EARTHWORKS CONTROL PROCEDURE

Revision No: ssue Date: Page No:

CONTENTS

1. PURPOSE:..............................................................................2 2. SCOPE:..................................................................................2 3. RESPONSIBILITIES:.................................................................2 4. RESOURCES AND RELATED DOCUMENTS:...................................3 5. DEFINITIONS:.........................................................................3 FOUNDATION LEVEL : LEAN CONCRETE BASE ON THE BUILDING WILL BE ACCEPTED AS FOUNDATION LEVEL. ................................3 6. APPLICATIONS:.......................................................................4
Before starting excavation work HN-QA-01-FR-01 numbered form will be submit to Consultant for approval and sign. .........................................................................................................4 Excavation will be done at boundaries and depth shown in the drawings and specified in the contract and according to order of Consultant . ................................................................4 Test pit will be open to locate underground lines, if necessary..........................................4 Existing undergound structures will be relocated before excavation. .................................4 Survey and excavation sketch will be done during all works. ............................................4 Cleaning and stripping excavations will be done...............................................................4 Excavation pits+trenches have to be deeper than 125 cm shored......................................4 Unsuitable soil in pipe trenches according to employer representatives will be taken out and filled with approved suitable soil according to specification approved. ........................................4 Excavated pipe trenches will be filled with approved granule materials according to contract and compacted according to contract......................................................................................4 All trenches and other excavations will be made with supports if needed...........................4 If backfill will be done for the foundations of building under the underground water level, appropiate material will be used for drainage and excavation will be plumped out till pit or trench is dry . 4 Excess excavated material shuold not be removed from the storage area without any consultant permission, if excavated material is suitable. This material firstly will be use for backfill. f backfill material in stock area isnt enough then will be carried from another suitable source. .........4 All kinds of backfill material will be used according to results of examination and test mentioned test plan after consutant approval. ..................................................................................4 Site must be free of all kinds of materials and vegetable land (all trees, roots, bushes and other plants should be thrown in) which is a part of Contracter s work........................................4 If there is water in the area to be filled, sufficient dewatering should be provided first, and then back to this area must be filled with the appropriate method of construction......................4 Approved fill and granular materials will be filled and compacted within 20 cm layers by approved compaction method, described in the contract..................................................................4 Filling work will be tested as described in the contract, test resulted will be recorded and finished by writting to related forms. ............................................................................................4

Document No:

HN-QA-01-PR 01 20.02.2013 2/5

EARTHWORKS CONTROL PROCEDURE

Revision No: ssue Date: Page No:

7. RECORDS: .............................................................................5

ATTACMENTS:

HN-QA-01-FR-01 Aplication Form For Excavation- Fill- Back fill - Road Works HN-QA-01-FR-02 Form of Field Consistency Test-Sand Cone Method HN-QA-01-FR-03 Calibration Report for Density of Sand and Cone.

1. Purpose:
The procedure for the approval and control of earthworks in the site are prepared.

2. Scope:
Covers all the earthworks in any part of Water Supply and Sanitation Adriatic Coast Phase III Herceg Novi WWTP.

3. Responsibilities:
Site Manager is responsible for supervising the activities specified in this procedure.

Document No:

HN-QA-01-PR 01 20.02.2013 3/5

EARTHWORKS CONTROL PROCEDURE

Revision No: ssue Date: Page No:

Site Engineer is responsible to find appropriate staff who will apply the specified activities in this procedure. Quality Control Manager is responsible for proofing that the procedure for the monitoring and implementation.

4.
o o o o o o o o

Resources and Related Documents:


Contract, Tender Documents, Technical Specifications Project Quality Plan Specifications Civil Works. DIN 4124 Excavation & trenches, slopes,breadths, of working spaces, planking and strutting. DIN 18300 General technical code for earthworks. DIN 18303 General technical code for excavation lining. DIN 18305 Groundwater management. Excavation Plans which will be published in conjunction with construction projects that will be a part of this procedure.

5.

Definitions:
Ground Level : Ground level before starting earth works, but after clean and stripping earth. Foundation Level : Lean concrete base on the building will be accepted as foundation level. Backfill : It means that earth is excavated for road, building foundation etc. according to related technical specifications of contract and then is filled with the same intensity as compressed.

Document No:

HN-QA-01-PR 01 20.02.2013 4/5

EARTHWORKS CONTROL PROCEDURE

Revision No: ssue Date: Page No:

6. Applications:
Before starting excavation work HN-QA-01-FR-01 numbered form will be submit to
Consultant for approval and sign.

Excavation will be done at boundaries and depth shown in the drawings and
specified in the contract and according to order of Consultant . Test pit will be open to locate underground lines, if necessary.

Existing undergound structures will be relocated before excavation. Survey and excavation sketch will be done during all works. Cleaning and stripping excavations will be done.
Excavation pits+trenches have to be deeper than 125 cm shored

Unsuitable soil in pipe trenches according to employer representatives will be taken


out and filled with approved suitable soil according to specification approved.

Excavated pipe trenches will be filled with approved granule materials according to
contract and compacted according to contract.

All trenches and other excavations will be made with supports if needed. If backfill will be done for the foundations of building under the underground water
level, appropiate material will be used for drainage and excavation will be plumped out till pit or trench is dry .

Excess excavated material shuold not be removed from the storage area without any
consultant permission, if excavated material is suitable. This material firstly will be use for backfill. f backfill material in stock area isnt enough then will be carried from another suitable source.

All kinds of backfill material will be used according to results of examination and test
mentioned test plan after consutant approval.

Site must be free of all kinds of materials and vegetable land (all trees, roots, bushes
and other plants should be thrown in) which is a part of Contracter s work.

If there is water in the area to be filled, sufficient dewatering should be provided


first, and then back to this area must be filled with the appropriate method of construction.

Approved fill and granular materials will be filled and compacted within 20 cm layers
by approved compaction method, described in the contract.

Filling work will be tested as described in the contract, test resulted will be recorded
and finished by writting to related forms.

Document No:

HN-QA-01-PR 01 20.02.2013 5/5

EARTHWORKS CONTROL PROCEDURE

Revision No: ssue Date: Page No:

7.

Records: All records will be taken in according to the quality plan. All forms will be filled by Quality Control Manager as specified in control and test plan. All records shall be kept open for inspection on request.