„HAZID-AIRPORT“

a Contribution to
Safety Management System

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 1


BRN, 10.10.05, V0.1
Challenges of the „Airport System“
• complicated/complex system, containing
– several process responsible organisations
– several customer-supplier relations, partly nested one
into the others
– interlocked areas of responsibility
• interfaces in the area of safety relevant
infrastructures and support services, specially
Airport Operator and Air Navigation Services
– several participants to the system
– different sets of standards to be applied (ICAO,
EUROCONTROL, EU)
– interorganisational processes
– conflict of objectives with process owners

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 2


BRN, 10.10.05, V0.1
Objectives of an overall SMS „Airport“

1. holistic approach übergeordnete Betrachtungsweise


des Gesamtsystems Flughafen

2. avoidance of system discontinuation and lacks of


responsibility

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 3


BRN, 10.10.05, V0.1
What is „HAZID-AIRPORT“?
• Systematic identification, analysis and assessment of
hazards (Preliminary Hazard Analysis)
• setting up and maintaining a Preliminary Hazard
Catalogue per Airport with SMS
• one the base lines for the steering of
– Safety Management Systems of Stakeholders
– active assets of FOCA (Regulation, Approval, Oversight)
• Airports with IFR OPS: Altenrhein, Bern, Les Eplatures,
Genève, Grenchen, Lugano, Sion, Zürich, Buochs
• other Aerodromes to be defined
• clear split of roles between Safety Responsibility
(Stakeholder) and Oversight (FOCA)

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 4


BRN, 10.10.05, V0.1
How does „HAZID-AIRPORT“ work?

• Embedding into SMS-Conzept with Stakeholders and


with FOCA
• Risik based and systematic Approach (Warning:
Complexity!)
• documented process
• Transparency between FOCA and other players within
the HAZID-Study circle
• punktual Safety Improvement Actions are executed
anytime when considered necessary

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 5


BRN, 10.10.05, V0.1
„HAZID-AIRPORT“ Process
1. Preparation Phase (FOCA)

2. Kick-off: 1 d Briefing of Safety officers of airports and ANS units

3. Workshop I: 3 d (Identification of Hazards)

4. Drafting of Preliminary Hazard List: 3 w

5. Workshop II: 5 d (completing Hazard List and Analysis)

6. Detail Review: 3 w

7. Workshop III: d (Finalisation)

TOTAL TIME PER CASE: ca. 4 months

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 6


BRN, 10.10.05, V0.1
Planning HAZID-AIRPORT (SPECIMEN)
LS..

LS..

LS..

LS..

LS..

LS..

LS..

LS..
LS.. (Pilot)

Prep.

2006 2007 2008 2009 t


gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 7
BRN, 10.10.05, V0.1
Summary

• HAZID-AIRPORT as an answer on the „Safety of the


Overall Airport System“ challenge
• recognised methodology
• supporting the initial phase of the Stakeholder‘s SMS
Processes
• common proceeding of Stakeholders and Regulator,
maintaining the defined roles and responsibilities
• organic part of the Safety Management Systems of
Stakeholders and FOCA
• to exclude any misunderstanding: do not wait for HAZID-
AIRPORT, just commence Safety Management now!

gsd,SI, Bundesamt für Zivilluftfahrt (BAZL) 8


BRN, 10.10.05, V0.1