Documente Academic
Documente Profesional
Documente Cultură
Calculation
Hours
Machining & Welding
4
Painting & Finising
2
Machining & Welding
2
Painting & Finising
1
Machining & Welding
2
Painting & Finising
2
2
Mach. & Weld. Hrs
Paint. & Finish Hrs
Ass/Test/Pack. Hrs
8
5
2
Data
Hours
Machining & Welding
5
Painting & Finising
4
Machining & Welding
3
Painting & Finising
2
Machining & Welding
2
Painting & Finising
2
Machining & Welding
2
Painting & Finising
2
2
Mach. & Weld. Hrs
Paint. & Finish Hrs
Ass/Test/Pack. Hrs
Let #
Units Produced for Body Plus 100 =
Units Produced for Body Plus 200 =
X
Y
12
10
2
M. Cost
$450
$300
$250
$50
$1,050
L.Cost
$20
$15
$20
$15
$20
$15
$12
Retail
$2,400
$259
Calculation
M. Cost
$650
$400
$250
$200
$75
$1,575
L.Cost
$20
$15
$20
$15
$20
$15
$20
$15
$12
Retail
$3,500
$414
50
16.666667
$26,233.33
Constraints
= 8 X + 12 Y
= 5 X + 10 Y
=2X+2Y
= Y 0.25*(X + Y)
= 0.25 X - 0.75 Y
=X0
=Y0
600
416.66667
133.33333
0
0
50
16.666667
Price
$1,680
<=
<=
<=
<=
>=
>=
600
450
140
0
0
0
0
Price
$2,450
Calculation
Profit / Unit
Price - Total Cost
$371
Calculation
Profit
Price - Total Cost
$461
Data
Calculation
Hours
Machining & Welding
4
Painting & Finising
2
Machining & Welding
2
Painting & Finising
1
Machining & Welding
2
Painting & Finising
2
2
Mach. & Weld. Hrs
Paint. & Finish Hrs
Ass/Test/Pack. Hrs
M. Cost
$450
$300
$250
$50
8
5
2
$1,050
Data
Hours
Machining & Welding
5
Painting & Finising
4
Machining & Welding
3
Painting & Finising
2
Machining & Welding
2
Painting & Finising
2
Machining & Welding
2
Painting & Finising
2
2
Mach. & Weld. Hrs
Paint. & Finish Hrs
Ass/Test/Pack. Hrs
Let #
Units Produced for Body Plus 100 =
Units Produced for Body Plus 200 =
X
Y
L.Cost
$20
$15
$20
$15
$20
$15
$12
Retail
$2,400
$259
Calculation
M. Cost
$650
$400
$250
$200
$75
12
10
2
$1,575
L.Cost
$20
$15
$20
$15
$20
$15
$20
$15
$12
Retail
$3,500
$414
60
10
$26,870.00
Constraints
= 8 X + 12 Y
= 5 X + 10 Y
=2X+2Y
= Y 0.25*(X + Y)
= 0.25 X - 0.75 Y
=X0
=Y0
Price
$1,680
600
400
140
7.5
0
60
10
<=
<=
<=
<=
>=
>=
600
450
140
0
0
0
0
$637
Price
$2,450
Calculation
Profit / Unit
Price - Total Cost
$371
Calculation
Profit
Price - Total Cost
$461
Reducing the cycle of time or increasing capacity of Machining & Welding. This is the bottle neck of current machine manufac
Security Systems
Discountted SS
1
2
3
600000
600000
250000
600000 555555.6 214334.7
Market Analysis
Discounted MA
%SS
%MA
Objective Function
Constraints
First Yea Max
Second Year Max
Third Year Max
Q1. Answer
%SS
%MA
NPV of Investment
1800000
1600000
0.608697732
0.869562721
Max (1800000 %SS + 1600000 %MA)
2486956.272
0.608697732
0.869562721
$1,848,637.14
Q2.
Year 1
SS
$365,219
MA
$434,781
Total HVC Investment
$800,000
Q3.
8%
Year 2
$365,219
$304,347
$669,566
Year 3
$152,174
$347,825
$500,000
$800,000
$619,968
$428,669
800000
648148
428669
Security Systems
Discountted SS
1
2
3
600000
600000
250000
600000 555555.5556 214334.7051
Market Analysis
Discounted MA
$500,000
$500,000
$350,000
$324,074
$400,000
$342,936
$900,000
$900,000
$700,000
$648,148
$500,000
$428,669
%SS
%MA
Objective Function
Constraints
First Yea Max
Second Year Max
Third Year Max
Q1. Answer
%SS
%MA
NPV of Investment
8%
1800000
1600000
0.68852527
0.819670509
Max (1800000 %SS + 1600000 %MA)
2550818.3
$822,950
$648,148
$428,669
900000
$648,148
$428,669
0.608697732
0.869562721
1848637.141
Q2.
SS
MA
Total HVC Investment
Year 1
Year 2
Year 3
$365,219
$365,219
$152,174
$434,781
$304,347
$347,825
$800,000
$669,566
$500,000
Q3.
An additional $100,000 investment in the first year would result in additional
63862.03 Present value of $63862.03 that
64%
Q4.
SS
MA
Total HVC Investment
Year 1
Year 2
Year 3
$413,115
$413,115
$172,131
$409,835
$286,885
$327,868
$822,950
$700,000
$500,000
Q5.
We would not advise additional investment of $100,000, as it results in the marginal profits of only $54751.4 (PV).
Q6.
Present value of $63862.03 that would be received after three years would be
54751.4