CHIMNEY PACKAGE FOR 2 X 500 MW TPP AT BHUSAVAL FOR MAHAGENCO

P/9228

Construction of One no. 275 m High, Multi Flue,Steel lined, R.C Chimney for 2 x 500 MW TPP at Bhusaval for MAHAGENCO.
BASELINE PROGRAM V/S ACTUAL /REVISED PROGRAM
CHIMNEY
Duration in Months
Sl.N
Work Description
o.
1 Site Mobilisation

Time Period
Planned L2
01/02/08 To 30/04/08
Actual/Revised L4 01/02/08 To 30/04/08
Delay

2 Construction
a) Raft foundations upto the
slipforming start point
i) Excavation in soft Soil, Murrum Planned L2
Actual/Revised L4
and Hard Rock
Delay
ii) P.C.C. for Raft Foundation
Planned L2
Actual/Revised L4
Delay
iii) Reinforcement and shuttering
Planned L2
Actual/Revised L4
fixing for Raft Foundation
Delay
iv) Concreting of Raft Foundation Planned L2
Actual/Revised L4
Delay
v) Conventional Method upto '0'
Planned L2
Actual/Revised L4
Level
Delay
b) Slip form setting
Planned L2
Actual/Revised L4
Delay
c) Shell from '0' m to 50 m height Planned L2
Actual/Revised L4
Delay
d) Shell from 50 to 100 m
Planned L2
Actual/Revised L4
Delay
e) Shell from 100 to 150 m
Planned L2
Actual/Revised L4
Delay
f) Shell from 150 to 200 m
Planned L2
Actual/Revised L4
Delay
g) Shell from 200 to 270 m
Planned L2
Actual/Revised L4
Delay
h)
Planned L2
Shell from 270 to 275 m (Steel
Actual/Revised L4
Flue)
Delay
I)
Planned L2
Fabrication of Steel flue can,
Actual/Revised L4
Internal Platform, Staircase etc.
Delay
j) Erection of Internal platform,
Planned L2
Actual/Revised L4
steel Flue can and staircase
Delay
& Insulation
k) Aviation warning works,
Planned L2
Actual/Revised L4
earthing,
Delay
Lighting protection and other
l) Painting, finishing clearance
Planned L2
Actual/Revised L4
and
Delay
other works
3 Commissioning
Planned L2

01/04/08 To 02/05/08
01/04/08 To 02/05/08
01/05/08 To 12/05/08
01/05/08 To 12/05/08
13/05/08 To 14/06/08
10/07/08 To 16/08/08
62 Days
15/06/08 To 15/08/08
23/07/08 To 05/09/08
21 Days
16/08/08 To 31/08/08
01/09/08 TO 15/09/08
15 Days
01/09/08 To 30/09/08
16/09/08 To 31/10/08
30 Days
01/10/08 To 30/11/08
01/11/08 To 31/12/08
30 days
01/12/08 To 15/01/09
01/01/09 To 15/02/09
30 days
16/01/09 To 02/02/09
16/02/09 To 02/03/09
30 days
03/02/09 To 28/02/09
03/03/09 To 28/03/09
30 days
01/03/09 To 31/03/09
29/03/09 To 21/05/09
45 Days
01/06/09 To 30/06/09
15/09/09 To 20/09/09
45 Days
01/08/08 To 30/10/09
15/01/09 To 30/11/09
30 Days
10/04/09 To 30/11/09
10/06/09 To 31/01/10
60 Days
01/09/09 To 15/01/10
01/09/09 To 16/02/10
30 Days
01/06/09 To 31/12/09
10/09/09 To 31/01/10
30 Days
01/12/09 To 31/01/10

Actual/Revised L4 01/01/10 To 20/02/10


Delay
20 Days

Feb-08

Mar-08

Apr-08 May-08 Jun-08

Jul-08

Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09

May-09

Jun-09

Jul-09

Aug-09 Sep-09 Oct-09 Nov-09

Dec-09

Jan-10

Feb-10

COOLING TOWER PACKAGE FOR 2 X 500 MW TPP AT BHUSAVAL FOR MAHAGENCO


P/9228

CONSTRUCTION OF 2 NOS. N.D. COOLING TOWER FOR 2 X 500 MW POWER PLANT AT BHUSAWAL
BASE LINE PROGRAM V/S ACTUAL PROGRAM
Duration in Months
Sl.
No.

Work Description

1 Site Mobilization

Feb-08

Planned L2

01/02/08 To 30/04/08

Actual/Revised L4

01/02/08 To 30/04/08

Mar-08

Apr-08

May-08

Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08

Dec-08

Delay
2 Construction
a) Foundations
Excavation for Tower Foundation
i)
Unit #1

Unit # 2

Planned L2

23/03/08 To 23/04/08

Actual/Revised L4

23/03/08 To 16/06/08

Delay

54 Days

Planned L2

01/06/08 To 02/07/08

Actual/Revised L4
01/06/08 To 30/12/08
Delay

172 Days

Planned L2

25/04/08 To 30/06/08

Actual/Revised L4

25/09/08 To 10/12/08

Approved Drg Delay

Delay

130 days

Unit # 2

Planned L2

04/07/08 To 30/09/08

Actual/Revised L4

15/11/08 To 10/02/09

Delay

100 Days

Planned L2

01/06/08 To 30/08/08

Actual/Revised L4

07/11/08 To 20/04/09

Delay

230 Days

Planned L2

01/09/08 To 30/11/08

Actual/Revised L4

01/12/08 To 30/06/09

Delay

210 Days

ii) Concreting of Tower Unit #1

b) Pond Wall Unit #1

Unit # 2

casting of a column and ring


c)
beam Unit #1

Unit # 2

shell upto 12 M by Conventional


d)
method Unit #1

Unit # 2

e) Jump Form Erection Unit #1

Unit # 2

Planned L2

01/08/08 To 30/11/08

Actual/Revised L4

17/12/08 To 03/06/09

Delay

183 days

Planned L2

01/12/08 To 30/03/09

Actual/Revised L4

15/01/09 To 20/09/09

Delay

190 Days

Planned L2

01/12/08 To 13/12/08

Actual/Revised L4

01/04/09 To 15/06/09

Delay

167 Days

Planned L2

01/04/09 To 13/04/09

Actual/Revised L4

21/09/09 To 05/10/09

Delay

172 Days

Planned L2

14/12/08 To 15/01/09

Actual/Revised L4

01/05/09 To 26/06/09

Delay

161 Days

Planned L2

14/04/09 To 15/05/09
Page 2 of 5

Jan-09

Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09

Nov-09

Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10

f) shell upto 50 M Unit #1

Unit # 2

g) shell from 50 M to 100 M Unit #1

Unit # 2

Actual/Revised L4

26/07/09 To 30/09/09

Delay

135 Days

Planned L2

18/01/09 To 02/02/09

Actual/Revised L4

27/06/09 To 26/09/09

Delay

204 Days

Planned L2

18/05/09 To 30/07/09

Actual/Revised L4

06/10/09 To 06/12/09

Delay

126 Days

Planned L2

03/02/09 To 30/03/09

Actual/Revised L4

27/09/09 To 12/11/09

Delay

221 Days

Planned L2

03/08/09 To 30/09/09

Actual/Revised L4

07/12/09 To 22/01/09

Delay

112 Days

h) shell from 100 M to 150 M Unit #1 Planned L2

Unit # 2

shell from 150 M to finish level


i)
Unit #1

Unit # 2

j)

Pond Partition Wall / Pond


flooring works Unit #1

Unit # 2

k)

13/11/09 To 30/12/09

Delay

225 Days

Planned L2

01/10/09 To 15/11/09

Actual/Revised L4

23/01/09 To 26/02/10

Delay

101 Days

Planned L2

01/01/10 To 28/01/10

Delay

165 Days

Planned L2

16/11/09 To 30/12/09

Actual/Revised L4

27/02/10 To 31/03/10

Delay

90 Days

Planned L2

25/12/08 To 30/03/10

Delay

30 Days

Planned L2

01/02/09 To 30/09/09

Actual/Revised L4

30/04/09 To 31/05/10

Delay

240 Days

Planned L2

01/10/08 To 30/10/09
16/03/09 To 30/03/10
150 Days
01/05/09 To 31/01/10

Actual/Revised L4

01/08/09 To 31/05/10

Delay

120 Days

Fabrication of Piping and Erection Planned L2


l)
Unit #1
Actual/Revised L4

m) Fill procurement / fixing Unit #1

01/06/08 To 28/02/09

Actual/Revised L4

Delay

Unit # 2

16/05/09 To 15/07/09

Actual/Revised L4

Fill Supporting and hot water duct Planned L2


Unit #1
Actual/Revised L4

Unit # 2

01/04/09 To 15/05/09

Actual/Revised L4

01/12/08 To 30/09/09
20/04/09 To 28/02/10

Delay

150 Days

Planned L2

01/05/09 To 31/01/10

Actual/Revised L4

20/08/09 To 31/05/10

Delay

120 Days

Planned L2

01/12/08 To 30/09/09
Page 3 of 5

Unit # 2

Actual/Revised L4

15/03/09 To 30/04/10

Delay

210 Days

Planned L2

01/05/09 To 28/02/10

Actual/Revised L4

01/07/09 To 15/06/10

Delay

120 Days

Electrical works such as Aviation Planned L2


n) Lightening, Lightening Protection,
Earthing etc. Unit #1
Actual/Revised L4

Unit # 2

Painting and Other Finishing


o)
works Unit #1

Unit # 2

p) Commissioning Unit #1

Unit # 2

01/05/09 To 30/10/09
01/11/09 To 30/04/10

Delay

180 Days

Planned L2

01/10/09 To 28/02/10

Actual/Revised L4

21/01/10 To 31/05/10

Delay

90 Days

Planned L2

01/07/09 To 30/10/09

Actual/Revised L4

01/10/09 To 30/04/10

Delay

180 Days

Planned L2

01/11/09 To 28/02/10

Actual/Revised L4

21/01/10 To 31/05/10

Delay

90 Days

Planned L2
Actual/Revised L4

01/10/09 To 30/11/09

Delay

150 Days

Planned L2
Actual/Revised L4
Delay

01/02/10 To 31/03/10
01/04/10 To 30/06/10
90 Days

01/10/09 To 30/04/10

Page 4 of 5

COOLING TOWER PACKAGE FOR 2 X 500 MW TPP AT BHUSAVAL FOR MAHAGENCO


P/9228

CONSTRUCTION OF 2 NOS. N.D. COOLING TOWER FOR 2 X 500 MW POWER PLANT AT BHUSAWAL
BASE LINE PROGRAM V/S ACTUAL PROGRAM
Sl.
No.

Duration in Months
Work Description

1 Site Mobilization

Program

Dates

Planned L2

01/02/08 To 30/04/08

Actual/Revised L4

01/02/08 To 30/04/08

Feb-08

Mar-08

Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08

Dec-08

Delay
2 Construction
a) Foundations
Excavation for Tower Foundation Planned L2
i)
Unit #1
Actual/Revised L4

ii) Concreting of Tower Unit #1

Approved Drg Delay


b) Pond Wall Unit #1

casting of a column and ring


c)
beam Unit #1

d)

shell upto 12 M by Conventional


method Unit #1

e) Jump Form Erection Unit #1

f) shell upto 50 M Unit #1

g) shell from 50 M to 100 M Unit #1

j)

k)

shell from 150 M to finish level


Unit #1

Pond Partition Wall / Pond


flooring works Unit #1

54 Days

Planned L2

25/04/08 To 30/06/08

Actual/Revised L4

25/09/08 To 10/12/08

Delay

130 days

Planned L2

01/06/08 To 30/08/08

Actual/Revised L4

07/11/08 To 20/04/09

Delay

230 Days

Planned L2

01/08/08 To 30/11/08

Actual/Revised L4

17/12/08 To 03/06/09

Delay

183 days

Planned L2

01/04/09 To 15/06/09

Delay

167 Days

Planned L2

14/12/08 To 15/01/09

Actual/Revised L4

01/05/09 To 26/06/09

Delay

161 Days

Planned L2

18/01/09 To 02/02/09

Actual/Revised L4

27/06/09 To 09/11/09

Delay

299 Days

Planned L2

03/02/09 To 30/03/09

Actual/Revised L4

10/11/09 To 21/12/09

Delay

274 Days

22/12/09 To 28/01/10

Delay

257 Days

Planned L2

29/01/10 To 10/02/10

Delay

209 Days

Planned L2

01/06/08 To 28/02/09

Actual/Revised L4

25/12/08 To 30/04/10

Delay

426 Days

Delay
Planned L2

01/10/08 To 30/10/09
16/03/09 To 31/05/10
212 Days
01/12/08 To 30/09/09
20/04/09 To 31/05/10
242 Days
01/12/08 To 30/09/09

Actual/Revised L4

15/03/09 To 31/05/10

Delay

242 Days

Electrical works such as Aviation Planned L2


n) Lightening, Lightening Protection,
Earthing etc. Unit #1
Actual/Revised L4
Delay

p) Commissioning Unit #1

16/05/09 To 15/07/09

Actual/Revised L4

Fabrication of Piping and Erection Planned L2


l)
Unit #1
Actual/Revised L4

Painting and Other Finishing


works Unit #1

01/04/09 To 15/05/09

Actual/Revised L4

Delay

o)

01/12/08 To 13/12/08

Actual/Revised L4

Fill Supporting and hot water duct Planned L2


Unit #1
Actual/Revised L4

m) Fill procurement / fixing Unit #1

23/03/08 To 16/06/08

Delay

h) shell from 100 M to 150 M Unit #1 Planned L2

i)

23/03/08 To 23/04/08

Planned L2

01/05/09 To 30/10/09
01/11/09 To 31/05/10
212 Days
01/07/09 To 30/10/09

Actual/Revised L4

01/10/09 To 31/05/10

Delay

212 Days

Planned L2
Actual/Revised L4

01/10/09 To 04/12/09

Delay

212 Days

01/10/09 To 30/06/10

Page 5 of 5

Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09

Nov-09

Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10