Documente Academic
Documente Profesional
Documente Cultură
Location
Owner
Date
Subject
Item No.
A.
Description
GENERAL REQUIREMENT
A.1 Mobilization and Demobilization
A.2 Temporary Facility
A.3 Temporary Electricitry and Consumption
A.4 Temporary Water line and Consumption
A.5 Materials Handling
Unit/s
lot
lot
l.s
l.s
lot
Quantity
Material Cost
Labor Cost
69,000.00
86,000.00
65,000.00
18,000.00
34,000.00
Direct Cost
69,000.00
86,000.00
65,000.00
18,000.00
34,000.00
Sub total =Php 272,000.00
B.
C.
D.
REBARWORKS
C.1 Footing
using D10 RSB
using D16 RSB
C.1 Columns
using D10 RSB
using D20 RSB
C.1 Tension Beams
using D10 RSB
using D16 RSB
using D20 RSB
C.1 Corbel
using D16 RSB
C.1 Concrete Gutter reinforcement
using D12 RSB
using D16 RSB
C.1 Slab on fill reinforcement
using D12 RSB
C.1 Suspended Slab reinforcement
using D10 RSB
using D12 RSB
C.1 Masonry wall reinforcement
using D12 RSB
C.1 Additional Longitudinal Reinforcement for footing
using D20 RSB
CONCRETING WORKS
D.1 Footing / Foundation
D.2 Column
D.3 Tension Beams
D.4 Slab on fill
D.5 Suspended Slab
D.6 Concrete Gutter
D.7 Corbel
lot
sq.m
lot
cu.m
cu.m
cu.m
cu.m
lot
1.00
912.00
1.00
599.67
194.12
844.88
166.86
1.00
28.75
41,000.00
316.78
324.99
630.00
710.00
32,000.00
27,000.00
26,220.00
41,000.00
189,963.46
63,087.06
532,274.40
118,470.60
32,000.00
pcs
pcs
101.00
215.00
228.21
241.35
pcs
pcs
2,042.00
806.00
pcs
pcs
pcs
27,000.00
34,086.00
41,000.00
246,952.50
82,013.18
691,956.72
154,011.78
32,000.00
Sub total= Php 1,309,020.18
8.63
7,866.00
95.03
97.50
189.00
213.00
56,989.04
18,926.12
159,682.32
35,541.18
23,049.21
51,890.25
68.46
72.41
6,914.76
15,567.08
29,963.97
67,457.33
228.21
246.12
466,004.82
198,372.72
68.46
73.84
139,801.45
59,511.82
605,806.27
257,884.54
883.00
323.00
321.00
228.21
241.35
246.12
201,509.43
77,956.05
79,004.52
68.46
72.41
73.84
60,452.83
23,386.82
23,701.36
261,962.26
101,342.87
102,705.88
pcs
380.00
241.35
91,713.00
72.41
27,513.90
119,226.90
pcs
pcs
270.00
144.00
229.63
241.35
62,000.10
34,754.40
68.89
72.41
18,600.03
10,426.32
80,600.13
45,180.72
pcs
1,578.00
229.63
362,356.14
68.89
108,706.84
471,062.98
pcs
pcs
51.00
29.00
228.21
229.63
11,638.71
6,659.27
68.46
68.89
3,491.61
1,997.78
15,130.32
8,657.05
pcs
510.00
229.63
117,111.30
68.89
35,133.39
152,244.69
pcs
102.00
246.12
25,104.24
73.84
7,531.27
32,635.51
Sub total= Php 2,351,861.42
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
186.98
65.18
44.81
159.07
3.50
9.17
4.53
3,660.00
3,660.00
3,660.00
3,660.00
3,660.00
3,660.00
3,660.00
684,346.80
238,558.80
164,004.60
582,196.20
12,810.00
33,543.90
16,579.80
915.00
915.00
915.00
915.00
915.00
915.00
915.00
171,086.70
59,639.70
41,001.15
145,549.05
3,202.50
8,385.98
4,144.95
1.00
132,000.00
132,000.00
39,600.00
39,600.00
855,433.50
298,198.50
205,005.75
727,745.25
16,012.50
41,929.88
20,724.75
Sub total= Php 2,165,050.13
171,600.00
E.
FORMWORKS
L.S
F.
MASONRY WORKS
CHB laying Installation Approx. Area = 919.04 sq.m
F.1 CHB 6" thickness
F.2 CHB 4" thickness
F.3 Bags Of Cement
F.4 Sand ( S-1 )
pcs
pcs
bags
cu.m
11,488.00
1,763.00
1,569.00
80.36
12.50
10.75
198.00
420.00
143,600.00
18,952.25
310,662.00
33,751.20
3.75
3.23
59.40
126.00
43,080.00
5,685.68
93,198.60
10,125.36
186,680.00
24,637.93
403,860.60
43,876.56
bags
cu.m
905.00
55.14
198.00
420.00
179,190.00
23,158.80
59.40
126.00
53,757.00
6,947.64
232,947.00
30,106.44
Sub total= Php 922,108.53
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
sheet/s
sheet/s
pcs
75.00
21.00
23.00
46.00
96.00
53.00
39.00
149.00
83.00
124.00
40.00
15.00
2.00
175.00
2,054.00
7,056.00
6,890.00
6,608.00
758.00
968.00
2,257.00
193.00
598.00
113.00
321.89
9,316.00
15,157.00
2,333.97
154,050.00
148,176.00
158,470.00
303,968.00
72,768.00
51,304.00
88,023.00
28,757.00
49,634.00
14,012.00
12,875.60
139,740.00
30,314.00
408,444.75
513.50
1,764.00
1,722.50
1,652.00
189.50
242.00
564.25
48.25
149.50
28.25
80.47
2,329.00
3,789.25
583.49
38,512.50
37,044.00
39,617.50
75,992.00
18,192.00
12,826.00
22,005.75
7,189.25
12,408.50
3,503.00
3,218.90
34,935.00
7,578.50
102,111.19
192,562.50
185,220.00
198,087.50
379,960.00
90,960.00
64,130.00
110,028.75
35,946.25
62,042.50
17,515.00
16,094.50
174,675.00
37,892.50
510,555.94
Sub total =Php 2,075,670.44
G.
STEEL WORKS
Truss 1
Angle bar 75 x 6mm
Angle bar 130 x 15mm
Angle bar 130 x 12mm
Angle bar 130 x 10mm
Angle bar 50 x 4mm
Angle bar 50 x 6mm
Angle bar 100 x 7mm
D10mm Sagrods
D16 Cross-Bracing
Standard Turnbuckle
D20 Achor bolt w/ knots
MS Plate 4' x 8' x 10mm
MS Plate 4' x 8' x 20mm
LC-Purlins 170 x 50 x 1.8 mm
pcs
pcs
pcs
pcs
sheet/s
80.00
46.00
84.00
160.00
3.00
4,319.00
756.00
661.00
113.00
9,316.00
345,520.00
34,776.00
55,524.00
18,080.00
27,948.00
1,295.70
226.80
198.30
33.90
2,794.80
103,656.00
10,432.80
16,657.20
5,424.00
8,384.40
449,176.00
45,208.80
72,181.20
23,504.00
36,332.40
382,395.00
3,658.20
59,112.30
33,476.56
5,876.00
Sub total = Php 484,518.06
78,338.00
125,685.30
14,320.80
41,912.00
63,000.00
Others
Epoxy Primer
Quick drying enamel
Rust Converter
Welding rod
Consumables
pcs
pcs
sheet/s
pcs
pcs
15.00
2.00
3.00
80.00
40.00
19,610.00
1,407.00
15,157.00
321.89
113.00
294,150.00
2,814.00
45,471.00
25,751.20
4,520.00
5,883.00
422.10
4,547.10
96.57
33.90
88,245.00
844.20
13,641.30
7,725.36
1,356.00
gals
gals
gals
box
lot
92.00
111.00
18.00
13.00
1.00
655.00
871.00
612.00
2,480.00
63,000.00
60,260.00
96,681.00
11,016.00
32,240.00
63,000.00
196.50
261.30
183.60
744.00
18,078.00
29,004.30
3,304.80
9,672.00
I.
ROOFING WORKS
H.1 Ga. 26 Pre-painted Rib type for long span
H.2 Bended Items ( Flushing, Roll, etc)
H.3 Accessories
L.m
lot
lot
1,204.00
1.00
1.00
291.03
140,400.00
61,000.00
350,400.12
140,400.00
61,000.00
87.31
42,120.00
18,300.00
105,120.04
42,120.00
18,300.00
455,520.16
182,520.00
79,300.00
Sub total = Php 717,340.16
FINISHING WORKS
I.1 Tile Works
Office floor tiles
C.R floor & wall tile
sq.m
sq.m
47.06
17.24
505.25
505.25
23,777.07
8,710.51
151.58
151.58
7,133.12
2,613.15
30,910.18
11,323.66
Sub total = Php 42,233.84
sq.m
sq.m
56.00
56.00
378.00
310.89
21,168.00
17,409.84
113.40
93.27
6,350.40
5,222.95
27,518.40
22,632.79
Sub total = Php 50,151.09
sq.m
sq.m
229.58
56.00
127.75
189.50
29,328.85
10,612.00
38.33
56.85
8,798.65
3,183.60
38,127.50
13,795.60
Sub total = Php 51,923.10
pc
pc
pcs
lot
1.00
1.00
2.00
1.00
6,700.00
5,600.00
3,200.00
1,890.00
6,700.00
5,600.00
6,400.00
1,890.00
2,010.00
1,680.00
960.00
567.00
2,010.00
1,680.00
1,920.00
567.00
8,710.00
7,280.00
8,320.00
2,457.00
Sub total = Php 26,767.00
I.5 Doors
Flush door/ door jamb
PVC door / door jamb
set
set
2.00
2.00
3,284.00
3,124.00
6,568.00
6,248.00
985.20
937.20
1,970.40
1,874.40
8,538.40
8,122.40
Sub total = Php 16,660.8
I.6 Window
Steel Casement window
Aluminum sliding window
set
set
1.00
1.00
4,680.00
4,980.00
4,680.00
4,980.00
1,404.00
1,494.00
1,404.00
1,494.00
6,084.00
6,474.00
Sub total = Php 12,558.00
set
set
sq.m
1.00
1.00
41,000.00
53,890.00
41,000.00
53,890.00
12,300.00
16,167.00
12,300.00
16,167.00
53,300.00
70,057.00
Sub total = Php 123,357.00
I. Others
Spiral stair
Sliding Gate including accessories
Pre-painted louver sheet for Ventilation
J.
PLUMBING WORKS
lot
1.00
138,902.00
138,902.00
Sub total = Php 138,902.00
K.
ELECTRICAL WORKS
lot
1.00
201,300.00
201,300.00
Sub total = Php 201,300.00
Note:
Prepared By:
PHP
12,076,680.25
Profit ( 10% )
Miscellaneous & Overhead ( 8%)
PHP
PHP
1,207,668.03
966,134.42
PHP
14,250,482.70