Verifying the Iur Interface

This task describes how to verify whether the Iur interface is operational. The verification is performed at the RNC. 8.1 Verifying the Iur Interface (over ATM) This task describes how to verify whether the ATM-based Iur interface is operational. The verification is performed at the RNC. 8.2 Verifying the Iur Interface (over IP) This task describes how to verify whether the IP-based Iur interface is operational. The verification is performed at the RNC.

Issue 02 (2007-08-15)

Huawei Technologies Proprietary

8-1

8 Verifying the Iur Interface

RNC Commissioning Guide

8.1 Verifying the Iur Interface (over ATM)


This task describes how to verify whether the ATM-based Iur interface is operational. The verification is performed at the RNC.

Prerequisite
l l

The RNC local office has passed commissioning. The RNC and another RNC are physically connected, that is, the connection has passed the hardware installation acceptance. Commissioning engineers of another RNC prove that the commissioning of another RNC is complete and the cell is set up. 8.1.1 Verifying Physical Links on the Terrestrial Interface at the RNC (over ATM) This task describes how to verify whether physical links on the ATM-based terrestrial interface are operational. 8.1.2 Verifying the Control Plane on the Iur Interface (over ATM) This task describes how to verify whether the control plane on the ATM-based Iur interface is operational. 8.1.3 Verifying the User Plane on the Iur Interface (over ATM) This task describes how to verify whether the user plane on the ATM-based Iur interface is operational.

1.

2.

3.

8.1.1 Verifying Physical Links on the Terrestrial Interface at the RNC (over ATM)
This task describes how to verify whether physical links on the ATM-based terrestrial interface are operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS and all the RBSs are operational. The LMT is started and properly communicates with the BAM.

Context
l

When the E1/T1 ports on the AEUa and AOUa boards serve as the bearing ports of the RNC, verify whether the E1/T1 physical links are operational. When the optical ports on the AOUa and UOIa boards serve the interconnection between the RNC and the peer end, verify whether the optical ports are operational. Only the UOIa board serves as the interface board in ATM transport over the Iu-PS interface and you only need to verify whether the optical ports are operational.

Procedure
l Verifying E1/T1 links 1.
8-2

On the MML client, run the DSP E1T1 command to set the parameters as follows:
Huawei Technologies Proprietary Issue 02 (2007-08-15)

RNC Commissioning Guide

8 Verifying the Iur Interface

Set Subrack No. to the number of the subrack where the interface board carrying the E1/T1 links to be queried is located. Set Slot No. to the number of the slot where the interface board carrying the E1/ T1 links to be queried is held. Set Board type to the type of the interface board carrying E1/T1 links to be queried. Set Link No. to the number of the E1/T1 links to be queried.

Expectation: For the associated E1 links, Link running state is Available. 2. If Link running state displays one of the following alarms, refer to 15.1 Unavailable E1/T1 Physical Links for troubleshooting:

Loss of Signal Alarm Indication Signal Loss of Frame Remote Alarm Loss of Multiple Frame Slip Alarm Fault

Verifying optical ports 1. On the MML client, run the DSP OPT command to set the parameters as follows:

Set Subrack No. to the number of the subrack where the optical ports to be verified are located. Set Slot No. to the number of the slot where the optical ports to be verified are held. Set Board type to the type of the board where the optical ports are located. Set Port No. to the number of the port of the board where the optical ports to be verified are located.

Expectation: For the associated optical ports, Optical port state is Normal. ----End

8.1.2 Verifying the Control Plane on the Iur Interface (over ATM)
This task describes how to verify whether the control plane on the ATM-based Iur interface is operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS subrack and all the RBS subracks are operational. The LMT is started and properly communicates with the BAM.

Procedure
Step 1 On the MML client, run the DSP SAALLNK command for each SPUa subsystem where the SAAL link on the Iur interface is terminated.
Issue 02 (2007-08-15) Huawei Technologies Proprietary 8-3

8 Verifying the Iur Interface


l

RNC Commissioning Guide

Set Subrack No. to the number of the subrack where the SAAL link on the Iur interface to be queried is terminated. Set Slot No. to the number of the SPUa slot where the SAAL link on the Iur interface is terminated. Set Subsystem No. to the number of the SPUa subsystem where the SAAL link on the Iur interface is terminated. Set SAAL link No. to the number of the SAAL link in the SPUa subsystem.

Expectation: Operational state is Available. Step 2 Run the DSP MTP3BLNK command to set the parameters as follows:
l l

Set Query type to BYDSP (QUERY BY DSP). Set DSP index to the DSP index of another RNC connecting to the Iur interface.

Expectation: Operational state is Available. Step 3 Run the DSP SSN command and set DSP index to the DSP index of another RNC connecting to the Iur interface. Expectation: SSN state is Enable. Step 4 Run the DSP N7DPC command and set DSP Index to the DSP index of another RNC connecting to the Iur interface. Expectations:
l l l l l

SCCP DSP state is Accessible. Peer SCCP state is Available. SCCP DSP congested state is Not Congested. MTP3B DSP congested state is Not Congested. MTP3B DSP state is Available.

Step 5 Run the DSP ADJNODE command and set Adjacent node ID to the ID of the adjacent node of another RNC. Expectation: Operational state is Available. ----End

8.1.3 Verifying the User Plane on the Iur Interface (over ATM)
This task describes how to verify whether the user plane on the ATM-based Iur interface is operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS subrack and all the RBS subracks are operational. The LMT is started and properly communicates with the BAM.

Procedure
Step 1 On the MML client, run the DSP AAL2PATH command and set Adjacent node ID to the ID of the adjacent node of the AAL2 path on the Iur interface to be queried.
8-4 Huawei Technologies Proprietary Issue 02 (2007-08-15)

RNC Commissioning Guide

8 Verifying the Iur Interface

Expectation: Operational state is Available. Step 2 If the RNC is configured with the IP path to another RNC, run the PING IP command to set the parameters as follows:
l l l l

Set Subrack No. to the number of the subrack carrying the Iur interface. Set Slot No. to the number of the slot where the board of the user plane to be queried is held. Set Source IP address to the IP address of the board carrying the Iur interface. Set Destination address to the IP address of another RNC.

Expectation: The Execution succeeded message is displayed.


NOTE

If the peer end has the firewall, a failure message is displayed.

----End

8.2 Verifying the Iur Interface (over IP)


This task describes how to verify whether the IP-based Iur interface is operational. The verification is performed at the RNC.

Prerequisite
l l

The RNC local office has passed commissioning. The RNC and another RNC are physically connected, that is, the connection has passed the hardware installation acceptance. Commissioning engineers of another RNC prove that the commissioning of another RNC is complete and the cell is set up. 8.2.1 Verifying Physical Links on the Terrestrial Interface at the RNC (over IP) This task describes how to verify whether physical links on the IP-based terrestrial interface are operational. 8.2.2 Verifying the Control Plane on the Iur Interface (over IP) This task describes how to verify whether the control plane on the IP-based Iur interface is operational. 8.2.3 Verifying the User Plane on the Iur Interface (over IP) This task describes how to verify whether the user plane on the IP-based Iur interface is operational.

1.

2.

3.

8.2.1 Verifying Physical Links on the Terrestrial Interface at the RNC (over IP)
This task describes how to verify whether physical links on the IP-based terrestrial interface are operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS and all the RBSs are operational. The LMT is started and properly communicates with the BAM.
Huawei Technologies Proprietary 8-5

Issue 02 (2007-08-15)

8 Verifying the Iur Interface

RNC Commissioning Guide

Context
l

When the E1/T1 port on the PEUa board serves as the bearing port of the RNC, verify whether the physical links on the E1/T1 port, PPP links, and MLPPP group are operational. When the FE/GE port on the FG2a and GOUa boards serve as the bearing port of the RNC, verify whether the physical links on the FE/GE port are operational.

Procedure
l Verifying E1/T1 links 1. On the MML client, run the DSP E1T1 command to set the parameters as follows:

Set Subrack No. to the number of the subrack where the interface board carrying the E1/T1 links to be queried is located. Set Slot No. to the number of the slot where the interface board carrying the E1/ T1 links to be queried is held. Set Board type to the type of the interface board carrying E1/T1 links to be queried. Set Link No. to the number of the E1/T1 links to be queried.

Expectation: For the associated E1 links, Link running state is Available. If Link running state displays one of the following alarms, refer to 15.1 Unavailable E1/T1 Physical Links for troubleshooting:

Loss of Signal Alarm Indication Signal Loss of Frame Remote Alarm Loss of Multiple Frame Slip Alarm Fault Set Subrack No. to the number of the subrack where the PPP link to be queried is located. Set Slot No. to the number of the slot where the interface board carrying the PPP link to be queried is held. Set PPP link No. to the number of the PPP link to be queried.

2.

Run the DSP PPPLNK command to set the parameters as follows:

Expectation: For the associated PPP link, Link state is UP. 3. Run the DSP MPGRP command to set the parameters as follows:

Set Subrack No. to the number of the subrack where the MLPPP link to be queried is located. Set Slot No. to the number of the slot where the interface board carrying the MLPPP link to be queried is held. Set MLPPP Group No. to the number of the MLPPP link group to be queried.

Expectation: For the associated E1 link, Link state is Normal. l Verifying physical links on the FE/GE Port On the MML client, run the DSP ETHPORT command to set the parameters as follows:
8-6 Huawei Technologies Proprietary Issue 02 (2007-08-15)

RNC Commissioning Guide

8 Verifying the Iur Interface

Set Subrack No. to the number of the subrack where the interface board carrying the FE/GE links to be queried is located. Set Slot No. to the number of the slot where the interface board carrying the FE/GE links to be queried is held. Set Port No. to the number of the FE/GE port to be queried.

Expectation: For the physical links on the FE/GE port, Link Availability Status is Available. If the verification fails and one of the following is displayed, refer to 15.2 Unavailable FE/ GE Physical Links.

Link Availability Status is Unavailable. Port state is Deactivated . Configured is No.

----End

8.2.2 Verifying the Control Plane on the Iur Interface (over IP)
This task describes how to verify whether the control plane on the IP-based Iur interface is operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS subrack and all the RBS subracks are operational. The LMT is started and properly communicates with the BAM.

Procedure
Step 1 On the MML client, run the DSP N7DPC command and set DSP index to the ID of the DSP to be queried. Expectation: Operational state is Available. Step 2 Run the DSP ADJNODE command and set Adjacent node ID to the ID of the adjacent node to be queried. Expectation: Operational state is Available. Step 3 For each SPUa subsystem where the SCTP is terminated on the Iur interface, run the DSP SCTPLNK command to set the parameters as follows:
l

Set Subrack No. to the number of the subrack to which the Iur interface to be queried is connected. Set Slot No. to the number of slot where the SCTP link is terminated. Set Subsystem No. to the number of the subsystem where the SCTP link is terminated.

l l

Expectation: Operational state is Available. Step 4 Run the DSP M3LKS command and set M3UA linkset index to the index of the M3UA linkset to be queried. Expectation: Operational state is Available. ----End
Issue 02 (2007-08-15) Huawei Technologies Proprietary 8-7

8 Verifying the Iur Interface

RNC Commissioning Guide

8.2.3 Verifying the User Plane on the Iur Interface (over IP)
This task describes how to verify whether the user plane on the IP-based Iur interface is operational.

Prerequisite
l l l

The communication between the RNC FAM and the BAM is operational. The RSS subrack and all the RBS subracks are operational. The LMT is started and properly communicates with the BAM.

Procedure
Step 1 On the MML client, run the DSP IPPATH command to set the parameters as follows:
l

Set Adjacent node ID to the ID of the adjacent node of the IP path on the Iur interface to be queried. Set IP path ID to the ID of the IP path on the Iur interface to be queried.

Expectation: Operational state is Available. Step 2 Run the DSP IPRT command to set the parameters as follows:
l

Set Subrack No. to the number of the subrack to which the Iur interface to be queried is connected. Set Slot No. to the number of the slot where the board of the Iur interface to be queried is held. Set Destination address to the IP address of the connected IPC.

Expectation: Operational state is Available. ----End