PPAP

Production Part Approval Process 4th Edition

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom

13.01.2007

Seite 1

Dipl.-Ing. Ralf Glner

PPAP

Its the goal of this lecture to


to show you the basic content and the rules of the

Production Part Approval Process


and to explain the purpose and the background but this lecture will not save you from learning how to practically use this system
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 2

Dipl.-Ing. Ralf Glner

PPAP

Notes to This Lecture


this lecture was created for training purposes only; it is not an extensive description, but a
help for getting started view of contents, basic idea and goals

The content of this lecture shall not be used as a reference for daily work
Please make sure that you are working only with original latest level documents

Creating this lecture, the valid standards of Dec 2006 were used This lecture does not refer to customer specific requirements, nor to special PPAP rules/requirements for bulk materials, tires, nor truck industry! Standards mentioned in this lecture can be obtained from the institutions listed in section 6. Internet Links

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 3

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

3. 4. 5. 6.

Summary of the Process The Documentation and its Preparation Summary Internet Links
+49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 4

2007 by R.Glner, D-85221 Dachau,

Dipl.-Ing. Ralf Glner

PPAP

1. Introduction
it is the purpose of advanced quality management to prevent that unreliable designs or processes are used in serial production

therefore it is necessary to have one extensive, strict approval process for new or changed designs or processes inevitably this process causes some administration work

but its worth while because it reduces the production of muda!


2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 5

Dipl.-Ing. Ralf Glner

PPAP

Saving by taking advantage of the Rule Of The 10: The cost of the remedy of a defect increases tenfold with every step, the project advances!
Early identification of a defect

EXPENSES

...saves the major part of the cost!

PROJECT TIME

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 6

Dipl.-Ing. Ralf Glner

PPAP

Savings by avoiding the 7+1 muda


over production muda in the process

errors

stock

muda

unnecessary unnecessary waiting movement transport time

Design ignoring the customers expectations

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 7

Dipl.-Ing. Ralf Glner

PPAP

Too high stocks...


take space raise assets employed require additional searching require additional administration require additional transport are a risk, because parts might exceed expiration date or become unsaleable are a risk, because parts might be damaged complicate the overview are often a consequence of a weak process cover weak process
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 8

Dipl.-Ing. Ralf Glner

PPAP

Requirement for low stocks...


are controlled and capable processes and Total Productive Maintenance since all kind of process problems will cause delivery stops, if the stocks are low!

lower stocks

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 9

Dipl.-Ing. Ralf Glner

PPAP

Advantages of controlled & capable production processes


satisfied customers by good quality and avoided muda

no scrap, no rework

constant flow of material

low stocks possible

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 10

Dipl.-Ing. Ralf Glner

PPAP

According to QS-9000...
such an extensive and strict process is an obligatory requirement (cp. QS-9000, main section I) the name of this process is

Production Part Approval Process

its explanation is one QS-9000 reference manual

QS-9000
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de

PPAP
PPAP_engl.PPT vom 13.01.2007 Seite 11

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6. General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

PPAP

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 12

Dipl.-Ing. Ralf Glner

PPAP

2.

Content of the QS-9000


General PPAP Process Requirements

PPAP

Introduction Section 1 Section 2 Section 3 Section 4 Section 5 Section 6

Customer Notification and Submission Requirements Submission Levels Part Submission Status Record Retention

Manufacturer Specific Requirements


Will not be discussed here! are to be found in internet OEM Homepages or
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 13

Dipl.-Ing. Ralf Glner

PPAP

Appendicies
Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Glossary Completion of the Part Submission Warrant Completion of the Appearance Approval Report PPAP, Dimensional Results PPAP, Material Test Results PPAP, Performance Test Results Bulk Material - Specific Requirements Tires - Specific Requirements Truck Industry - Specific Requirements

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 14

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 15

Dipl.-Ing. Ralf Glner

PPAP

PPAP is, so to speak, the goal of APQP...


APQP makes sure that all requirements are recognized before the Product Development is started that those special characteristics of the product are specified which influence these requirements that it is verified again and again that the planed design can safely meet these requirements, if the special characteristics are within tolerance that only those production processes are specified, which are controlled and capable according to SPC regarding these characteristics A test production and PPAP are used to validate that all processes are under control and capable the produced parts fulfil all requirements
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 16

Dipl.-Ing. Ralf Glner

PPAP

Purpose and Applicability It is the purpose of PPAP to


define generic requirements for production part approval determine if all customer engineering design record and specification requirements are properly understood by the organization determine that the manufacturing process has the potential to produce the product consistently meeting these requirements during an actual production run at the quoted production rate

Applicability (

PPAP, Introduction)

PPAP shall apply to internal and external organization sites supplying production or service parts, production materials or bulk materials.
For bulk material PPAP is not required unless specified by the customer

a supplier of standard catalogue production or service parts shall comply with PPAP unless formally waived by the customer
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 17

Dipl.-Ing. Ralf Glner

PPAP

Submission of PPAP The organization shall obtain full approval from the authorized customer product approval activity for:
1. a new part or product 2. correction of a discrepancy on a previously submitted part 3. product modified by an engineering change to
design records specifications materials

4. any situations required by section 3 Note: If there is any question concerning the need for PPAP, contact the authorized customer representative.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 18

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6. General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

PPAP

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 19

Dipl.-Ing. Ralf Glner

PPAP

(2.) 2. 2.1 2.2

PPAP Process Requirements Significant Production Run PPAP Requirements 2.2.1 2.2.2 2.2.18
Requirements describing the details of documentation to be attached Will be discussed in chapter 4 of this presentation!

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 20

Dipl.-Ing. Ralf Glner

PPAP

(2.)2.1 Significant Production Run


Products for PPAP shall be taken from a significant production run This production run shall be from one hour to eight hours of production, and with the specific production quantity to total a minimum of 300 consecutive parts, unless otherwise specified by the authorized customer representative This significant production run shall be conducted at the production, at the production rate, using the production tooling, production gaging, production process, production materials, and production operators. Parts from each unique production process, e.g. duplicate assembly line and/or work cell, each position of a multiple cavity die, mold, tool or pattern, shall be measured and representative parts tested
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 21

Dipl.-Ing. Ralf Glner

PPAP

(2.)2.2 PPAP Requirements


the supplier shall meet all specified requirements
as listed in this handbook and all customer-specific requirements

Production parts shall meet all customer engineering design record and specification requirements
including safety and regulatory requirements

If any part specification cannot be met, the organization shall document their problem-solving efforts and shall contact the authorized customer representative for concurrence in determination of appropriate corrective action.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 22

Dipl.-Ing. Ralf Glner

PPAP

View over the documentations to be created


(see chapter 4 of this presentation for details)

Warrant

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 23

Dipl.-Ing. Ralf Glner

PPAP

Content of the documentation to be created


1. Design Record 2. Authorized Engineering Change Documents 3. Customer Engineering Approval 4. Design-FMEA 5. Process Flow Diagram(s) 6. Process-FMEA 7. Control Plan 8. Measurement System Analysis Studies 9. Dimensional Results 10. Records of Material/ Performance Test Results 11. Initial Process Studies 12. Qualified Laboratory Documentation 13. Appearance Approval Report 14. Sample Production Parts 15. Master Sample 16. Checking Aids 17. Customer-Specific Requirements 18. Part Submission Warrant
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 24

Dipl.-Ing. Ralf Glner

PPAP

Paperwork or EDP?

PPAP?

all forms mentioned in this document may be replaced by identical computer generated forms these documents have to be approved by the customer product approval activity before first submission at Adare Carwin a floppy with all forms can be obtained

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 25

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6. General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

PPAP

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 26

Dipl.-Ing. Ralf Glner

PPAP

2.3. Customer Notification and Submission Requirements( PPAP, Section 3)


1. Customer Notification
The organization shall notify the authorized customer representative of any planned changes to the design, process or site. Examples are indicated in Table 3.1
Notification of all changes to desing nad process is the the organizations resonsibility.

Upon notification and approval of the proposed change by the authorized customer representative, and after change implementation, PPAP submission is required unless otherwise specified

2. Submission to Customer
The organization shall submit for PPAP approval prior to the first production shipment in the following situations (see Table I.3.2) unless the authorized customer representative has waived this requirement. The organization shall review and update all applicable items in the PPAP file to reflect the production process,
regardless of whether or not the customer requests a formal submission.

The PPAP file shall contain the name of the authorized customer representative granting the waiver and the date.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 27

Dipl.-Ing. Ralf Glner

PPAP

Table 3.1: Customer Notification Required


1. 2. 3. 4. 5. use of other construction or material than was used in the previously approved part or product production from new or modified tools (except perishable tools), dies, molds, patterns, etc., including additional or replacement tooling production following refurbishment or rearrangement of existing tooling or equipment production from tooling and equipment transferred to a different plant location or from a additional plant location. change of subcontractor for parts, non-equivalent materials or services (e.g.: heat-treating, plating) that affect customer fit, form, function, durability, or performance requirements product produced after tooling has been inactive for volume production for twelve months or more product and process changes that impact fit, form, function, performance, and/or durability of the salable product
+49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 28

6. 7.

2007 by R.Glner, D-85221 Dachau,

Dipl.-Ing. Ralf Glner

PPAP

Table 3.2: Submission to Customer


1. 2. 3. 4. a new part or product (i.e.: a specific part, material, or color not previously supplied to this specific customer) correction of a discrepancy on a previously submitted part engineering changes to design records, specifications, or materials for production product/part number(s) bulk material only: process technology new to the supplier, not previously used for this product

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 29

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6. General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

PPAP

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 30

Dipl.-Ing. Ralf Glner

PPAP

2.4. Submission Levels Note:

The content of the documentation to be generated is always the same! The supplier has to retain everything (e.g.. as a copy)! the Submission Level just indicates what has to be submitted to the customer!
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 31

Dipl.-Ing. Ralf Glner

PPAP

There are five Submission Levels:


1. warrant only (and if applicable an Appearance Approval Report) 2. warrant with product samples and limited supporting data 3. warrant with product samples and complete supporting data 4. warrant with other requirements as defined by the customer 5. warrant with product samples and complete supporting data available for review at the organizations manufacturing location

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 32

Dipl.-Ing. Ralf Glner

PPAP

The customer decides about the submission level


I want I need I wish

...looking at:

the status of the supplier (Ford Q1, ...) his experience with earlier approval processes the know-how of the supplier concerning this product the importance of the part so the submission level might be different for every product
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 33

Dipl.-Ing. Ralf Glner

PPAP

S = submit
retain a copy at an appropriate location, (including manufacturing)

R = retain at appropriate locations


(including manufacturing)

has to be made readily available to the customer representative upon request

* = retain at appropriate locations


submit upon request

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 34

Dipl.-Ing. Ralf Glner

PPAP

LEVEL 3 IS THE STANDARD LEVEL"


IT SHALL BE USED FOR ALL SUBMISSIONS UNLESS SPECIFIED OTHERWISE BY THE RESPONSIPLE CUSTOMER PRODUCT APPROVAL ACTIVITY Level 1 = just warrant and (if applicable) Appearance Approval Report Level 2 = standard minus process description and background information Level 3 = standard Level 4 = warrant, other requirements as defined by the customer Level 5 = the complete list, and everything will be checked at the suppliers site!
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 35

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Requirements Customer Notification and Submission Requirements Submission Levels Part Submission Status Record Retention

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 36

Dipl.-Ing. Ralf Glner

PPAP

After everything is ready, it will be submitted to the customer!

namely at the responsible product approval activity the customer will inspect everything and notify the organization of the result using the Part Submission Status

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 37

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Status


ORGANIZATIONS MAY NEVER SHIP PRODUCTION QUANTITIES BEFORE CUSTOMER APPROVAL!

Upon approval of the submission, the organization shall assure that future production continues to meet all customer requirements For those organizations that have been classified as self-certifying by a specific customer (PPAP Submission Level 1), submission of the required organization-approved documentation will be considered as customer approval unless the organization is advised otherwise.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 38

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Status:

A
Approved

B
Interim Approval

C
Rejected

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 39

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Status A = Approved


indicates that the part or material meets all customer specifications and requirements the organization therefore is authorized to ship production quantities of the product subject to releases from the customer scheduling activity

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 40

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Status B = Interim Approval


Permits shipment of material for production requirements on a limited time or piece quantity basis. Interim Approval will only be granted when the organization has:
clearly defined the non-compliances preventing approval; and, prepared an interim approval action plan agreed upon by the customer

The organization is responsible for implementing containment actions to ensure that only acceptable material is beeing shipped to the customer. PPAP re-submission is required to obtain a status of Approved material covered by an interim approval that fails to meet the agreed-upon action plan either by the expiration date or the shipment of the authorized quantity will be rejected. No additional shipments are authorized unless an extention of the interim approval is granted.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 41

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Status C = Rejected

Means that the PPAP submission does not meet the customer requirements, based on
the production lot from which it was taken, and/or accompanying documentation

In such cases, the submission and/or process (as appropriate) shall be corrected to meet the customer requirements. The submission shall be approved before production quantities may be shipped.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 42

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6. General PPAP Process Requirements Customer Notification and Submission Requirements Submission to Customer - Levels of Evidence Part Submission Status Record Retention

PPAP

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 43

Dipl.-Ing. Ralf Glner

PPAP

Record Retention and Sampling


PPAP records, regardless of submission level, shall be maintained for the length of the time the part is active (in production or service) plus one calendar year the supplier shall ensure that the appropriate PPAP records from a superseded part PPAP file are included, or referenced in the new part PPAP file

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 44

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Requirements Customer Notification and Submission Requirements Submission Levels Part Submission Status Record Retention

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 45

Dipl.-Ing. Ralf Glner

PPAP

3. Summary of the Process


before delivering new or changed parts or changing the production processes the supplier has to document that he has successfully finalized all activities of to ensure
that the product will meet all requirements that the processes are under control and capable These activities are mostly described in QS 9000 APQP

the documentation consist of the Part Submission Certificate and the required attachments according to his Submission Level the supplier has to submit everything or just parts of it to the customer the customer checks the documentation and sets the Part Submission Status depending on that the supplier can start delivery or not
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 46

Dipl.-Ing. Ralf Glner

PPAP

Teamwork: How to judge about PPAP?


Task: Assume you have received a PPAP Submission Level 3 from your supplier. Supplier has design responsibility. How to make sure whether or not the supplier worked carefully?
but without leaving your desk!

Time frame:
Preparation 15 min.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 47

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Requirements Customer Notification and Submission Requirements Submission Levels Part Submission Status Record Retention

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 48

Dipl.-Ing. Ralf Glner

PPAP

4. The Documentation and its Preparation

Warrant

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 49

Dipl.-Ing. Ralf Glner

PPAP

Only English report forms have to be filled out and submitted to the customer!

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 50

Dipl.-Ing. Ralf Glner

PPAP

Content of the documentation to be created


1. Design Record 2. Authorized Engineering Change Documents 3. Customer Engineering Approval 4. Design-FMEA 5. Process Flow Diagram(s) 6. Process-FMEA 7. Control Plan 8. Measurement System Analysis Studies 9. Dimensional Results 10. Records of Material/ Performance Test Results 11. Initial Process Studies 12. Qualified Laboratory Documentation 13. Appearance Approval Report 14. Sample Production Parts 15. Master Sample 16. Checking Aids 17. Customer-Specific Requirements 18. Part Submission Warrant
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 51

Dipl.-Ing. Ralf Glner

PPAP

4.1 Design Records


all design records for the saleable product e.g.
CAD/CAM Data part drawings specifications

including component drawings For parts identified as black box the design record specifies the interface and performance requirements The organization shall provide evidence that the Material/Substance Composition reporting has been completed and that reported data complies with all requirements
Reporting and requirements as prescribed by the customer Reporting may be entered into International Materials Data System (IMDS), www.mdsystem.com/index.jsp

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 52

Dipl.-Ing. Ralf Glner

PPAP

4.1 Design Records /


Where applicable, the Organization shall identify polymeric parts with the ISO symbols
for plastics: 100g, see ISO 11469 / 1043-1 for elastomers: 100g, see ISO 11469 /1629

4.2 Authorized Engineering Change Documents


all authorized engineering change documents, which are not yet recorded in the design record but incorporated in the product, part or tooling

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 53

Dipl.-Ing. Ralf Glner

PPAP

4.3 Customer Engineering Approval

where specified by the customer, the organization shall have evidence of customer engineering approval

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 54

Dipl.-Ing. Ralf Glner

PPAP

4.4

Design-FMEA

If the supplier is design responsible a Design-FMEA is required according to the customer-specific requirements e.g. QS-9000 FMEA (Potential Failure Mode and Effect Analysis)

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 55

Dipl.-Ing. Ralf Glner

PPAP

4.5 Process Flow Diagrams

see QS-9000

APQP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 56

Dipl.-Ing. Ralf Glner

PPAP

4.6

Process-FMEA

according to the customer-specific requirements e.g. QS-9000 FMEA (Potential Failure Mode and Effect Analysis)

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 57

Dipl.-Ing. Ralf Glner

PPAP

4.7

Control Plan
The Organization shall have control plan that defines all controls used for process control and complies with the customerspecified requirements, e.g. QS-9000 APQP control plans for families of similar parts are acceptable if the new parts have been reviewed for commonality Note: Certain customers require control plan approval e.g. customer signature on the control plan, prior to submission.
QM-Plan according to QS-9000

APQP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 58

Dipl.-Ing. Ralf Glner

PPAP

4.8 Measurement System Analysis Studies


the organization shall have applicable Measurement System Analysis Studies (e.g. Gage R & R) for all new or modified gages, measurement, and test equipment See QS-9000 MSA (Measurement System Analysis reference manual.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 59

Dipl.-Ing. Ralf Glner

PPAP

4.9 Dimensional Results


The organization shall provide evidence that dimensional verifications required by die design record and the Control Plan have been completed and results indicate compliance with specified requirements. The organization shall have dirnensional results for each unique manufacturing process, e.g. cells or production limes and all cavities, molds, patterns or dies The organization shall record, with the actual results: all dimensions (except reference dimensions), characteristics, and specifications as noted an the design record and Control Plan.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 60

Dipl.-Ing. Ralf Glner

PPAP

4.9 Dimensional Results /


The organization shall indicate
the date of the design record, change level, and any authorized engineering change document not yet incorporated in the design record to which the part was made.

The organization shall record


the change level, drawing date, organization name and part number

on all auxiliary documents (e.g. supplementary layout results sheets, sketches, tracings, cross sections, CMM inspection point results, geometric dimensioning and tolerancing sheets, or other auxiliary drawings used in conjunction with the part drawing).
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 61

Dipl.-Ing. Ralf Glner

PPAP

4.9 Dimensional Results /


Copies of these auxiliary materials shall accompany the dimensional results according to the Retention/Submission Requirements Table. A tracing shall be included when an optical comparator is necessary for inspection. The organization shall identify one of the parts measured as the master sample
NOTE 1: The Dimensional Results form in Appendix C, a pictorial, geometrie dimensioning & tolerancing [GD&T] sheets, or a checked print where the results are legibly written on a part drawing including cross sections, tracings, or sketches as applicable may be utilized for this purpose. NOTE 2: Dimensional results typically do not apply to bulk materials.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 62

Dipl.-Ing. Ralf Glner

PPAP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 63

Dipl.-Ing. Ralf Glner

PPAP

4.10 Records of Material/Performance Test Results

The organization shall have records of test results for


material tests performance tests

for tests specified


in the design record in the control plan

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 64

Dipl.-Ing. Ralf Glner

PPAP

4.10.1 Material Test Results


The organization shall perform tests for all parts and product materials when chemical, physical, or metallurgical requirements are specified by the design record or control plan Material test results shall indicate and include:
the design record change level of the parts tested; any authorized engineering change documents that have not yet been incorporated in the design record; the number, date, and change level of the specifications to which the part was tested; the date on which the testing took place; the quantity tested; the actual results; the material suppliers name and, when required by the customer, the customer-assigned supplier/vendor code.

NOTE: Material test results may be presented in any convenient format. An example is shown in Appendix D.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 65

Dipl.-Ing. Ralf Glner

PPAP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 66

Dipl.-Ing. Ralf Glner

PPAP

4.10.1 Material Test Results /


For products with customer-developed material specifications and a customer-approved supplier list, the organization shall procure materials and/or services (e.g., painting, plating, heat-treating, welding) from suppliers on that list.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 67

Dipl.-Ing. Ralf Glner

PPAP

4.10.2 Performance Test Results


The organization shall perform tests for all part(s) or product material(s) when performance or functional requirements are specified by the design record or Control Plan. Performance test results shall indicate and include: die design record change level of the parts tested;
any authorized engineering change documents that have not yet been incorporated in the design record; the number, date, and change level of the specifications to which the part was tested; the date on which the testing took place; the quantity tested; the actual results.

NOTE: Performance test results may be presented in any convenient format. An example is shown in Appendix E.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 68

Dipl.-Ing. Ralf Glner

PPAP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 69

Dipl.-Ing. Ralf Glner

PPAP

4.11

Initial Process Studies

4.11.1 General 4.11.2 Quality Indices 4.11.3 Acceptance Criteria for Initial Study 4.11.4 Unstable Processes 4.11.5 Processes With One-Sided Specifications or Non-Normal Distributions 4.11.6 Actions To Be Taken When Acceptance Criteria Are Not Satisfied

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 70

Dipl.-Ing. Ralf Glner

PPAP

4.11.1 General
the level of initial process capability or performance shall be determined to be acceptable prior to submission for all special characteristics designated by the customer or the organization (sc,cc) the organization shall perform measurement analysis to understand how measurement error is affecting the study measurements (see Measurement System Analysis reference manual) for explanations about Cpk or Ppk see Process Control manual) SPC (Statistical

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 71

Dipl.-Ing. Ralf Glner

PPAP

Turning Point

Mean Value x

Standard Deviation s

Gau Normal Distribution


2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 72

Dipl.-Ing. Ralf Glner

PPAP

Definitions Process under Control / Capable Process


not capable capable

2007 by R.Glner, D-85221 Dachau,

under control
+49-8131-53595, www.glaessner.de

not under control

PPAP_engl.PPT vom 13.01.2007

Seite 73

Dipl.-Ing. Ralf Glner

PPAP
Example
Process Capability Index

The Capable Process Cp = Process Capability Index


Shows proportion of the permissible tolerance interval to the scatter Scatter is measured in multiples of the standard deviation s If the scatter is with +/- 3 s within the tolerance, then Cp=1

Comment

No capability High amount of scrap

No capability If centered pretty exact, just about no scrap

Very good capability Statistically no scrap

No capability Not centered Scrap

Cpk = Critical Process Capability Index


Supplementary considers the mean of the process not being equal to the middle of the tolerance interval
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de

Good capability Process is centered enough Little scrap

Example 1 to 3

Process adjusted exactly to center of tolerance interval

PPAP_engl.PPT vom 13.01.2007

Seite 74

Dipl.-Ing. Ralf Glner

PPAP

4.11.2 Quality Indices


Initial process studies shall be summarized with capability or performance indices, if applicable. NOTE 1: The initial process study results are dependent on the purpose of the study, method of data acquisition, sampling, amount of data, demonstration of statistical control. etc. See the QS-9000 Statistical Process Control reference manual for additional information in understanding the basic principles of statistical stability and process measures (indices). For guidance on items listed below, contact the authorized customer representative.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 75

Dipl.-Ing. Ralf Glner

PPAP

Cpk and Ppk


Cpk - The capability Index for a stable process.
The estimate of sigma is based on within subgroup variation . Cpk is an indicator of process capability based on process variation within each subgroup of a set of data. Cpk does not include the effect of process variability between the subgroups. Cpk is an indicator of how good a process could be if all process variation between subgroups was to be eliminated. Therefore, use of Cpk alone may be an incomplete indicator of process performance.

Ppk - The performance index.

The estimate of sigma is based on total variation (all of individual sample data using the standard deviation. Ppk is an indicator of process performance based on process variation throughout the full Set of data. Unlike Cpk, Ppk is not limited to the variation within subgroups. However, Ppk cannot isolate within subgroup variation from between subgroup variation.

When calculated from the same data set, Cpk and Ppk can be compared to analyze the sources of process variation. For more information, see QS-9000 Statistical Process Control.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 76

Dipl.-Ing. Ralf Glner

PPAP

Purpose of Initial Process Studies


The purpose of the initial process study is to understand the process variation, not just to achieve a specific index value. When historical data are available or enough initial data exist to plot a control chart (at least 100 individual sarnples), Cpk can be calculated when the process is stable. Otherwise, for processes with known and predictable special causes and output meeting specifications, Ppk should be used. When not enough data are available (< 100 samples) or there are unknown sources of variation, contact the authorized customer representative to develop a suitable plan.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 77

Dipl.-Ing. Ralf Glner

PPAP

Examination of the stability (Process control)

process seems stable

process seems instable

examine capability continue with 4.11.3

Process may not meet customer requirements continue with 4.11.4

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 78

Dipl.-Ing. Ralf Glner

PPAP

4.11.3 Acceptance Criteria for Initial Study


Capability Index for stable process

Index > 1.67


the process currently meets the acceptance criteria after approval, begin production and follow control plan

1.33 Index 1.67


the process may be acceptable contact the authorized customer representative for a review of the study results

Index < 1.33


the process does not currently meet the acceptance criteria contact the authorized customer representative for a review of the study results
PPAP_engl.PPT vom 13.01.2007 Seite 79

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

Dipl.-Ing. Ralf Glner

PPAP

4.11.4 Unstable Processes


Depending on the nature of the instability, an unstable process may not meet customer requirements. The organization shall identify, evaluate and, wherever possible, eliminate special causes of variation prior to PPAP submission. The organization shall notify the authorized customer representative of any unstable processes that exist and shall submit a corrective action plan to the customer prior to any submission. NOTE: For bulk materials, for processes with known and predictable special causes and output meeting specifications, corrective action plans may not be required by the customer.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 80

Dipl.-Ing. Ralf Glner

PPAP

4.11.5 Processes With One-Sided Specifications or Non-Normal Distributions


The organization shall determine with the authorized customer representative alternative acceptance criteria for processes with one-sided specifications or nonenormal distributions. NOTE: The above mentioned acceptance criteria assume normality and a two-sided specification (target in the center). When this is not true, using this analysis may result in unreliable information. These alternate acceptance criteria could require a different type of index or some method of transformation of the data. The focus should be on understanding the reasons for the nonnormality (e.g., is it stable over time?) and managing variation. Refer to the Statistical Process Control reference manual for further guidance.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 81

Dipl.-Ing. Ralf Glner

PPAP

4.11.6 Actions To Be Taken When Acceptance Criteria Are Not Satisfied


The organization shall contact the authorized customer representative if the acceptance criteria cannot be attained by the required PPAP submission date. The organization shall submit to the authorized customer representative for approval a corrective action plan and a modified Control Plan normally providing for 100% inspection. Variation reduction efforts shall continue until the acceptance criteria are met, or until customer approval is received. NOTE: 100% inspection methodologies are subject to review and concurrence by the customer.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 82

Dipl.-Ing. Ralf Glner

PPAP

4.12 Qualified Laboratory Documentation


Inspection and testing for PPAP shall be performed by a qualified laboratory as defined by customer requirements (e.g., an accredited laboratory). The qualified laboratory (internal or external to the organization) shall have a laboratory scope and documentation showing that the laboratory is qualified for the type of measurements or tests conducted. When an external/commercial laboratory is used, the organization shall submit the test results on the laboratory letterhead or the normal laboratory report format. The name of the laboratory that performed the tests, the date (s) of the tests, and the standards used to run the tests shall be identified.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 83

Dipl.-Ing. Ralf Glner

PPAP

4.13 Appearance Approval Report (AAR)


AAR = approval report for the appearance of appearance items concerning requirements on color, structure, or surface For completion of AAR, see instruction in PPAP, appendix B A separate AAR shall be completed for each part or series of parts for which a submission is required if the product/part has appearance requirements on the design record Upon satisfactory completion of all required criteria, the supplier shall record the information on the AAR
since the Appearance Approval Report is a industry wide used form not all customers will require entries in every position

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 84

Dipl.-Ing. Ralf Glner

PPAP

4.13 Appearance Approval Report (AAR) /


The completed AAR and representative production products/parts shall be submitted to the location specified by your customer to receive disposition AARs (complete with part disposition and customer signature) shall then accompany the PSW at the time of final submission based upon the submission level requested

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 85

Dipl.-Ing. Ralf Glner

PPAP

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 86

Dipl.-Ing. Ralf Glner

PPAP

4.14 Sample Production Parts


The organization shall provide sample products as specified by the customer.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 87

Dipl.-Ing. Ralf Glner

PPAP

4.15 Master Sample


The organization shall retain a master sample for the same period as the production part approval records, or
a) until a new master sample is produced for the same customer part number for customer approval, or b) where a master sample is required by the design record, Control Plan or inspection criteria. as a reference or standard.

The master sample shall be identified as such, and shall show the customer approval date on the sample. The organization shall retain a master sample for each position of a multiple cavity die, mold, tool or pattern, or production process unless otherwise specified by the customer.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 88

Dipl.-Ing. Ralf Glner

PPAP

4.16 Checking Aids


If requested by the customer, the organization shall submit with the PPAP submission any part-specific assembly or component checking aid. The organization shall certify that all aspects of the checking aid agree with part dimensional requirements. The organization shall document all released engineering design changes that have been incorporated in the checking aid at the time of submission. The organization shall provide for preventive maintenance of any checking aids for the life of the part. measurement system analysis studies, e.g. gage R&R, accuracy, bias, linearity, stability studies, shall be conducted in compliance with the customer requirements. See MSA (Measurement Systems Analysis reference manual).
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 89

Dipl.-Ing. Ralf Glner

PPAP

4.17 Customer-Specific Requirements


The organization shall have records of compliance to all applicable customer-specific requirements. For bulk materials, applicable customer-specific requi rements shall be documented on the Bulk Material Requirements Checklist.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 90

Dipl.-Ing. Ralf Glner

PPAP

4.18. Production Part Submission Warrant


Upon completion of all PPAP requirements, the organization shall complete the Part Submission Warrant (PSW).
Warrant

A separate PSW shall be completed for each customer part number unless otherwise agreed to by the authorized customer representative. If production parts will be produced from more than one cavity, mold, tool, die, pattern, or production process. e.g., line or cell, the organization shall complete a dimensional evaluation on one part from each. The specific cavities, molds, line, etc., shall then be identified in the Mold/Cavity/Production Process line on a PSW, or in a PSW attachment.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 91

Dipl.-Ing. Ralf Glner

PPAP

4.18. Production Part Submission Warrant/


Warrant The organization shall verify that all of the measurement and test results show conformance with customer requirements and that all required documentation is available and, for Level 2, 3, and 4, is included in the submission as appropriate.

A responsible official of the organization shall approve the PSW and provide contact information.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 92

Dipl.-Ing. Ralf Glner

PPAP

Part Submission Warrant


consists of: Information about the part Some formal information Materials reporting Reason of the submission Requested submission level Result of the submission Declaration For customer use (result)

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 93

Dipl.-Ing. Ralf Glner

PPAP

Detail of Part Submission Warrant

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 94

Dipl.-Ing. Ralf Glner

PPAP

Dimension Results / Part Weight (Mass)


The organization shall record on the PSW the part weight of the part as shipped, measured and expressed in kilograms to four decimal places (0.0000) unless otherwise specified by the customer. The weight shall not include shipping protectors, assembly aides, or packaging materials. To determine part weight, the organization shall individually weigh ten randomly selected parts, calculate and report the average weight. At least one part shall be measured from each cavity, tool, line or process to be used in product realization. NOTE: This weight is used for vehicle weight analysis only and does not affect the approval process. Where there is no production or service requirement for at least ten parts, the organization should use the required number for calculation of the average part weight.
2007 by R.Glner, D-85221 Dachau, +49-8131-53595, www.glaessner.de PPAP_engl.PPT vom 13.01.2007 Seite 95

Dipl.-Ing. Ralf Glner

PPAP

Contents
1. 2. Introduction Content of the QS-9000
1. 2. 3. 4. 5. 6.

PPAP

General PPAP Requirements Customer Notification and Submission Requirements Submission Levels Part Submission Status Record Retention

3. 4. 5.

Summary of the Process The Documentation and its Preparation Summary

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 96

Dipl.-Ing. Ralf Glner

PPAP

The Attempt to Run PPAP without APQP!

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 97

Dipl.-Ing. Ralf Glner

PPAP

The Production Part Approval Process is an extensive strict approval process for new or changed designs or processes.

Summary

It is very formalized, so it inevitably causes some administration work, but it doesnt demand anything that makes no sense from an engineers point of view! Later changes of the product or the process are expensive and take a lot of time. The prerequisite to fulfill PPAP demands is a carefully done quality planning according to QS-9000 APQP.

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007

Seite 98

Dipl.-Ing. Ralf Glner

PPAP

6.

Internet Links
http://www.din.de http://www.iso.ch http://www.cenorm.be https://www.carwin.co.uk/qs/qs9000default.htm http://www.aiag.org http://www.iaob.org http:// www.vda-qmc.de

2007 by R.Glner, D-85221 Dachau,

+49-8131-53595, www.glaessner.de

PPAP_engl.PPT vom 13.01.2007