Construction of One no. 275 m High, Multi Flue,Steel lined, R.C Chimney for 2 x 500 MW TPP at Bhusaval for MAHAGENCO.
BASELINE PROGRAM V/S ACTUAL /REVISED PROGRAM
CHIMNEY
Duration in Months
Sl.N
Work Description
o.
1 Site Mobilisation
Time Period
Planned L2
01/02/08 To 30/04/08
Actual/Revised L4 01/02/08 To 30/04/08
Delay
2 Construction
a) Raft foundations upto the
slipforming start point
i) Excavation in soft Soil, Murrum Planned L2
Actual/Revised L4
and Hard Rock
Delay
ii) P.C.C. for Raft Foundation
Planned L2
Actual/Revised L4
Delay
iii) Reinforcement and shuttering
Planned L2
Actual/Revised L4
fixing for Raft Foundation
Delay
iv) Concreting of Raft Foundation Planned L2
Actual/Revised L4
Delay
v) Conventional Method upto '0'
Planned L2
Actual/Revised L4
Level
Delay
b) Slip form setting
Planned L2
Actual/Revised L4
Delay
c) Shell from '0' m to 50 m height Planned L2
Actual/Revised L4
Delay
d) Shell from 50 to 100 m
Planned L2
Actual/Revised L4
Delay
e) Shell from 100 to 150 m
Planned L2
Actual/Revised L4
Delay
f) Shell from 150 to 200 m
Planned L2
Actual/Revised L4
Delay
g) Shell from 200 to 270 m
Planned L2
Actual/Revised L4
Delay
h)
Planned L2
Shell from 270 to 275 m (Steel
Actual/Revised L4
Flue)
Delay
I)
Planned L2
Fabrication of Steel flue can,
Actual/Revised L4
Internal Platform, Staircase etc.
Delay
j) Erection of Internal platform,
Planned L2
Actual/Revised L4
steel Flue can and staircase
Delay
& Insulation
k) Aviation warning works,
Planned L2
Actual/Revised L4
earthing,
Delay
Lighting protection and other
l) Painting, finishing clearance
Planned L2
Actual/Revised L4
and
Delay
other works
3 Commissioning
Planned L2
01/04/08 To 02/05/08
01/04/08 To 02/05/08
01/05/08 To 12/05/08
01/05/08 To 12/05/08
13/05/08 To 14/06/08
10/07/08 To 16/08/08
62 Days
15/06/08 To 15/08/08
23/07/08 To 05/09/08
21 Days
16/08/08 To 31/08/08
01/09/08 TO 15/09/08
15 Days
01/09/08 To 30/09/08
16/09/08 To 31/10/08
30 Days
01/10/08 To 30/11/08
01/11/08 To 31/12/08
30 days
01/12/08 To 15/01/09
01/01/09 To 15/02/09
30 days
16/01/09 To 02/02/09
16/02/09 To 02/03/09
30 days
03/02/09 To 28/02/09
03/03/09 To 28/03/09
30 days
01/03/09 To 31/03/09
29/03/09 To 21/05/09
45 Days
01/06/09 To 30/06/09
15/09/09 To 20/09/09
45 Days
01/08/08 To 30/10/09
15/01/09 To 30/11/09
30 Days
10/04/09 To 30/11/09
10/06/09 To 31/01/10
60 Days
01/09/09 To 15/01/10
01/09/09 To 16/02/10
30 Days
01/06/09 To 31/12/09
10/09/09 To 31/01/10
30 Days
01/12/09 To 31/01/10
Feb-08
Mar-08
Jul-08
May-09
Jun-09
Jul-09
Dec-09
Jan-10
Feb-10
CONSTRUCTION OF 2 NOS. N.D. COOLING TOWER FOR 2 X 500 MW POWER PLANT AT BHUSAWAL
BASE LINE PROGRAM V/S ACTUAL PROGRAM
Duration in Months
Sl.
No.
Work Description
1 Site Mobilization
Feb-08
Planned L2
01/02/08 To 30/04/08
Actual/Revised L4
01/02/08 To 30/04/08
Mar-08
Apr-08
May-08
Dec-08
Delay
2 Construction
a) Foundations
Excavation for Tower Foundation
i)
Unit #1
Unit # 2
Planned L2
23/03/08 To 23/04/08
Actual/Revised L4
23/03/08 To 16/06/08
Delay
54 Days
Planned L2
01/06/08 To 02/07/08
Actual/Revised L4
01/06/08 To 30/12/08
Delay
172 Days
Planned L2
25/04/08 To 30/06/08
Actual/Revised L4
25/09/08 To 10/12/08
Delay
130 days
Unit # 2
Planned L2
04/07/08 To 30/09/08
Actual/Revised L4
15/11/08 To 10/02/09
Delay
100 Days
Planned L2
01/06/08 To 30/08/08
Actual/Revised L4
07/11/08 To 20/04/09
Delay
230 Days
Planned L2
01/09/08 To 30/11/08
Actual/Revised L4
01/12/08 To 30/06/09
Delay
210 Days
Unit # 2
Unit # 2
Unit # 2
Unit # 2
Planned L2
01/08/08 To 30/11/08
Actual/Revised L4
17/12/08 To 03/06/09
Delay
183 days
Planned L2
01/12/08 To 30/03/09
Actual/Revised L4
15/01/09 To 20/09/09
Delay
190 Days
Planned L2
01/12/08 To 13/12/08
Actual/Revised L4
01/04/09 To 15/06/09
Delay
167 Days
Planned L2
01/04/09 To 13/04/09
Actual/Revised L4
21/09/09 To 05/10/09
Delay
172 Days
Planned L2
14/12/08 To 15/01/09
Actual/Revised L4
01/05/09 To 26/06/09
Delay
161 Days
Planned L2
14/04/09 To 15/05/09
Page 2 of 5
Jan-09
Nov-09
Unit # 2
Unit # 2
Actual/Revised L4
26/07/09 To 30/09/09
Delay
135 Days
Planned L2
18/01/09 To 02/02/09
Actual/Revised L4
27/06/09 To 26/09/09
Delay
204 Days
Planned L2
18/05/09 To 30/07/09
Actual/Revised L4
06/10/09 To 06/12/09
Delay
126 Days
Planned L2
03/02/09 To 30/03/09
Actual/Revised L4
27/09/09 To 12/11/09
Delay
221 Days
Planned L2
03/08/09 To 30/09/09
Actual/Revised L4
07/12/09 To 22/01/09
Delay
112 Days
Unit # 2
Unit # 2
j)
Unit # 2
k)
13/11/09 To 30/12/09
Delay
225 Days
Planned L2
01/10/09 To 15/11/09
Actual/Revised L4
23/01/09 To 26/02/10
Delay
101 Days
Planned L2
01/01/10 To 28/01/10
Delay
165 Days
Planned L2
16/11/09 To 30/12/09
Actual/Revised L4
27/02/10 To 31/03/10
Delay
90 Days
Planned L2
25/12/08 To 30/03/10
Delay
30 Days
Planned L2
01/02/09 To 30/09/09
Actual/Revised L4
30/04/09 To 31/05/10
Delay
240 Days
Planned L2
01/10/08 To 30/10/09
16/03/09 To 30/03/10
150 Days
01/05/09 To 31/01/10
Actual/Revised L4
01/08/09 To 31/05/10
Delay
120 Days
01/06/08 To 28/02/09
Actual/Revised L4
Delay
Unit # 2
16/05/09 To 15/07/09
Actual/Revised L4
Unit # 2
01/04/09 To 15/05/09
Actual/Revised L4
01/12/08 To 30/09/09
20/04/09 To 28/02/10
Delay
150 Days
Planned L2
01/05/09 To 31/01/10
Actual/Revised L4
20/08/09 To 31/05/10
Delay
120 Days
Planned L2
01/12/08 To 30/09/09
Page 3 of 5
Unit # 2
Actual/Revised L4
15/03/09 To 30/04/10
Delay
210 Days
Planned L2
01/05/09 To 28/02/10
Actual/Revised L4
01/07/09 To 15/06/10
Delay
120 Days
Unit # 2
Unit # 2
p) Commissioning Unit #1
Unit # 2
01/05/09 To 30/10/09
01/11/09 To 30/04/10
Delay
180 Days
Planned L2
01/10/09 To 28/02/10
Actual/Revised L4
21/01/10 To 31/05/10
Delay
90 Days
Planned L2
01/07/09 To 30/10/09
Actual/Revised L4
01/10/09 To 30/04/10
Delay
180 Days
Planned L2
01/11/09 To 28/02/10
Actual/Revised L4
21/01/10 To 31/05/10
Delay
90 Days
Planned L2
Actual/Revised L4
01/10/09 To 30/11/09
Delay
150 Days
Planned L2
Actual/Revised L4
Delay
01/02/10 To 31/03/10
01/04/10 To 30/06/10
90 Days
01/10/09 To 30/04/10
Page 4 of 5
CONSTRUCTION OF 2 NOS. N.D. COOLING TOWER FOR 2 X 500 MW POWER PLANT AT BHUSAWAL
BASE LINE PROGRAM V/S ACTUAL PROGRAM
Sl.
No.
Duration in Months
Work Description
1 Site Mobilization
Program
Dates
Planned L2
01/02/08 To 30/04/08
Actual/Revised L4
01/02/08 To 30/04/08
Feb-08
Mar-08
Dec-08
Delay
2 Construction
a) Foundations
Excavation for Tower Foundation Planned L2
i)
Unit #1
Actual/Revised L4
d)
j)
k)
54 Days
Planned L2
25/04/08 To 30/06/08
Actual/Revised L4
25/09/08 To 10/12/08
Delay
130 days
Planned L2
01/06/08 To 30/08/08
Actual/Revised L4
07/11/08 To 20/04/09
Delay
230 Days
Planned L2
01/08/08 To 30/11/08
Actual/Revised L4
17/12/08 To 03/06/09
Delay
183 days
Planned L2
01/04/09 To 15/06/09
Delay
167 Days
Planned L2
14/12/08 To 15/01/09
Actual/Revised L4
01/05/09 To 26/06/09
Delay
161 Days
Planned L2
18/01/09 To 02/02/09
Actual/Revised L4
27/06/09 To 09/11/09
Delay
299 Days
Planned L2
03/02/09 To 30/03/09
Actual/Revised L4
10/11/09 To 21/12/09
Delay
274 Days
22/12/09 To 28/01/10
Delay
257 Days
Planned L2
29/01/10 To 10/02/10
Delay
209 Days
Planned L2
01/06/08 To 28/02/09
Actual/Revised L4
25/12/08 To 30/04/10
Delay
426 Days
Delay
Planned L2
01/10/08 To 30/10/09
16/03/09 To 31/05/10
212 Days
01/12/08 To 30/09/09
20/04/09 To 31/05/10
242 Days
01/12/08 To 30/09/09
Actual/Revised L4
15/03/09 To 31/05/10
Delay
242 Days
p) Commissioning Unit #1
16/05/09 To 15/07/09
Actual/Revised L4
01/04/09 To 15/05/09
Actual/Revised L4
Delay
o)
01/12/08 To 13/12/08
Actual/Revised L4
23/03/08 To 16/06/08
Delay
i)
23/03/08 To 23/04/08
Planned L2
01/05/09 To 30/10/09
01/11/09 To 31/05/10
212 Days
01/07/09 To 30/10/09
Actual/Revised L4
01/10/09 To 31/05/10
Delay
212 Days
Planned L2
Actual/Revised L4
01/10/09 To 04/12/09
Delay
212 Days
01/10/09 To 30/06/10
Page 5 of 5
Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09
Nov-09