SECTION 01700 CLOSE-OUT REQUIREMENTS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

SUBSECTION INDEX Part 1 - General

DESCRIPTION

1.01 1.02 1.03 1.04 1.05 1.06

Requirements Included Record Document Submittals Operating and Maintenance Instructions Final Cleaning Continuing Inspection Delivery Turnover Inventory Requirements

DATE JOB/EWO

Part 2 - Products (Not Used) Part 3 - General (Not Used)

REV. NO.

PART 1 - GENERAL 1.01 A. Requirements Included Close-out requirements include those general requirements in preparation for Initial Acceptance, final payment and normal termination of the contract. Specific requirements for individual units of work are specified in the technical sections of these specifications. Related Requirements: 1. 2. 1.02 A. Section 01340: Shop Drawings, Samples and Miscellaneous Submittals. Section 01720 Record Documents.

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

B.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Record Document Submittals Immediately prior to the time of Initial Acceptance, complete the record documents in accordance with the requirements of Section 01720 "Record Documents", and submit to Saudi Aramco for acceptance. The record documents are as follows: 1. 2. 3. Record Drawings As-Built Drawings Record Specifications
DWG. TYPE PLANT NO. INDEX DRAWING NO.

Date:

B.

Section 01700
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC K55 A

VE-417361 BI-25-00002

RABIGH

SAUDI ARABIA

15-Sep-07

JOB/EWO#

1 OF 4

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.

SAUDI ARAMCO OIL COMPANY


THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

CERT

4. 5. 6. C.

Record Shop Drawing Information Record Miscellaneous Submittals Record Samples

ENGG

DESCRIPTION

The documents shall be organized in a logical order, bound or filed, ready for continued use and reference. Immediately prior to the time of Initial Acceptance, Saudi Aramco will meet with the Contractor at the site, and will determine which of the record samples maintained by the Contractor during the progress of the work are to be submitted. Any samples not required by Saudi Aramco shall be properly disposed of by the Contractor. Operating and Maintenance Instructions Arrange for each installer of work requiring continuing maintenance or operation to meet with the operating personnel at the project site to provide basic instructions needed for proper operation and maintenance of the entire work. Include instructions by manufacturer's representatives where installers are not expert in the required procedures. Review maintenance manuals, record documentation, tools, spare parts and materials, lubricants, fuels, identification system, control sequences, hazards, cleaning and similar procedures and facilities. Review maintenance and operations in relation with applicable guarantees, warranties, agreements to maintain, bonds, and similar continuing commitments.

D.

DATE JOB/EWO

1.03 A.

REV. NO.

B.
DISCIPLINE ENGINEER

__ ________ _ DATE: ________

C.

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

D.

CONSTRUCTION AGENCY
________________ DATE:

1.04 A.

Final Cleaning Special cleaning for specific units of work shall be as specified in the various technical specifications. Provide final cleaning of the work at the time indicated, consisting of cleaning each surface or unit of work to the normal "clean" condition expected for a firstclass building cleaning and maintenance program. Comply with manufacturer's instructions for cleaning operations. As a minimum, the following are examples of the cleaning levels required. 1. 2. Remove labels which are not required as permanent labels. Clean exposed hard-surfaced finishes, including metals, concrete, painted surfaces, special coatings, and similar surfaces, to a dirt free condition, free of dust, stains, films and similar noticeable distracting substances.
DWG. TYPE PLANT NO. INDEX DRAWING NO.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

B.

Date:

Section 01700
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC K55 A

VE-417361 BI-25-00002

RABIGH

SAUDI ARABIA

15-Sep-07

JOB/EWO#

2 OF 4

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.

SAUDI ARAMCO OIL COMPANY


Except as otherwise indicated, avoid the disturbances of natural weathering of exterior surfaces. Restore reflective surfaces to original condition. 3. Remove debris and surfaces dust from limited-access spaces including trenches, equipment vaults and similar spaces. Clean project site including landscape development areas, of litter and foreign substances. Sweep paved areas to a broom-clean condition; remove stains, petro-chemical spills and other foreign deposits. Rake grounds which are neither planted nor paved to a smooth, even textured surface.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

4.
DESCRIPTION

C.

DATE JOB/EWO

Except as otherwise indicated or requested by Saudi Aramco, remove temporary protective devices and facilities which were installed during the course of the work to protect previously completed work during the remainder of the construction period. Comply with safety standards and governing regulations for cleaning operations. Do not burn waste materials at the site, nor bury debris or excess materials on the property, nor discharge volatile or other harmful or dangerous materials into drainage system. Remove waste materials from the site and dispose of. Continuing Inspection Where required by special guarantee, warranties, agreements to maintain, workmanship bonds and similar continuing commitments, comply with requests to participate in inspections at the end of each time period of such continuing commitments. Delivery Turnover Inventory Requirements Upon product delivery the Contractor shall: 1. Conduct tests and operational checks to ensure serviceability of property to be transferred. Verify cleanliness and overall condition as acceptable. Prepare the inventory list on form furnished by Saudi Aramco. Coordinate with Saudi Aramco to obtain forms, and to ensure completeness and accuracy of the TRANSFER/CUSTODY document. Designate a contractor representative authorized to sign the TRANSFER/CUSTODY document upon completion of the turnover inventory.
Section 01700

D.

REV. NO.

DISCIPLINE ENGINEER

1.05 A.

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

1.06 A.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

2. 3. 4.
Date:

5.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC K55 A

VE-417361 BI-25-00002

RABIGH

SAUDI ARABIA

15-Sep-07

JOB/EWO#

3 OF 4

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.

SAUDI ARAMCO OIL COMPANY


Note: Property considered to be unclean, unserviceable and/or unfit for use will be rejected by Saudi Aramco.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

Part 2 - Products (Not Used) Part 3 - General (Not Used)

DESCRIPTION

- END OF SECTION -

REV. NO.

DATE JOB/EWO

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

Section 01700

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC K55 A

VE-417361 BI-25-00002

RABIGH

SAUDI ARABIA

15-Sep-07

JOB/EWO#

4 OF 4