Sunteți pe pagina 1din 47

F900713008 Rev 2013-03-19

TECHNICAL SPECIFICATION

SVC Light COMPENSATOR for MISCO

1 of 47

F900713008 Rev 2013-03-19

TABLE OF CONTENTS
SECTION 1 .................................................................................................................................. 3
INTRODUCTION GENERAL DESCRIPTION................................................................................................... 3 References thus far ......................................................................................................................................... 6

SECTION 2 ................................................................................................................................ 18
DESIGN DATA .................................................................................................................................................. 18

SECTION 3 ................................................................................................................................ 22
TECHNICAL DATA OF MAIN EQUIPMENT ..................................................................................................... 22

SECTION 4 ................................................................................................................................ 25
SELLERS SCOPE OF SUPPLY ....................................................................................................................... 25

SECTION 5 ................................................................................................................................ 32
BUYERS SCOPE OF SUPPLY ........................................................................................................................ 32

SECTION 6 ................................................................................................................................ 34
TESTS AND GUARANTEED PERFORMANCE ................................................................................................ 34

SECTION 7 ................................................................................................................................ 37
SPARE PARTS AND SPECIAL TOOLS............................................................................................................ 37 (NOTE! Quoted separately) ............................................................................................................................... 37

SECTION 8 ................................................................................................................................ 39
SELLERS SUPERVISION OF ERECTION, COMPLETE COMMISSIONING AND ACCEPTANCE TESTS..... 39

SECTION 9 ................................................................................................................................ 42
DOCUMENTATION........................................................................................................................................... 42

SECTION 10 .............................................................................................................................. 45
PROJECT TIME SCHEDULE............................................................................................................................ 45 SINGLE LINE DIAGRAM .................................................................................................................................. 45

Confidentiality -The contents of this ABB Tender (including prices and all commercial and technical information) are proprietary to ABB Power Technologies AB and its affiliates in the ABB Group. These contents must not be disclosed to any third party or otherwise used for any purpose other than for the evaluation of this Tender or in Contract negotiations with ABB. The photographical illustrations in this specification may deviate to some extent from the proposal since their purpose are to inform the receiver and give a general image of an ABB supply related to the proposed technology rather than being an illustration of the exact scope of this Tender.

2 of 47

F900713008 Rev 2013-03-19

SECTION 1
INTRODUCTION GENERAL DESCRIPTION ABB takes pleasure in presenting the following proposal for a Static Var Compensator (SVC) for MISCO, Oman. By selecting ABB for the supply and implementation of the SVC Light, the delivery will be based on state-of-the-art technology. In addition, project management, design and engineering will be performed by a dedicated SVC organisation. The organisation has unique knowledge of Electrical Arc Furnaces compensated by Static Var Compensation. ABB would like to highlight the following key features of our proposal: Arc Furnace operation improvement: ABB has unique experience of SVC Light for Arc Furnace applications, including documented furnace power increases and other profitability enhancing features. Excellent flicker mitigation performance: Well proven and documented flicker mitigation performance. World Class System Study Expertise: ABB has the in-house expertise needed and experience required to perform the required and necessary system studies. We also possess great skills in magnetic and sound level calculations. Key components: All major key components are manufactured within ABB. MACH 2 control and protection system: The MACH 2 system is the most advanced and high performance control and protection system for high voltage applications on the market. Dedicated SVC organisation: Over 300 people, including professional engineers as well as other dedicated staff, highly skilled for ABB's long-term commitment in this business.

3 of 47

F900713008 Rev 2013-03-19 In addition to the project engineers, the organisation includes the following: System engineers Mechanical design engineers Electrical design engineers Control system engineers Quality ensuring personnel Installation and commissioning engineers

ABB has acquired more than 30 years of satisfactory operation of Static Var Compensators. In 1972 the first SVC was commissioned for an electric arc furnace, which has been followed by a number of successful installations. Over the past decades ABB has supplied more than 400 SVC s in more than forty countries. By our count ABB has supplied more SVCs over the past years than have been supplied by all of our competitors combined. ABB is certified according to ISO 9001 and ISO 14001.

4 of 47

F900713008 Rev 2013-03-19

Unique flicker mitigation

The SVC Light almost instantaneously compensates the fast reactive power variations created by an Electrical Arc Furnace. Flicker mitigation up to 5-7 times has been verified by field measurements. Figure below shows one flicker registration from an actual SVC Light installation.
Hagfors 14-20/4-2000
7 6.5 6 5.5 5 4.5 Pst(10 min) 4 3.5 3 2.5 2 1.5 1 0.5 0 10:42 04-14-00 20:42 14-apr 6:42 15-apr 16:42 15-apr 2:42 16-apr 12:42 16-apr 22:42 16-apr 8:42 17-apr 18:42 17-apr 4:42 18-apr 14:42 18-apr 0:42 19-apr 10:42 19-apr 20:42 19-apr 6:42 20-apr

EAF in operation

Flicker generated by external sources

Tim e , da te

Arc Furnace operation improvement An ideal operation of an Electrical Arc Furnace requires a constant and stable voltage supply. The power to the furnace is sensitive to instable and large voltage variations. By means of a SVC Light, the voltage at the feeding network is stabilised and kept nearly constant during the whole power-on time. The melting power is the product of the arc current and voltage. With a stable voltage support at the furnace bus, the available melting power would be higher which results in a shorter tap-to-tap time. A reduced tap to tap provides increased production, energy savings, and reduced electrode consumption. The table below shows an example of increased furnace power evaluated from actual field measurements.

Description Tap no. Without SVC Light With SVC Light Difference Increased power

Boring 13 13.96 MW 15.88 MW 1.912 MW +13.7 %

Melting 15 21.72 MW 24.64 MW 2.914 MW +25.2 %

Red. melt. 13 17.94 MW 19.68 MW 1.742 MW +9.7 %

Superheat. 12 15.47 MW 16.98 MW 1.517 MW +9.8 %

5 of 47

F900713008 Rev 2013-03-19 References thus far

The following projects have been successfully installed or are under construction. Project Rating Application Order Hellsjn 3 MW Interconnection Hagfors 0-44 Mvar Flicker mitigation Gotland 50 MW Wind power Tjreborg 7 MW Wind power Directlink 180 MVA Interconnection Trier 0-38 Mvar Flicker mitigation Eagle Pass 36 MW Asynchronous Tie CSC 330 MW Interconnection Murraylink 200 MW Interconnection Tornio 0-164 Mvar Flicker mitigation Evron 0-36 Mvar Balancing Holly -80-110 Mvar Dynamic voltage support ZPSS 0-164 Mvar Flicker mitigation Ameristeel 0-64 Mvar Flicker mitigation Siam Yamato 0-120 Mvar Flicker Mitigation Martham 1 MW/15 min Energy Storage Kotobuki 0-64 Mvar Flicker mitigation GHC 0-164 Mvar Flicker mitigation Uni Steel 0-164 Mvar Flicker mitigation South Steel 0-175Mvar Flicker mitigation Abul Khair Steel 2x 0-110Mvar Flicker mitigation Bremen -32-48Mvar Flicker mitigation MGI 0-164Mvar Flicker mitigation Evraz 0-80Mvar Flicker mitigation POSCO Vina 0-144Mvar Flicker mitigation

1994 1997 1997 1998 1998 1999 1999 2000 2000 2001 2002 2003 2006 2006 2008 2008 2008 2009 2009 2010 2011 2011 2012 2012 2012

6 of 47

F900713008 Rev 2013-03-19

GENERAL AIMS OF A SVC LIGHT The electrical supply to large and varying loads in an industrial process raise a number of questions to which attention must be paid when load and system networks are designed. Large load variations of heavy-duty power equipment, e.g., in industrial steel plants such as electrical arc furnaces or rolling mills, have disturbing effects on the electric supply system. The disturbances are mainly caused by fluctuations in the reactive power and/or asymmetrical loading of the supply network. Although large electrical loads, as mentioned above, may have different behaviour in terms of cyclic and magnitude profiles, still some common characteristics could be noted: High ratings of individual loads, e.g., electrical arc furnaces or rolling mill connected to weak networks. Generation of flicker. Large and abrupt changes in active and reactive profiles. Generation of harmonic current components. Poor fundamental power factor. Voltage fluctuations. These disturbing factors lead to the concept of power stabilisation by means of a Flicker Compensator, sold under the product name SVC Light. The voltage stabilising effect of the reactive power compensation equipment leads to an appreciable productivity increase compared to a system running without an SVC Light. The main features and benefits of a SVC Light installation are: Ultra-fast stabilisation of works bus voltage. Excellent flicker reduction. Increased melting power of EAF. Lower electrode consumption. Decreased melting time. Harmonic reduction by electronics. Simple filters. Very low harmonic contents into the supply system. High power factor.

7 of 47

F900713008 Rev 2013-03-19

Compensator description The basic design of the circuit can be seen from the Single Line Diagram. A vital part of the circuit is the Voltage Source Converter (VSC). The converter is based on transistors, so called IGBTs (Insulated Gate Bipolar Transistor). The converter and its transistors are of the same basic type as those used for motor control in all kinds of applications for more than a decade. ABB has, however, extended the power range of the converter in order to be suitable for the Flicker Compensator application. A VSC is built up by an AC side, connected to the bus, and a DC side, connected to a capacitor bank. The capacitor provides enough energy for the converter to meet the most severe transients on the bus, which is an important source of flicker. The converter is connected to the bus via a phase reactor. This reactor is of the same air core type, which is used for conventional harmonic filters and SVCs. One advantage with the Voltage Source Converter is that it can instantaneously produce both capacitive and inductive reactive power. Since the furnace requires capacitive reactive power only, capacitor filter banks are connected in parallel with the converter, to provide a suitable reactive power offset. The filters banks support the converter in reducing harmonics on the furnace bus as well. Our IGBT valve contains as a minimum one redundant IGBT/phase. The advantage is in case of a IGBT failure, you will still be able to operate the SVC with full performance. If another IGBT fails (in the same stack), you can still run the plant without trip, but with slightly reduced performance. To conclude, the ABB IGBTvalve is designed for high availability.

Example: IGBT valve

8 of 47

F900713008 Rev 2013-03-19

Function of the compensator The function of the proposed Flicker Compensator can be described as follows: When the furnace starts, the need for reactive power will change from one instant to the next. If not compensated, this will lead to dramatic voltage variation on the furnace bus, leading to variation at the Point of Common Coupling (PCC) and from there, on to the rest of the network. With an SVC Light installed, however, the Compensators control system measures the power drawn by the furnace and provides the reactive power necessary to compensate the furnaces need. Technically, this is done by controlling the current through the phase reactor connected in series with the IGBT valve. Since the converter is normally controlled 1650 times per second, even the fastest variations can be counteracted. As a comparison, it can be mentioned that a conventional SVC system is controlled 100 times per second. This speed is afforded by the capability of the IGBT transistors used for switching in the converter. In addition, the high control speed of the converter allows compensation of several of the harmonics generated by the furnace. The reactive power rating of the Compensator has to be chosen to match the reactive power need of the furnace. Compensator components The compensator is built up of the following main components: VSC consisting of a water-cooled IGBT valve, DC capacitors, and series reactors. The IGBTs are cooled by means of water-to-water or a water-to-air heat exchanger. Filter capacitor banks. Control and protection equipment. MV Power distribution equipment.

9 of 47

F900713008 Rev 2013-03-19 The IGBT In the SVC Light, the voltage from the Voltage Source Converter is controlled to obtain exact and correct reactive current through the phase reactors. The VSC is designed around Insulated Gate Bipolar Transistors, IGBT.

Example: IGBT module To achieve the sufficient control range, the converter has stacks of series connected IGBTs for each switching function. IGBT redundancy guarantees high availability. If one of the series IGBTs fails, the valve is still fully operational. Replacements can be done during scheduled maintenance. IGBTs are extremely fast, highly dynamic electronic switches based on semiconductor technology. They are fully maintenance free and highly reliable. The same type of transistors are used for many different applications such as UPSs (Uninterruptible Power Supplies), drives, traction converters (locomotives, etc.) as well as SVC Light Flicker Compensator systems. The main advantages of the IGBTs are: High reliability, 100% factory tested Extremely fast Extremely powerful due to high blocking voltage and high rating currents. Capability to switch off the current during short circuit conditions in the load Compatible with tough environments due to the dust tight metal-ceramic housing. Absolutely maintenance free

10 of 47

F900713008 Rev 2013-03-19

Cooling system, water-water The VSC valve is water cooled by means of a cooling system consisting of an internal closed fine water system (supplied by ABB) and an external raw water system (supplied by the client). The fine water system and the raw water system are interconnected by a water-to-water plate heat exchanger (supplied by ABB) through which the heat losses are dissipated. The raw water system is an external system that cools the heat exchanger. To assure maximum performance of the cooling system the temperature and the quality of the incoming raw water should not exceed values specified in this specification. The incoming raw water should also be adequately free from particles in order not to clog the heat exchanger thereby avoiding frequent de-mounting and cleaning. To assure this, a mechanical filter should be fitted in the raw water circuit. To increase the availability of the system, the temperature and flow of the raw water is constantly monitored by the cooling system control.

Example: Cooling system, Water to water (valve in green) The VSC valve is water cooled by means of a cooling system consisting of a pump unit with built-in heat exchanger through which the heat losses are dissipated. The pump unit is equipped with one or two pumps, depending on the redundancy requirements. The fine water system consists of two circuits, the main circuit and the water treatment circuit.
11 of 47

F900713008 Rev 2013-03-19 The cooling liquid (deionized water) is circulated by the centrifugal pump through the main circuit to the thyristor valve and the heat exchanger. A strainer ensures that the cooling liquid doesnt contain any particles when it enters the VSC valves. Since the cooling liquid will be in contact with the electrical environment of the IGBTs the conductivity of the coolant must be low. To maintain the conductivity at a low level, a certain part of the cooling liquid is continuously flowing through the water treatment circuit that is connected in parallel with the main circuit. The water treatment circuit consists of a deionizer filled with deionising resin, an expansion vessel, a mechanical filter, and valves and monitoring instruments. Through the deionizer the conductivity decreases to below 1.0 S/cm. The filter after the deionizer purifies the cooling liquid from particles before it reaches the main circuit. The expansion vessel absorbs the volume changes caused by thermal fluctuations as well as possible leakage. The expansion vessel is pressurised with air. Important data points of the fine water system are constantly monitored. Alarm and trip signals are given for flow, temperature, conductivity and expansion vessel water level. The flow in the water treatment circuit is visually indicated. All parts of the fine water system in contact with deionising water are made of noncorrosive materials to minimise the risk of corrosion and electrolytic effects and to keep the proper characteristics of the water. All parts of the fine water system itself are mounted on a single skid for easy delivery and installation. A factory test of all functions is carried out before shipment where a pressure drop in the thyristor valve is simulated and the cooling system is tested regarding flow, pressure drop, vibrations, noise, signal interface and instrument settings.

Example: Cooling system visualization in HMI

12 of 47

F900713008 Rev 2013-03-19 Harmonic filters With the total harmonic generation in mind, it is important to tune and rate the needed filters ensuring that no situations exist where a resonance mode will be hit where any significant harmonic generation by the furnace is present. Specifically, the furnaces generate 2nd harmonic currents. In the absence of a 2:nd harmonic filter a dangerous resonance may result, leading to possible transformer saturation, etc. The 2:nd harmonic filter is damped in order to, in a wide band, filter out the harmonics around the 2:nd order. A special C-type configuration is here used for a reduction of the fundamental losses, which normally will be high in tuned damped filters for low harmonics. The other filters (3rd and high pass) are needed for the filtering of the harmonics generated by the furnaces and from the VSC converter. The total Mvar installed are divided between the different filters to yield the best performance. The proposed filter configuration will ensure that one of the main goals of the design work - that of avoiding the introduction of resonances - is met. The other main goal, to limit the harmonic distortion at PCC bus, will also be met with the proposed SVC Light configuration.

Example: Harmonic filter

13 of 47

F900713008 Rev 2013-03-19 Control and Protection System (MACH 2) In order to achieve todays and future demands, ABB has developed a fully computerised and microprocessor based control and protection system for industrial environment. The system is named MACH 2.

State of the art development with fully computerized protections gives: Easy maintenance Less cabling Easy overview Easy settings procedure Space saving

The MACH 2 system is the most advanced and highest performance control and protection system for high voltage applications on the world market. The system has gradually evolved from an unequalled installed base of High Voltage DC (HVDC), Static Var Compensator (SVC), SVC Light, and Series Compensation (SC) control systems. Important control functions are built around a host computer based on latest processors, a general-purpose processor and four high performance digital signal processors. Standard functionality with the following highlights: Redundant controller Sequence of Events Recorder (SER) with 1 ms GPS resolution TFR functionality Integrated protection functionality Remote Access through Firewall modem GSM/3G (subscription required, not included) Full graphical status presentation (HMI) Environmental proof controller cabinet (IP5X for MACH2 and IP2X for I/O) GPS clock time synchronisation Firewall protected electronic perimeter Access Point with file transfer server and malware protection software (subscription required, not included)
14 of 47

F900713008 Rev 2013-03-19

Redundant controllers The base concept of MACH2 control system consists of redundant (duplicated) controllers. Redundant controls systems have been requested by many customers e.g., power utilities over decades. The availability will be improved by running two controllers in parallel in order to achieve a seamless switchover, in case of malfunction. In addition, the redundant controllers give the incomparable possibility for software upgrades and/or fault tracing, without switching off the SVC Light. Maintenance of the controller can easily be performed with the other controller running the SVC Light . The MACH 2 system is built up of the following major parts: High-speed digital programmable SVC Light control system hosting the following: SVC Light control, e.g. Mvar, flicker, power factor control. SVC Light sequence control, e.g. start and stop of the SVC Light Protection system

The control computer uses the inputs from the nearby instrument transformers, evaluates the signals and controls the VSC with advanced algorithms to achieve the best possible results based on your needs. The control computer also handles the protection of the SVC Light. Examples of protections include, but are not limited to, are under voltage-, over voltage-, over current-, over load-, unbalance and earth fault protections. The programming is realized by using graphical block function.

Optical interface for thyristor valve (Valve Control Unit) The Valve Control Unit, VCU, can be seen as a fast I/O system to the IGBT valves. The design comprises one central unit per phase and a number of optical units. The Firing Control system is continuously sending control pulses to the central unit board in the valve control. In the central control unit the control pulses are converted to short firing pulses for firing of the IGBTs via the optical units in the VCU, light guides and Thyristor Control Unit (TCU) in the valve. The valve control system can be split up into the following main components: Valve Control Unit Light signal transmission. Thyristor monitoring.

15 of 47

F900713008 Rev 2013-03-19

Example: Control and HMI configuration Operator Work Station: The Human Machine Interface to the control system is implemented with an industrial type PC, called Operator Work Station (OWS), connected via a local LAN (Ethernet) to the control computer. The main features of OWS are: Full graphic status indications of the SVC Light SVC Light sequence control, e.g. start and stop of the SVC Light, reference settings, maneuvering of breakers and disconnect switches, etc. IGBT Monitoring. A graphic presentation of the actual status of each IGBT and valve control circuit boards. Supervision of each circuit board. Setting and monitoring of protections. Sequence Event Recorder. The Event, Alarm and Active faults are shown on separate lists with a time resolution of 1 ms. The time synchronisation is performed by a GPS-clock. Trend curves of voltages and reactive power. Debugging facilities for the main application programs e.g. sequence control. Standard Transient Fault Recorder (TFR) functionality with TFR evaluation tool.

16 of 47

F900713008 Rev 2013-03-19

Example: Picture from the OWS, SVC Light overview.

English language will be used for all text on the OWS in the base concept (options for other languages are available) The software running on the OWS for the operator control is InTouch program from Wonderware.

Example: Picture from the OWS, Sequence Event Recorder Event list

17 of 47

F900713008 Rev 2013-03-19

SECTION 2
DESIGN DATA The design of the compensator is based on the following data below. Modifications during project phase that is being requested/caused by the buyer may bring additional costs and may also have impact of time of delivery and performance of the plant. Such late modifications have to be compensated for.

Point of Common Coupling (PCC) data Short circuit capacity in Point of Common Coupling, PCC, (min/max) Rated voltage Frequency System grounding Step-down transformer data Rated power Rated voltage Impedance main tap (for performance) Short circuit impedance (span, for rating) Number of step-down transformers in parallel SVC bus data Rated voltage Earthing system Maximum operating voltage Impulse withstand voltage Power frequency withstand voltage EAF Transformer Transformer rated power Transformer impedance (based on rated power)
18 of 47

Minimum 6945 MVA, Max.(- to be defined) 220 kV, 3-phase + 5 , -5 % 50 1% Grounded

120/ 150 MVA 220 X*Y% / 33 kV (Steps to be defined) 12.5 % @ 150MVA 12.5 % @ 150MVA TBA? 1 pc

33 kV, 3-phase , +10, -10% Grounded 36 kV 170 kV 70 kV

150 MVA 8%

F900713008 Rev 2013-03-19 Transformer voltage ratio Main operative tap Impedance of main operative tap 33 kV/ 1.25-0.7kV 1.25 kV (To be defined) 8%

EAF Reactor (if applicable) Rated inductance Taps (percentage of rated impedance) Impedance of main operative tap XX mH - TBA 100-X-X-X-X-0 % - TBA 0.8 ohm

Load data, Electrical Arc Furnace Rated capacity Max EAF power Power factor Furnace reactance Furnace resistance Maximum short circuit power of EAF bay (downstream of MV bus) including EAF reactor and transformer Severity factor, Kst Max flicker without SVC Light , Pst (95%) 150 MVA (maximum) 96MW 0.73-0.78 p.u. (To be defined) 3.1 mOhm 0.22 mOhm 236 MVA 70 (consideration for 100 % scrap melting) < 2.6 p.u. (consideration for 100 % scrap melting)

Harmonic current generation from Electrical Arc Furnace in percent of rated current Harmonic order 2:nd 4:th 6:th 8:th 10:th Harmonic current (%) 3.5 1.3 0.6 0.4 0.5
19 of 47

Harmonic order 3:rd 5:th 7:th 9:th 11:th

Harmonic current (%) 7.5 4.6 1.4 0.5 0.5

F900713008 Rev 2013-03-19

Load data, Ladle Furnace Rated capacity Power factor 22 +20% MVA 0.8 p.u. (To be defined)

Harmonic current generation from Ladle Furnace in percent of rated current Harmonic order 2:nd 4:th 6:th 8:th 10:th Harmonic current (%) 2.5 1.4 0.3 0.2 0.1 Harmonic order 3:rd 5:th 7:th 9:th 11:th Harmonic current (%) 3.5 3.0 1.1 0.1 0.4

Power cables- To be defined EAF MV bus Lenght (m)* Dimension of cables: # parallel cables # phases area mm2 3 3 3 3 3 < 200 LF MV bus < 200 Stepdown trf MV bus < 200 SVC MV bus < 200 Misc MV bus N/A

*If >200m, the other parameters must be provided as well

20 of 47

F900713008 Rev 2013-03-19

Miscellaneous data (To be provided by the Buyer) Control voltage AC AC Supply Control voltage DC DC Supply Raw-water quality: Temperature Flow (minimum) PH Chloride Size of particles Environmental Data Maximum wind velocity Maximum out door temperature Minimum out door temperature Maximum relative humidity Control room temperature Valve room temperature Altitude above sea level Contamination Seismic intensity Zone factor: 0.15g, Importance factor 1.25 Sound requirements None 95 km/h + 50 C + 5 C 90-100 % +5 to +25 C +5 to +40 C < 1000 IEC 60815 (2008), very heavy Zone UBC 1997:2A +10 to +40 degrees Celsius 2000 l per minute 7-9 < 300 mg/liter < 0.25 mm 415/240 V, AC 10 % (to be defined) 3-phase 63 A + 1-phase 25 A (preliminary) (AC Load typically <15kVA) 110 V, DC 10 % (to be defined) 20 A (DC Load typically <1000W)

21 of 47

F900713008 Rev 2013-03-19

SECTION 3
TECHNICAL DATA OF MAIN EQUIPMENT VSC valve Rated power Rated current for the IGBT Connection Cooling Erection Indoor temperature Firing system IGBT type Standards Heat exchanger Cooling water (fresh) inlet Thyristor cooling water (fine) Water circuit Water quality for thyristor cooling Standard DC capacitors With internal fuses, discharge resistors (Within 10 minutes down to 75V), all-film technology, non-PCB, with star-point CT, assembled in racks and cans of stainless steel. Cooling Erection Standard VSC phase reactor coils Type Number of coils Rated power, 3-phase Rated current Cooling Erection Standards
22 of 47

87,5 Mvar 1531 A 1 x 3-phase Water Indoor +5 C to +40 C Fibre optic ABB IEC 61954

temp max 35 degrees C temp max 40 degrees C closed demineralised, deionised IEC

Natural Indoor IEC 60871-1

air-core 3x1 13 Mvar 1531 A Natural Outdoor IEC 60076-6

F900713008 Rev 2013-03-19

Filter circuits Harmonic order Rated voltage Rated power 2nd 33 x 3rd 33 y HPth 33 z kV Mvar

Filter capacitor With internal fuses, discharge resistors (Within 10 minutes down to 75V), all-film technology, non-PCB, with star-point CT, assembled in racks and cans of stainless steel. Cooling Erection Standard Filter reactors Type Number of coils Cooling Erection Standard Filter resistors Cooling Erection Standard Circuit breakers Type Rated voltage: Rated nominal current: Rated short-time withstand current Capacitive Switching Class Standard Natural Outdoor Latest IEC air-core 3x1 Natural Outdoor IEC 60076-6 Natural Outdoor IEC 60871-1

SF6, Outdoor (LTB/D recommended) 72 kV 2500 A 31 kA C2 IEC 62271-100

23 of 47

F900713008 Rev 2013-03-19

Please note that all above data on equipment are preliminary and may be subject to change at final design.

24 of 47

F900713008 Rev 2013-03-19

SECTION 4
SELLERS SCOPE OF SUPPLY One Static Var Compensator in accordance with the enclosed single-line diagram and layout. We have based our offer on inputs given. Modifications during project phase that are being requested/caused by the buyer may bring additional costs and may also have impact on time of delivery and performance of the plant. These extra costs will be back-charged to the buyer. The compensator regulation range will be from 0 to +175 Mvar reactive power generation. The SVC Light will be designed in accordance with ABB standard and IEC where relevant.

VSC valve equipment 3 1-phase, water cooled IGBT valve for dynamic control 3 1-phase set of DC capacitors 1 Valve control unit and IGBT monitoring. 1 Cooling system for the IGBT valve. The system comprises: two pumps (one as 100 % standby, equal ware) deionization equipment, valves, piping, control and meters equipment all mounted on a skid. Heat exchanger is also included. 1 Tool box for changing IGBTs 1 Set of valve grounding equipment capable of grounding 3 one phase valves at a time. VSC DC Capacitors 1 DC capacitor bank designed for required power. VSC phase reactors 3 Air-cooled reactors of air-core type, one coil per phase
25 of 47

F900713008 Rev 2013-03-19

Filters 3 Filter capacitor banks tuned to suitable harmonic orders.

Each capacitor bank comprises of the following: Capacitor units, frames, insulators and interconnection material. Air core reactors in series with the capacitor bank for tuning of the filter to the respective harmonic. 2 3 3 CT for capacitor unbalance protection (not for HP-filter) CT:s (one per phase) for harmonic filter overload protection (not for HP-filter) CTs (one per phase) for resistor overload protection (not for HP-filter)

The 2nd HF and HP filter includes damping resistors.

26 of 47

F900713008 Rev 2013-03-19

SVC Light Switchgear 2 Outdoor/ indoor breaker type LTB 72, SF6 3 Surge arresters 6 ECT or LEM

27 of 47

F900713008 Rev 2013-03-19 SVC Plant design The Plant design is performed based on industry standards such as IEC, IEEE, EN and ASCE in combination with electrical system data and environmental data. Necessary steel structures, busworks, connection materials, insulators, wall bushings etc. for installation of the SVC equipment and optical fibre control cables for connections within the SVC are included . Electromechanical dimensioning Due to the relatively high current levels in SVC plants aluminum busbars are frequently used and their ampacity is determined using IEEE 605 and environmental data. Mechanical dimensioning Calculation and dimensioning of the plant is based on the ASCE 113 substation structure design guide using the environmental data specified by the buyer in combination with electrical system design data as input. For seismic design IEEE 693 - Recommended Practice for Seismic Design for Substations is used. Steel structure The steel structures are highly standardized by ABB and used for every project, in order to provide for fast design time with proven reliability. As a consequence of this, European standard steel profiles are used all over the world. Typical qualities are S275 and S355, which has yield limits of 275 MPa and 355 MPa. The steel is hot dip galvanized with a procedure carried out according to EN ISO 1460/1461, which is equivalent with ASTM A123. The average weight of the zinc coating is not less than 610 g/m2 or 85 m.

28 of 47

F900713008 Rev 2013-03-19

Control and protection System A microprocessor based control and protection system type MACH 2 including: High-speed digital programmable SVC Light control and protection system (duplicated for improved availability. One computer as hot standby). Optical interface for IGBT valve (Valve Control Unit) Operator Work Station (OWS)

The following protections are integrated in the system. Over voltage and under voltage protections for SVC Light Overcurrent, and overload protection for VSC 2nd and 3rd filter bank Earth fault protection of SVC bus Overvoltage and unbalance protection for 2nd and 3rd filter bank

Services Project Administration including: Project Management Supply Management Quality Control Logistics

Engineering including: System Engineering; Main Circuit Equipment Design Harmonic Study Protection Coordination and Settings Electrical Engineering Software programming Mechanical Engineering; Design of mechanical details, such as steel structure, bus works, supports etc. Site layout, Foundation plan and Foundation load etc.

29 of 47

F900713008 Rev 2013-03-19

OPTIONS BELOW ARE NOT INCLUDED IN THE BASE OFFER. THEY CAN BE QUOTED SEPARATELY AT REQUEST.

Option, Spare parts Spare parts can be quoted separately with reference to section 7

Option, Remote Operation Work Station (RWS). The RWS will have the same functionality as the local OWS, enabling a remote control of the SVC LIGHT. In order to connect the RWS to the local PC LAN in the SVC Light control building, the LAN has to be extended by means of electrical/optical converters and optical fibre cables.
Remote Control Building Local Control Building

Remote OWS

OWS
LAN SWITCH

MACH 2

1 1 1

Industrial type PC. Optical fibre cable connection. The length of the fibre optical cable is limited to 200 m. Software with applicable licences.

Option, OWS Language The language of the HMI and eventlists is in English language. Other languages can be supplied upon request.

Option, Built-in flicker meter ABB can provide a built-in flicker meter, normally connected to the Point of Common Coupling. The flicker level is evaluated and presented continuously at the HMI screen. The flicker meter is fully compatible with IEC recommendations.

30 of 47

F900713008 Rev 2013-03-19

Option, Gate Way Station (GWS) A Gate Way Station, GWS, could be connected to the local area network, LAN. The GWS will handle the communication with a remote SCADA system if such a system is installed at the site. The output of the GWS is a serial RTU protocol, e.g. RP570 (ABB), DNP3.0 (Harris) or IEC 870-5-101. The signals are available in the SVC Light control room. 1 1 Gate Way Station Software with applicable licences. Design, installation, testing and documentation.

Option, basic FACTS On-Line Support ABB can offer service connected to the FACTS On-Line support. We offer different levels of services including phone support, corrective maintenance, preventive maintenance, passive remote access and active remote access. We can provide 24h access of dedicated engineers who can monitor your SVC Light from remote, helping to trouble-shoot if requested With Remote Access Service (RAS) function, it is possible to access the local PC LAN from remote via modems over an ordinary telephone line. For this, a modem is connected to the OWS. From a remote PC it is then possible to call the OWS PC over a telephone line and log in on the OWS. From the remote PC it is for instance possible to: Retrieve event lists. Retrieve trend curves. Retrieve TFR records. Get status from the SVC Light via InTouch *) Enables ABB personnel to trouble-shoot the SVC Light from remote if desired.

Telephone connection and fees are not included in ABB scope. The hardware for the functionality mentioned above is included in the base concept. It is also possible to create a dedicated SVC Light homepage, and through the Internet retrieve above information. This option will bring some additional costs.

31 of 47

F900713008 Rev 2013-03-19

SECTION 5
BUYERS SCOPE OF SUPPLY

The following items (but not limited to these) are included in the buyers scope of works: Civil design. Supply Buyers civil design to ABB for information Civil work. Assure that the SVC site does not contain any magnetic material Assure the ground is correctly levelled Control and SVC Light building with heat and air-conditioning systems and EMC safe valve room. Cooling water Grounding material below ground. Grounding calculations except Cu-wire dimensioning, if required by buyer. Outdoor lightning protections. Design EAF RC-circuit based on harmonic content from VSC. If not, there is a risk of resistor heating. To avoid problems the number of parallel cables shall be reduced and harmonic pattern for VSC must be included in the design.(Typical figures for RC-circuit is 50ohm, 0,2uF. Please note that this indicative figure cannot be taken for granted) Busbar and connection systems for the breakers. Security fences around the SVC Light and circuit breakers (if applicable). Proper interlocking and responsibility for setting up rigid safety instructions and procedures, for personal safety. Provision of suitable interlocking and labels, ensuring safe working conditions. Lighting HV/MV cables (including terminations, cable markings and suitable protection by surge arresters) LV control and power cables within the SVC Light area. ABB will specify what cables to use, both size and type of screen. AC/DC auxiliary power supply (separate supply for breaker control circuits). These supplies shall be provided into the control room. Auxiliary (+/-) 24 VDC for ECT/LEM in EAF bay. Installation of ECT/LEM in furnace feeder. Please note that all EAF power cables shall be fitted in a circular hole with diameter 268mm/phase, and that EAF cables are fully insulated (ABB needs to be involved in the final decision of the location of ECT/LEM). If buyer needs a larger cross section area, ABB will charge extra for additional LEMs. Erection and erection material. Current signal from LF, SVC feeders (upstream CB) and Step-down transformer feeders wired to the SVC control system.

32 of 47

F900713008 Rev 2013-03-19 Voltage signal from 33 kV busbar and from PCC for SVC Light control and protection. Spare parts for above items.

33 of 47

F900713008 Rev 2013-03-19

SECTION 6
TESTS AND GUARANTEED PERFORMANCE Factory testing All main components of the compensation system are subjected to factory routine tests in accordance with ABB standard test procedures. Performance testing After the furnace(s) and SVC Light have been started up, the power supply parameters will be determined and the following tests will be carried out by ABB: Power factor performance test. Flicker performance test Harmonics performance test Voltage unbalance test Preconditions The guaranteed performance of the proposed SVC Light is based on data and preconditions given in this specification with its annexes. The EAF and LF:s should be operated according to information given in Section 2, Design Data. A higher value for the furnace reactance would give a better safety margin for the flicker. Minimum short circuit power at PCC: as declared in Design Basis Data Section 2. The network impedance is inductive and linear with the frequency. During the tests, the same furnace operation procedure should be present with and without SVC Light. Maximum active power in the EAF is 150 MVA. The furnaces shall be operated under normal conditions, no electrode breakage, switching of transformers and with normal raw mineral quality and mix. Measurement equipment, which will be used, will be brought by ABB and after tests taken back by ABB. Power factor performance tests Evaluated by recording kWh and kvarh at the incoming feeders with the SVC Light in full operation.
cosphimean kWh kvarh2 kWh2

(24 hours average)

Duration of test: 24 hours. Equipment to be used: kWh and kvarh meters (furnished by the Buyer). Measurements performed by the Seller.
34 of 47

F900713008 Rev 2013-03-19 Harmonics performance test Voltage: Measured by means of a harmonic analyser at PCC. The total harmonic voltage distortion is defined as: THD =

(U )
n2 1

19

Un

Duration of test: 24 hours. Equipment to be used: Harmonic analyser (furnished by ABB) Note: The existing background harmonics, measured without the furnaces and SVC Light, will be linearly deducted from the total voltage distortions. For voltage distortion, we have applied the calculation method Harmonics (G) described in IEC 61000-4-7. The harmonic voltage distortion is defined as a 95% probability value (10 min). Flicker performance test The flicker and voltage variations on the PCC busbar with the furnace and with/ without SVC in operation is measured and registered. The measurements are performed with the UIE/IEC flicker meter. The flicker and voltage variation is defined as a 95% probability value (10 minutes). Background values are linearly deducted from the measured values. As an alternative, simultaneously the arc furnace and the sum of the arc furnace and SVC currents are measured. The level of voltage fluctuations causing flicker with and without compensation are evaluated from the measured currents. The flicker reduction factor is evaluated. Duration of the test: minimum 24 hours period. Equipment to be used, UIE/ IEC flicker meter and data acquisition computer (furnished by ABB). Unbalance test The voltage unbalance is measured at the PCC. The unbalance voltage without the furnace in operation is deducted from the measured value. Duration of the test: 24 hours. The unbalance is measured as 95% probability, 10 minutes mean value. Equipment to be used: Unbalance measuring instrument (furnished by ABB) Guaranteed Performance Based on the Design Data and preconditions, the load and the SVC in normal operation, the Seller guarantees the following performances. The minimum short circuit power at PCC is as declared in Design Basis Data Section 2:

35 of 47

F900713008 Rev 2013-03-19 Performance parameter Power factor Flicker, Pst (95%) Flicker, Plt (95%) Voltage Unbalance (95%) Total Voltage Distorsion, THD (95%) Individual harmonics(voltage) (95%) Guaranteed value 0.95 p.u.lag 0.6 *1) 0.5 1.0% 2.0% 1.5%

*1) Note the Pst of 0.6 is the emission level which considering zero background flicker and preconditions as per Design Basis data Section 2.

36 of 47

F900713008 Rev 2013-03-19

SECTION 7
SPARE PARTS AND SPECIAL TOOLS (NOTE! Quoted separately) The following spare parts and special tools are recommended by ABB, and they are included in our offer as an option.

Pcs 9 5 11 1 1

Description

VSC valve
IGBT. Diode. Light Guide Set of Pex tubes Set of O-rings.

IGBT Valve Control


1 1 1 Valve control central unit, PS900A Valve control 16 ch optical I/O, PS905A Valve Control Backplane, PS916

Cooling equipment
2 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 Service kit for pump, 8810026 Deraeration valve, 3120112 Grease gun, 9480001 Grease cartridge, 9420002 Contactor for pump Overvoltage protection for pump Aux. relay SL180724 Aux. relay MR 11-pol DC/DC converter PS950-card, 6470001 Temperature PT-100 Sensor, 6220011 Temperature PT-100 Transmitter, 6360036 Pressure transmitter exp.vessel, 6240016 Level switch, 6210058 Conductivity transmitter, 6110040 Conductivity sensor Filter cartridge in proc. circuit, 2500015 Deionizer filter compl. with resin, 190126

Electronic boards for control


1 1 1 1 1 1 1 High performance DSP board, PS802 CAN/HDLC Optical Bridge, PS831 Switch control board, PS850E 110/125V Digital input board, PS851 Digital output board, PS853 AC Voltage Measurement board, 4 kHz, PS841 AC Current measurement board, PS846(5A) 37 of 47

F900713008 Rev 2013-03-19


1 1 1 1 1 1 High performance I/O DSP board, PS861 Isolation Amplifier Board, PS862G Isolation Amplifier Board, PS862XQ Bus extension & termination board, PS873B Power Supply Unit, PS896E 24V DC, 30W Electrical and optical communication board PS932

Control & Protection Computers


1 1 1 1 MACH computer excl. SG102 board SG102 Optical Interface Board OWS/SER computer Computer maintenance kit

Panel equipment
1 1 1 Panel ventilation fan Exhaust filter (5 pcs) Fan cover

Power supplies Power Supply Unit, QUINT-PS-1AC/24VDC/20A Capacitors

1 1 1 1 2

Capacitor units for FC2 (C1) Capacitor units for FC2 (C2) Capacitor units for FC3 Capacitor units for HP DC Capacitor LEM LEM (current transformer)

Special tools and instruments


1 1 Portable Capacitance Bridge Combiflex tool set

38 of 47

F900713008 Rev 2013-03-19

SECTION 8
SELLERS SUPERVISION OF ERECTION, COMPLETE COMMISSIONING AND ACCEPTANCE TESTS Responsibilities of the Buyer and Seller during erection and commissioning: Sellers responsibilities The Seller will undertake supervision of the erection and complete commissioning of the SVC. The terms and conditions of these services are in accordance with the following: The ABB erection Supervisor shall, during the installation work period, provide technical assistance to the client within the following areas: Interpretation of the installation requirements from drawings and installation manuals etc. The instructions will be given in English. Co-ordination of the communications between the site and the ABB Home Office/ Suppliers when technical clarifications are required. To provide technical instruction during the erection period. The Seller shall be responsible for correctness of instructions given by Sellers personnel during erection. Commissioning and training ABB will perform complete commissioning. On site training (1-2 days) performed by commissioning engineer on site. This training will provide basic skills in maintenance and operation of the SVC. Buyers responsibility The Buyer shall send to ABB there civil drawings for information. The Buyer shall inform ABB when the civil work is completed and the equipment is on site. The ABB checklist Inspection of Site work shall be filled in, signed and sent back to ABB together with pictures which show the work performed. Based on this information ABB will together with the Buyer, decide the start date of erection work. A notice from Buyer of minimum 30 working days is required depending on VISA and work permit procedures in the Buyers country and available ABB resources. The Buyer is responsible for manpower at site. A site manager from the Buyer shall be present during the erection. The site manager shall be in power to make decisions in matters about the erection work. The Buyer is responsible for the installation equipment and the tools necessary for the installation work. The erection work will be performed by the Buyers own installation crew.
39 of 47

F900713008 Rev 2013-03-19 The Buyer is responsible for coordination and planning of the actual site works, according to the instructions from Seller. The buyer is responsible for that relevant safety, security, health and environmental rules and regulations are implemented and followed by all personnel at site.

Others The buyer shall assist ABB with VISA and Work Permit applications to be able to send personnel to site. The Seller will send special instruments required for the commissioning, performance and guarantee test for use by the Commissioning Engineers. These special instruments shall be returned back to Seller at the end of commissioning. The buyer shall assist in completing the custom formalities applicable for bringing and sending back the special equipment. The SVC will not be allowed to be taken into commercial operation unless the Buyer has taken over the responsibility of the SVC by signing the Provisional Acceptance Certificate or Taking over Certificate.

Man weeks of Sellers supervision engineering for erection, commissioning and performance test Item 1 2 3 Specialty Erection supervision (+ valve specialist) Commissioning Performance test No. of Sellers personnel 1-2 2 1 Duration ( week ) 9 6 1 Man-week 11 12 1

A working week is 40 hours over five days. If overtime is needed the Seller has the right to charge buyer additional cost. Overtime: 200 EUR/hour Work free day: 270 EUR/hour

The commissioning will NOT start until the erection is fully completed. If the commissioning can not start in direct connection to the erection work the Buyer must inform ABB about a new requested start date for the commissioning. The ABB checklist Commissioning start shall be filled in , signed by the Buyer and sent back to ABB. Based on this information ABB will decide, together with the Buyer, the commissioning start date. A notice from Buyer of minimum 30 working days is required depending on VISA and work permit procedure in the Buyers country and available ABB recourses.
40 of 47

F900713008 Rev 2013-03-19 It is considered that the ABB personnel can stay and perform work at site without interruptions. It is considered one two-way ticket for each person that will be sent to site. If the above work is delayed or interrupted due to Buyer and more trips are required, the Seller has the right to charge Buyer for direct cost + 10 % handling fee. Time estimations above are realistic based on Sellers experience. However item 1 is outside sellers control, since the Buyer is responsible for the installation crew. Item 2 and 3 are considered lump-sum. If delays on item 1, 2 and 3 are caused by the Buyer, the Seller has the right to charge buyer 1240 EUR per additional manday (8 hours). If Item 2 and 3 are performed at shorter time than above no related price deduction will be applied. Responsible site manager from the Buyer shall sign all time sheets for the supervisor of the installation work. Performance test activity can take place separately at other time, for instance after trial operation period. A notice from Buyer of minimum 30 working days is required depending on VISA and Work Permit rocedure in the Buyers country and available ABB recourses.. Seller has considered separate travel cost for this purpose.

Definition: Seller = ABB SVC supplier, Buyer = Not the SVC supplier, i.e. OEM the end-user or related subcontractors etc.

41 of 47

F900713008 Rev 2013-03-19

SECTION 9
DOCUMENTATION All documents will be delivered in electronic format when available. Paragraph 1 - Basic design documents Within 1 month after the contract comes into force, the Seller shall submit for approval the following documents: Single-line diagram Protection block diagram Design Basis Document (to be completed by Buyer) SVC layout Case marking proposal PAC draft /TOC draft Comments shall be made by Buyer latest within 2 weeks after received documents; otherwise the documents are deemed accepted. For modifications to already approved documents ABB will be entitled to time and money.

Paragraph 2 - Design report and interface Within 3 months after the contract comes into force, documentation of the design calculations and interface of the SVC will be submitted to the Buyer. Drafts of the following documents should be submitted: Main Component Design Report Interface diagram (to be completed by Buyer within two weeks) Paragraph 3 - Civil design information Within 4 months after Seller has received the approved SVC layout and Single-line diagram from Buyer, the Seller shall submit the following documents as base for the civil design: Busbar System data Heating/Ventilation Cable Trenches Foundation Plan Foundation Data SVC building Grounding Plan below ground with required Cu wire dimension

42 of 47

F900713008 Rev 2013-03-19

Paragraph 4 - Grounding and cable information Within 5 months after the Seller has received approved SVC layout and Single-line diagram from the Buyer, the Seller shall also submit the following information: Grounding Plan & Grounding Details List of materials for grounding Preliminary cable list Grounding Plan & Grounding Details above ground Paragraph 5 - Installation documentation The Seller shall submit 1 CD of the Installation Documentation Manuals at FOB delivery, including the following documents. Final drawings according to Paragraph 1 - 3. General instructions for installation Branch drawings including material lists Steel structure drawings Detail drawings (connectors, bus bars, bushings, insulators, labels etc.) Dimension & Rating plate drawings of High Voltage equipment Installation manuals for High Voltage equipment Installation of Control Cables Assembly drawing of Control Panels Cable table & Connection table Paragraph 6 - Plant documentation The Seller shall submit 1 CD with Plant Documentation within one month after delivery FOB, including the following documents: Applicable documents according to paragraph 1 - 5. Descriptions & Instructions Protection setting list Operation-, maintenance- & fault tracing manuals Control System description Component Lists Connection Tables Plant Circuit & Software diagrams Factory routine test reports

43 of 47

F900713008 Rev 2013-03-19

Paragraph 7 - Language The language of all documentation is English. Paragraph 8 - As-built documentation 2 sets of paper copies of the as-built documents and one CD that have been modified after site erection and commissioning will be delivered to the Buyer 1 month after completion of commissioning and testing.

44 of 47

F900713008 Rev 2013-03-19

SECTION 10
PROJECT TIME SCHEDULE- PRELIMINARY

45 of 47

F900713008 Rev 2013-03-19 SINGLE LINE DIAGRAM- PRELIMINARY

46 of 47

F900713008 Rev 2013-03-19

LAYOUT- PRELIMINARY

47 of 47

S-ar putea să vă placă și