ARISTOTELION UNIVERSITY OF THESSALONIKI SCHOOL OF TECHNOLOGY FACULTY OF RURAL AND SURVEYING ENGINEERING DEPARTMENT OF TRANSPORTATION AND HYDRAULIC ENGINEERING
CORRIDOR X ALIGNMENT
Main Axis: Salzburg Ljubljana Zagreb Beograd Nis Skopje Veles Thessaloniki Branch A: Graz (Austria) Maribor (Slovenia) Zagreb (Croatia) Branch B: Budapest (Hungary) Novi Sad (F.R. Yugoslavia) Beograd (F.R. Yugoslavia) Branch C: Nis (F.R. Yugoslavia) Sofia (Bulgaria) and further via Corridor IV to Istanbul Branch D: Veles (F.Y.R.O.M.) Bitola (F.Y.R.O.M.) Florina (Greece) and further via Florina Kozani (via Egnatia) to Igoumenitsa
Road Corridor X consists of a total length of 2299,6 km, as follows: Main Axis: 1451,4 km Branch A: 163,4 km Branch B: 352,9 km Branch C: 191,8 km Branch D: 140,1 km Permitted maximum speed along the road axis: 120km/h (in most of the parts). The axis consists of highways or motorways. 53,8% of the road network consists of motorways. 32,7% of the Corridor X road network will be reconstructed or upgraded by the end of 2005.
Rail Corridor X consists of a total length of 2528,2 km, as follows: Main Axis: 1742,3 km Branch A: 154,3 km Branch B: 305,6 km Branch C: 161,0 km Branch D: 165,0 km The whole axis consists of single and double tracks lines per direction in a proportion of 64% and 36% respectively 89% of the total length of the Axis is electrified. 10% of the Corridor X rail network will be reconstructed or upgraded by the end of 2010.
MAIN RESULTS OF THE SURVEY: General description of the existing situation (1/2)
The road main Corridor X and branch A is generally in good geometrical, maintenance and operational condition, and it consists of highways and motorways, in a proportion of 28,4% and 71,6% respectively.
At the moment 66,4% of the main Corridor X and branch A has been constructed with two lanes per direction and is characterized by operational speed over 100km/h. Works are taking place concerning the upgrade and the rehabilitation of the axis.
The rail network (both main and branch A) of this northern part of the Corridor is in accordance to the road one, but branch A does not run through Croatia. It consists of 65,2% dual-track infrastructure, and maintenance is considered medium in Croatia and high in Austria and Slovenia. The running time for passenger trains on the main part of the corridor in Slovenia is 2,5 hours and for freight is 3 hours. The delays observed at the Dobova (SlovenianCroatian border) custom control are usually 0,5 hours for the passenger trains and 1 hour for freight trains.
Delays at the other border crossings are estimated to be 30 min maximum for passenger trains.
For the freight trains the maximum delay observed at the Austrian-Slovenian and the Croatian-Yugoslavian borders is approximately 1 hour.
MAIN RESULTS OF THE SURVEY: General description of the existing situation (2/2)
Hungarys part of Corridor X is branch B that links Budapest to Belgrade. In a total length of 353km, the branch consists of motorways (97km) and highways (256km), with permitted speed that varies between 80-120km/h. The Hungarian part will be fully constructed as motorway by the end of 2005. The rail branch B of the corridor ends up at Novi Sad (upgrade needed has been estimated to be completed by 2010). The running time in the Hungarian territory is 3 hours for passenger trains and 5 hours for freight trains.
The delays at the Hungarian-Yugoslavian border (Kelebia) are 50 min for passenger trains and 180-250 min for freight trains.
The rail Corridor X infrastructure has been estimated to be reconstructed/upgraded by the year 2010 in Yugoslavia, and by the year 2004 in Bulgaria. It should be mentioned that the traction system of branch C is not electrified but diesel. More than half of the road Corridor X in F.Y.R.O.M. and in Greece is not a motorway. It ends up to Thessaloniki and to Florina through its branch D. It also crosses with Egnatia. The rail infrastructure is 100% single track. At present, the delay for the border crossing from F.Y.R.O.M. to Greece has been estimated to be 5 hours.
MAIN RESULTS OF THE SURVEY: Road Corridor X expected situation by the year 2005
Main axis: 90% motorways (+18%) Branch : 90% motorways (+35%) Branch B: 100% motorways (+72%) Branch C: 74% motorways (+48%) Branch D: No improvement
Hungary: 100% motorways Yugoslavia: 100% motorways Croatia, Slovenia: Almost 100% motorways
MAIN RESULTS OF THE SURVEY: Rail Corridor X expected situation by the year 2010
Main axis: +10% double track alignment Branch : +10% double track alignment Branch B: +49% double track alignment Branch C: +53% electrified lines Branch D: +88,5% electrified lines
Hungary: 100% double track alignment Yugoslavia: slide increase of double tracks F.Y.R.O..: Full electrification Greece: increase of double tracks (Main axis)
CONCLUSIONS (1/2)
PAN-EUROPEAN RAIL CORRIDOR X 35,8% is double track (this means that about 2/3 of the railway axis need to be improved in terms of double track infrastructure). 11,3% still needs electrification. PAN-EUROPEAN ROAD CORRIDOR X 46,2% is single carriageway. SITUATION PER COUNTRY The whole railway network (Main part and branches) in Austria, Hungary and Slovenia is now electrified, while the respective percentage is 84,3% in Croatia, 88,1% in Yugoslavia, 74,1% in Bulgaria, 60,7% in F.Y.R.O.M. and 81,2% in Greece. The transformation of the existing road network to motorway standards is a more crucial task in some countries where more than half of the road network is not a motorway nowadays (e.g., in Slovenia 59,5%, in Croatia 25,9%, in Yugoslavia 52,2%, in Hungary 41,9%, in F.Y.R.O.M. 63,8% and in Greece 51%).
CONCLUSIONS (2/2)
The improvement of the current infrastructure does not necessarily mean the overall improvement in the operation of the Corridor, unless specific measures are implemented at cross border stations. Therefore special attention must be paid to the improvement of the cross border stations processes since substantial benefits can be obtained at relatively low cost. Generally, the delays at the border-crossings along Corridor X must be reduced according to the AGTC treaty (European Agreement on Important International Combined Transport Lines and Related Installations), which imposes a maximum delay limit of 30 minutes. Corridor X should be upgraded at fully operational level through the cooperation and coordination of the concerned countries, in the framework of the stabilization process in the Southeastern Europe and the European Union, and in order to serve the international transportation. Cooperation in the sector of transportation and economic activities will bring the nations together, harmonize their relationships and contribute to a common set of objectives for the development of the region. Common will for stability and development, should open the horizons for a global utilization of Corridor X not only by the neighboring countries but countries of other continents too.
COST ESTIMATION FOR ROAD SECTIONS FACING THE MOST IMPORTANT PROBLEMS
Axis Main Axis Branch A Branch B Branch C Length (Km) 312 58,2 246 153 Cost (millions ) 922,5 180 738 450
Total
Branch D
769,2
105
2290,5
n.a.
Country
FYROM (except D) FRY Croatia Slovenia Hungary Bulgaria
Length (Km)
51,5 445,6 48,8 114,3 60 49
Cost (millions )
135,5 1295 150 370 180 160
Total
769,2
2290,5
ARISTOTELION UNIVERSITY OF THESSALONIKI SCHOOL OF TECHNOLOGY FACULTY OF RURAL AND SURVEYING ENGINEERING DEPARTMENT OF TRANSPORTATION AND HYDRAULIC ENGINEERING
April 2002
B. BRANCHES OF CORRIDOR X
Branch A
Slovenia: Maribor Gruskovje (S/C border): 38,8km Croatia: Makelj (S/C border) Krapina: 19,4km F.R. Yugoslavia: Horgos (Hungary border) Batajnica (Belgrade): 176km Hungary: Kiskunfelegyhaza Szeged Roszke (H/Y border): 60km
Branch B
Branch C
F.R. Yugoslavia: Nis Dimitrovgrad (F.R. Yugoslavia): 104km Bulgaria: Kalotina (Y/B border) Sofia (Beginning of Ring Road, North Arc): 49km
F.Y.R.O.M.: Veles Prilep Bitola (F.Y.R.O.M.): 104,6km
Branch D
Length 75,5km
Existing situation: Road is under construction (highway with 1 traffic lane per direction -> motorway) The construction of the motorway started in 1999 Estimated duration of the works: 60 months A.A.D.T.: Section Bic-Novo Mesto Novo Mesto-Brezice Brezice-Obrezje Year of AADT per section 1 9 99 1 9 99 1 9 99 AADT (both directions) 14.000 11.500 6.500 Percentage of passenger cars (%) 83 83 83
2 Zupanja
Lipovac
29,43km
Velika Kopanica Zupanja: - Existing situation: Highway with 1 traffic lane per direction - The earthworks for the construction of the motorway (2x2 traffic lanes per direction) are complete Zupanja Lipovac: - Existing situation: Highway with 1 traffic lane per direction - Technical study for the construction of motorway is almost completed (about 80% in year 2000) - Estimated cost for the construction of motorway: 90 million EURO EXPECTED A.A.D.T.: Section Velika Kopanica - Zupanja Zupanja - Lipovac (C/Y border)
Sub-section 1: Existence of reconnaissance study Estimated cost for the construction of motorway: 30 million EURO Sub-section 2: Existence of construction plans and specifications for the construction of motorway Estimated cost for the construction of motorway: 24 million EURO (+ cost for the repair of the bridge) Sub-section 3: Existence of construction plans and specifications for the construction of motorway Estimated cost for the construction of motorway: 60 million EURO (+ cost for the repair of the bridge)
EXPECTED A.A.D.T.: Section Target year Expected AADT (both directions) Expected percentage of passenger cars (%) 70 56 60 Comments
Length 23,24km
Existing situation: Highway (27,129km - 1 traffic lane per direction) Existence of construction plans and specifications for the construction of motorway Estimated cost for the construction of motorway: 69 million EURO A.A.D.T.: Section Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica Leskovac (Pecenjevce) - Grdelica EXPECTED A.A.D.T.: Section Target year Leskovac (Pecenjevce) Grdelica 2 02 0 Year of AADT per section 1 9 90 1 9 95 1 9 96 1 9 97 1 9 98 1 9 99 2 0 00 AADT (both directions) 9 4 64 3 5 34 4 1 28 4 6 12 5 2 21 3 2 90 4 2 50 Percentage of passenger cars (%) 52 75 74 74 72 68 72
Length 98km
Character of the study Comments 1. Partly new route 2. Sub-section of Lescovac Kumanovo
Existing situation: Highway (94,858km - 1 traffic lane per direction) Existence of study in sub-section Grabovnica-Bujanovac (72,5km location study) Existence of construction plans and specifications for the construction of motorway in sub-section Bujanovac (Levosoje) F.Y.R.O.M. border Estimated cost for the construction of motorway: 294 million EURO In the Quick-start projects of the EIB it is included the rehabilitation of the sub-section Bujanovac-Presevo (15km 8 million EURO)
A.A.D.T.: Section Grdelica - Vladicin Han Grdelica - Vladicin Han Grdelica - Vladicin Han Grdelica - Vladicin Han Grdelica - Vladicin Han Grdelica - Vladicin Han Grdelica - Vladicin Han Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) Vladicin Han - Presevo (Y/F border) EXPECTED A.A.D.T.: Section Vladicin Han Y/F border Target year 2015 Year of AADT per section 1990 1995 1996 1997 1998 1999 2000 1990 1995 1996 1997 1998 1999 2000 Expected AADT (both directions) 20.632 AADT (both directions) 9.434 3.566 4.028 4.270 4.868 3.256 4.010 8.772 3.730 4.144 4.884 4.570 3.261 4.010 Expected percentage of passenger cars (%) 70 Percentage of passenger cars (%) 52 75 74 74 72 71 75 56 78 78 82 80 77 75 Comments Estimated in 1997
Existing situation: Highway (7km - 1 traffic lane per direction) Estimated cost for the upgrading of the road to motorway: 10 million EURO Flat terrain: ~1,5 million EURO/km A.A.D.T.: Section Year of AADT AADT (from- AADT (toper section to) from) 1 998 1 999 9 89 8 66 1.209 1.016 AADT (both Percentage of directions) passenger cars (%) 71,97 2.198 1.882 80,02
Tabanovce (Y/F border) Kumanovo Tabanovce (Y/F border) Kumanovo EXPECTED A.A.D.T.: Section Tabanovce (Y/F border) Kumanovo
Target year 20 20
Length ~15,5km
Existing situation: Motorway is partly under construction (highway with 1 traffic lane per direction -> motorway) Existence of construction plans and specifications for the construction of motorway The project consists of 3 phases From 1.10.2000 a section of 5,3km (from Negotino to Demir Kapija) is under construction Phare Programme 1998, 7,3 million EURO, estimated duration of works: 18 months. The government is responsible for the possible needed expropriations In 18.09.2000 tender documents were under preparation for the next 4km Phare Programme 1999 Existence of technical study for the rest section (~6km) Financing not secured
Length 44,5km
Character of study Comments 1. Rehabilitation of the existing carriageway and construction of a new carriageway 2. Existence of feasibility study (Scetauroute) 3. Problematic section 3 (Axios Canyon)
Existing situation: Road with 1 traffic lane per direction (47,462km): Demir Kapija - Udovo (22,27km): Mountainous terrain in both sides next to Vardar river. The level of the road is at 40m above river level (887m tunnels & 1.240m bridges) Udovo - Gevgelija (25,192km): Valley with flat terrain and little topographic difficulties Estimated cost for the upgrading and rehabilitation of the existing road: 32 million EURO Financing secured for the upgrading and rehabilitation of the existing road: EIB (10 million EURO), EBRD (15 million EURO), Helenic Republic (4 million EURO), Fund for National and Regional Roads (3 million EURO) Existence of construction plans and specifications for the construction of motorway Financing not secured. Estimated cost: 160 million Euro A.A.D.T. (Scetauroute): Section Year of AADT AADT (both per section directions) Demir Kapija - Gevgelija Before 1990 8.500 - 9.000 Demir Kapija - Udovo 1998 2.600 Udovo - Miletkovo 1998 1.800 Miletkovo - Prdejci 1998 3.100 Prdejci - Gevgelija 1998 3.400 International transit flow is very low today (about 20% of the whole traffic)
EXPECTED A.A.D.T. (Scetauroute): Section Target year Expected AADT for Expected AADT existing road for motorway network (both directions) (both directions) Demir Kapija - Udovo 200 3 5.200 5.800 Udovo - Miletkovo 200 3 4.400 4.400 Miletkovo - Prdejci 200 3 5.600 6.200 Prdejci - Gevgelija 200 3 6.000 6.800 Demir Kapija - Udovo 202 0 8.200 10.200 Udovo - Miletkovo 202 0 6.800 6.800 Miletkovo - Prdejci 202 0 9.000 10.400 Prdejci - Gevgelija 202 0 9.800 11.200 CROSS BORDER STATION (Scetauroute) F.Y.R.O.M. vehicles Cross border Year Entrance E x it Bogorodica 1999 110.883 113.427
Expected AADT for motorway pessimistic scenario (both directions) 4.900 3.700 5.300 5.800 8.700 5.800 8.800 9.500
EXPECTED TOURISTS (FROM AND WITH DESTINATION GREECE) WHO WILL PASS THROUGH THIS SECTION (Scetauroute) Year Optimistic Pessimistic scenario scenario 2003 900.000 840.000 2020 1.400.000 1.200.000
BRIDGES NEEDED FOR THE CONSTRUCTION OF MOTORWAY (Scetauroute): Demir Kapija - Udovo: o There are 11 bridges with a total length of 1.237m which they need rehabilitation o Need for 8 new bridges (total length: 1.160m, surface: 12.860m2) Udovo - Gevgelija: o There are 5 bridges with a total length of 349m o There are 4 underpasses with a total length of 74m o There are 3 overpasses with a total length of 87m o Need for destruction and reconstruction of 4 bridges (129m) o Need for destruction and reconstruction of 2 underpasses (34m) o Need for destruction and reconstruction of 3 overpasses (87m) o Need for 5 new bridges (total length: 367m, surface 8.752m2) o Need for 4 new underpasses (total length: 87m, surface 2.238m2) o Need for 7 new overpasses (total length: 332m, surface 2.415m2) o Total: Need for 16 new constructions (776m, 13.405m2) TOTAL COST FOR CONSTRUCTION OF MOTORWAY (INCLUDED CONSTRUCTIVE WORKS Scetauroute): Section Cost in million EURO Cost per kilometer (in million EURO) Demir Kapija - Udovo (20km) 85,239 4,262 Udovo - Smokvica (12,7km) 25,548 2,012 Smokvica - Gevgelija (11,8km) 14,767 1,251 125,554 2,822 Total:
Existing situation: Highway with 1 traffic lane per direction (38,8km) Expected starting date of the construction of motorway: 2002 Estimated duration of the works: 24 months Estimated cost for the construction of motorway: 120 million EURO A.A.D.T.: Section Maribor - Ptuj (Hajdina) Ptuj (Hajdina) - Gruskovje (S/C border) Year of AADT per AADT Percentage of section (both directions) passenger cars (%) 199 9 14.000 88 199 9 6.000 85
Existing situation: Highway with 1 traffic lane per direction (19,4km) Existence of feasibility study for the construction of motorway Expected starting date of the construction of motorway: 2001 Estimated duration of the works: 48 months Estimated cost for the construction of motorway: 60 million EURO EXPECTED A.A.D.T.: Section Makelj (S/C border) - Krapina
Existing situation: Highway with 1 or 2 traffic lanes per direction Existence of construction plans and specification for the construction of motorway Estimated cost for the construction of motorway: (528 million EURO)
A.A.D.T.:
Section Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Horgos (H/Y border) - Novi Sad Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Novi Sad Batajnica (Belgrade) Year of AADT per section 1990 1995 1996 1997 1998 1999 2000 1990 1995 1996 1997 1998 1999 2000 Expected AADT (both directions) 34.300 AADT (both directions) 5400 4431 5583 7198 6787 2761 4160 7501 6832 8526 9582 9637 6404 8820 Expected percentage of passenger cars (%) 75 Percentage of passenger cars (%) 75 80 82 86 84 85 71 77 83 83 88 87 84 80 Comments 1. 17.300 at Horgos & 34.300 at Batajnica 2. Estimated in 1997
EXPECTED A.A.D.T.:
Section Horgos (H/Y border) Batajnica (Belgrade) Target year 2020
Existing situation: Road with one traffic lane per direction (70km) Existence of technical study for the construction of motorway Estimated cost for the construction of motorway: 180 million EURO Concession contract signed for the implementation (BOUYGUES and BAU HOLDING are main shareholders of the Concession Company Indicative shares: Colas, Strabag, MOL, Magyar Intertoll) Possible EBRD involvement Expected starting date of the construction of motorway: 2003 Estimated duration of the works: 24 months
A.A.D.T.: Section Kiskunfelegyhaza Kistelek Kistelek Szeged Szeged Roszke (H/Y border) EXPECTED A.A.D.T.: Section Kiskunfelegyhaza Kistelek Kiskunfelegyhaza Kistelek Kistelek Szeged Kistelek Szeged Szeged Roszke (H/Y border) Szeged Roszke (H/Y border) Year of AADT per section 19 98 19 98 19 98 AADT (both directions) 4.800 9 26 9 26 Percentage of passenger cars (%) 72 76 76
Target year 20 03 20 13 20 03 20 13 20 03 20 13
Expected AADT (both directions) 15.000 20.000 15.000 20.000 15.000 20.000
Existing situation: Highway with 1 traffic lane per direction (12,562km) Existence of construction plans and specification for the construction of motorway Estimated cost for the construction of motorway: 36 million EURO A.A.D.T.: Section Nis (Komren) - Malca Nis (Komren) - Malca Nis (Komren) - Malca Nis (Komren) - Malca Nis (Komren) - Malca Nis (Komren) - Malca Nis (Komren) - Malca EXPECTED A.A.D.T.: Section Nis (Komren) - Malca Year of AADT AADT (both directions) per section 19 90 6 396 19 95 2 336 19 96 2 662 19 97 3 444 19 98 3 568 19 99 2 230 20 00 3 120 Percentage of passenger cars (%) 77 76 81 81 79 74 75 Comments Estimated in 1997
Target year Expected AADT Expected percentage (both directions) of passenger cars (%) 20 16 11.600 70
Length 58,515km
Existing situation: Highway with 1 traffic lane per direction (60,83km) Existence of reconnaissance study including Traffic, Geotechnical, Hydrological, Climate and nvironmental impacts studies Estimated cost for the construction of motorway: 180 million EURO
A.A.D.T.: Year of AADT Percentage AADT per (both of passenger section directions) cars (%) Malca - Bela Palanca (West) 1990 6.356 78 Malca - Bela Palanca (West) 1995 2.194 75 Malca - Bela Palanca (West) 1996 2.282 80 Malca - Bela Palanca (West) 1997 3.032 80 Malca - Bela Palanca (West) 1998 3.126 77 Malca - Bela Palanca (West) 1999 1.880 74 Malca - Bela Palanca (West) 2000 2.460 72 B. Palanca (W) B. Palanca (E) 1990 6.228 78 B. Palanca (W) B. Palanca (E) 1995 1.973 76 B. Palanca (W) B. Palanca (E) 1996 2.328 81
B. Palanca (W) B. Palanca (E) 1997 2.987 82
Section
Section B. Pal. (W) B. Pal. (E) B. Pal. (W) B. Pal. (E) B. Pal. (W) B. Pal. (E) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W) B. Palanca (E) - Pirot (W)
Year of AADT Percentage AADT per (both of passenger section directions) cars (%) 1998 3.069 78 1999 1.765 73 2000 2.420 72 1990 6.106 77 1995 1.934 75 1996 2.282 80 1997 2.928 81 1998 3.009 76 1999 1.730 72 2000 2.160 73
Length 5,25km
Existing situation: Highway with 1 traffic lane per direction (5,25km) Existence of reconnaissance study Estimated cost for the construction of motorway: 15 million EURO A.A.D.T.: Section Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) Pirot (West) - Pirot (East) EXPECTED A.A.D.T.: Section Year of AADT per section 1 990 1 995 1 996 1 997 1 998 1 999 2 000 AADT (both directions) 6.350 2.011 2.373 3.045 3.129 1.799 2.280 Percentage of passenger cars (%) 79 77 81 82 78 74 77
Target year Expected AADT Expected percentage Comments (both directions) of passenger cars (%) Pirot (West) - Pirot (East) 2016 10.000 67 Estimated in 1997
Length 19,995km
Existing situation: Highway with 1 traffic lane per direction (25,475km) Existence of reconnaissance study including Traffic, Geotechnical, Hydrological, Climate and Environmental impacts studies Estimated cost for the construction of motorway: 60 million EURO A.A.D.T.: Section Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) Pirot (East) - Dimitrovgrad (Y/B border) EXPECTED A.A.D.T.: Section Pirot (East) - Dimitrovgrad (Y/B border) Target year 20 1 6 Year of AADT AADT Percentage of per section (both directions) passenger cars (%) 1990 6.387 77 1995 1.848 76 1996 2.226 77 1997 2.958 83 1998 3.111 80 1999 1.821 78 2000 2.010 77 Expected percentage of passenger cars (%) 66 Comments Estimated in 1997
Kalotina (Y/B border) Dragoman: - Existing situation: Road with 1 traffic lane per direction (12,5km) - Existence of feasibility study for the construction of highway (12,5km) Dragoman Slivnitca: - Existing situation: Road with 1 traffic lane per direction (12,5km) - Existence of feasibility study for the construction of motorway (13,45km) - Estimated cost for the construction of motorway: 42 million EURO Slivnitca Sofia (Beginning of Ring Road, North Arc): - Existing situation: Highway with 1 traffic lane per direction (23km) - Existence of feasibility study for the construction of motorway (23,05km) - Estimated cost for the construction of motorway: 70 million EURO
A.A.D.T.: Section Kalotina (Y/B border) - Dragoman Kalotina (Y/B border) - Dragoman Dragoman - Slivnitca Dragoman - Slivnitca Slivnitca - Sofia (Beginning of Ring Road) Slivnitca - Sofia (Beginning of Ring Road) EXPECTED A.A.D.T.: Section Kalotina (Y/B border) - Dragoman Kalotina (Y/B border) - Dragoman Kalotina (Y/B border) - Dragoman Kalotina (Y/B border) - Dragoman Dragoman - Slivnitca Dragoman - Slivnitca Dragoman - Slivnitca Dragoman - Slivnitca Slivnitca - Sofia (Beginning of Ring Road) Slivnitca - Sofia (Beginning of Ring Road) Slivnitca - Sofia (Beginning of Ring Road) Slivnitca - Sofia (Beginning of Ring Road) Year of AADT AADT Percentage of per section (both directions) passenger cars (%) 1 9 95 6.883 60,66 2 0 00 7.753 61,52 1 9 95 6.584 68,02 2 0 00 7.435 68,77 1 9 95 9.894 69,73 2 0 00 11.177 70,5 Target year 20 0 5 20 1 0 20 1 5 20 2 0 20 0 5 20 1 0 20 1 5 20 2 0 20 0 5 20 1 0 20 1 5 20 2 0 Expected AADT (both directions) 8.923 10.267 11.786 13.543 8.554 9.844 11.304 12.988 12.859 14.797 16.992 19.524 Expected percentage of passenger cars (%) 61,39 61,43 61,55 61,54 68,69 68,71 68,82 68,81 70,4 70,44 70,54 70,53
Existing situation: Road with 1 traffic lane per direction (72,6km) Existence of feasibility study for the construction of highway A.A.D.T.: Section Veles - Prilep (Novo Lagovo) Year of AADT per section 19 9 8 AADT (both directions) 4.123 Percentage of passenger cars (%) 66
On-going widening, which will be completed within 2-3 years (Cost for all the Branch: 150 million Euro).
Length -
Character of the study Comments 1. Technical Secretariat has no information about studies for this section 2. Sub-section of Veles-Bitola
Existing situation: Highway with 1 traffic lane per direction (32km) A.A.D.T.: Section Prilep Bitola Prilep Bitola
On-going widening, which will be completed within 2-3 years (Cost for all the Branch: 150 million Euro).
Length 20km
Character of the study Comments 1. Reconstruction of the existing road 2. Involvement of EBRD & WB
Existing situation: Road with 1 traffic lane per direction (20,45km) Existence of feasibility study for the construction of highway with 2 lanes per direction A.A.D.T.: Section
Year of AADT per section Bitola Greek border 1 998 Bitola Greek border 1 999
EXPECTED A.A.D.T.: Section Target Expected AADT Expected AADT year (from to) (to - from) Bitola Greek border 3.632 2.506
On-going widening, which will be completed within 2-3 years (Cost for all the Branch: 150 million Euro).
ARISTOTELION UNIVERSITY OF THESSALONIKI SCHOOL OF TECHNOLOGY FACULTY OF RURAL AND SURVEYING ENGINEERING DEPARTMENT OF TRANSPORTATION AND HYDRAULIC ENGINEERING
April 2002
Source Actual estimations Actual estimations TINA Final Report 1999 TINA Final Report 1999 TINA Final Report 1999
Total
1.928,5
Main Axis: Croatian Border-Beogad (119,5km) Max permitted speed 50km/h on the railway line to the borders
YUG
MAIN PART
119,5
11,1
88,9
Electric 25KV/50Hz
Max permitted speed: C/Y Border Maintenance: -Sid - Beograd Low on track 120km/h & Beograd - C/Y Border/ High on track Beograd - Sid C/Y Border C/Y Border - Beograd 50km/h
YUG
MAIN PART
YUG
BRANCH C
MAIN PART MAIN PART MAIN PART MAIN PART MAIN PART BRANCH D BRANCH D
Beograd Existng/ Rehabilitation Mladenovac - Velica foreseen Plana Beograd - Rakovica Existng/ Rehabilitation Mala Krsna - Velika foreseen Plana Existng/ Rehabilitation Velika Plana - Nis foreseen Nis - Grdelica Existing Presevo (Y/F border) Stara Pazova - Beska Existng/ Rehabilitation Novi Sad - Subotica foreseen (H/Y border) Nis - Dimitrovgrad Existng/ Rehabilitation Yugoslavian / foreseen Bulgarian Border Tabanovce (Y/F border) - Skopje Existing Zgropolci Zgropolci - Demir Existng/ Rehabilitation Kapija foreseen Demir Kapija Existng/ Rehabilitation Miravci foreseen Miravci - Gevgelija Existing Border zone Gevgelija Existng/ Rehabilitation - Idomeni (F/G foreseen border) Veles - Bitola Existing Bitola - Kremenika Existing (F/G border)
90,4
84,4
15,6
Electric 25KV/50Hz Electric 25KV/50Hz Electric 25KV/50Hz Electric 25KV/50Hz Electric 25KV/50Hz Diesel
Low
80
0 82,5 0 2,4
103,9
100
Medium
100
104,218 50 21,5 30 10 129,325 16,704 100 100 0 0 Diesel Diesel Medium Low 100 30 100 0 Electric 25KV/50Hz Medium 100
YUG
BRANCH C
1800000
-28%
1200000
1318000
+1%
F.Y.R.O.M. MAIN PART F.Y.R.O.M. MAIN PART F.Y.R.O.M. MAIN PART F.Y.R.O.M. MAIN PART F.Y.R.O.M. MAIN PART F.Y.R.O.M. BRANCH D F.Y.R.O.M. BRANCH D
1662000
-35.8% *
3381126 (estimation)
2166000
-56.1% *
No data. No data.
No data. No data.
No data. No data.
No data. No data.
No data. No data.
*The passenger and freight flows in period 1990-2000 were dropped by 50% (as concluded by EIB also in the preliminary report - November 2000). The flows in FYROM for 1990 are estimated proportionally, if we assume that in 2000 the percentage of incoming flows by alternative routes are equal to the percentage of flows that in 1990 prefered Corridor X in absence of border-crossing procedures. A study by the FYROM railway authorities forecasts 5570000tn/year for the main part of the Corridor in FYROM. A traffic study by the Yugoslav railway authorities (1985) for the section Stara Pazova - H/Y Border (Branch B), forecasts 6202000 passengers in 2010 and 7281000 passengers in 2020 (optimistic scenario), and 4987000 passengers in 2010 and 5736000 passengers in 2020 (pessimistic scenario).
YUG
MAIN PART
1985
No data
Completed
2010
YUG
MAIN PART
No data
No data
No data
2010
No data
YUG
BRANCH B
1992
No data
Completed
2020
YUG
BRANCH C
No data
No data
No data
2010
No data
Zgropolci - Demir F.Y.R.O.M. MAIN PART Kapija (sub-section of main part) - Miravci
1999
End of 2000
No data
National & Intrnational/ Public (P.E. Macedonian Railways) Stability Pact expected to be involved National
Cross border zone between Gevgelija - Feasibility and technical study Idomeni (F/G border)
No data
No data
Completed
No data
Quick-start projects: Track rehabilitation: CROATIA/Y border - Beograd EUR9million, Belgrade - Y/FYROM border EUR21million, Beograd - Y/HUNGARIAN border EUR11million, Nis - Y/BULGARIAN border EUR10million Signalling, Telecommunications and power supply rehabilitation: CROATIA/Y border - Beograd EUR2million, Belgrade - Y/FYROM border EUR8million, Beograd - Y/HUNGARIAN border EUR4million, Nis - Y/BULGARIAN border EUR6million Bridge construction: Bribge at Ostruznica (one track, 640m) EUR17million Rolling stock rehabilitation Near-term projects: Bridge construction: Bribge at Zezelj (single track, 467m) EUR30million