Documente Academic
Documente Profesional
Documente Cultură
INDIA-SOCIO-ECONOMIC SCENARIO
1200 million people - Second-largest population after China
Impressive annual GDP growth averaging 7.6% from 2000 to 2007 and around 8 % since then
Among top five countries of the world in terms of absolute GDP, based on purchasing power parity (PPP)
2
INDIA-SOCIO-ECONOMIC SCENARIO
(Contd.)
BUT.. On per-capita income basis - well behind other fast-growing nations Human development index Very poor Poverty still remains a major challenge.
Per capita electricity consumption (779 KW) far below the world average (2500 KW) Nearly 60 crore Indians do not have access to electricity
NATIONAL ELECTRICITY POLICY OBJECTIVES Access to Electricity To be made available for all households Availability of Power - Demand to be fully met by 2012 Per Capita Electricity Ensuring Per capita availability of electricity over 1000 units by 2012.
5
100
POWER GENERATION
798949.5 Million Units up to Feb-12 against the target of 855000 Million Units for 2011-12 Energy deficit of 11.1 % and peak demand deficit of 12.1 % during February-2012.
8
Power generation to grow at an average rate of not less than 6 % in years to come
9
Above trend to continue in future It is estimated that Coal would account for 56 % of installed capacity in 2030
10
POWER COAL DEMAND-SUPPLY GAP Most of the recent incremental generation capacity additions - coal based Future Scenario - to remain unchanged
IX Plan (Actual) Incremental capacity 19119 addition (MW) Coal Based (MW) 7930 X Plan (Actual) 20950 XI Plan (Likely) 52000 XII Plan (Potential) 80000
8575
35000
62700
11
Trend over the years - gap between demand of coal and its indigenous availability is increasing resulting into increased volume of coal import
Period Coal consumption By TPPs (MT) 300.561 322.437 346.543 360.845 377.875 292.652 Total Coal receipt by TPPs including import (MT) 301.417 321.433 349.754 367.652 380.336 292.370 Import of coal by Power Sector (MT) 7.780 8.067 14.190 23.230 30.302 33.251
12
Gap between demand and supply of thermal coal is showing increasing trend. Besides Power, Coal is also required by the other industrial sectors of the Country. Projected Demand Supply Gap : As high as 943 MT in 2031-32
XI Plan (2011-12) (Target in MT) XII Plan (2016-17) (Projection in MT) XIII Plan (2021-22) (Projection in MT) IEP (2031-32) (Projection in MT)
(GSI Figures)
Geological hard coal resources of 286 BT, but only 40 % proven Experts estimate that only 21% of the inplace resources can be recovered (inplace resource to mineable reserve ratio of 4.7:1) Recoverable coal reserves, thus, about 58.6 BT. Thus, urgent need to bring inferred and indicated resources under proven category by increased rate of detailed exploration Prop up the rate of promotional drilling for augmenting the overall resource base Introduce modern techniques for achieving higher exploration rate.
15
INITIATIVES TAKEN
CIL in association with GSI, MECL and private drillers has upped drilling performance Aim - to increase resources in proved category and add new resources through promotional drilling. Drilling targets increased from 520000m in FY-10 to 610000m in FY-12. Going for adoption of modern exploration technologies for rapid delineation of resources. Efforts are being made towards classification of resources as per UNFCC code.
16
Indigenous coal production from primarily three sources CIL, SCCL and Captive Block Miners and others. Limited scope of augmenting coal output from SCCL Onus on CIL and captive Mining. 17
MANAGING THE SUPPLY SIDE (Contd.) CHALLENGES BEFORE CIL Growth from 70 MT in early 1970s to in excess of 400 MT at present Stagnating in recent years
Year FY-05 FY-06 FY-07 FY-08 FY-09 FY-10 FY-11
MT
324
343
361
379
404
431
431
Reasons Problems of Land acquisition Delays in obtaining Environmental Clearances Law and Order problems Low Productivity
18
Delays in obtaining Environmental Clearances Normative time for obtaining EC is 2-3 years, but on average it takes 5-6 years In the FY-11, 154 projects (210 MT total capacity) of CIL were waiting for environmental clearance. Augmentation of production from existing projects also requires fresh EC delay in expansion Projects
20
Low Productivity
Production from the UG mines showing downward trend over the years UG mines are operating with very low productivity. Mass production technology adopted in very few mines. Many small Open cast mines also operating with very low capacity HEMMs and low efficiencies
21
Import of Coal
Gap between demand of Coal and indigenous availability of power coal is showing increasing trend. Besides Power Sector, Coal is also required by the other industrial sectors of the Country. In view of the projected demand of coal and anticipated indigenous availability, the demand-supply gap is likely to get wider:
XI Plan (2011-12) (Target in MT) XII Plan (2016-17) (Projection in MT) XI Plan (2021-22) (Projection in MT) IEP (2031-32) (Projection in MT)
Up till now, the demand-supply gaps were not very wide and therefore have been managed by import of coal at a relatively smaller scale. However, to meet the burgeoning coal demand, there is no other way but to go for the import of coal in a comprehensive and planned manner.
26
Import of Coal
Issues involved
International coal market is facing severe competition owing to spurt in coal demand from all corners. Rising demand of coal in the international market to lead to increased price volatility. Present capacity of Indian ports not enough to handle the imported quantity Total coal handling capacity of 81 MT against coal traffic of 92 MT (FY 09) idling of vessels Entry of cape size vessels restricted owing to lower draft of Indian ports requiring more number of trips of small size vessels Proposed capacity addition of ports will not be sufficient to handle the projected volume of coal import.
27
29
WAY FORWARD
Major chunk of coal movement by Rail (49 %) [ Road (27 %) and MGR (19 %)] Scope of augmenting evacuation capacity through roads is limited. MGR is an area specific mode of transport cater to a limited area Hence, burden of coal transportation to be borne primarily by the Railways Coal traffic by rail mode to surpass 900 Million tonnes by 2030. Need of dedicated rail lines special NS & EW corridors may have to be considered by railways. Introduction of lighter wagons Will reduce the high net to tare load ratio. A good option is to use Inland Water Transport for Thermal Power Plants located near the river basins eg Farakka & Kahalgaon Super TPS Emphasis on coal beneficiation will result in enhanced thermal efficiency of power plants and also reduction in hauling need by 6-10 %. Need to upgrade sidings and associated loading equipments, Loading & unloading infrastructure needs to be fully mechanized Aerial ropeway, Conveyor belt and Merry-Go-Round rail systems etc. need to be created and re-vamped wherever necessary
30
MANAGING DEMAND SIDE OF COAL A VIABLE OPTION OF REDUCING DEMAND-SUPPLY GAP contd. Design of new Power Plants
Adoption of supercritical (SC) and ultra-supercritical (USC) steam conditions for new generating plants, in conjunction with modern steam turbine designs key to improved plant efficiency Coal consumption is almost half in comparison to conventional sub-critical power plants.
32
Checking the Transmission and distribution losses Transmission and distribution losses are still hovering around 30 % a staggering loss. On the other hand such losses are as low as 4 % in Japan, South Korea Even many developing countries have managed to peg this loss under 15 % Urgent need to curb such losses, which in turn would result in reduced coal demand.
33
Judicious use of electricity, use of energy efficient home appliances, conservation of power etc. Electricity saved is equivalent to electricity generated. More emphasis on other sources Nonconventional sources, Nuclear power, Hydel power, gas based power etc. Developing alternative sources of energy such as CBM, CMM, Shale gas, Coal to liquid etc.
34
35
Conclusion India has the secondlargest population after China, with an estimated 1200 million people. Although Indias annual GDP growth has been impressive in recent years, but human development index has not improved. Poverty still remains a major challenge. If India has to eradicate poverty and meet its human development goals, it needs to sustain an economic growth of 8 % to 10 % over the next 25 years for which proportionate growth in power sector is a must. Power sector has a very important role to play in achieving the desired growth rate in a sustainable manner. To meet the power requirements, the sector will have to add at least 20-30 GW of generation capacity on yearly basis. Indian power sector is heavily dependent on coal for meeting its power generation targets. About 66 % of the coal in the country is presently consumed in the power sector (Year-2010). At present about 55 % of total electricity production in India is from Coal Based Thermal Power. It is estimated that Coal would account for about 56 % of power generated in India even in 2030. Thus coal is going to remain mainstay for achieving the Power generation targets for many years to come. At present, India is unable to meet its thermal coal requirements from indigenous sources. The gap between the demand of thermal coal and indigenous supply is gradually getting wider. During the current financial year 2011-12, the anticipated gap between the requirement and availability of domestic coal has been estimated around 54 MT, which is being made up by import of coal. In view of the projected demand of coal and projected availability of indigenous coal, the demand-supply gap is bound to get wider in the coming years. It, therefore, becomes extremely important for the growth of countrys power sector to not only ensure development and availability of domestic coal resources but also look for import of coal in a sustained manner to fill up the demand-supply gap. However, there are various issues and challenges, which need to be tackled for a secured supply of coal to the country in general and power sector in particular. There is immediate need for initiating multipronged corrective actions to overcome the various issues and challenges, which are coming in the way secured supply of coal to the industries. Some of the suggested actions are augmentation of indigenous coal resources, ease and clarity in land acquisition process, effective and time bound Environmental & Forestry clearance process, emphasis on increased productivity in mines, adoption of modern technology-both in mining as well as power generation, stress on coal beneficiation, effective action towards securing import of coal from reliable foreign sources in a sustained and cost effective manner, modernization of coal evacuation infrastructure, laying emphasis on increased generation efficiency, checking T & D losses etc.
36