PSCAD GETTI NG-STARTED
TUTORI ALS








Getting Started and Basic Features








Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 3
Date: March12, 2007

3 / 72
Getting Started - Tutorial 1

Objective(s):
- Getting familiar with PSCAD.
- Getting familiar with different sections of the Master Library.
- Different ways to access the master library.
- Creating a simple case.
- Data entry.
- Plotting and control.
- Interactive controls.


T1.1 Create a new case by using either the Menu or Toolbar. A new case should appear
in the Workspace settings entitled noname [psc]. Right-click on this Workspace settings
entry and select Save As and give the case a name.

NOTE: Do not use any spaces in the name!

Create a folder called c:/PscadTraining/Tutorial_01. Save the case as case01.psc

T1.2 Open the main page of your new case. Build a case to study the inrush phenomena
when energizing a transformer. The component data is as shown. The transformer is rated
66/12.47 kV.
BRK
Timed
Breaker
Logic
Open@t0
I
a
66 kV,60 Hz Source
Z+=3.9Ohms / 75.58 deg
Z0 =14.95 Ohms / 80.46 deg
Y-Y Transformer
7.5 MVA
Z =6.14 %
Full load loss =0.3%
No load loss =0.5%
No load current 1 %
#
1
#
2
B
R
K
1
e
6
E_66
66 kV BUS
R
L
R
R
L

Fig.1 Transformer energizing circuit.
T1.3 Plot the currents (Ia) and voltages (E_66) on the HV side of the transformer. Note:
Ia and Ea contains the three waveforms of the three phases.
4 / 72

Fig.2 Basic steps to create a graph with a selected signal.

T1.4 The LV side of the transformer is not connected to a load or any other system
equipment. The breaker is closed at 0.5 s to energize the transformer 66 kV side.
Inrush is related to core saturation. Verify that saturation is included in the model used
for this simulation.
Ask your instructor to explain the large resistance connected to the HV side.
Inrush current magnitude depends on the point on wave switching conditions. Use a
manual switch to operate the breaker. Note the point on wave dependency of the inrush
peak.
BRK
Main ...
BRK_Control
1
C O

Fig.3 Two state switch attached to a control panel.
5 / 72

T1.5 Modify the case to include a 12.47 kV/0.5 MVA (Wound rotor type) induction
machine. This case will be used to study the process of starting an Induction motor. The
component data is as shown.
Capacitor
800 KVars per phase
40.94 [uF]
B
_
m
o
t
EN484 Feeder
81m U/G
54m OH
P
I
C
O
U
P
L
E
D
S
E
C
T
I
O
N
Shortline of 7.4 km
Z+=0.2 E-4 +j0.3 E-3 Ohms/m
Z0 =0.3 E-3 +j0.1 E-2 Ohms/m
Use defaultvalues for the capacitances
0
.
0
0
.
0
TIN
X
2
W
*
0.8 TIN
E
m
o
t
Mechanical Torque
This block models the mechanical
characteristics of a typical load.
500 kVAInduction machine.
Squerriel Cage Type.
13.8 kV(L-L) 7.697 kV
(Phase)
Irated =0.02804 [kA]
Inertia =0.7267 [s]
Stator resistance =0.005 PU
Rotor Resistance =0.008
B_mot
Timed
Breaker
Logic
Open@t0
42.5 [uH]
Etrv
S T
L
N
I

M
W
0.001
I
b
R_C1
R_C1
Main...
R_C1
1
C O
12.47 kV BUS


You may use the wire mode to connect different components.
T1.6 Enter the component data.
Note: Use typical data for the machine.
T1.7 Plot the currents on either side of the transformer (ia and ib).
T1.8 The input torque to the machine is equal to 80% of the square of the speed. Derive
this signal using control blocks. i.e
6 / 72
2
8 . 0 w T
m
=
Use control blocks to implement the above equation.

Your instructor will explain the calculation program structure of EMTDC and the
definition of electric and control type models.
T1.9 The breaker (initially open) should be closed at 0.2s to start the motor.
T1.10 Plot the machine speed, the mechanical torque and the developed electric torque.
Note: Some variables can be measured from within the component. These are normally
listed under the parameter section I nternal output variables

I f time permits

T1.11 Add a load of 1 MVA at 0.8-power factor at 12.47 kV. The same transformer
supplies this load. Does the load see an unacceptable voltage sag during motor start?













7 / 72
Data:
Motor
500 kVA Induction machine.
Wound rotor Type.
13.8 kV(L-L) 7.697 kV (Phase)
Irated =0.02804 [kA]
Inertia =0.7267 [s]
Stator resistance =0.005 PU
Rotor Resistance =0.008 PU

Short Line
Short line of 7.4 km
Z+=0.2 E-4 +j0.3 E-3 Ohms/m
Z0 =0.3 E-3 +j0.1 E-2 Ohms/m
Use default values for the capacitances

Mechanical Load model
X
2
W
*
0.8 TIN
Mechanical Torque
This block models the mechanical
characteristics of a typical load.


Capacitor leg
Capacitor
800 KVars per phase
40.94 [uF] 42.5 [uH] R_C1

8 / 72









PSCAD ESSENTI AL TRAI NI NG


Tutorials 1 6
1. Initializing a simulation
2. Switching study
3. Transformers and inrush
4. Transmission lines
5. Power electronic switching
6. Induction machine dynamics
7. Synchronous Machines and controls
8. Wind farms and doubly fed machines


Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007

9 / 72
Tutorial1TwoAreaPowerSystemInitializingthesimulationtoaspecificload
flow.
T1.1CreateanewcasebyusingeithertheMenuorToolbar.Anewcaseshouldappear
intheWorkspacesettingsentitlednoname[psc].RightclickonthisWorkspacesettings
entryandselectSaveAsandgivethecaseaname.
NOTE:Donotuseanyspacesinthename!
Createafoldercalledc:/PscadTraining/T_01.SavethecaseasT_01_a.psc
T1.2 Open the main page of your new case. Build a case representing a simplified two
area power system as shown in the figure below. A 55 km transmission line connects
StationAtoa100MWwindfarm.AllotherconnectionstoStationAarerepresentedby
anequivalent230kVsource.Theequivalentsourceimpedanceisderivedfromasteady
state fault study at 60 Hz. The line is represented by its series reactance. The
transformerisrepresentedbyitsimpedance,referredtothe230kVside.
R
L
R
R
L
R
L
R
R
L
P1
Q1
P2
Q2
Q2
0.074 0.14
100 MVA Transformer
33/230 kV, Z =0.1 pu
55 km line
230 kV
230 kV Eq. source
Station A Wind Farm
Z_positive =10 Ohms at 88
deg.
Z_zero =7 Ohms at 82 deg.

Fig1. Two area system
T1.3Thewindfarmisalsorepresentedbyanetworkequivalence.Thepositivesequence
impedanceofthissourceat33kVis1Ohmat89deg.
NOTE: Referredtothe230kVsidetheimpedancevalueAns:48.577at89
0


T1.4Thevoltagebehindtheequivalentimpedanceatthewindfarmis35kV.Thephase
angleis7degrees.Determinethepowerflowacrosstheline.
Note:Convertedtothe230kVside,theequivalentvoltageis243.939kVat7deg
Note:ThesimplifiedcalculationsareoutlinedintheaccompanyingMathCADworksheet.
10 / 72
T1.5Plotthepowerandreactivepowerflowatbothendsoftheline.Thesesignalscan
beobtainedfromthevoltagesourcemodelsasinternaloutputs.
T1.6 Use proper scale factors inside the Output Channels to convert PU values to MW
andMVar.Verifytheresults.
T1.7Howdoyouchangethetimestep,thesimulationtimeandtheplottime?Howdo
youdeterminethesimulationtimestep?
T1.8Canyousaveresultstoexternaloutputfilesforpostprocessing?
T1.9Ifyouspecifiedtowritedatatooutputfiles,wherearetheylocated?

Savethecase!

ThecaseshouldbesavedasT_01_b.pscbeforeproceeding.
Different parts of the simulation model can be arranged inside page modules. PSCAD
allows nested page modules. If you make a change to your existing case, PSCAD will
identify the page modules where changes took place. Only these modules will be re
compiled.(Timesavingsinlargecases)
T1.10Createapagemoduleandincludetheequivalentsourceforthewindfarminside
this module as shown in the figures 2 and 3. What is the use of the XNODE
component?
Note: Your instructor will briefly discuss the use of signal transmitters which can also
beusedtotransmit(control)signalsfromapagetoanother.

R
L
R
R
L
P2
Q2
Q2
0.074 0.14
Wind
Farm
a

Fig.2Mainpage
11 / 72

R
L
R
R
L
a
P1
Q1

Fig.3.Subpage

Savethecase!
ThecaseshouldbesavedasT_01_c.pscbeforeproceeding.
T1.11ModifythesourceatStationAtocontrolitsparametersexternally.Addacontrol
paneltospecifythesevalues.Canthevaluesbechangedduringasimulation?
Note: Make sure that the angle is specified in degrees (parameter setting inside the
sourcemodel)
Note:Observetheeffectofvaryingthevoltageangle/magnitudeonPandQflow
R
L
V
F
P
h
R
R
L
60.0
Main : Controls
250
220
V230
230
90
-90
0
10
9
8
7
6
5
4
3
2
1
1

Fig.4.Externalcontrolofthesourceparameters.

T1.12 Modify the circuit to include breakers, breaker controls, meters and the PSCAD
fault component. The case should look like as shown in figure 5. Plot, E1, I1 and the
rmsvalueofE1.
12 / 72

R
L
V
F
P
h
R
R
L
P2
Q2
Q2
0.074 [H] 0.14 [H]
Wind
Farm
a
BRK1
Timed
Breaker
Logic
Closed@t0
BRK1
BRK2
Timed
Breaker
Logic
Closed@t0
BRK2
Timed
Fault
Logic
0 =No Fault
1 =Phase Ato Ground
2 =Phase B to Ground
3 =Phase C to Ground
4 =Phase AB to Ground
5 =Phase AC to Ground
6 =Phase BC to Ground
7 =Phase ABC to
Ground
8 =Phase AB
9 =Phase AC
10 =Phase BC
11 =Phase ABC
E1
I1
I1
E1
E1
BRK3
BRK3
Timed
Breaker
Logic
Closed@t0
60.0
Faultinception - 0.4 s and at0.404 s
V
A
Main: Controls
250
220
V230
230
90
-90
Ph230
0
10
9
8
7
6
5
4
3
2
1
FTYPE
1

Fig.5.Meters,breakersandfaults.
T1.13SimulateanAGfault.Thefaultinceptiontimeis0.4s.Thefaultdurationis0.5s.
NotethedcoffsetofI1.
(ThedcoffsetcancausemaloperationofprotectionduetoCTsaturation.Wewillstudy
thisinlateronasaseparateexample.)

T1.14Whatfactorsinfluencetheinitialdcoffsetanditsrateofdecay?Changethefault
inceptiontimeto0.404sandobservetheresults.
T1.15 Breaker 3 is initially closed. Open and close this breaker at 0.5 s and 0.65 s
respectively.
Savethecase!
ThecaseshouldbesavedasT_01_d.pscbeforeproceeding.
T1.16 Include a FFT block in your simulation cases shown in figure 6. Convert I1 to its
sequence components. Verify the results of the FFT for different fault types. Add a
polymetertoobservethefrequencyspectrum.
Note:Theinstructorwilldemonstratetheuseofthephasormeter.

13 / 72
I1
I1
I1
1 1 1
XA
XB
XC
Ph+
Ph-
Ph0
Mag+ Mag- Mag0
(31)
(31)
(31)
(31) (31) (31)
dcA dcB dcC
F F T
F =60.0 [Hz]
2
1
2
3

Fig.6.FFTBlock.
T1.17LoadthecaseT_01_e.pscfromtheexamplecasesgiventoyouascoursematerial.
Studythesequencerunitsavailabletodefineaseriesoftimedevents.
Savethecase!

















14 / 72
Tutorial2CapacitorSwitchingStudy:
T2.1 Create a folder called c:/PscadTraining/T_02. Save the case T_01_e.psc as
T_02_a.psc.
The utility plans to add 300 MVars of capacitive reactive power at station A to support
the 230 kV bus voltage. A transient study is required to design equipment of this
installation.
Calculations and simulations are required to determine the values/ratings of the
associatedlimitingreactors(inrushandoutrush)
Modifythesimulationcasetoincludeasubpageasshowninfig.1.
R
L
V
F
P
h
R
R
L
60.0
230 kV
Voltage support
Cap. Bank
GT230

Fig.1CapacitorbanksatStationA.
The circuit inside the sub page represents a 230 kV capacitor bank with 4 steps per
phase (see attached diagrams). Each step is rated at 25 Mvar/phase. The capacitor
banks are solidly grounded. The inrush and the outrush reactors sizes are to be
determinedsothattheswitchingtransientsdonotexceedthebreakercapabilitiesand
arewithintheIEEEstandards.
The values of the outrush/inrush reactors have been determined using IEEE
C37.06.2000.
T2.2 UsemanualbreakercontrolstoswitchthebreakersR1,R2andR4.Alsomeasure
thecurrentsinthebreakers.
T2.3AddatimedbreakercomponenttocontrolbreakerR3,measurethecurrentsinR3.
Note:DiscusswithyourinstructorthepurposeofmakingR3operationcontrollable.
15 / 72
T2.4 Add meters to measure the currents and voltages on the system side of the
outrushreactor.
T2.5RunthecasewithR1closed,R2andR4open,andR3settocloseat0.2s.
T2.6ObservethepeakvalueandfrequencyofoscillationofthecurrentinR3.
T2.7 Observe the peak value and frequency of oscillation of the current at the outrush
reactor.
T2.8Notethedifferencesbetween(7)and(8).Discusstheresults.
Important: Ensure that you are using the proper time step and for visualization
purposes,theproperplotstep!
T2.9 A Peak inrush current depends on POW switching. This should be studied to
ensurethatthebreakermeetstheTRVanddi/dtcapabilities.
T2.10UsetheMultipleRuncomponenttocontroltheR3closingtime.Alsorecordthe
currentsinBreakerR3andmainfeedercurrent.
Setthemultipleruntoswitchfor5sequentialpointsonthewave.
Canwedorandomswitchingoveracycle?
Canweoptimizetherunlengthusingasnapshot?
Take a snapshot at 0.199sec and the run multiple run for 20 sequential points on the
wave.
Compare your results with IEEE standard results. Can the simulation time step be
changedwhenthecaseisrunfromasnapshotfile?
T2.11 What are some considerations for the selection of timestep for this type of
simulation?

T2.12 EXTRA: Check the impedance spectrum using the Harmonic Impedance
component. This is an important step in the design of capacitor banks. The addition of
thecapacitorscangiverisetosystemresonancesthatarenotacceptable.
Isthiscircuitappropriatetocheckforsystemresonances?Why?(notenoughdetailsof
thesystemaroundtheStationAbusisincludedtocapturethefrequencyeffects)
16 / 72
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1.00E-06
1 3 5 7 9 11 13 15 17 19
Series1


Savethecase!

ThecaseshouldbesavedasT_02_b.pscbeforeproceeding.
T2.13Modifythecircuitasshowninfigure2toincludesurgearrestors.
The surge arrestors should protect the capacitors from switching over voltages. Re
strike of capacitors breaker can cause large overvoltage transients and is usually the
criteriafortheselectionofMOVs.DiscussthedataentryfortheMOVmodel.
17 / 72
0
.
0
0
3
1
7
Outrush
Reactors
R1 R2
R2
R
1
-
7
9
.
8
2

[
M
V
A
R
]
0
.
0
8
0
1
3

[
M
W
]
R
2
-
3
.
9
8
8
e
-
0
0
5

[
M
V
A
R
]
0
.
0
5
6
3
5

[
M
W
]
R
3
-
7
9
.
7

[
M
V
A
R
]
0
.
0
9
2
0
2

[
M
W
]
Timed
Breaker
Logic
Closed@t0
R3
-
3
.
9
8
8
e
-
0
0
5

[
M
V
A
R
]
0
.
0
5
6
3
5

[
M
W
]
R4
R4
Timed
Breaker
Logic
Closed@t0
MOV
kJ oules
I
m
o
v
MOV

Fig.2.Surgearresters.
T2.13 Breaker R3 is initially closed. It is opened at 0.204 s but restrikes at 0.2124 s.
Observe the energy accumulation in the MOV of phase A. can the MOV handle this
energy?IsastatisticalstudyrequiredtodesigntheMOVratings?
Savethecase!

ThecaseshouldbesavedasT_03_a.pscbeforeproceeding.






18 / 72
Tutorial3Inrushcurrentandlineenergizing.
T3.1 Create a folder called c:/PscadTraining/T_03. Save the case T_02_b.psc as
T_03_a.psc.
Open the capacitor main breaker R3. Keep all other breakers closed. Make the fault
componentinactive.
Mosttransientstudiesrequiretheaccuratemodelingoftransformersandtransmission
lines. Transformer inrush requires the accurate modeling of the nonlinear iron core.
Switching transient studies require the modeling of transmission lines to include the
effectsfrequencydependentlineparametersandtravelingwavephenomena.
T3.2 Use detailed models to represent the 33/230 kV transformer and the 55 km
transmission line. The transformer has a YY configuration and consists of three single
phaseunits.Thenoloadcurrentis1%.Thenoloadandcopperlossesare0.003puand
0.002purespectively.
The conductor arrangement of the line is as shown below. Use the frequency
dependentphasemodeltorepresenttheline.

30 [m]
10 [m]
C1
C2
C3
10 [m]
Ground_Wires: 1/2"HighStrengthSteel
Conductors: chukar
Tower: 3H5
10 [m]
0 [m]
5 [m]
G1 G2

Fig.1.230kVTransmissiontower.

19 / 72
R
L
V
F
P
h
R
R
L
P2
Q2
Q2
Wind
Farm
a BRK1A
BRK2
Timed
Breaker
Logic
Open@t0
BRK2
E1
I1
I1
E1
E1
BRK3
60.0
3 Phase
RMS
Three Phase
RMS Voltage Meter
Faultinception - 0.4 s and at0.404 s
230 kV
Voltage support
Cap. Bank
GT230
Timed
Fault
Logic
BRK3
Timed
Breaker
Logic
Open@t0
#1 #2
Line_01
Line_01
Line_01
I2
E2
BRK1C
Timed
Breaker
Logic
Open@t0
BRK1B
Timed
Breaker
Logic
Open@t0

Fig.2.Twoareasystemmodelforatransientstudy.

InrushStudy:
T3.3 Open the breakers #2 and #3. The transformer is energized on no load by closing
thebreaker#1.Closebreaker1at0.15sandobservetheinrushcurrents.
T3.4 Add a 1 Ohm resister in series with the 33 kV winding and observe the results.
Whateffectdoestheresistancehaveonthedecayoftheinrushcurrent?
T3.5 Does the breaker closing instant influence the magnitude of inrush? Close the
breakerat0.1535sandobservethecurrentonphaseA.
T3.6Enablethesinglepoleoperationmodeofthebreaker.Closethepolesatinstants
whenthevoltageoftherespectivephaseisatamaximum.Observeresults.
T3.7Whatsituationwouldcausethetransformertosaturateonbothhalvesofavoltage
cycle?
Savethecase!

ThecaseshouldbesavedasT_03_b.pscbeforeproceeding.
20 / 72
LineEnergizingStudy:
T3.8 Close breaker # 1 and open breaker # 3. Include the multiple run component to
controltheoperationofbreaker#2whichisinitiallyopen.TheclosinginstantB1derived
fromthemultiplerun.

Multiple
Run
Ch. 1 V1
Meas-Enab
.
.
.
E1
B1
0.15
D
+
F
+
B2
B1
1
1
overvoltage.out


Fig.3.Multipleruncomponentforbreakercontrol.
T3.9 The breaker closing instant (B1) should be changed for each run. The breaker is
opened0.15safteritsclosingoperation.Setthemultipleruntoswitchfor10sequential
pointsona60Hzwaveform.RecordthepeakvoltageE1atthereceivingend.
Savethecase!
ThecaseshouldbesavedasT_03_c.pscbeforeproceeding.
Linesonthesamerightofway:
A 130 km transmission line connects the Generating Station C and Station A. This line
runs parallel to the 55 km line between Station A and the Wind Farm for 20 km from
Station A. The generating voltage is stepped up to the transmission level through an
11/230kV,YYbank.
T3.10Extendthemodeltoincludethe130kmlineandthegeneratorasshowninfigure
4.Thetransmissionlinesarearrangedinasubpageasshowninfigure5.
Savethecase!

21 / 72
V
F
P
h
BRK2
Timed
Breaker
Logic
Closed@t0
BRK2 E1
I1
BRK3
60.0
3 Phase
RMS
Three Phase
RMS Voltage Meter
230 kV
Voltage support
Cap. Bank
GT230
BRK3
Timed
Breaker
Logic
Closed@t0
Line_01
E2
T lines
Line_01
Line_02
Line_03
Line_02
E4
I4
BRK4
Line_03
#1 #2 RL
RRL
Zpos =0.01 Ohms at 89 deg.
Zzero =0.011Ohms and 80 deg.
11/230 kV, 500MVA
Z=0.08 PU
Station C
Timed
Fault
Logic

Fig.4.Threeareasystem
Line_01
Line_01
Line_02
Line_02
1
Line_03
Line_03

Fig.5.Linearrangementinsidethesubpage.
T3.11 The voltage behind the equivalent source impedance of the voltage source
representingthe4generatorsatStationCis12kVat21degrees.
T3.12UsetheMathcadworksheettoverifyresults.
T3.13 Change the configuration of the 11/230 kV transformer to represent a DY unit.
Adjustthe11kVsourceangletoreflectthischange.
22 / 72
Tutorial 4 Wind Generator model and a Soft Start mechanism
fortheGenerator.
T4.1 Create a folder called c:/PscadTraining/T_04. Save the case T_03_c.psc as
T_04_a.psc.
Thewindturbinesinthewindfarmaredrivinginductiongeneratorsoperatingat33kV.
ThetotalMVAofthestationis100MVA.Replacetheequivalentsourcewithadetailed
modelofaninductiongenerator.Assumeallgeneratorsatthewindfarmareoperating
underidenticalconditions.Theinductiongeneratorconnectionisshowninfigure1.
a
1.0
WIN
S
TL
I M
W
Rrotor
R
r
o
t
o
r
+
R
r
o
t
o
r
+
R
r
o
t
o
r
+
A
B
Ctrl
Ctrl = 1 -0.8
DIST
TIN
External rotor
resistance
Wind...
10
0
Rrotor
0
o
h
m
TIME
DIST
StoT
-0.5
P
o
w
e
r A B
P Q
Iabc
P1 Q1
StoT
3
4
0

[
u
F
]

Fig.1.Inductiongenerator.

T4.2Closebreaker#1at2s.Keepallotherbreakersclosed.Assumethemachinespeed
isat1pubeforeclosingbreakerA.Hasthepowerflowchanged?
T4.3 Calculate the value of the shunt capacitance required to maintain the original
powerflow.SeeMathcadcalculations.Lowerthetimestepto25us.
T4.4 Will the system be stable if a sudden wind gust causes the input torque to the
machinetoincreaseby60%(or80%)?

Savethecase!
ThecaseshouldbesavedasT_03_b.pscbeforeproceeding.
23 / 72
T4.5Discusshowasmallwindgeneratormaybeconnectedtothesystem.
UsingBRKAappropriately,connectthewindgeneratortothesystemat1s.
T4.6Notethelinecurrentsonthesystemsidewhenthewindfarmisconnectedtothe
system. Change the initial speed of the machine to 0.6 pu and re run the simulation.
Notethecurrenttransients.
A Soft Starter shown in figure 2 is used to limit the starting currents when connecting
theinductiongeneratorstothesystem.Thebacktobackthyristorsareusedtocontrol
the voltage applied to the machine while its speed builds up. The firing angle
characteristicsaregiveninthetableinthefilesoftstart.txt.Modelthecircuitshownin
figure2.Thefiringcontrolsforthethyristorsareshowninfigure3.
BRKA
Timed
Breaker
Logic
Open@t0
T
2
T
2
T
2
T
2
T
2
T
2
Ec
FP1
FP2
FP3
FP4
FP5
FP6
1
BRK_SW
BRK_SW
BRK_SW
Ea
Eb
BRKA
BRK_SW
TIME 1
[Windfarm] ANG
ANG
A
B
Ctrl
Ctrl = 1
ANG1
ANG
180.0
BRKA
NA NB

Fig.2.SoftStarter.
24 / 72
THYRISTOR FIRING PULSE
CONTROL CIRCUIT
FP1
FP2
ANG_1
L
H
2
L
H
2
1
8
0
.
0
D
+
F
+
Va
Vb
Vc
PLL
theta
Ea
Eb
Ec
Va
Vb
Vc
PLL
theta
Eb
Ec
Ea
Va
Vb
Vc
PLL
theta
Ec
Ea
Eb
ANG_1
ANG_1
ANG_2 ANG_3
FP3
FP4
L
H
2
L
H
2
1
8
0
.
0
D
+
F
+
ANG_2
ANG_2
FP5
FP6
L
H
2
L
H
2
1
8
0
.
0
D
+
F
+
ANG_3
ANG_3
ANG1
ANG1 ANG1

Fig.3.Firingcontrols.
T4.7Observethestartingcurrentswithandwithoutsoftstart.

25 / 72
Tutorial5Includingamachinemodelinasimulation.
T5.1 Create a folder called c:/PscadTraining/T_05. Save the case T_04_c.psc as
T_05_a.psc.
T5.2 Use the methods discussed in the supplementary exercises to replace the 11 kV
sourcemodelwithadetailedhydrogeneratormodel.
T5.3 Enter the ratings of the machine to reflect the 500 MVA, 11 kV unit. (This may
representanumberofidenticalunitsoperatinginparallel).
T5.4Includethegeneratorcontrolsinthesimulation.
T5.5 The voltage magnitude and the phase angle of the 11 kV source are used to
initialize the machine. Observe the power flow and explain the reasons for minor
differences.
T5.6Tryusingsuitablecontrolmethodstoadjustthemachinepowerflowtotheoriginal
values.
T5.7Howdowemodelathermalgenerator?
26 / 72
Tutorial6Doublyfedinductionmachinemodel.
T6.1 Create a folder called c:/PscadTraining/T_06. Load the library file
dqo_new_lib.psl. Load the cases T_06_a and T_06_b.psc given to you with the course
material.SavethisfileinyourT_06folder.
T6.2Understandthebasicconceptofthedoublefedconnection.
T6.3Identifytheroleofdifferentcontrolblocksinthemodel.
T6.4 Are all models in the control system found in the master library? Can the user
define custom components and use then along with standard models from the master
library?
T6.5Verifytheoperationofthetwocases.

Vbeta
Vsmag
Vc
Va
Isc
C
-
D
+
Isb
Vb
C
-
D
+
phisy
phisx
X
Y
Y
r to p
X
mag
phi
phsmag
G
sT
1 +sT
Valfa
G
sT
1 +sT
1
sT
1
sT
phis
A
B
C
3 to 2
Transform
alfa
beta
*
0.037 Isa
C
-
D
+
*
0.037
*
0.037

Stator flux vector
Iraa
Irbb
Ircc
Ira_ref
Irb_ref
Irc_ref
slpang
to Stator
D
Q
Rotor
alfa
beta
A
B
C
2 to 3
Transform
alfa
beta

Rotor reference currents







27 / 72



















Transient Recovery Voltage Across
Breaker Poles
(TRV)











Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007

28 / 72
Breaker TRV Studies - Tutorial 1


Objective:
Fundamental aspects of Breaker TRV
Selection of time step
Influence of stray capacitance
Influence of loads and losses (resistance)
IEEE defined breaker capability curves
TRV under fault and normal switching conditions and use of multiple run

T1.1 Open the case T_03_a.psc that was completed in Tutorial 3. Rename this as
T_03_a_trv.psc. Keep breakers #1, #2 and #3 closed and the capacitor banks open. Run
the case and make sure the power flow is as expected.

T1.2 Apply a three phase fault to ground at 0.4s. The duration is 1s.

T1.3 Open breaker #3 at 0.44 s. Observe the voltage across the breaker poles.

T1.4 Discuss the reason for TRV. Now lower the time step to 2 us and observe the
results. This will make clear that for TRV studies, a small time step is necessary.




Fig.1. Breaker TRV and the IEEE TRV limits

T1.5 In TRV studies, the stray capacitances near the breaker must be modeled
adequately. How do we determine these values?
T1.6 IEEE standards (IEEE C37.011) define the TRV capability curves for different
breakers. These limits depend on a number of factors.
- Breaker voltage rating
0.021820 0.021825 0.021830 0.021835 0.021840 0.021845 0.021850
-25.0
-20.0
-15.0
-10.0
-5.0
0.0
5.0
10.0
15.0
20.0
y
TRV_ENV(+) TRV_ENV(-) Ea

0.0200 0.0220 0.0240 0.0260 0.0280 0.0300 0.0320 0.0340
-30
-20
-10
0
10
20
TRV_ENV(+) TRV_ENV(-) Ea
29 / 72
- Fault current rating
- Actual fault level
Open the two PSCAD included with the course material. The two cases are
TRV_Case_01.psc and TRV_Case_02.psc. TRV_Case_02.psc is from a low voltage
distribution system of a utility in Florida. It was used to identify TRV issues and to
identify corrective measures.
T1.7 Observe how the IEEE TRV limits are simulated.
T1.8 What are the measures available to reduce TRV levels?

30 / 72









Large I ndustrial Loads I nduction
Motor Transients


Objectives:

Induction motor starting
Motor data
Voltage dips and fluctuations - Flicker
Motor starting methods
Motor load types
Soft starting
Reading data from external files
Control blocks
Power electronic switches








Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007

31 / 72
I nduction Machine Dynamics/Transients - Tutorial 1


T1.1 Connect a 13.8 kV, 15 kA induction motor to an infinite bus through a transformer
and a breaker. The infinite bus voltage is 66 kV.


#1 #2
Is
BRK
0.001
13.8 kV,2.2 kA motor
50.19 MVA, Inertia(J )=2.2 pu
BRK
*
W
W
TIN
TIN
0.0
0.0
S
TL
I M
W
P
o
w
e
r
A B
P Q
Pmot Qmot



T1.2 The load torque applied to the motor is related to the motor speed. Derive a control
block that will generate a torque signal that is proportional to the speed. (TIN =k*w)
T1.3 The motor is to be switched on to the supply using a breaker. Use a two state
switch to send a signal to the breaker.
T1.4 Observe the starting characteristics. Plot the line current, speed, Electric and
mechanical torque and the terminal voltage at the machine.
T1.5 What could cause the motor be driven into a generating mode.
T1.6 Load the case ind_motor_starting_01.psc.
This case models the loads of an industrial plant. Identify different components in the
model.
T1.7 Note the voltage dip during motor starting. Is this a power quality concern?

T1.8 What methods can be employed to limit starting transients?

T1.9 What could cause the motor be driven into a generating mode.

32 / 72
T1.10 Induction motor transients can lead to serious power quality issues. The simulation
example in case ind_motor_starting_01.psc illustrates the voltage dips seen by the other
loads connected to the transformer. Load and run this case.
a) Does additional rotor resistance affect the starting transients?
b) See the effect of rotating inertia and mechanical damping on the transients.
c) What are the typical loads types (characteristics) that are encountered in
industry applications?

T1.11 Load the case ind_motor_starting_02.psc. Note the load torque profile. Observe
the voltage variation at the load terminal.

T
2
T
2
T
2
T
2
T
2
T
2
Ec
FP1
FP2
FP3
FP4
FP5
FP6
1
BRK_SW
BRK_SW
BRK_SW
Ea
Eb
C
B
A
BRK
a2
b2
c2
a1
b1
c1


Fig.2. Soft starter

T1.12 Soft starting methods such as that shown in Fig 2 are used to limit the starting
current of large induction machines. Discuss the current limiting mechanism of this
scheme. Load the case ind_motor_starting_03.psc.
a) What is the role of the PLL?
b) How are signals transmitted from the main page to the sub page?
c) Can PSCAD read data from external files? List a few applications where this
can be useful?
Verify the operation of the soft switch.
33 / 72








Fast Front Studies




Lightening Strike


Objectives:

Representing stray capacitances
Representing arresters
Representing Bus-bars
Representing long lines
Positioning of Arresters







Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007



34 / 72
Fast front studies - Tutorial 1


T1.1 The circuit shown below represents the arrangement of a transformer sub-station.
This model is used to study the over voltages at a transformers terminal during a
lightning strike on a station bus bar.


TA1
1
TA1
1
TA1
3
5
0
.
0
3
5
0
.
0
3
5
0
.
0
Lightning Current
e
Bx
e
Bx
TIME
B
-
F
+
Simple Lightning Surge 1.2*50 Usec:
I =1.02*I1 * [EXP(-13000 * t) - EXP(-4.4E6 * t) ]
bYC1
1
bYC1
1
bYC1
bYC2
1
bYC2
1
bYC2
0
.
0
0
2
7
0
.
0
0
2
7
0
.
0
0
2
7
Steep Front
Surge
Arrester
P
N
Winding Capacitance for
220 kVAutotransformer
(approximate)
*
ABB EXLIMSurge
Arrester 192 kV
0
.
5
Va Vtf
*
1.02
10 mStation Bus 90 mStation Bus
1 kmTransmission Line
Approximate surge
impedance
line termination
0
.
0
0
0
3
0
.
0
0
0
3
0
.
0
0
0
3
0
.
0
0
0
6
0
.
0
0
0
6
0
.
0
0
0
6
Straycapacitance
of equipment
Straycapacitance
of equipment
To accountfor the fundamental
frequencyvoltage component,
the dc source is setto peak
ac volts.





Fig.1. Circuit for lightening study

T1.2 Identify different components of the model
T1.3 How do you represent the transformer? Where do you obtain the data?
T1.4 How are transmission lines and cables represented for the purpose of this study?
Can we justify this representation?
T1.5 Does the position of the arrester have an impact on the over-voltage at the
transformer? Place the arrester at the transformer terminal and observe the over-voltage.
T1.6 What does the dc source represent?
T1.7 How do we model the lightening surge? How do we define parameters for the
surge?

35 / 72














Ferro-Resonance I nvestigation








Objectives:

Transformer parameters
Saturation
Selection of the simulation time step







Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007



36 / 72
Ferro-resonance - Tutorial 1


T1.1 Open the case ferroresonance.psc. This case is used to study a ferro resonance
event during a breaker malfunction.


2
.
5
1
2
.
5
1
2
.
5
1
B
R
K
C
VbusA
LINEA
LINEB
LINEC
B
R
K
B
B
R
K
A
VbusC
VbusB
LINEA
LINEB
3 Phase
z1 and z0
A
B
C
Eq. Source
with
LINEC
SystemEquivalent
Source Representation
0
.
0
0
1
5
0
.
0
0
1
5
0
.
0
0
1
5
VSecA
VSecB
VSecC
VPriA
VPriB
VPriC
Timed
Breaker
Logic
Closed@t0
30MVADistributionTransformer
230kV/13.2kV, Delta/Wye-Gnd
Ztx=7.65%
Timed
Breaker
Logic
Closed@t0
A
B
C
A
B
C
SECTION
PI
COUPLED
230kV, 20mile TransmissionLine
A
B
C
A
B
C
13.2
#2 #1
230.0
30 [MVA]
Timingfor Line Breaker
Phase A: Closed (stuck)
Phase B: Opens at100mSec
Phase C: Closed(stuck)
Timed
Breaker
Logic
Closed@t0
50MVAr@ 230kV
1.5mH Outrush Reactor
OutputVoltages
SecondaryLoad
0.350 [MW]
Disable saturation
andre run



Fig.1. Circuit for Ferro resonance Case Study

T1.2 Check the data entry for transformer saturation. What do different entries represent?
T1.3 Include transformer losses. Do you see a change in results?
T1.4 Open the capacitor banks. Are the results different?
T1.5 Change the line length and observe the results?
T1.6 What effect does the load have on the over voltage transients?
T1.7 Are the transients sensitive to the transformer core characteristics?
37 / 72












Faults and Current Transformers and
Relays












Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007

38 / 72
Faults and Current Transformers and relays - Tutorial 1

Objective

Getting familiar with models related to fault simulation.
Getting familiar with different CT models.


T1.1 Create a new case by using either the Menu or Toolbar. A new case should appear
in the Workspace settings entitled noname [psc]. Right-click on this Workspace settings
entry and select Save As and give the case a name.
NOTE: Do not use any spaces in the name!
Create a folder called c:/PscadTraining/Faults. Save the case as case01.psc

T1.2 Open the main page of your new case. The single line diagram shown below is a
part of a substation feeding a shunt reactor. The reactor is modeled in two parts to enable
a falut at point B, inside the turns. The component data is as shown. (make the
transformer losses zero to limit the number of nodes if using the student version)


Station 115 kV
bus
Station 13.8 kV
bus
RL
RRL
0.0125
Short line
E
L
I
L
Ea
Ir1 Ir2
0.0125
A B
REACTORS
0.005 0.1
#1 #2
115 kV,50 Hz Source
Z+=1.1Ohms / 88 deg
Z0 =2 Ohms / 86 deg
Y-D Transformer
Z =8%
Full load loss =0.3%
No load loss =0.5%



You may use the wire mode to connect different components.

T1.3 Build the case in PSCAD and enter the component data.

T1.3 Plot the current IL and the voltage EL.

T1.4 Use the fault component to simulate a phase A to ground falut at location A at 0.1s.

39 / 72
Timed
Fault
Logic


T1.5 Observe the fault curent, IL. What is the reason for the presence of the initial DC
exponential component?

T1.6 What affects the rate of decay of the DC components. Change the resistance of the
short line to 1 Ohm and observe the results.

T1.7 Does the instant of the fault inception have an effect on the DC offset.?

T1.8 What negative impacts can the DC offset have on the system protection.?

T1.9 Connect the phase A line current at point A to the CT model as shown below. The
CT ratio is 5:400. The CT burden is 0.15 Ohms in series with 0.8mH. Plot the secondary
current and the flux density.

IL
1
Burden resistance
1 and 0.1 Ohms


T1.10 Increase the burden resistance to 4 Ohms and observe the results. Note the half
cycle saturation effects due to the dc offset in the primary current.
T1.11 The reactor is protected by a differential relay scheme. Use the 2-CT model in
PSCAD to connect one phase of the reactor protection scheme.
Ir1
Ir2
1
1


T1.12 Verify the burden current in the differential CT connection for faults at A and B.
T1.13 Does the impedance of the connection leads have an effect on the results.? How is
this impedance accounted for.?
T1.14 Open the case ftdiff.psc. Check the performance of the differential relay during
transformer energization.


40 / 72

Faults and Current Transformers and relays - Tutorial 2

Objective:

Getting familiar with models in the Relay section of the master library.

T2.1 Create a new case by using either the Menu or Toolbar. A new case should appear
in the Workspace settings entitled noname [psc]. Right-click on this Workspace settings
entry and select Save As and give the case a name.
NOTE: Do not use any spaces in the name!
Create a folder called c:/PscadTraining/Faults. Save the case as case02.psc

T2.2 Open the main page of your new case. Construct the simple two area system shown
in the diagram. The voltage sources are set to 230 kV. The inputs to the page module
Relay are all real data inputs.

0.1
8.0 0.08 2.0 0.02
ABC->G
Timed
Fault
Logic
I1
E
0.1
Relay
Ea
Ia
Ib
Ic
Ic
Ib
Ia
Ea
I1
E
1 2 3
1
Ia Ib Ic
Ea
Expand this page to view the
relaycomponents


T2.3 Use the modules in the relay section of the master library to construct a simple
distance relay. The different modules are shown below.





41 / 72


VM
IM
I0M
VP
IP
I0P
R
X
V
a
I
a
+kI
0
Mag
Ph
dc
(7)
(7)
F F T
F =60.0 [Hz]
Mag
Ph
dc
(7)
(7)
F F T
F =60.0 [Hz]
Mag
Ph
dc
(7)
(7)
F F T
F =60.0 [Hz]
Ia
Ea
B
+
D
+
F
+
Ic
Ib
Ia
1
1
1
1
1
1
EaM
EaP
IaM
IaP
I0M
I0P
EaM
EaP
IaM
IaP
I0M
I0P
N
D
N/D
376.99
R
X
R
X
R
X
21
Ia
Ib
Ic
Ea
Impedance calculation
Mho
Characteistics
FFTto extract the
fundamental


T2.4 Identify the function of each module.
T2.5 Verify the operation of the relay.





42 / 72







Power Quality








Electric Arc Furnace Model












Prepared by: Wang Pei
Date: February 2007
Revision:
Date:
43 / 72
Electric arc furnace model

The developed EAF model is based on the non-linear differential equations as outlined in
[1], which models the non-linear characteristics of the electric arc as pictured in Fig. 1a.
The equations representing the arc voltage (v) to arc current (i) are shown below, where r
is the arc radius:
i
k
k r k
r dt
dr
r
m
n 2
3
2 1
2
= +
+


i v
r
k
m
=
+2
3


The parameters ki, r and n characterize the arc under a given operating condition. In
reality, this V-I characteristic shows much more noise due to the unpredictable and
chaotic nature of the load. Fig. 1b shows a more realistic EAF V-I characteristic.






Arc Data Setting:
Parameters k1 to k3 can be selected to obtain the EAF settings, such as active power,
reactive power and power factor close to what were measured in the practical system. As
the EAF model is sensitive to the system connected, parameters k1 to k3 may need to be
re-tuned if the system configuration changes. The EAF model is designed to be able to
take the inputs parameters as variables so the optimization routines of PSCAD can be
used to expedite the process.

Modulation Type setting:
The randomness feature of the EAF model is simulated by adding certain sinusoidal and
Gaussian noise. The magnitude/frequency of sinusoidal modulation and the standard
Main: XY Plot
-1.50 -1.00 -0.50 0.00 0.50 1.00 1.50
-100
-75
-50
-25
0
25
50
75
100
+y
-y
-x +x
XAxis Y Axis
I2 V2
Aperture 2.5550660793 Width
11.661 Position 0.000s 20.000s
(b) Actual (a) Ideal
Fig. 1 Ideal and actual V-I characteristic of an EAF
44 / 72
deviation of Gaussian function can be specified. Each phase can be independently
controlled.


It is important to note that it is impossible to get a simulation case to match the observed
results perfectly due to the nature of the problem. The important thing is to capture the
essential features and the trends of a practical arc furnace.

Reference:
[1] A Harmonic Domain Computational Package for Non-Linear Problems and its
Application to Electric Arcs, E. Acha, A. Semlyen, N. Rajakovic. IEEE Transactions on
Power Delivery,Vol 5, No.3, J uly 1990.
45 / 72














FACTS DEVI CES






Active Filters

I nstantaneous Reactive Power Method
Synchronous Reference Frame Method









Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007
46 / 72
Facts Devices - Tutorial - l

Objective:
Getting familiar with power electronic firing models
Getting familiar with control system building block models
Active filter theory


T14.1 Open the two PSCAD cases provided with the course material. The two cases are:
Activefilter_SRF.psc
Activefilter_I RP.psc
They are located in the folder named Active_filter

T14.2 The main loads on both these case produce significant harmonics. Study the
different models used in the control circuit for the variable speed drive in
Activefilter_I RP.psc.

T14.3 Study the control technique used in both IRP and SRF methods.

T14.4 Study how the current reference PWM is implemented to in the active filter bridge.
What is the function of the interpolated firing pulse module?




6
6
6
6
L
H
H
ON
OFF
L
(1)
(4)
(5)
(6)
2
2
2
(2)
(3)
2
2
2
0.002
1
2
3
4
5
6
H_on
H_off
G11
G21
G31
G41
G51
G61

Fig.1. Integrated firing pulse module
T14.5 Change the parameters of the filters in the control circuit of the active filter and
see the change in response. Can we use FFT to extract the frequencies of interest?
47 / 72














PSCAD BASI C TRAI NI NG







Synchronous Machines

Exercises 1 - 2










Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007
48 / 72
Exercise 1

One machine infinite bus case

E1.1 Open the case case_01_startup.psc.

A
B
C
E
F
3 Phase
RMS
TM
LRR
S2M
Iffa
Iffb
Iffc
0
.
0
1
A B C
V
F
P
h
HydroGener
w
Te
A
B
C
If Ef Ef0 Ef If
Tm0 Tm
Tm
17.32
60.0
Timer
Timer
I
F
W
0.495


E1.2 How do you start the machine as a voltage source. How do you switch from a
voltage source to a machine rotating at a fixed speed? How do you enable the rotational
dynamics of the machine ?

E1.3 What are the functions of signals Ef0 and Tm0 of the synchronous machine model.

E1.4 Set the machine initial voltage magnitude to 1.04 pu and the phase to 0.75 rad.

E1.5 Run the case and note the Power and Reactive Power levels at steady state. Also
measure the input torque Tm and the field voltage Ef at steady state.

E1.6 Start the machine in the normal machine mode and observe the results.

E1.7 Use the steady state Tm and Ef values in E5.5 as inputs to Tm and Ef. Start the
machine in the machine mode. Observe results.
49 / 72
Exercise 2

I nitializing the machine to a load flow

E2.1 Open the case Gen_Pqini_startmetds_01.psc.

A
B
C
W
E
F
I
F
3 Phase
RMS
TM
Tmstdy
1.0
S / H
in
hold
out
S2M
VT
IT
3
If Ef
Ef0
Vref
Exciter_(AC1A)
Vref0
w Tm
Wref
z
zi
Hydro Tur 1
w
Wref
z0
z
Hydro Gov 1
Iffa
Iffb
Iffc
0
.
0
1
A B C
HydroGener
VT
IT
3
w
Te
A
B
C
If Ef Ef0 Ef If
Tm0 Tm
Tm


E2.2 Make sure the machine is rated at 150 MVA, 17.32 kV. It should be connected to an
infinite bus rated at the same voltage through a transmission line of inductance 0.01 H.
E2.3 Calculate the machine terminal voltage in PU and the phase angle in radians, if the
steady state power and reactive power flow is 54 MW and 27 MVar respectively.
E2.4 Set the machine initial conditions so that the simulation will give the correct steady
state P and Q flow.
E2.5 How are the governor, turbine and the exciter initialized?
E2.6 Start the machine as a source and simulate the case.
E2.7 Start the simulation with the machine in the normal machine mode. What
additional initial conditions are to be supplied to the machine?
50 / 72



PSCAD ESSENTI AL TUTORI ALS






Synchronous Machine Application Studies














Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007











51 / 72
Two area power system:

Twoarea_system.psc

This case shows two hydro generators connected through a tie line. When the system load
changes, the tie line power is determined by the governor droop settings.
Check if the machine inertia affects the results.
Changes the droop settings to see the effects.

Small signal stability:

Ex_Smallsignal.psc
Ex_Smallsignal_exciter.psc
(The machine parameters and the systemparameters are as given in the book, Power
SystemStability and Control by Prabha Kundur.
The steady state P and Q values are 0.9 and 0.3 respectively.
The oscillation frequency, upon a small disturbance is around 1 Hz and agrees with the
Eigen Value calculation.)


These cases illustrate the oscillations in a system when a small disturbance is applied.
The oscillation frequencies are in agreement with frequency domain Eigan value
calculations.
Does machine parameters affect the oscillation frequency?
Does the machine inertia affect the oscillation frequency?
Does the load flow condition effect the oscillation frequency?


Critical clearing time for faults:

Ex_fault_exciter.psc
Critical clearing time for this fault is 0.1 if the regulator gain is over 400. For values less
than 400, the system becomes unstable. Try different fault clearing times and exciter
gains to see how they are related.

Power System Stabilizer:

Ex_pss_tune.psc
The system shown in this case is unstable if run without a power system stabilizer. Run
the case with a constant field voltage and see if the system is stable. This will verify that
the instability is due to the exciter action.
Can we make the system stable by reducing the exciter gain?
Design a power system stabilizer (PSS) to minimize the speed change upon a disturbance.
Use the optimization method of PSCAD to design the PSS parameters.
52 / 72


















CONVERSI ON OF LOAD FLOW
DATA FI LES



Direct Conversion of PSS/E Files for PSCAD
Model Building









Prepared by: Pei Wang
Date: Feb. 2006
Revision:
53 / 72
Conversion of load flow dats files Tutorial -1
Direct conversion of PSS/E files


Objectives:

Getting familiar with building large systems in PSCAD
Using E-TRAN to convert PSS/E data files
Guidelines to determine detailed network for EMT study
Validation of developed model


T1.1 Create two cases with E-TRAN for the IEEE 39 bus systems: one using only the
.raw file and the other including the dynamic data .dyr file.
- Practice with the selection of zone/area/bus/proximity/
- Network equivalences
- Manual modifications required for EMT study purpose


Fig. 1.Single line diagram of IEEE 39 bus system




54 / 72
T1.2 E-TRAN Runtime Library for PSCAD and custom substitution libraries
- Series components (Tline/Transformer) and shunt components (generator)
- Use of the sample substitution library


Angle(deg)
Pout(MW)
Qout(MVAR)
4.1825
632.0
109.911
Initial Conditions from Loadflow
E
Volts(pu) 0.9972
/ 1.0
/ 1.0
TE
Ef
Ef0
If
E
TM0 TM
1 Vm VT
Wpu
G
1 +sT
G
1 +sT
G
1 +sT
E
Te
3
A
V
Tm
Tm0
Ef0
Tm w
Ef If
E
GENROU
E
Enab
VT
IT
3
IF EF
EF0
Vref
VS
IEEET1
VCT
VREF
EnabExc
Exciter VREF
is loadflow terminal voltage...
VREF
0.0
VS
E
TM0
Enab
W
Wref
TM
IEEEG1
EnabGov
WRef
1.0

Fig. 2: Detailed machine mode in the substitution library for EMT study

T1.3 Method to determine the kept system (frequency scan)


Fig. 3 Frequency scan results at interested bus

T1.4 Model verification.
- Comparison of P, Q, V
- Short circuit data
55 / 72
Converting a Solved PSS/E Case to PSCAD for Transient Simulations
Many utilities have their power systems modeled in load flow programs. A great deal of
effort is required to re-enter network data for transient simulation studies in
Electromagnetic Transient (EMT) type programs. This application note describes the use
a new tool that allows for an automated setup of PSCAD simulation cases by directly
importing data from solved PSS/E load flow cases, thus maximizing the simulation
engineer productivity. Some helpful tips are also provided on how to ensure the validity
of the transient study by effectively selecting the size of the subsystem to be simulated in
PSCAD. Some key points addressed here are:
- Direct conversion of the PSS/E file: Basic steps
- E-TRAN Runtime Library for PSCAD and E-TRAN custom substitution libraries
- Network equivalences
- Guidelines to determine the extent of the network to be modeled in detail
- Model validation
- Importing dynamic data from the PSS/E *.dyr file
The IEEE 39-bus system (see Figure 1) is used as the base case to illustrate the PSS/E to
PSCAD conversion process. The IEEE 39-bus system is a standard system used for
testing new power systems simulation methodologies. It was created based on a
simplified model of the New England power system. The 39-bus system has 10
generators, 19 loads, 36 transmission lines and 12 transformers.
The conversion of the system into PSCAD is achieved through E-TRAN, a program
developed by Electranix Corporation. In addition to converting PSS/E data into PSCAD
cases, this program offers many powerful features that could be manipulated by the
simulation engineer to reduce the time spent on a study. The softwares most relevant
features are outlined in this document.
56 / 72
GEN
10
GEN
1
GEN
2
GEN
4
GEN
5
GEN
6
GEN
7
8
GEN
G
E
N
9
BUS30
BUS2
BUS37
BUS25
BUS31
BUS6
BUS34
BUS20 BUS33
BUS19
BUS35
BUS22
BUS38
BUS36
BUS23
BUS39
BUS1
BUS9
BUS8
BUS7
BUS5
BUS4
BUS3
BUS18
BUS26
BUS28
BUS17
BUS27
GEN
3
BUS32
BUS10
BUS11
BUS12
BUS13
BUS16
BUS24
BUS21
BUS15
BUS14
BUS29
VBUS5
VBUS26
VBUS28
VBUS15
V
B
U
S
1
7
VBUS16
VBUS14
VBUS21
VBUS24
VBUS1
VBUS9
VBUS8
VBUS31
VBUS30
VBUS2
VBUS37
VBUS25
VBUS6
VBUS39
VBUS12
VBUS11
VBUS13
VBUS32
VBUS34
VBUS33
VBUS20
VBUS19
VBUS38
VBUS10
VBUS29
VBUS4
VBUS3
VBUS27
VBUS36
VBUS23
VBUS35
VBUS22
VBUS18
Slack Bus
E_1_2_1
T
E_2_3_1
T
E_3_4_1
T
E_4_5_1
T
E_6_7_1
T
E_7_8_1
T
E_8_9_1
T
E_9_39_1
T
E_1_39_1
T
E_2_25_1
T
E_25_26_1
T
E_26_27_1
T
E_26_28_1
T
E_28_29_1
T
E_26_29_1
T
E_17_27_1
T
E_16_17_1
T
E_15_16_1
T
E_16_19_1
T
E_16_21_1
T
E_16_24_1
T
E_14_15_1
T
E_4_14_1
T
E_17_18_1
T
E_3_18_1
T
E_6_11_1
T
E_13_14_1
T
E_21_22_1
T
E_22_23_1
T
E_23_24_1
T
E_5_8_1
T
P
=
7
4
3
.8
Q
=
1
1
4
.2
V
=
1
.0
2
9
V A
P
=
5
2
9
.7
Q
=
2
3
5
.7
V
=
0
.9
9
6
1
V A
P
=
6
9
7
.9
Q
=
2
2
6
.8
V
=
0
.9
9
1
8
V A
P
=
5
3
5
.2
Q
=
1
6
4
.5
V
=
1
.0
1
8
V A
P
=
6
6
2
.4
Q
=
1
3
3
.8
V
=
1
.0
0
7
V A
P
=
5
7
3
.7
Q
=
1
0
1
.5
V
=
0
.0
6
8
1
9
V A
P
=
5
5
1
.2
Q
=
2
2
.9
6
V
=
1
.0
4
V A
P
=
2
5
3
.9
Q
=
1
6
3
.6
V
=
1
.0
5
2
V A
P =975.2
Q =54.56
V=1.026
V
A
P
=
6
8
1
.8
Q
=
2
3
5
.6
V
=
1
.0
5
9
V A
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P,Q
Load
100.0
E 25.0
P
,Q
L
o
a
d
1
0
0
.0
E
2
5
.0
P,Q
Load
100.0
E 25.0
<
-- 1
0
0
-->
T
-L
in
e
L
in
e
1
E
<
-- 1
0
0
-->
T
-L
in
e
L
in
e
1
E
<
-- 1
0
0
-->
T
-L
in
e
L
in
e
1
E
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1
230.0 230.0
E
:
1
2
3
0
.0
2
3
0
.0
E :
1
2
3
0
.0
2
3
0
.0
E :
1

Figure 1 Single line diagram of the IEEE 39 bus system in PSCAD
Converting the base PSS/E Case to PSCAD
When converting a case from the PSS/E load flow data file (*.raw) and dynamic data file
(*.dyr), E-TRAN allows for several options that provide enhanced flexibility to the final
user.
To convert the *.raw/*.dyr files, start the E-TRAN program. The pop-up dialog will
prompt the user through the conversion steps (see Error! Reference source not found.).
The user will have to specify the location of the *.raw/*dyr data files and the target *.psc
file. In the next dialog, the user will specify if the entire network is to be kept or if only
a specific part is kept and the rest equivalenced. In most transient studies there is no
added benefit in modeling the details of the network beyond a few buses away from the
location of main interest. E-TRAN allows for the system to be partially or fully converted
(all its nodes) into PSCAD.
. .
57 / 72



Figure 2 E-TRAN dialog boxes
The conversion process will generate a PSCAD (*.psc) file in the specified location. The
network equivalent sources will have their magnitudes and phase angles automatically set
for the same power flow as in the original PSS/E file.
58 / 72
E-TRAN Runtime Library for PSCAD
The E-TRAN Runtime Substitution Library (see Figure 3) contains a series of models
specially developed for PSS/E-PSCAD conversions that translates PSS/E component
information into equivalent PSCAD component information. The E-TRAN Runtime
Substitution Library is provided with the program and contains the models that will
appear in the converted PSCAD case. To run the converted PSCAD case:
- Open PSCAD
- Load the E-TRAN Runtime substitution library
- Load the PSCAD case
- Verify the load flow results

Figure 3 E-TRAN Runtime library for PSCAD
Custom Substitution Libraries and data entry
Load flow programs represent the power system network using simplified models
consisting of resistances, inductances and capacitances. When converted to a PSCAD
case, these components can be replaced by more detailed models to represent the
respective unit. Therefore, depending on the user needs, some of the models
automatically substituted from the E-TRAN substitution library may require additional
data or may have to be replaced by more complex models from the PSCAD master
59 / 72
library. Fortunately, E-TRAN allows the user to create a user substitution library where
any additional information will have to be entered by the users only once, when the
component is used the first time.
An example that calls for the use of the custom substitution library could be a
transmission line, where the PI section or the Bergeron models used to represent it may
have to be replaced by a more accurate frequency dependant model, which will require
specific information on the tower, conductor and right of way dimensions.
In the custom substitution library the user can predefine the substitution of a specific
system component to be done with a pre-filled out PSCAD master library component (or
a user built component) by referencing to the bus number they are connected to (see
Figure 4)
B_456_ B_822_T1
T
A detailed frequency dependant TLine
From bus 456 to bus 822, Circuit T1
~
E
Source1
Syncronous machine
at bus 159

Figure 4 Examples of custom substitution library components
You can save detailed device data in this library, and E-TRAN will use this data (substituting it for the simple load
flow data) every time a region of the network is converted into PSCAD. The goal is to eventually have all detailed
model data entered into this library. Once this is achieved, this library can be used to generate PSCAD cases for any
location of your system.
The models in the Substitution Library can also be customwritten components, or even page components. A page
component can also have as many layers of sub-pages as required. Each page can also contain sliders, plots, graphs,
control-panels etc... When E-TRAN copies the data fromyour Substitution Library, it will also replace initial condition
information. For example, E-TRAN will modify synchronous machine data to replace the data for the terminal voltage,
angle, P and Q.
The construction of the custom library will require a significant investment of time for
large networks. However, once it is completed, you can convert any part of your network
without having to do any manual data entry. This was identified as a key time saving
feature by large utilities and consultants who are required to work on different parts of
large networks when undertaking different projects.


60 / 72
Deciding on the Part of the Network to be Kept
A transient study would require the detailed modeling of a small part of the network
around the main point of interest. Typically, this would be about 2 or 3 buses away from
this point. E-TRAN allows the users to efficiently decide and check if the kept network
details are adequate for a given study. The following steps are recommended. This makes
use of the network frequency scan component of PSCAD (see Figure 5).
- Convert the PSS/E file to PSCAD, keeping the details 2 or 3 buses away from the
main point of interest and equivalencing the rest.
- Use the frequency scan component of PSCAD to plot the impedance vs.
frequency characteristic of this system at the bus concerned.
- Reconvert the PSS/E file, this time, keeping the details of one more bus away
than in the earlier step.
- Plot the impedance vs. frequency characteristics of this system at the bus
concerned and compare with the first plot.
- Repeat the process until the differences in frequency characteristics are minor in
the frequency range of interest. Adding more details of the network beyond this
point is unlikely to improve results.
Z(f)
0.0 -
2000 [Hz]

Figure 5 PSCAD Frequency Scan component
61 / 72

Figure 6 Frequency scans 2, 3, 6 buses away at bus No. 15 for the system under study
Figure 6 shows the use of the frequency scan feature. Here different network equivalents
were constructed using E-TRAN for the IEEE 39 bus system at bus No. 15 for 2, 3, 6
buses away (with 6 buses away comprising the whole network). These network
equivalents were created using the load flow data file only (*.raw). It can be observed
that the frequency spectrums of the equivalent networks start providing a good
approximation for the whole network starting at 4 buses away.
Validation
A quick method to validate the simplified equivalent system provided by E-TRAN is to
compare the values calculated by PSCAD for node voltages, transmission line load flows
or P, Q flows at generation busses with the ones previously calculated by PSS/E. For
such purpose, use the multi-meter to display the voltage at the node of concern and the P
and Q flows in the respective transmission line. Then, display the same information for
such node in the PSS/E load flow utility. The converted PSCAD case will have auto
generated labels that display the P, Q flows at generation buses. Figure 7 shows the
PSS/E and PSCAD results for the voltage magnitude and angle at node 15 as well as the
P and Q flows for the nodes 15 to 16 transmission line.


62 / 72
PSS/E Load Fl ow output
BUS 15 LBUS15 345 AREA CKT MW MVAR MVA %I 1.0154PU -7.75 DEG
1 350.31KV
TO 16 LBUS16 345 1 1 -314.7 -151.7 349.3

LBUS15
N15
E_15_16_1
T
Z(f)
0.0 -
2000 [Hz]
V15_Ang
P =-314.7
Q =-151.7
V =1.015
V
A
P1 : ...
V15 Angle
-7.74857

Figure 7 Comparison of load flow results between PSCAD and PSS/E
Short-circuit level calculation at certain buses for the converted PSCAD case is also
recommended. The short-circuit results can be compared to those from the PSS/E study
or utility system data for validation purpose. Once the PSCAD system has been validated,
it is ready to be used for transient studies.
I mporting Dynamic Data from the .dyr File
During the conversion process the user can specify to import dynamic data from the
PSS/E *dyr file. If this option is selected, all generators in the kept part of the network
will be replaced by detailed machine models (see Figure 8). The machine controls and
related models (exciter, governor, PSS, turbine) will also be included in the PSCAD
model. All information necessary to initialize these models will either be imported from
the *raw/*dyr files or be computed by E-TRAN. Thus, the simulation will automatically
come to the specific steady state after a few cycles of simulation time.
63 / 72
Angle(deg)
Pout(MW)
Qout(MVAR)
4.1825
632.0
109.911
Initial Conditions from Loadflow
E
Volts(pu) 0.9972
/ 1.0
/ 1.0
TE
Ef
Ef0
If
E
TM0 TM
1 Vm VT
Wpu
G
1 +sT
G
1 +sT
G
1 +sT
E
Te
3
A
V
Tm
Tm0
Ef0
Tm w
Ef If
E
GENROU
E
Enab
VT
IT
3
IF EF
EF0
Vref
VS
IEEET1
VCT
VREF
EnabExc
Exciter VREF
is loadflow terminal voltage...
VREF
0.0
VS
E
TM0
Enab
W
Wref
TM
IEEEG1
EnabGov
WRef
1.0

Figure 8 Detailed synchronous machine model automatically generated by E-TRAN with
parameters taken from the PSS/E *.dyr and *.raw files
64 / 72
LBUS01
N1
E_1_2_1
T
LBUS02
N2
E_2_3_1
T
LBUS03
N3
E_3_4_1
T
LBUS04
N4
P,Q
Load
322.0
E
2.4
P,Q
Load
500.0
E
184.0
E_3_18_1
T
LBUS18
N18
P,Q
Load
158.0
E
30.0
E_2_25_1
T
LBUS25
N25
E_25_26_1
T
LBUS26
N26
P,Q
Load
224.0
E
47.2
P,Q
Load
139.0
E
17.0
22.0 345.0
E
:
1
GBUS37
N37
VN37
~
E
540.0
0.445
E_37_0_1
22.0 345.0
E
:
1
GBUS30
N30
VN30
~
E
250.0
146.154
E_30_0_1
E_1_39_1
T
GBUS39
N39
VN39
E_9_39_1
T
LBUS09
N9
E_8_9_1
T
LBUS08
N8
P,Q
Load
1104.0
E
250.0
~
E
1000.0
88.281
E_39_0_1
P,Q
Load
522.0
E
176.0
P =522
Q =176
V
A

Figure 9 IEEE 39 bus system converted to PSCAD for bus No. 1 (3 nodes away)
A subsequent validation document will discuss the conversion process in more detail.
This will include a discussion on importing dynamic devices, saturation and comparison
of low frequency transients with transient stability results.
References
[1] Electranix Corporation E-TRAN V1.1: Electrical Translation Program for Power
Systems. Users Manual February 2003
Prepared by:
J uan Carlos Garcia
Dharshana Muthumuni
Pei Wang
65 / 72





PSCAD ADVANCE TRAI NI NG







Tutorial on Creating Custom Components










Prepared by: Dharshana Muthumuni
Date: August 2005
Revision: 2
Date: Feb 16, 2007







66 / 72
PSCAD Advanced Training - Tutorial 1

Adder

Purpose:
To get familiar with the Component Workshop (or the design editor).
Create input/output nodes.
Get familiar with the graphic, Parameters and the script sections of the editor.


Create a library file.
Use the component workshop to create a simple control block to do the following
computation.

C B K A K = + 2 1

A and B - External inputs
K1 and K2 Internal parameters
C Output

Include the component in a case and verify its accuracy

Modify the component so that K1 and K2 can be entered as variables.
Verify the modified component.


B
C
A
Adder












67 / 72
PSCAD Advanced Training - Tutorial 2

I ntegrator

Purpose:
Calling external subroutines.
Storing data for computations in following (future) time steps.

The block should perform the following function

}
= xdt y
x input
y output

To keep things simple, use rectangular integration.

t t x t t y t y A + A = ) ( ) ( ) (

This will require the storage of past value of y.
Allow for the input of initial value of y.
Use an external FORTRAN Subroutine to do the calculations.



x y
Integrator


















68 / 72

PSCAD Advanced Training - Tutorial 3

Electrical Component Transformer (coupled wires)

Purpose:
Design an electrical component.
Using branch and transformer sections of the script


Design a model of two magnetically coupled wires.
The model is to be interfaced with other electrical components in the master library.

The inductances and resistances are the inputs.

(

+
(

=
(

ib
ia
Rb o
o Ra
ib
ia
dt
d
Lb Mab
Mab La
vb
va


Use the transformers section to enter the L and R values.
Connect the model to a source and verify the model.

Two coupled
wires with capacitance
a1
b1
a2
b2


Use the Branch section to add stray capacitance between the wires on the input side.

















69 / 72
PSCAD Advanced Training - Tutorial 4

Electrical Component A simple DC Machine

Purpose:
I nterface an electric component as a voltage source. (Branch based interface)


Design a simple model of a DC machine.

Field circuit - Series L and R
Armature circuit A series branch of L, R and a voltage source of magnitude Eb.

w k Eb u = _
speed w=
( )
kf if
e k
/
1
5 . 188
150
_

= u
if Field current
kf Input parameter (constant)
The inductances and resistances are the other inputs.

f1
a1
a2
w
f2
Simple
DC Machine

















70 / 72
FORTRAN CODES

I ntegrator:

!
SUBROUTINE INTEGRATOR(x,y,YINI)
!
! Purpose - integration of a real signal
! Language - Fortran 77/90
! Date -
! Author -
!
! Include Files
! -------------
INCLUDE 'nd.h'
INCLUDE 's1.h'
INCLUDE 'emtstor.h'
!
! Variable Declarations
! ---------------------
REAL x,y,YINI
REAL YOLD
INTEGER ISTORF
!
! Program begins
! --------------
! ISTORF =NSTORF
NSTORF =NSTORF +1
! it is good to assign NSTORF to ISTORF and
! have all the user assigned STORx locations at the
! top, then you can even use the other functions
! available in EMTDC in your code without worrying
! about which STORx locations are
! used by them
YOLD =STORF(ISTORF)
! here NSTORF points to the first STORF location
! used in the routine, in the old method in V2, NEXC
! pointed to the last STOR location in the previously
! called subroutine/function.
Y =x*DELT +YOLD
! output at time zero
IF (TIMEZERO) THEN
Y =YINI
ENDIF
! save the data for next time step
STORF(ISTORF) =y
!
RETURN
END


71 / 72
Simple DC Machine:


SUBROUTINE SIMPLEDC(Kf,w,A1A2,F1F2,SS)
!
! Dharshana : 04 Aug 2002
!
INCLUDE 'nd.h'
INCLUDE 's0.h'
INCLUDE 's1.h'
INCLUDE 's2.h'
INCLUDE 'branches.h'



REAL Kf,Ifld,w,k_pi
INTEGER A1A2,F1F2,SS




! Activate the source on branch A1A2
SOURCE(A1A2,SS)=.TRUE.


!
! Read the field current and the armature current during the previous time step

Ifld=CBR(F1F2,SS)*1000

!
! Define the noload excitation charactersitics for the machine
!
k_pi =(150/188.5)*(1 -EXP(-Ifld/Kf))
!
EBR(A1A2,SS)=-k_pi*w/1000
!

RETURN
END
!
72 / 72











That concludes the Introduction to PSCAD and Applications course. Thank
you for your attention and participation. As you work with PSCAD in the
future, please remember we are available to provide assistance with any
simulation or modeling difficulties you may encounter. Please do not
hesitate to contact us at:

support@pscad.com



As well, additional training courses are available, please refer to
www.pscad.com for more information. We are also able to offer customized
courses to suit your specific requirements. Please do not hesitate to contact
us for more information at:

info@pscad.com


Manitoba HVDC Research Centre Inc.
244 Cree Crescent
Winnipeg, Manitoba, Canada R3J 3W1
T 204 989 1240 F 204 989 1277
sales@pscad.com www.hvdc.ca

S-ar putea să vă placă și