1. Purpose
This guide is intended to give a description how to organize the interface with the Electrical group on projects. This guide shall be read with reference 3.1.
2. Established Interfaces
A list detailing interfaces is Attachment 2.
voltage and type of power supply required e.g. D. C., single or three-phase AC; number of circuits required (including spare capacity); uninterruptable; normal/alternate mains etc.; length of time that the supply is required in the event of a failure mains; duration of changeover from mains to standby ( e. g. 50 m. s. ) ; voltage regulation and tolerance; distribution boards requirements (presentation in the form of a key-one line diagram is preferred); required power in watts; allowable voltage drop; type of protection (fuse, automatic breaker etc.).
trench routes, including termination points of runs, space requirements including spare capacity, minimum installation depth; road crossings where applicable; segregation required between instrument cables and between instrument and electrical cables; details of any instrument cables to be routed in electrical cable trenches; fireproofing requirements where applicable.
Close coordination between the groups is mandatory to avoid duplication and to come to a sound design. Coordination with the Under Ground group for trenches and crossings will be done by the Electrical group.
2.8 Earthing
A philosophy drawing shall be prepared indicating:
method of termination; application of chokes; earth electrode resistance requirement for each system; segregation between systems where applicable; earthing of field instruments; earthing systems in control rooms and equipment rooms.
3. References
3.1 Document Number BN-EP-304 Title Procedure for Work Division between Control 3 Systems and Electrical Groups Level 3
1.
Is pump start/stop for level control without alarm completed by Electrical or via interposing by Contol Systems Group?
Are there running lights, not shown on EFD, located on instrument panel?
Are there alarms for transformers, H and V, fire, etc., on instrument panel?
10
11
Are there temperature signals for winding and bearing of electric motors? (intrinsically safe)
12
13
Is power supply for tank level (Enraf) inclusive distribution, up to instrument, completed by Electrical?
14
15
16
17
18
Is there electrical power (see also 13) for local analyzers or other instruments? Are local distribution boards required?
19
20
Agree estimate loads for instrument power consuming, type of power and is a key-line helpful? Is there telecommuncation, via instrument cable wire, with plug-in desk, microphone of sound power in instrument panel? Are there graphics, Amp. meters for electrical or TV screens, in instrument panel?
21
22
23
Is location of trunk, junction boxes, switches and local panels on columns determined?
24
25
Is cable-pulling contract by Electrical, inclusive cable markers and end protection cover?
26
27
28
Is coordination for underground by Electrical (See also internal procedure for coordination with Civil) ? Are cables for instruments in electrical trench only to be shown on electrical cable list? (Control Systems Group should make reference only to that list behind cable number.) Is agreed which drawings need both Control Systems and Electrical Group issue approval before sending out?
29
30
31
32
Is a splice box necessary in substation or control room for multicore runs? (One multicore, several destinations).
33
34