Sunteți pe pagina 1din 28

MD(Trafo)/ST/02

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test GENERAL DATA

HV
RATING ONAN / ONAF NOMINAL VOLTAGE FULL LOAD CURRENT (RATED TAP) VECTOR GROUP SHORT CIRCUIT IMPEDANCE HV/LV TYPE/FORM (given by manufacturer) YEAR OF MANUFACTURE ZERO SEQUENCE IMPEDANCE NO OF TAPS NO OF FANS NO OF PUMPS NO OF RADIATORS TYPE OF OIL TOTAL OIL QUANTITY BREATHER TYPE OLTC MAKE / MOTOR OLTC TYPE / MOTOR TOTAL WEIGHT CONSERVATOR TYPE NEUTRAL GROUNDING METHOD TRAFO TYPE (ICT, IBT, IDT Etc.) SUB STATION VOLTAGE COMMISSIONING DATE OF S/S COMMISSIONING DATE OF TRAFO. TYPE OF INSULATION PAPER % Max. Tap ( 1 ) Rated Tap ( MVA kV A

LV

Min. Tap (

NORMAL / THERMALLY UPGRADED

DATA ENTERED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

CHECKED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/03

Page Contract No. Sub Station Trafo ID Manufacturer Sl. No. : :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test FINAL CHECKS

Correctness of oil level in all bushings and oil filled chambers. All air release plugs (including radiators)& Buchholz relays vented Pressure relief diaphragm intact All bushing connections checked Neutral & Transformer Earth connection satisfactory Position of all switches in MK & MDU ON position. All CT connections are through / shorted WTI Ammeter circuit link connections are correct CT test windings open No damage for insulators and clean No oil leakage Rating, diagram, Id plates fitted satisfactorily Dehydrating breathers satisfactory and pipe work joint is tight All cabling and wiring visually satisfactory All valves are in correct operational position with respect to valve schedule diagram (Ensure valves on both sides of relays and to HV cable box are open). All valves labeled & locked and blanking covers provided wherever necessary All protective and cable box covers fitted. All pre-commissioning tests (including oil tests) completed & results are satisfactory. Copies of test reports available. Condition of Gland earthing of all cables in MK & MDU Permanent Identification tags for all control cables on both ends Availability on marked up drawing copy MK & MDU Close all opening (center cable) in to AVR panel MK and HV/LV cable box.
CHECKED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section: WITNESSED Signature: Name: Designation: Dept.& section: APPROVED

MD(Trafo)/ST/16

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

INSULATION RESISTANCE CHECK OF DEVICES / CONTACTS Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Test voltage Ambient Temp. Terminals IR value numbers (M. in MK Ohms) N/A N/A Remarks

Device/Component HV bushing test tap HV-N bushing test tap Buchholz relay Oil level gauge (MT) Oil level gauge (OLTC) Rubber bag failure relay PRD (MT) PRD (OLTC) OLTC surge relay OTI WTI - HV WTI - LV Heater HV cable box Heater LV cable box Heater Marsh. kiosk Heater - MDU

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature:

WITNESSED Signature: Name: Designation: Dept.& section: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/23

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. OIL LEAK TEST OF TRANSFORMER :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Hourly Reading/ details:


Date Time Ambient Temp. ( C) Tr. OTI reading (C) Pressure at Top (Bar) Pressure at Transformer Bottom (Bar) Result / observation Remarks

-----

Before the application of Pressure

Pressure gauges- Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company:

Top Bottom WITNESSED Signature: Name: Designation: Dept.& section: Signature: Name: Designation: Dept.& section: APPROVED

MD(Trafo)/ST/15

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. TAP POSITION INDICATION CHECK: :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Tap Positi on MDU

Input to Transducer

Transducer output for TPI (mA) at AVR panel

Transducer (SCADA) Output (mA)

Tap Position at AVR Panel

Tap Position at DCS

Tap Position at SCADA

Remarks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section: WITNESSED Signature: Name: Designation: Dept.& section: APPROVED

MD(Trafo)/ST/26

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

TEST ON TRANSFORMER OIL AFTER COMPLETE SITE PROCESSING

Sl. No. 1 2 3 4 5 6 7 8 9 10

Property Breakdown Voltage Water Content Dissipation Factor at 900C. Resistivity at 900C. Neutralization Value Interfacial Tension Oxidation Stability Flash Point Inhibiter Content Corrosive Sulphur Content

Unit

Requirement Test Result as per Spec.

Remarks

(Test certificate from independent test laboratory is attached)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/25

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

TEST RESULTS / PROPERTIES OF INSULATING OIL BEFORE FILLING IN THE TRANSFORMER Property
Kinetic viscosity at 400C 150C Flash Point Pour Point Appearance
0 0

Unit
mm2 / S C C

Test Results

Remarks

Density at 200C Interfacial tension at 250C Neutralization Value Corrosive Sulphur Water Content Antioxidant additives DBPC Oxidation stability Induction period Breakdown Voltage Dissipation factor at 900C and 40 Hz to 60 Hz

kg/dm2 N/m mg KOH/g

mg/kg

Wt % h kV

(Copy of Test certificate from oil manufacturer is attached)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/11

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

CALIBRATION OF OIL & WINDING TEMPERATURE INDICATORS


1. MAKE: BATH TEMPERATURE ( C) INDICATOR READING (0C) ALARM CONTACT SETTING (0C) TRIP CONTACT SETTING (0C) Remarks: 2. MAKE: BATH TEMPERATURE ( C) INDICATIOR READING ( 0C) ALARM CONTACT SETTING (0C) TRIP CONTACT SETTING (0C) Remarks: 3. MAKE: TEST TEMPERATURE (0C) INDICATIOR READING (0C) ALARM CONTACT SETTING (0C) TRIP CONTACT SETTING (0C) Remarks: OPERATION OF CONTACTS (0C) OPERATION OF CONTACTS (0C) WINDING TEMPERATURE INDICATOR (LV) TYPE: SERIAL NO. OPERATION OF CONTACTS (0C) OPERATION OF CONTACTS (0C)
0
0

OIL TEMPERATURE INDICATOR TYPE: SERIAL NO.

OPERATION OF CONTACTS (0C) OPERATION OF CONTACTS (0C)

WINDING TEMPERATURE INDICATOR (HV) TYPE: SERIAL NO.

Make and Sl.No. of Temp. Bath Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/09

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

MEASUREMENT OF TAN DELTA & CAPACITANCE


Ambient temp. Top oil temp. -

a) Transformer Winding:
Sl. No.
APPLIED VOLTAGE (kV)

CAPACITANCE (pF) Measured combination Measured Value Factory Value Difference (%)

CURRENT

(mA)

Dissipation Factor (TAN DELTA)


(%)

1 2 3 4 5 6

b) BUSHINGS Make and Type of bushings:


Sl. No. 1 2 3 4 Applied voltage (kV) Measured on ( Sl. No. of bushings) HV/LV (U) HV/LV (V) HV/LV (W) HV/LV (N)

CAPACITANCE (pF)
Measured value Factory value Difference (%)

Current (mA)

Dissipation Factor (tan delta) (%)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/18

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. COOLING EQUIPMENT :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

A) OPERATION / CONTROLS CHECK


MANUAL OPERATION DIRECTION OF FANS / PUMPS AUTO CONTROL FROM HV W. T. I AUTO CONTROL FROM LV W. T. I AUTO CONTROL FROM O T. I CHECK INTERLOCKING OF COOLING FANS WITH FPS OPERATION UNDER VOLTAGE RELAY OPERATION AND ALARM CONTACT MAIN CONTROL MCB TRIP FAN CONTROL SWITCH TRIP PUMP / FAN ON INDICATION PUMP / FAN FAILURE INDICATIONS OPERATION OF BUCHHOLZ RELAY WHEN SIMULTANEOUS SWITCHING OF PUMPS CHECK FOR STAGGERED STARTING OF COOLER FANS/PUMPS WIRING CHECKS ( T. B NO, FERRULES, GROUPING OF ALARM CONTACTS ETC. AS PER DRAWINGS) GROUP 1 (START) GROUP 1 ( STOP ) GROUP 2 (START) GROUP 2 ( STOP ) 0 0 0

C C
0

C C

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/14

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

ON LOAD TAP CHANGER OPERATION CHECKS Tap changer details Make Type/Model Sl. No. MDU Type Year of Mfg. Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Tap Changer Motor Make Motor Type Rating (KW) Voltage Rated current Remarks

Description of check Local operation possible when selector s/w in local position Remote operation not possible when selector s/w in local position Emergency switch operation Handle interlock End limit switches in extreme taps Step by step operation Position indication in MDU Position indication RCP No of rotations for one step operation Local operation is not possible when selector s/w in Remote position Remote operation is possible when selector s/w in Remote position Over travel in operation is within limits Starting current of motor Running current of motor Phase discrepancy in operation (if separate poles for each phases) Time for one tap changing Normal tap Time for one tap changing run through tap (where applicable) Contacts for all alarm/indication circuits Over load tripping of motor (Setting of MPR) IR value of motor and wiring with 500volts Megger Lighting and heater controls (operation of door switch, thermostat etc.)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/06

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. MAGNETIZING CURRENT MEASUREMENT :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

HV Winding Tap No. Applied voltage Measured exciting current (mA) U phase V phase W phase Remarks

LV Winding Applied voltage Measured exciting current (mA) U phase V phase W phase Remarks

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/17

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. FAN MOTOR CHECK :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Make Type / Model

Rating Rated current

KW/HP

FAN NO. SERIAL NO. CHECK for DIRECTION OF ROTATION STARTING CURRENT (A) U phase RUNNING CURRENT V phase (Amps) OVER LOAD DEVICE W phase

OVER LOAD SETTING (Amps) TRIP OPERATION TIME (Sec) BLOCKED ROTOR CURRENT (Amps) ALARM CONTACT (OK/Not OK)

IR VALUE AT 500 V (M Ohms)

CHECK FAN RUNNING STARTS WHEN ONE PHASE IS DISCONNECTED RUNNING / NOT RUNNING CHECK FOR HEATING AND LIGHTING CONTROLS (DOOR S/W, THERMOSTAT ETC.) -

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/07

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. HV WINDING RESISTANCE MEASUREMENT :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

(Temp
Tap No. Applied current U-N Measured Resistance (Ohms) Average Resistance V-N W-N corrected to 75C (R) Factory value at 75C

C) Remarks

Note : Graph plotted ( Tap no on x-axis and R on y-axis) for all the three phases to be attached)

(Temp
TAP No UV (Ohms) V- W (Ohms) WU (Ohms)

C) Average (Ohms)

LV WINDING RESISTANCE MEASUREMENT


TAP No. uv/u-n (Ohms) vw/v-n (Ohms) wu/w-n (Ohms)

(Temp
Average (Ohms)

C) Factory value (Ohms)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/01

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. INDEX :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Item Transformer general data Final checks (To be carried out prior to energisation) Insulation Resistance measurement of Transformer (Winding and core) 2kV test on core and clamping structure Ratio and Vector group tests Magnetizing current measurement Winding Resistance measurement Short circuit Impedance measurement Measurement of Tan delta and Capacitance Frequency Response analysis Calibration of Temp. Indicators Gradient check of Winding Temperature indicators Measurement of transducer for Remote Temp. Indicator Operation check of On load Tap changers Tap position indication check Insulation resistance check of devices Fan motor check Operation check of cooling equipments Protective device wiring check Checks on AVR Tap changer and cooler alarms check Parallel operation checks Oil leak test BDV test on insulating oil Tests on insulating oil (oil characteristics) Tests on transformer oil after complete processing DGA test on insulating oil

Page No.

PREPARED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

CHECKED Signature:

APPROVED

Name: Designation: Dept.& section:

MD(Trafo)/ST/04

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

INSULATION RESISTANCE MEASUREMENT & CORE INSULATION TEST


INSULATION RESISTANCE - WINDING

Measured at 5000 Volts Measured between 15 Seconds (M. Ohms) HV - LV and EARTH LV - HV and EARTH HV LV Remarks:CORE INSULATION TEST
INSULATION RESISTANCE -

Top Oil temperature 60 Seconds (M. Ohms) 600 Seconds (M. Ohms)

C P.I. value (R600/R60)

Measured at 2000 volts Measured between Core - Earth Clamps - Earth Core - clamps Remarks: Before 2kv Test (M.ohms) After 2kv Test (M.ohms)

Oil Temperature -

Remarks

HV TEST(2kV Test) on Core insulation


1. Applied 2kV, AC, between core & clamps connected together and tank for one minute Leakage current mA Result : Withstood / Failed 2. Applied 2kV, AC, between core and core clamps for one minute Leakage current mA Result : Withstood / Failed
Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/12

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

GRADIENT CHECK OF WINDING TEMPERATURE INDICATORS


Indicator Sl.No. Bath Temp. ( C) Current injected (Amps) Indicator Reading (C) Gradient (C) Required gradient (C) Remarks

GRADIENT CHECK OF REMOTE WINDING TEMPERATURE INDICATORS


Indicator Sl.No. Bath Temp. (C) RWTI output (mA) Current injected (Amps) Local WTI Reading (C) Output (mA) Gradient (mA) Required gradient (mA)

Remarks

Instrument Name, Make & Serial No. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature:

APPROVED Name: Designation: Dept.& section:

MD(Trafo)/ST/13

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

TEMPERATURE TRANSDUCER OUTPUT MEASUREMENT DETAILS OF DEVICES ROTI :

RWTI (HV) : RWTI (LV) : Device connected to DCS/SCADA Bath temp. (C) OTI OTI reading Transducer output (mA) WTI (HV) WTI reading Transducer output (mA) WTI (LV) WTI reading Transducer output (mA) Reading at Remarks DCS SCADA

40 50 60 70 80 90 100 110 120 130 140 150

Instrument Name, Make & Serial No. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/08

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. SHORT CIRCUIT IMPEDANCE MEASUREMENT :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Tap No.

Measured voltage on HV (volts) U - V V -W W -U

Measured HV current (Amps) U V W

Impedance (%) at . MVA base U V W Average

Factory value

Impedance (%) =

*Rated current x Measured voltage x 100 *Rated voltage x Measured current

(* At corresponding tap)
Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/05

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. RATIO AND VECTOR GROUP TESTS LV volts u-v/u-n v-w/v-n w-u/w-n Measured ratio
(Average)

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test HV volts Tap No. U-N V-N W-N

Nominal Error ratio (%)

Remarks

Voltage continuity check during tap changing operations - OK / Not OK


VECTOR GROUP CHECK

Connected terminals U& u of transformer together, Tap changer being on rated tap. Applied 3-phase voltage on HV terminals.
Vector Diagram Measured voltages on U-V V-W W-V Remarks :Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

V-v W-w U-n

V-w W-v N-n

WITNESSED Signature:

APPROVED Name: Designation: Dept.& section:

MD(Trafo)/ST/19

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. PROTECTIVE DEVICES WIRING CHECK :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Sl. No.

Description

Initiated from

Terminal No. in MK

Terminal No. in LCC

Terminal No. in RCP/ RPs

Remarks/ Results SCS/Scada

Transformer Alarms 1 Buchholz Alarm 2 Oil temp. high 3 Wind. Temp. high( HV) 4 Wind. Temp. high (LV) 5 Rubber bag fail 6 Oil level high (MT) 7 Oil level low (MT) 8 Oil level high (OLTC) 9 Oil level low (OLTC)

Transformer Trips 1 Buchholz relay 2 Oil temp. high 3 Wind. Temp. high 4 PRD (MT) 5 PRD (OLTC) 6 Surge Relay (OLTC) 7 Pressure relay OLTC 8 PRD cable box

Buchholz Relay alarm contact operation check by N2 injection Remarks:

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature:

APPROVED Name: Designation: Dept.& section:

MD(Trafo)/ST/24

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test BDV TEST ON INSULATING OIL : Sl. Test no. No. Sampling done from : 1 Test no: 1 2 3 4 5 6 Test no: 2 Test no: 3 Test no: 4 Test no: 5 Test no: 6

Breakdown voltage (in kV)

Remarks

Average Sampling done from : 1 Test no: 1 2 3 4 5 6 Test no: 2 Test no: 3 Test no: 4 Test no: 5 Test no: 6

Average
Sampling done from :

1 2 3 4 5 6

Test no: 1 Test no: 2 Test no: 3 Test no: 4 Test no: 5 Test no: 6

Average

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/22

Page Contract No. : Sub Station :

of

Page 1of 2 of MD(Trafo)/ST/22

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Trafo ID Manufacturer Sl. No.

OLTC PARALLEL OPERATION CHECKS


A. PARALLEL MANUAL MODE

MASTER/ FOLLOWER/ INDEPENDENT Sl. No . MDU 1 2 3 4 5 6 7 8 9 10 11 12 R R R R R R R R R R R R H H H H H H H H H H H H SWITCH SELECTIONS AVR R R R R R R R R R R R R TR 1 M F F M M I M F I M I I TR 2 F M F F I M M F I I M I TR 3 F F M I F F M F I I I M TR 1


OPERATE AS MASTER OPERATE AS FOLLOWER OPERATE AS FOLLOWER OPERATE AS MASTER OPERATE AS MASTER

RESULT / REMARKS OLTC OPERATION Operated from TR 2


OPERATE AS FOLLOWER OPERATE AS MASTER OPERATE AS FOLLOWER OPERATE AS FOLLOWER OPERATE AS INDEPENDENT OPERATE AS MASTER

TR 3
OPERATE AS FOLLOWER OPERATE AS FOLLOWER OPERATE AS MASTER OPERATE AS INDEPENDENT OPERATE AS FOLLOWER OPERATE AS FOLLOWER

AVR panel

DCS

SCADA

OPERATE AS INDEPENDENT

NO OPERATION IS POSSIBLE NO OPERATION IS POSSIBLE OPERATE AS INDEPENDENT OPERATE AS MASTER OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS MASTER OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS INDEPENDENT OPERATE AS MASTER

M Master R Remote

F Follower A - Auto

I Independent H Hand (manual) Contd. on Page 2of 2 of MD(Trafo)/ST/22

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature:

APPROVED Name: Designation: Dept.& section:

MD(Trafo)/ST/20

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT Contractor Date of test

AUTOMATIC VOLTAGE REGULATOR (AVR) CHECK Make: Control voltage: Band width setting: % ( Over voltage blocking: Check Points Sl.No.
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10

volts) %

Sl.No. PT sec. voltage: Under voltage blocking:

Status description Operation


AVR in Auto mode

Check point
No manual operation possible from MDU, SCC and AVR Auto operations with the variations in PT sec. voltage. Tap Raise command when PT sec. voltage reduced and vice versa Auto operations not possible Manual operations possible from AVR Manual operations possible from SCC Operation possible from MDU Operation not possible from AVR & SCC Operation not possible from MDU&SCC Operation possible from AVR Operations not possible from MDU & AVR Operation possible from SCC only No operations possible No operations possible

Result

Remarks

AVR in manual mode MDU in local position MDU & AVR in remote position MDU in remote & AVR in Supervisory

Under voltage blocking Over voltage blocking AVR Display Voltage Current Tap No Frequency Master/Follower/Independent mode Paragramar functions (Breaker status indication)

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/21

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

TAP CHANGER & COOLER ALARMS & INDICATIONS CHECK

Sl.No.

Alarm description

Initiated at

DCS

SCADA

Remarks

1. ALARMS 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 TC out of step TC incomplete TC motor supply faulty TC control supply faulty AVR faulty VT supply fail Cooling equipment Faulty IDT/ET MK/MDU heating/lighting supply faulty

2. INDICATIONS 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 Tap Changer in Remote Tap Changer in Supervisory Tap Changer in Auto Tap Changer in Manual TC in progress TC in Independent mode TC in Master/follower mode Tap position indications Cooling fans running

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/28

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT Contractor Date of test

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/27

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. :

of

DEWA
TRANSFORMER SITE TEST REPORT Contractor Date of test

DGA TEST ON TRANSFORMER OIL Date of Sampling Sampled by Tests carried out by Test Results Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 TDCG (ppm / %) CO2 / CO Dissolved gas Hydrogen (H2) Methane (CH4) Ethane (C2H6) Ethylene (C2H4) Acetylene (C2H2) Carbon Monoxide (CO) Carbon Dioxide (CO2) Oxygen (O2) Nitrogen (N2) Concentration (ppm) Remarks : : : Oil Temperature Sampling Point : :

Sample identification : Test report reference :

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

MD(Trafo)/ST/10

Page Contract No. : Sub Station Trafo ID Manufacturer Sl. No. FREQUENCY RESPONSE ANALYSIS :

of

DEWA
TRANSFORMER SITE TEST REPORT
Contractor Date of test

Test report

- Enclosed / Not enclosed

Report No -

Number of pages -

Instrument Name, Make & Serial no. Calibration due date TESTED Signature: Name: Designation: Dept./Company: Signature: Name: Designation: Dept.& section:

WITNESSED Signature: Name: Designation: Dept.& section:

APPROVED

S-ar putea să vă placă și