METHOD STATEMENT FOR BLOCK WORKS

Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT

METHOD STATEMENT FOR BLOCK WORKS (CIVIL)

AMENDMENTS
REV. NO PAGE NUMBER DESCRIPTION OF AMENDMENT APPROVED BY (SIGNATURE) EFFECTIVE DATE

METHOD STATEMENT FOR BLOCK WORKS

DESCRIPTION Prepared by Reviewed by Approved by

TITLE ENGR. PRASATH.S

SIGNATURE

DATE

CONTENTS
Page 1 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT

1. ACTIVITY 2. INTRODUCTION 3. TERMINOLOGY 4. SIGNIFICANT HAZARDS IDENTIFIED 5. ROLES & RESPONSIBILITIES & ORGANIZATION CHART 6. SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES 7. REQUIREMENTS 7.1 Plans/Records & Job instructions (Documentations) 7.2 Training 7.3 PPE (Personal Protective Equipment) 7.4 Equipment & Tools required 8. EMERGENCY PROCEDURES 9. REFERENCE 10. ATTACHMENT

1). ACTIVITY:
Page 2 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
This activity deals with the Procedure of Laying of Concrete Blocks from basement level up to 2 nd Floor level as per approved Drawing. 2). INTRODUCTION The Block works are carried out to build walls for internal for partition from basement up to 2 nd floor and vertically (to plumb) to provide the required size/levels at exact coordinates as per approved drawings. 3). TERMINOLOGY O/E: Owner / Engineer PPE: Personal Protective Equipment QC: Quality Control 4). SIGNIFICANT HAZARDS IDENTIFIED Injury to person Wrist Pain/Stress/fatigue Slip/trip/fall hazards Back injury Cutting machine Collapse of Block walls Injury to Eye/Eye Irritation Electric Shock

5). ROLES & RESPONSIBILITIES & ORGANIZATION CHART Project Manager


o Ensure that appropriate resources are provided for the safe delivery of the work

Site In charge o o Ensuring the relevant document Plans the necessary men and material resources for timely completion and quality

Site Engineer Page 3 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
o o o o o o o Ensuring the controls at work spot in person Verifying the % compliance as per risk assessment. Ensuring the emergency preparedness. Arranging the required inspections and permit Ensures all scaffolding erected safely and scaffolding tag system followed Ensures availability of the necessary resources. Ensuring availability of all activity relevant latest approved drawing and documents

QA/QC Engineer o o o o Ensuring quality of work carried out at site Ensuring for inspection on hold points Maintaining all QC records Coordinating with O/E for inspections

Supervisor / Foreman o o o o o o o o Obtaining the permit (if required -e.g. Steel cutting) Conducting Tool Box Talk (TBT) based on risk assessment Arranging for appropriate tools and necessary skilled work force as required. Ensuring the works are carried out as per approved and latest drawing/documents Ensuring for Housekeeping always at work place Implementing the control measures as per risk assessment and also as mentioned in the permit. Close monitoring till completion of work. Close the work permit after restoration of work spot.

Workmen o Wearing appropriate PPEs. o Understanding and following the instructions given by line staff. o Following the scaffolding tag system o No horseplay and shortcuts. o Informing the supervisor/foreman about any near misses, injuries and unusual Safety Officer o Ensures all safety measures implemented/followed as per risk assessment and HSE Plan o Should inform the site engineer for any deviations from required procedure/standard practice o Should conduct a safety briefing in co-ordination with site engineer/supervisor over a specific HSE issue o Ensure all First aid cases are entered in first aid register and necessary awareness given to the victim o Ensures for inspection of power tools and scaffoldings Organization Chart (see for attachment) Page 4 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
6). SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES BLOCKWORKS A) Cleaning & Treatment Clean the surfaces of the area where to start laying blocks and sprinkle with water and removing of all loose concrete and shall be free from deleterious materials, projecting nails, splits and other defects. Chipping the face of the columns/RC wall where the block works are along the way for fixing . B) Fixing Only approved materials shall be used in Block works as per specifications and O/E requirements. Surveyor will give the coordinates and levels where will be the locations and limits of block works. Surveyor shall be responsible for setting out, layout, lines and other dimensional requirement in accordance with the approved drawing. Submerge/soak the concrete blocks before construction. Damp-proof courses shall be laid on and bedded in a bed of 1:4 cement mortar in as long lengths as practicable. Where joints have to be made, they must be lapped at least 20 cm in the runs and for full width on corners and the meeting surfaces, sealed with an adequate application of black bituminous water-proofing paste. At ground floor levels, the damp proof course for a wall shall extend to the full width on top of first row of blocks. Exposed DPC shall be protected from direct sun. The vertical damp proof course at reveals shall extend the full width of the return. Approved Damp proof material shall be placed at any wetted areas like kitchen, toilets and around the perimeter wall of the building. Approved G.I. metal lathe bedding and G.I. Dove tail flat metal shall be provided for 1 st layer and every 2nd layer of concrete blocks. All the joints shall have 300mm overlapping. Mortar for block work shall be cement mortar in the proportions 1 : 3 to 1 : 4 (Cement to sand). All materials shall be screened before mixing to remove lumps. Mortar, whether with or without plasticizer, shall be mixed only in sufficient quantity for the work immediately in hand and no partly set mortar shall be used. Mortar joints in block work have to be racked out to a depth of at least 15mm. All the openings related to services / Door / Windows / Ventilator will be made as per the approved drawings. All mortars shall be mixed by Mechanical Mixer. Pre-fabricated wooden box of pre-determined volume shall be used to measure the volume in sand in proportion with 1 bag of cement. The box/es shall measure 33cm X 33cm X 33cm which constitutes 3 or 4 times the volume of 1 bag cement as per specification. Therefore the proportions to be followed on the site shall be 1 bag
Page 5 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
of cement to 3 or 4 boxes of sand as per specification. Only clean potable water shall be used to mix the mortar to the desired consistency. Cement and sand shall be from approved source. Concrete blocks shall be cut by the cutting machine so as to obtain sharp corners and to fit to adjoining works neatly. Chipped and broken blocks shall be removed. Verticality of block walls must be checked and monitored using plum bob and level bar (spirit level). The horizontal alignment must be verified using aluminum tube with straight edge. Block works more than 3 m in height shall be reinforced with reinforced concrete stiffening frame work comprising of 200 x 300 mm verticals at 4.00 meter c/c and 200 x 300 mm horizontals at mid-height or at every 3.00 meters in case wall height is bigger than 6.00 meters. Solid block works shall be provided wherever service pipes, cables, etc. are passing in wall (e.g. auxiliary electrical rooms, bathrooms, kitchens, etc.) Block work under the ground slab, retaining walls and around foundations shall be solid block at least 200 mm thick and made by SRC or MSRC (type-II) cement according to underground soil conditions. Block work partitions less than 200 mm in thickness shall be solid block. Reinforced concrete frames of at least 200 mm width and the same thickness of the wall strengthen all opening through the block walls.

C) Inspection and Testing Before block work to be started and after concrete block has been laid, O/E shall be notified through inspection request. O/E comments on work shall be rectified and notified for re-inspection, if any. Approved block work materials shall be tested to laboratory for verification to meet the standard specifications and requirements. Tests shall be conducted for every 200 m2 of walls/each consignment of block brought to site. All concrete blocks shall comply with BS 6073. The compressive strength of the blocks shall comply with the following: o Concrete hollow blocks: Average of 10 blocks 7.0 N/sq. mm Lowest individual block 5.5 N/sq. mm o Concrete solid blocks: Average of 10 blocks 13 N/sq. mm Lowest individual block 8.0 N/sq. mm Curing Water curing shall be done until 7days as per specifications and O/E requirements.

D)

Page 6 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
7). REQUIREMENTS 7.1 Plans /Records and Job instructions (Documentations) Before commencing the work the following things should be available: Approved drawings / Material approval for the work Method statement for the work Key site plan for that work area All tools & machineries Emergency escape route without obstructions

7.2 Trainings Trained/Experienced & Skilled persons shall be used for the work All operator / Laborers are safety trained and toolbox shall be conducted.

7.3 PPE (Personal Protective Equipment) Protective footwear Protective clothing Protective gloves Safety helmet Safety goggles Hi-visibility jacket Ear Plug Flagging tape Warning tape Flasher light Safety Harness (above 1.8m)

7.5 Equipment and Tools required Manpower requirement 1. 2. 3. 4. 5. General Supervisor/Foreman - 02 nos Charge hand - 02 nos Masons - 20 nos Helpers - 10 nos Scaffolders -04 nos.
Page 7 of 8

METHOD STATEMENT FOR BLOCK WORKS


Effective Date : Document No : MS-07-BW Revision No : 01 Approved By :

PROJECT
Equipment 1. Tilting type concrete mixer 2. Mason tools Viz.trowel, plumb bob, tape, angles-square, spirit level, curing hose 3. Surveying instrument Total station, Automatic Level 4. Power tools (Electric Angle Grinder) 5. Aluminum Tube 6. Brush/Electric air blower for cleaning 7. Hammer 8. Sieve Mesh 9. Shovel 10. Concrete Block cutting machine 8). EMERGENCY PROCEDURES In case of any emergency situation the workmen should follow the emergency response procedure and must gather in the assembly point. The emergency response procedure should be conveyed to the work men through the toolbox talk in prior to the carrying out of the activity. 9). REFERENCES DRWG. NO. N7204.1E-R-E5300-S-7152 REV. A SHEET 1~1 DRWG. NO. N7204.1E-R-E5300-S-7153 REV. A SHEET 1~1 DRWG. NO. N7204.1E-R-E5300-S-7154 REV. A SHEET 1~1 DRWG. NO. N7204.1E-R-E5300-S-7155 REV. A SHEET 1~1 DRWG. NO. N7204.1E-R-E5370-S-7203 REV. A SHEET 1~2 DRWG. NO. N7204.1E-R-E5370-S-7204 REV. A SHEET 1~1 REF: N-7204.1E/MASS/0025 CEMENT REF: N-7204.1E/MASS/0022 CONCRETE BLOCKS REF: N-7204.1E/MASS/00__ DAMP PROOF REF: N-7204.1E/MASS/00__ G.I. METAL LATHE REF: N-7204.1E/MASS/00__ G.I. DOVE TAIL (30X125MM) 10). ATTACHMENTS Risk assessment sheets Risk assessment sheets Risk assessment sheets Risk assessment sheets Risk assessment sheets Risk assessment sheets Organization Chart Annexure A (Using of power tools) Annexure B (Use of Working at heights) Annexure C (Unsafe scaffolds and working platform) Annexure D (Using of chemicals) Annexure E (Working at night) Annexure F (Working at hot weather condition)