Documente Academic
Documente Profesional
Documente Cultură
1. Background
2. General Construction Principles
3. Option 1, Initial Phasing Recommendation
4. Examination of Alternative Phasing Options
5. Option 2, Landscaping first
6. Option 3, Foundations first
7. Funding
8. Summary and Request for Authorization
APPENDIX
Phase 2 - 7 Months
July 2010 - March 2011
Phase 3 - 11 Months
March 2011 - January 2012
Phase 3 - 11 Months
March 2011 - January 2012
KEY
Stone Staging
General Staging
*
OAD
A C CESS R
WEST
EAST
ACCE
SS ROAD
*
CONSTRUCTION FENCE
PHASE 1 CONSTRUCTION
~40,000 SF
SS ROAD
ACCE
WEST
EAST
ACCE
SS RO
A D
EAST
ACCE
SS ROAD
*
Phase 1 Complete
Phase 2 Complete
PHASE 2 COMPLETE
The finished project will include the Monumental Stair, East and West perimeter paved promenades, and
two allees of trees flanking the great Lawn - all culminating in the forecourt promenade and the "Room"
at the southernmost end of the Island, offering magnificent views of Manhattan, Queens, and Brooklyn.
EXHIBIT 8 - Logistics of Delivery and Setting of Stone
While interdependent, each major component of the Park has its own series of challenges and
demands specific types of construction equipment and building methodologies that must be logically
sequenced and coordinated so as not to disturb finished work, disrupt building process, increase
cost, or impede progress.
The current shipping route requires a deck barge be used to transport the stone along the ocean route from
the north to Roosevelt Island. We anticipate the stone will arrive at Roosevelt Island in November 2009.
Just before the arrival of the granite, a 330-ton crane will be delivered to the site via barge and lifted on to
the island with the use of a floating crane mounted on that barge. The 330-ton crane will be assembled on
the southern end of the island in the area of the ‘Room.’ This 330-ton crane will be used to move the granite
from the staging area and to set the large stones in place. At maximum lifting capacity, this crane has a reach
of approximately 100 feet. [Exhibit 8a: Crane and Barge Specifications]
The floating crane will stay to meet the stone barge, unload the granite blocks for the ‘Room,’ and place them
in the designated stone staging areas. When all of the stone has been unloaded, the stone barge and floating
crane will leave, and the 330-ton crane will begin setting the stone in its final location.
The barges will anchor temporarily in the East Channel as close to the eastern edge of the island as allowable.
The rock outcropping off the southern tip of the island prevents staging the work in that area.
Upon completion of the setting of the stone for the Room, the 330-ton crane will be disassembled and
removed from the site, and work will continue with Phase 2 and Phase 3.
Phases 2 and 3 – Stone for the Paved Promenades and Landscaped Garden
The stone to be used in Phases 2 and 3 is smaller blocks of granite, which can be trucked to the site via the
bridge from Queens to Roosevelt Island. While these blocks are smaller than those for the ‘Room,’ they do
require the use of a crane for setting. A smaller 35-ton crane will perform this work. This crane can be driven
to the island via the bridge, and will move around the site as necessary to install the larger stones that are
part of Phases 2 and 3, finish capstones, sloped granite, stair treads, etc.
330 Ton Stone Setting Crane
330 Ton Stone Setting Crane - Elevation
330 Ton Stone Setting Crane: Base - Front Elevation
330 Ton Stone Setting Crane: Base - Side Elevation
300 Ton Floating Barge Crane
300 Ton Floating Barge Crane
35 Ton Crane for Phase 2 & 3 Stone Setting
35 Ton Crane for Phase 2 & 3 Stone Setting
EXHIBIT 9 - Construction Schedule
Activity Original Early Early
Description 2008 2009 2010 2011 2012
ID Duration Start Finish DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT O
Froject Schedule & Milestones
* At the September 11, 2008 RIOC Board meeting, we faced an October 31, 2008 deadline, set by
the quarry company, to qualify to purchase the granite for a price quoted in October 2007. Before we
finalized the sale, the quarry company reorganized and withdrew the October 2007 offered price and
would not honor the agreement. This development means we are now competitively bidding the stone.
The economic downturn enables us to negotiate a very good price.
The quarrying and fabrication of the granite is a long lead-time item (it needs to be ordered well in
advance). In order to begin construction later this year and stay on schedule, it is essential to place the
order for granite before the end of February.