Sunteți pe pagina 1din 6

SAUDI ARABIAN OIL COMPANY NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

METHOD STATEMENT FOR GRAVITY TESTING OF UNDER GROUND SEWER SYSTEM SUB CONTRACT NO: 308200 DOCUMENT NO: 308200 -MST-PP-004 REV 0

Client : SAUDI ARAMCO SNAMPROGETTI

Project : NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Contractor : DODSAL& CO.

Date : 11.04 .2002

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Page 1

of 6

METHOD STATEMENT FOR GRAVITY TESTING OF UNDER GROUND SEWER SYSTEM

REVISION CONTROL

Revision Status 0

Date of Issue 11.04.2002

Details of Revision INITIAL

Prepared by DODSAL V.K.SAMY

Reviewed by DODSAL S.V.RANGAN

Approved by DODSAL AB

Approved by SP

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Page 2

of 6

METHOD STATEMENT FOR GRAVITY TESTING OF UNDER GROUND SEWER SYSTEM

INDEX

1.0 2.0 3.0 4.0 5.0 6.0

PURPOSE SCOPE REFERENCES DEFINITIONS PROCEDURE DOCUMENTATION

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Page 3

of 6

1.0

PURPOSE To define preparation and method used to conduct GRAVITY leak testing of under ground (RTR pipes) oily water sewer system as required in the specification.

2.0

SCOPE To ensure that the under ground sewer piping system has been successfully leak tested from man hole to man hole or catch basin to the man hole according to the design limit and specification.

3.0

REFERENCE DOCUMENTS 3.1 INTERNATIONAL CODES AND STANDARDS PIP- CVS-02700 3.2 SAUDI ARAMCO DOCUMENTS ScheduleQ Saudi Aramco Engineering Standards SAES - S 020 04-SAMSS -034 SAEP - 327 G.I .2.100 3.3 Industrial Drainage and Sewers RTR (Fibre Glass) Pressure Pipe and Fittings Disposal of wastewater from cleaning, flushing and hydrostatic tests Work permit system Under Ground Gravity Sewers

SNAMPROGETTI DOCUMENTS Quality Control plan for IK activity General requirements for field quality control. Field Quality Control Plan for Piping Piping Material specification Dodsal Documents Inspection and test plan for gravity leak testing Of Sewer piping Inspection and test plan for RTR Piping ; 308200-ITP-PP-004 : 308200-ITP-CI-010
Page 4

: SPC-J64-ZA-E-9601 Rev D : SPC-J64-ZA-E-9607 Rev A : SPC-J64-ZA-E-9618 Rev A : SPC-J64-GA-E-60001 Rev B

Rev 0 Rev 2

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

of 6

4.0

DEFINITIONS COMPANY CONTRACTOR SUB CONTRACTOR OWS SAUDI ARABIAN OIL COMPANY (SAUDI ARAMCO) SNAMPROGETTI DODSAL & CO OILY WATER SEWER SYSTEM

5.0 0 5.1 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 0

PROCEDURE Responsibility The Hydro test Engineer shall be responsible for preparation of the test procedure, delivery of the approved test package to job site The Site Piping Engineer shall ensure the completeness of the piping system before testing through pre-test punch listing. Dodsal RTR QC Inspector to check the system, verify all QC documents, clears the system for Gravity leak testing and co - ordination with the inspection group. The Asst. Piping Engineer and / or Piping Foremen shall prepare the system for leak test. DODSAL RTR piping QC Inspector to check the system and he shall issue RFI to SNAMP and SAUDI ARAMCO for witness of the gravity leak test.

5.2 SAFETY 5.2.1 5.3 The piping system to be tested shall be properly supported and restrained from movements.

MATERIALS All preparatory materials PLUGS or balloon of various Sizes and vent pipe etc

5.4

GENERAL REQUIREMENTS 5.4.1 5.4.2 Prior to the conduct of b leak test, the pre-test punch lists YES ITEMS if any shall be cleared. Sewers that have not been back filled shall be watertight for a period of 4 hours. Sewers that have been back filled shall be watertight for a period of 24 hours.

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Page 5

of 6

5.5

SEQUENCE OF OPERATION 5.5.1 The system may be separated into sub-system for testing. The Under Ground services lay-out Drawing shall show the limit and method of isolation for system or sub- system shall be prepared prior to testing. Fill the system / sub system with approved test fluid (Raw Water) All openings not included in the test shall be isolated by stopper/ plug/ balloon. Air venting shall be provided during filling the sewer pipes. The test water will be filled to the rim of man hole as per SAES- S 070 Para. 18.8. (f). If any leakage is found the system shall be dewatered. Leaks shall be repaired. Test fluid (Raw Water) shall be refilled and test will be continued.

5.5. 2

5.5. 3 5.5.4

5.5.5 Test shall be considered satisfactory if there is no evidence of leakage or loss of WATER LEVEL after the specified test period of 4 Hours / 24 Hours (FULLY BURIED LINES) 5.5.6 5.5.7 Upon completion, the system shall be drained fully. The drained water will be disposed off safely into the sewer drains/ Filled for testing other system( Re use) or safer destinations, which are acceptable to Saudi Aramco. The test result will be documented on the Pressure Test Information Sheet (2462-1-ENG).

5.5.8

DOCUMENTATION SAUDI ARAMCO Documents: Form Code 2462-1-ENG Report Dodsal Documents: 308200/DOD/F-060 REV 1 Piping Punch list Pre test checklist Title Pressure test Information Sheet

308200/DOD/F-063 REV 1

CHEMICAL ANALYSIS OF TEST FLUID (RAW WATER)

308200-MST-PP-004 REV 0 NEAT KHUFF CONDENSATE FRACTIONATION PROJECT

Page 6

of 6

S-ar putea să vă placă și