EAC = AC + [(BAC-EV)/CPI] Use when variances are typical (Note: This is the same as EAC = BAC/CPI) VAC = BAC EAC ETC = BAC EV Use when variances are atypical ETC = (BAC EV)/CPI Use when variances are typical ETC = EAC AC Use when original estimates were flawed
Network Diagram
Precedence Diagramming Method (PDM)
Also called Activity on Node (AON): Activities are in boxes Most commonly used today Has 4 relationships: F-S, S-S, F-F, S-F No dummies (zero duration dependencies) allowed Can analyze using either Three-Point Estimates or CPM Also called Activity on Arrow (AOA) Only 1 relationship: F-S Can have dummies Can analyze using either Three-Point Estimates or CPM Graphical Evaluation and Review Technique (GERT) - Allows loops and repetitive activities
Page 1
TUTOR CONFLUX
Channels of Communication
Between Team Members = N(N-1)/2
TUTOR CONFLUX
LS ES: Calculates slack with forward pass LF EF: Calculates slack with backwards pass Lag Time: Inserted wait time between activities Lead Time: Overlapping activities, also called paralleling or fast tracking. Lead In; Lag Out
Accuracy of Estimates
Order of Magnitude:-50% to +50% Budget Estimate:-10% to +25% Definitive Estimate:-5% to +10%
Page 3
TUTOR CONFLUX
Closing
Project is closed when administrative closure is complete. Administrative closure is done at end of each Project Phase and at the end of the Project. Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract. Contract Closure Procedure is produced under Close Project