MID-TERM PROGRESS REPORT

On the course of our final year project, the following works has been completed so far : 1. The site for the hydropower project has been selected as Lower Chepe situated at Gorkha and Lamjung districts. 2. The weir axis has been temporarily fixed. 3. The catchment area of the project has been calculated and was found to be 165.37 sq km. 4. The Thiessen polygon has been developed. 5. The meteorological stations required at Gharedhunga was confirmed 6. For the hydrological data, hydrological station at Garambesi was suitable so was selected. 7. The hydrological data has been collected from Department of Hydrology and Meteorology (DHM).

Submitted By:
Bikram Jadharee(066/BCE/14) Bikram Khusu(066/BCE/16) Prabin Koju(066/BCE/51) Ravi Koju(066/BCE/63) Roshan Sibanjar(066/BCE/65)

Submitted To:
Department of Civil Engineering Khwopa College of Engineering

Date of Submission:2069-10-21