown in every section and plan plot. The unique data model employed by Present offers many important benefits: o o Saves on disk storage because the source data is never duplicated. Ensures that Present can be used with any user selected database management system, spreadsheet program or text tables. Ensures that all plots accurately reflect the master data files because plots are dynamically linked to the source data files. Saves you time in managing project documents and updating project plots when project data is added or edited.
Document Wizard
M24D Manual 2 Mine2-4D Projects
79
Probably the simplest and easiest way to start using Earthworks Present is to use the Document Wizard. The Document Wizard steps you through the initial stages of building a new project including: o Importing drillhole data such as collar coordinates, surveys, assays, and other downhole logs and then use the data to create desurveyed drillhole traces. Importing other data including points, strings (polylines), wireframes, and models. block
Checking the imported data for possible errors and displaying the results in the report view. Create a complete set of plan, EW and NS section plots.
There are two ways to start the Document Wizard: o When Earthworks Present starts, the Startup dialog gives you the opportunity to check the Document Wizard radio button. The document wizard starts automatically whenever you select the New command from the File menu.
2. The next menu you see will be a welcome page, press the Next > button to start loading the data.
M24D Manual 2
Mine2-4D Projects
80
3. Set the prompts in the Import Data Types menu to match those in the image below and press the Next > button to continue.
4. The next menu will be titled Import String/Polyline Tables. Press the Add button and when prompted set the Driver Category and Data type settings to match those in the image below and then press the OK button.
5. When prompted with the Open Source File (Datamine String) menu, make sure the Files of Type is set to All Files.
6. Select the walld0.dm file and press the Open button. 7. Next you will be asked to select which fields you wish to load. Select All and then press the OK button.
M24D Manual 2 Mine2-4D Projects
81
2. Press the Next button to continue. 3. The Document Wizard Menu should now be titled Import Wireframe/Surface Tables. Field Import Tables Wireframe/Surface Description Press the Add.. button Set the Driver Category to Datamine and the Data Type to Wireframes and press the OK button.
M24D Manual 2
Mine2-4D Projects
82
Open Source File (Datamine Wireframe Triangles) Open Source File (Datamine Points) Import Tables Wireframe/Surface
Select the schwred_all_0tr.dm file. Select the schwred_all_0pt.dm file. Press the Add.. button As before Select the wred0tr.dm file. Select the wred0pt.dm file. Press the Next > button to finish.
Driver Category/Data Type Open Source File (Datamine Wireframe Triangles) Open Source File (Datamine Points) Import Tables Wireframe/Surface
2. Press the Finish button to complete the import. 3. Save your project using the File | Save command in the main Present menu. When prompted set the document name to training.epr. Make sure you save the document in the training directory (C:\database\training\Common_Data).
M24D Manual 2
Mine2-4D Projects
83
4. Note that these steps are only done once. Once the links are set up and the project has been saved your sections will automatically reflect the content of your current mining database.
3. Press the OK button to continue and answer Yes to the prompt asking if you want to rescale all plot items. 4. Select the Format | Grid option from the pulldown menus. annotation to that displayed in the image below. Change the grid
M24D Manual 2
Mine2-4D Projects
84
5. In the Grid menu click on the Font button below the text settings. In the Font menu leave the Font: and Font style: settings set to the default values and change the Size: value to 12. Press the OK buttons to close the two menus. 6. Select the View | Property Windows | Workspace and Properties options.
2. Press the padlock symbol next to the scale menu to fix the scale at 1:500 for all Plan views. 3. To set the clipping to 25 metres using the pull down clipping menu in the top left hand corner.
M24D Manual 2
Mine2-4D Projects
85
Try using these commands to understand how they work. Help on what each command does is available by placing the mouse cursor over the relevant icon or using the F1 key. 2. To step through the sections try using the 2 arrow icons in the top rack of icons.
3. MAKE SURE THE SECTION IS SET TO 45300 mE BEFORE STARTING THE NEXT EXERCISE. 4. Select the item called Plan Projection Section Level 700 in the Workspace Window (located in the left of the screen). 5. The properties window (located in the right of the screen) will now display a list of properties relating to the Plan View. Make Sure that the Section Mid-point Easting, Northing and Level details are as follows:
M24D Manual 2 Mine2-4D Projects
86
M24D Manual 2
Mine2-4D Projects
87
2. Select the schedwre_all_0tr.dm. Toggle on the Intersection with Section check box and set the display to Hidden. 3. If you click on the Colour tab you will notice each of the 3 files is being coloured on an attribute field and a default legend. 4. Press the OK button and move on to the next exercise.
M24D Manual 2
Mine2-4D Projects
88
2. Click in the cell containing the text Plan Projection Section Level 700.00 using the right mouse button and select the Insert Row option. Adjust the cell heights and position of the title box to match the image below.
3. Remove the text from the second cell and add the text Wanabe Mining NL to the uppermost cell. These edits can be made by right clicking in each cell and selecting the Cell Contents option. 4. Use the Insert | Scale Bar to add a scale bar to the cell below the main title. Similarly use the Insert | Clip Art option to add the company logo to the right of the title. The logo is stored in C:\Windows\coffebean.bmp. 5. Your title box should look similar to the following. You will need to modify both the cell sizes and font sizes to get a result similar to the image below.
You will have noticed some lines of text are hard coded while others as set as Fields such as the section easting. By using fields some of the title box text will change as each new section is displayed. Try stepping through a few sections.
M24D Manual 2
Mine2-4D Projects
89
13
3. Enter a name for your plot in the Session box, and select the default plot Metric_QuickPrint.eprv. ( Mine2-4D stores all Present template files in the directory C:\Program Files\Earthworks\Mine2-4D\Present. The file extension .eprv is used to distinguish between a Present template file and a standard Present file. 4. Press NEW to continue. 5. When Present opens, your plot should look similar to the following:
M24D Manual 2
Mine2-4D Projects
90
900.0 E
19 00.0 N
19 00.0 N
18 00.0 N
18 00.0 N
17 00.0 N
17 00.0 N
900.0 E
Section 1 of 1
Tim 17:04 e:
Any changes made to the plot can be added to the template by saving the Present file with the extension .eprv to the C:\Program Files\Earthworks\Mine2-4D\Present directory.
M24D Manual 2
Mine2-4D Projects
91
14
M24D Manual 2
Mine2-4D Projects
92
3. In the Browse For Folder dialog, find and select the folder the 660 Level within the C\Database\Training\M24D\Underground folder note that this location will depend upon where the training data has been placed) 4. Enter a name for the new project ie: 660Level, then click OK. The project should automatically be created and then checked out by the system and executed on your computer. (Warning: you may need to select or enter license details at this stage.)
3. To attach these files to your project, select Add File to Project Add Files to Project| Manually).
4. Select the Create Naming Convention to enable the naming convention menu. 5. Select the Create Additional Attributes to enable the attributes menu. 6. Select the Interrogate Geological Model to enable the interrogation menu, depletion menu and the design evaluation process.
M24D Manual 2
Mine2-4D Projects
93
Exercise 3 - Interrogation
1. For the 660 Level, we want to ensure that all the fixed-cross section development wireframes are depleted from the model PRIOR to evaluating the complex solid wireframes. To do this, setup the model interrogation form as follows:
The degree of subcelling that is specified will have an impact on both the processing time and percentage error of the reported volumes. An increased degree of subcelling will reduce the percentage error of the reported volumes, as the depleted model cells will be able to more closely follow the depleted design outline. However increased subcelling will also increase processing time. In order to get an indication of the degree to which both will be affected, you are able to use the Splitting Tool.
94
3. The point at which the volume error is reduced without an excessive increase in processing speed should give you an indication of the subcelling amount to use in the Geological interrogation. For this exercise, a subcelling of 8 gives us the same relative accuracy without any significant increase in processing time.
M24D Manual 2
Mine2-4D Projects
95
External Data External Data will not be used during this exercise. For reference, it allows property and attribute fields evaluated within Mine2-4D to be over-written by external data sources (such as spreadsheets etc).
M24D Manual 2
Mine2-4D Projects
96
Attributes are used to carry additional information about activities, much the same as a column of data in a spreadsheet. They may then be used in filtering, to provide 'pointers' to different areas in the mine and to create the naming convention for each activity. Examples of Attributes: Level to define separate mining horizons. Zone to define different geological zones within the mine or different climate zones (indicating areas that require greater ventilation). Orebody to define the orebody within which a mining segment is located. Support to define areas within the mine that require different levels of ground support.
Almost anything can be added as an attribute, and as such, attributes should be applied on the basis that they will increase the level of understanding of the design and add to the quality of information gained from the schedule. It should be warned that excessive use of attributes can prove to be time consuming in their application and in the end may simply create greater confusion than clarity.
Exercise 7 Properties
1. As per the initial Future_Infrastructure project, define CU as a Property to ensure that it is evaluated during the Solids and Evaluation stage. 2. Check that the Weight for CU is on Mined Tonnes. This ensures that results are reported as a weighted average grade with Mined Tonnes as the weighting.
M24D Manual 2 Mine2-4D Projects
97
Question: What is the difference between the Insitu, Mined, Depleted and Void Volumes? The Insitu Volume is the volume of the original wireframe shape before depletion. (The reported Insitu volume for any wireframe should be the same as that reported by running the wireframe-volume command (wvo)). Alternatively, the Mined Volume is the volume of the un-depleted model within the wireframe. Therefore the Mined Volume will not contain any depleted material or any void material. The Mined Volume can be depleted in two ways: With as-mined depletion from the block model, or With design-depletion where the design development is depleted from the block model prior to evaluation of the stoping areas. This type of depletion is defined in the Project Setup under Geological Interrogation.
Any depleted material is reported via the Depleted Volume property. The Void Volume represents any volume within a wireframe that is not covered by the block model. This may occur as the result of filtering of the model, as the result of the application of a legend or as the result of errors in the block model. Void volumes can also represent areas of waste when an ore-only model is used during evaluation. By default the Mined Volume is automatically diluted to include any Void Volume, with tonnages and grades adjusted accordingly. Therefore the relationship between Insitu, Mined and Depleted Volumes is as follows: Insitu Volume = Diluted Mined Volume + Depleted Volume If Perform Dilution Calculations is toggled OFF during the Geological Interrogation, then the relationship becomes as follows:
M24D Manual 2 Mine2-4D Projects
98
For more information on the base properties that are created in Mine2-4D, please refer to Appendix A.
M24D Manual 2
Mine2-4D Projects
99
2. The order of entries in the Naming Convention setup can be easily modified with the use of the arrow buttons on the right of the dialog.
M24D Manual 2
Mine2-4D Projects
100
It is possible to build an EPS template from within Mine2-4D by altering the settings within the Scheduler menu. Be aware that more complex EPS templates are better managed from within EPS! For this exercise, we are going to use the EPS Template created in the earlier exercises. 1. Within the Current Scheduling Project | Scheduler Setup File Location, browse to the Template.ews file that was created and saved to the folder C:\Database\Training\Mine2-4D\Common Data. 2. Select a Target Start date of 1 July 2010. 3. This completes the Project Setup options for the 660 Level. Select OK to exit from the dialog whilst saving settings.
Exercise 10 Design
Now that the Project Setup has been completed for the 660 Level, it is necessary to repeat the design processes that were used on the Future_Infrastructure project. Please be aware that prior to creating wall strings and solids it will be necessary to spend some time observing the 660 level data and possibly making changes to the design types and string attributes. The following pages list the steps to follow and contain several images of examples of how to set up the data: Design Editing The first step is to load the development string data (660sill.dm) into the Design Window. 1. Check the direction of the strings, and ensure that the green Cross Cut string is flanked on both sides by red Primary drives. You may find that it is necessary to edit a number of your Primary and Secondary drives to ensure the design is practical. If you are familiar with your menu or short cut keys, feel free to use these items. Alternatively, you can use the Design Editing dialog available from the Design | Design Editing section of the Vertical Menu.
M24D Manual 2
Mine2-4D Projects
101
2. Edit the Design Directions 3. Carry out Data Validation 4. Edit the Design Definitions. You will need to do this for both the Fixed Cross Sectional stings and the Complex Solid strings. Examples of both are provided below. 5. In order for Mine2-4D to be able to differentiate between stopes, each stope must have a different combination of colour, linestyle and symbol. As such, each stope must be individually defined in the Design Definitions form. It is possible to enter a unique stope name as the M4DDESC description for each stope. Should you decide to do this, it will be necessary to generate a sequencing rule for each of the unique stope descriptions. It is a good idea to keep the M4DDESC description as generic as possible this will reduce the number of sequence rules you need to define late on 6. The number of Strings/Segment refers to the level of detail with which your stopes are wireframed. In this example the stopes are created from two string sections, therefore the option is irrelevant. However, if your complex solid shapes were made up of >2 string sections, it would be possible to nominate the number of strings used to create each wireframe. For example a stope defined by 30 string sections could be wireframed as one single shape incorporating all 30 string sections, or it could be wireframed as 29 individual wireframes, each incorporating 2 adjacent strings. 7. Upon completion, select Connect. This step updates the Mine2-4D database (the .m4d file) and ensures that the design definitions are attached to the visual tables. Should you alter your design at any stage of the process, it is essential that you return to this stage and re-connect to the database.
It is good practice to create your Activity Descriptions as a combination of CODE and LONGHAND DESCRIPTION of the activity. The initial code can be very useful in the naming convention, while the longhand description allows new users to quickly grasp the setup of the Design Definition table.
M24D Manual 2
Mine2-4D Projects
102
Exercise 11 Preparation
1. Use the Preparation Non Visual Attributes dialog to assign the attribute LEVEL = 660 to all strings in the 660sill.dm and 660stope.dm files. 2. Preparation Generate walls and points. This step needs to be carried out for both your fixed cross sectionals AND complex solids. Wall generation for your complex solids consists of drawing a centerline that connects the centre-of-gravity points for each complex solid wireframe. The direction of this stope centerline is taken to be the direction of mining. As the 660 level consists of two-string section wireframes only, the wall generation does not create any centerlines, but only single-point references.
M24D Manual 2
Mine2-4D Projects
103
3. Preparation - Apply Automatic Activity Attributes. Use this dialog automatically apply the WPLACE attribute as defined in the Project Settings.
to
3. To create complex solid wireframes, first nominate the wireframe linking method you wish to choose and then select AutoLink All. 4. Check the actual wireframes shapes that are generated using the Autochange and Auto Visualise toggles. The proportional length method is recommended for this example but different wireframe data will respond better to different methods. Straight geometric shapes appear to work best with the proportional length method. More complex shapes can respond better to either the minimum surface area or equi-angular shape methods. If you notice that any of your wireframes have been generated incorrectly, you will need to manually edit the results.
M24D Manual 2 Mine2-4D Projects
104
the button to generate tag strings to assist your wireframe creation. AutoLink Current Stope to wireframe an individual stope shape. 6. Complete the Evaluation
M24D Manual 2
Mine2-4D Projects
105
M24D Manual 2
Mine2-4D Projects
106
2. In Project Setup, create a new property to describe the derived backfill volume you are about to define.
M24D Manual 2
Mine2-4D Projects
107
3. Select the Dependency Layers option from the bottom of the Scheduler section in Project Setup and define a separate dependency colour for Backfill. This will be used during the automatic sequence generation to differentiate between sequence links.
4. Still in project setup, use the newly created filter and properties to define the Backfill Activity as follows:
M24D Manual 2 Mine2-4D Projects
108
5. You will need to scroll to the right and choose a colour for you derived activity walls. (Grey). 6. Select OK. 7. There is no need to re-create your walls and solids for your designed activities, but the following steps are essential: a. Generate the wall strings for your derived activities by selecting the Generate Derived Activities button from the Preparation Tab in Mine2-4D. (There is no need to create solids for our derived activity as we did not choose a wireframe colour during the Project Setup). b. Update the evaluated Backfill properties by selecting Generate Derived Activities from the Evaluation tab):
8. Edit sequencing rules. (See overleaf for examples). For this exercise, assume that backfilling in each Primary Stope will occur 2 days after stoping has finished. Development in the Secondary Drives cannot commence until 5 days after the completion of filling activities in all adjacent Primary Stopes.
M24D Manual 2
Mine2-4D Projects
109
M24D Manual 2
Mine2-4D Projects
110
Exercise 15 - Reporting
To complete the project, export the data to EPS and create a 3-D animation, using the following steps. (For more information, refer to notes for the Future_Infrastructure project). 1. Sequence Export (selecting the Use Template check box) 2. Open Selected Scheduler 3. Synchronise Scheduler Objects 4. Reporting - Schedule Colouring and Create Animations
3. Right click on the grey grid area and Add Records in order to build the following Legend:
M24D Manual 2
Mine2-4D Projects
133
4. Select Exit and then Save to save the Legend. 5. From the Vertical Menu Planning | Reporting | Properties section, select the Colour Objects button (shown overleaf).
6. Select the drop down button to the left of the <Default> entry to select the newly created legend CU.
7. The 3D solids will now be coloured according to the grade legend defined:
M24D Manual 2
Mine2-4D Projects
134
8. When you are satisfied, select File | Exit to close Mine2-4D and return to the Design Manager. 9. You will notice that the 660 Level project is still checked-out on your system. You should check the project back in by right-clicking on the project then selecting Check In and entering an appropriate comment.
M24D Manual 2
Mine2-4D Projects
135
15
The Project Cascader can also be accessed directly from the Mine2-4D Systray.
M24D Manual 2
Mine2-4D Projects
136
In the Project tab, select the previously created 660level Mine24D Project (located in C:\ Database \ Training \ M24D \ Underground \ 660Level). Checkboxes are available to select the cascade tables that you wish to copy from the selected project:
M24D Manual 2
Mine2-4D Projects
137
Be aware that if you toggle on the FXS Design Table Rule, you will actually copy the design strings from one project to another.
M24D Manual 2
Mine2-4D Projects
138
M24D Manual 2
Mine2-4D Projects
139
Appendix A:
The values contained in the Base properties fields vary depending upon whether a Geological Evaluation has been performed or not. If a Geological Evaluation has NOT been performed, the Base Properties will be stored in the evald table. (The d indicates that they are the dummy values. These are so named as they have not been obtained from a geological evaluation against a block model). Should you perform a Dummy Export to scheduler, these are the values that will appear in the Scheduler. The values in the evald table are obtained as follows: Field Metres Fixed Cross Sections Distance along defining centreline Cross Sectional Area of defining shape. Set to 0 for Shanty backs. Insitu Volume * Density Metres * Density Insitu Volume For Shantybacks this will be recalculated at the end of the FXS wireframing to reflect the true 3D Volume of the solid created. Default density from Design Definitions 1 1 Insitu Tonnes Insitu Volume 0 0 Outlines Distance along defining centreline (only if Segment distance set >0) The 3D area of the perimeter. Insitu Volume * Density Area * Height If Advanced Outlines are selected, after the Outline wireframing is complete, the true 3D Volume of the solids created is calculated. Default density from Design Definitions 1 1 Insitu Tonnes Insitu Volume 0 0 Complex Solids Always set to 0
Always set to 0 Insitu Volume * Density After Walls and Points creation = 1000 After CXS Wireframing the true 3D Tonnage of the solids created is calculated. Default density from Design Definitions 1 1 Insitu Tonnes Insitu Volume 0 0
Density Tonnage Factor Grade Factor Mined Tonnes Mined Volume Void Volume Depleted Volume (If selected by the user)
M24D Manual 2
Mine2-4D Projects
140
If a Geological Evaluation has been performed, the evalg table is created. This contains the results of the Geological Evaluation. The evald table is untouched and still retains the original values before the geological evaluation. The fields in the evalg table take on a slightly different value depending on how the Geological Interrogation is performed. The following diagram illustrates the most complicated Geological Interrogation scenario:
Assume that in this example depletion has been performed. The Depleted Segment has already been interrogated and then depleted from the block model. If we now consider the interrogation of the remaining solid represented by the red outline, we have the following terms: Model Volume: - Volume of geological block model contained within the Solid. Depleted Volume: - Volume of previously depleted solids. Void Volume: - Entire volume of solid being evaluated less the model volume and depleted volume - ie that volume that has no Block Model cells within it.
The definition of the values in the evalg table after the geological evaluation has been performed is therefore as follows:
M24D Manual 2
Mine2-4D Projects
141
Field Metres Area Insitu Tonnes Insitu Volume Density Tonnage Factor Grade Factor Mined Tonnes Mined Volume Void Volume Depleted Volume (If selected by the user)
Fixed Cross Sections As in evald As in evald (Model Volume * Model Density) + ((Depleted Volume + Void Volume) * Default Density) Model Volume + Depleted Volume + Void Volume Mined Tonnage / Mined Volume 1 1 (Model Volume * Model Density) + (Void Volume * Default Density) Model Volume + Void Volume Void Volume Depleted Volume
The Default Density refers to the Density as defined in the Project Setup | Default Values table. The Model Density, which exists as a standard field called DENSITY, is always used in preference to the Default Density should it exist in the model. The project database will always contain the above values for the base properties. It is possible to over-write these values through the use of formula in this case the project database will retain the original values and the EPS Scheduler will contain the newly calculated values.
M24D Manual 2
Mine2-4D Projects
142
Appendix B:
walld[] wallf[] walls[] walls_all_[]
During the Mine2-4D processes the following Mine2-4D tables are created: fixed cross sectional wall strings outline wall strings complex solid wall strings combined file containing the wall strings for all the design types
Assuming that the d[], f[] and s[] and all_[] suffixes are used throughout Mine2-4D, the following main tables are created for each design type as they are defined in the Project Setup: points* wall* out* wre* a 3D point in space for each activity a 3D string for each activity a 3D string outline for each complete fxs design string (only created if create single outline is toggled on during fxs wall creation) a 3D solid for each activity
sched_wre* a 3d solid for each activity, honouring the schedule colouring definition defined during the reporting process. tag* link* evald[] tonnage. evalg[] tag strings created during the solids creation process link strings created by the automatic and manual sequencing processes dummy evaluation containing "estimated" values for meters and evaluated results obtained from interrogation against block model
All of these tables are linked on SEGMENT. This is a unique identifier that is exported to the EPS Scheduler as the ID field.
M24D Manual 2
Mine2-4D Projects
143
Appendix C:
SEGMENT NUMBERING
The SEGMENT/ID field Is made up of 10 characters. If decoded: 1 = D,F,S or C depending on whether the activity is a fixed-cross-section, outline or complex solid. 2 = absent, unless that activity is a derived activity. If a derived activity, it takes the value from the derived activity prefix as specified in the Project Setup. For FXS and OUTLINES: 3 to 7 = the M4DSID (Mine2-4D String ID field). This field is updated whenever the definition database is connected to the design, ensuring that each string contains a unique ID. If a string is deleted from a project then the M4D SID will NEVER be repeated. Care should be taken when copying strings in Mine2-4D as the M4DSID will be duplicated and the program will automatically remove that M4DSID permanently from the project. 8 to 10 = the activity number For CXS: 3 to 7 = M4DNUM. This is a standard field added to the design strings upon connection to the definition database.. 8 to 10 = the activity number.
M24D Manual 2
Mine2-4D Projects
144
Datamine Software Limited Somerset, United Kingdom BA5 2AW Tel: +44 1749 679299 Fax: +44 1749 670290 www.datamine.co.uk 2 St Cuthbert Street, Wells
M24D Manual 2
Mine2-4D Projects
145