Bullheading procedures are produced with reference to the particular circumstances at the rig site. For example, during a workover operation a procedure for bullheading will be drawn up along the following lines: Calculate the surface pressure that will cause formation fracturing during the bullheading operation. Calculate the tubing (or drill pipe) burst pressure as well as casing burst (to cover the possibility of tubing/drillpipe failure during the operation). Calculate static tubing head (or drillpipe) pressure during bullheading. Slowly pump fluid down the tubing/drillpipe. Monitor pump and casing pressure during the operation. As an example, consider the following well which is to be killed by bullheading brine down the tubing: Data Depth of formation/top perforation = 10,000 feet TVD Formation pressure, EMWpf = 9 ppg Formation fracture pressure, EMWpfb = 14 ppg Tubing 41/2", N80,11.6# Internal capacity = 0.0155 bbls/ft Internal yield = 7,774 psi Shut-in tubing head pressure = 3,650 psi Gas density = 0.1 psi/ft Calculations Total internal volume of tubing = 10,000 ft x 0.0155 bbls/ft = 155 bbls Maximum allowable pressure at pump start up = (14 ppg x 10,000 ft x 0.052) - (0.1 psi/ft x 10,000 ft) = 6,280 psi Maximum allowable pressure when the tubing has been displaced to 9ppg brine = (14 ppg - 9 ppg) x 10,000 ft x .052 = 2,600 psi Static tubing head pressure at initial shut-in = 3,650 psi Static tubing head pressure when tubing has been displaced to brine = 0 psi (i.e. the tubing should be dead) The above values can be represented graphically (as shown in the Figure A9.1 below). This plot can be used as a guide during the bullheading operation. 337

Procedimentos Bullheading so produzidos com referncia s circunstncias particulares na plataforma. Por exemplo, durante uma operao de workover um procedimento para bullheading ser elaborado com as seguintes linhas: Calcular a presso da superfcie que vai causar a formao de fratura durante a operao bullheading. Calcular presso de ruptura do tubo (ou tubos de perfurao), bem como invlucro burst (para cobrir a possibilidade de falha do tubo / drillpipe durante a operao). Calcular presso esttica na cabea da tubulao (ou drillpipe) durante bullheading. Bombear o lquido lentamente para baixo da tubulao / drillpipe. Bomba e o monitor de invlucro de presso durante a operao. Como um exemplo, considere a seguinte situao de salmoura que deve ser morta por bullheading:

Dados Profundidade de formao / top perfurao = 10.000 ps TVD Presso de formao, EMWpf = 9 ppg Presso de fratura formao, EMWpfb = 14 ppg Tubing 41/2 ", N80, 11,6 # capacidade interna = 0,0155 barris / ft Rendimento interno = 7.774 psi Shut-cabea da tubulao de presso = 3650 psi Densidade do gs = 0,1 psi / ft

Clculos volume interno total de tubulao = 10.000 ps x 0,0155 bbls / ft = 155 barris Presso mxima admissvel na bomba de arranque = (14 ppg x 10.000 ps x 0,052) - (0,1 psi / ft x 10.000 ps) = 6.280 psi Presso mxima admissvel quando o tubo foi deslocada para salmoura 9ppg = (14 ppg - 9 ppg) x 10.000 ps x 0,052 = 2.600 psi presso esttica na cabea da tubulao inicial fechado-in = 3.650 psi presso esttica da cabea de tubulao quando tubulao foi deslocada para salmoura = 0 psi (ou seja, a tubulao deve ser morto) Os valores acima podem ser representados graficamente (como mostrado na figura abaixo). Esta trama pode ser usada como um guia, durante o bullheading operao.

S-ar putea să vă placă și