Documente Academic
Documente Profesional
Documente Cultură
1) i) ii) iii) iv) v) vi) vii) 2) i) ii) iii) iv) v) vi) 3) i) ii) iii) 4) i) ii) iii) 5)
Tower Line from Gadwal to Maktal HT line taping point @ Yellampally Village to Pump House Stage-I Switch Yard No. of towers - 35 Nos Completed Total length of tower line - 9.160 Km./8.36 Km 30.12.2012 Foundation of Towers - Completed (35 No.s) Erection of Towers - Completed (35 Nos) Stringing of Conductor - Completed (35 Nos) Statutory inspection by TLC - After CEIG Inspection 10.01.2013 Charging of Tower Line - After CEIG Inspection 17.01.2013 Switchyard at Koilsagar L.I. Scheme Stage-I Erection of Equipments - CT,PT,CVT, isolators, Breakers etc., - Completed Statutory inspection by CEIG - No 10.01.2013 Statutory inspection by TLC - No 17.01.2013 Statutory inspection by MRT - No 30.01.2013 Erection of Energy Meters & Service release by APCPDCL - No 30.01.2013 Charging of Switchyard - No 15.02.2013 Station Transformer (1 No) Erection - Completd Testing - No 18.02.2013 Charging - No 15.02.2013 Motor Transformers (2 Nos) (S.F.C) Supply Completed Erection 30.10.2012 Testing - No 18.02.2013 Charging - No 15.02.2013 Pump House - Electro Mechanical works
Unit wise status enclosed ina separate sheet Cistern & Delivery Mains Laying of delivery Mains Delivery Mains (2 m Dia, 2 rows of 220 mtr i) - is in Progress length) - Completed ii) Cistern 7) Fire Fighting & Ventilating System Supply comleted i) Fire Fighting System - Erection to be done Supply comleted ii) AC, Ventillating System - Erection to be done 8) Land Scape Gardening, Internal Roads & Compound Wall 6) i) Land Scape Gardening ii) Internal Roads iii) Compound Wall / Fencing Hand railing in Cistern & Pump House and iv) Miscellaneous works - Layout drawing to be - submitted by the EPC - Agency -
20.11.2012
31.12.2012 31.01.2013
31.12.2012
Status of Work Assembly & Erection of Pump upto pit liner is completed Supply Completed, Erection to be done Supply Completed, Erection to be done Supply Completed, Erection to be done
Balance Work 30.01.2013 20.02.2013 30.12.2012 30.01.2013 30.11.2012 30.11.2012 20.11.2012 25.02.2013 27.02.2013 28.02.2013 20.01.2013 28.02.2013 25.02.2013 25.02.2013 30.10.2012
Drainage & Dewatering system Supply Completed, Erection to be done Discharge valve & Servo motors Supply Completed, Erection to be done Delivery mains Motor & Staion transformers Control & Protection panels for motors Control & Protection panels for transfermors Aircompressor System HT Panels SFC equipment 1,2 & 3 SCADA System a) Mimic panel E/W completed, Pipe line Laying is in progress Erection Completed , Testing to be done Erection Completed , Testing to be done Erection Completed , Testing to be done Supply Completed, Erection to be done Erection Completed , Testing to be done Erection Completed , Testing to be done Supply to be done Erection is in Progress
Assembly of Pump upto pit liner is completed Supply Completed, Erection to be done Supply Completed, Erection to be done Supply Completed, Erection to be done
28.02.2013 20.03.2013 30.01.2013 28.02.2013 30.11.2012 30.11.2012 30.11.2012 25.03.2013 20.03.2013 28.03.2013
Drainage & Dewatering system Supply Completed, Erection to be done Discharge valve & Servo motors Supply Completed, Erection to be done Delivery mains Motor & Staiontransformers Control & Protection panels for motors Control & Protection panels for transformers Erection Completed , Testing to be done Erection Completed , Testing to be done Erection Completed , Testing to be done Erection Completed , Testing to be done
REMARKS
Page 5 of 5
Status
Remarks
Gravity Canal
1 Under Tuneel @ Km. 1.438 2 D.L.R.B @ Km. 2.585 3 Under Tuneel @ Km. 4.109 4 Canal Syphon @ Km. 4.558 5 Super Passage @ Km. 5.238 6 S.L.R.B @ Km. 5.816 7 Under Tuneel @ Km. 6.466 8 S.L.R.B @ Km. 6.522 9 Under Tuneel @ Km. 7.395 10 S.L.R.B @ Km. 7.604 11 Under Tuneel @ Km. 8.358 12 D.L.R.B @ Km. 9.137 13 AQUIDUCT @ Km. 10.155 14 Canal Syphon @ Km. 10.984 15 D.L.R.B @ Km. 11.736 16 S.L.R.B @ Km. 11.925 17 S.L.R.B @ Km. 12.148 18 Super Passage @ Km. 12.496 19 Canal Syphon @ Km. 13.062 20 S.L.R.B @ Km. 14.704 21 INFALL REGULATOR @ Km. 15.000
Status
COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED Super Structure Under Progress COMPLETED COMPLETED COMPLETED
Remarks
15.11.2012