Sunteți pe pagina 1din 59

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK

( C ) HUN BIN, DAERAH TIMUR LAUT SUMMARY OF TENDER BILL NO. 1 2 3 4 5 6 7 8 DESCRIPTION OF WORKS GENERAL ITEMS SITE CLEARANCE AND DEMOLITION WORKS EARTHWORKS DRAINAGE PAVEMENT WORKS ROAD FURNITURE GEOTECHNICAL WORKS STRUCTURES 8.1 BRIDGE WORKS 8.1A TEMPORARY CROSSING 8.1B PILING WORKS 8.1C SUBSTRUCTURE 8.1D SUPERSTRUCTURE 8.1E APPROACH ROAD AND PAVEMENT 8.1F MISCELLANEOUS WORKS 8.2 CULVERT & VEHICULAR UNDERPASS 8.2.1 TEMPORARY CROSSING 8.3 PEDESTRIAN BRIDGE TRAFFIC MANAGEMENT AND CONTROL ENVIRONMENTAL PROTECTION WORKS ROUTINE MAINTENANCE WORKS PROVISIONAL SUM PAGE BQ1-1/4 - BQ1-4/4 BQ2-1/5 - BQ2-5/5 BQ3-1/4 - BQ3-4/4 BQ4-1/6 BQ4-6/6 BQ5-1/16 - BQ5-16/16 BQ6-1/6 - BQ6-6/6 BQ7-1/9 - BQ6-9/9 AMOUNT (RM) . . .. . . . .

BQ8.1A-1/4 - BQ8.1A-4/4 BQ8.1B-1/7 - BQ8.1B-7/7 BQ8.1C-1/6 - BQ8.1C-6/6 BQ8.1D-1/14 - BQ8.1D-14/14 BQ8.1E-1/4 - BQ8.1E-4/4 BQ8.1F-1/3 - BQ8.1F-3/3 BQ8.2-1/9 - BQ8.2-9/9 BQ8.3-1/12 - BQ8.3-12/12 BQ9-1/4 - BQ9-4/4 BQ10-1/5 - BQ10-5/5 BQ11-1/7 - BQ11-7/7 BQ12-1/3 - BQ12-3/3

N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A .

9 10 11 12

TOTAL AMOUNT

RINGGIT MALAYSIA: .. Completion period:.. Weeks Contractor Signature: Name: Company Stamp: Date: Witness

. . . . . .

Signature:. Name:.. NRIC No.:

Date:

* Delete where not applible

SUMMARY - 1/1

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRKJ ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 1 - GENERAL ITEMS ITEM NO. 1.1 1.1.1 DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT RM SEN

CONTRACTUAL REQUIREMENTS Performance Bond a) Banker's/ Insurance/ Financial Institution Guarantee* b) Performance Guarantee Sum* sum sum

1.1.2 1.1.2.1

Insurances Insurance of the Works including Insurance Against Personal Injuries and Damage to Properties SOCSO/ Workmen Compensation Insurance SO/PD'S REQUIREMENTS Accommodation for the SO/PD's Staff Establishment, maintenance and removal of office including fittings and furnitures ans listed in Appendix `1F' of the Specification** a) Alternative I - JKR Design Type A/B/C/D/E/F/G** b) Alternative II - Relocatable Type (new/used)* c) Alternative III - Rental of shoplot* Establishment, maintenance and removal of laboratories Services for the SO/PD's Staff Provision of suitable transport services as listed in Appendix `1C' of the Specification a) ___ no type ___ (___ vehicle months)# b) ___ no type ___ (___ vehicle months)# Operation and maintenance of vehicles a) ___ no type ___ (___ vehicle months)# b) ___ no type ___ (___ vehicle months)# Equipments for use by the SO/PD's Staff Provision and maintenance of laboratory equipments as listed in Appendix `1D' of the Specification Provision and maintenance of office equipments as listed in Appendix '`1E' of the Specification** a) 1 no. computer b) ___ no. photocopy machine c) 1 no. digital camera d) ___ no. fax e) 1 no. printer Carried to Collection

sum sum

1.1.2.2 1.2 1.2.1 1.2.1.1

sum sum sum sum N/A

1.2.1.2 1.2.2 1.2.2.1

sum sum

N/A N/A

1.2.2.2

sum sum

N/A N/A

1.2.3 1.2.3.1

sum

N/A

1.2.3.2

sum sum sum sum sum

N/A N/A

* Tenderer to delete where not applicable ** Designer to decide which is applicable # Duration to be inserted by tenderer based on tendered period

BQ1 - 1/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRKJ ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 1 - GENERAL ITEMS ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT RM SEN

f) ___ no. scanner g) ___ no. _____ 1.2.4 1.2.4.1 1.2.4.2 1.2.5 1.2.6 1.2.6.1 1.2.6.2 1.2.6.3 Attendance for the SO/PD's staff Drivers (____ man month)# Laboratory assistants (____ man month)# Setting out, levelling and checking of all Works Miscellaneous Project sign boards (2 no.)** Progress photograph (12 months)# Performance report comprising 5 sets** of progress report, project report and quality control report (12 months)# Provide and update the Works Programme using Master Programme to produce Critical Path Method (CPM) and Works Breakdown Structure (WBS) etc. including supply of software as specified in Appendix `1G' As-built drawing including periodic updating as specified in Appendix `1H' Clearing up of site on completion License security services Quality Assurance Plans CONTRACTOR'S REQUIREMENTS Establishment, maintenance and removal of accommodation and buildings Office Stores and workshops Workmen accommodations

sum sum

N/A N/A

sum sum sum

N/A N/A

sum sum

sum

1.2.6.4

sum

1.2.6.5

sum sum sum sum

1.2.6.6 1.2.7 1.2.8 1.3 1.3.1

1.3.1.1 1.3.1.2 1.3.1.3

sum sum sum

Carried to Collection

* Tenderer to delete where not applicable ** Designer to decide which is applicable # Duration to be inserted by tenderer based on tendered period

BQ1 - 2/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRKJ ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 1 - GENERAL ITEMS ITEM NO. 1.3.2 DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT RM SEN

Temporary works** a) access and haul roads, b) hoardings, c) temporary drainage

sum

1.3.3 1.3.4

Supervision (___man-months)# Mobilisation and demobilisation of construction plants and equipments excluding piling and specialise plants OCCUPATIONAL SAFETY AND HEALTH REQUIREMENT** Occupational safety and health officer (__ man month)# Health and safety report (___month)# DESIGN AND BUILD ELEMENT** Design fees Supervision fees (___ man-months)# Independent Checkers Structural Geotechnical Road safety Data Collection Detailed Engineering survey Traffic survey Soil investigation PAYMENT FOR LEVY TO CIDB Allow a Provisional Sum for payment to Lembaga Pembangunan Industri Malaysia (CIDB) under Part VIII of the Act 1994 and the construction Industry (Levy

sum sum

1.4

1.4.1 1.4.2 1.5 1.5.1 1.5.2 1.5.3 1.5.3.1 1.5.3.2 1.5.3.3 1.5.4 1.5.4.1 1.5.4.2 1.5.4.3 1.6

sum sum

N/A N/A

sum sum

N/A N/A

sum sum sum

N/A N/A N/A

sum sum sum

N/A N/A N/A

sum

Carried to Collection

* Tenderer to delete where not applicable ** Designer to decide which is applicable # Duration to be inserted by tenderer based on tendered period

BQ1 - 3/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRKJ ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 1 - GENERAL ITEMS ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT RM SEN

COLLECTION PAGE

BQ 1 - 1/4 BQ 1 - 2/4 BQ 1 - 3/4

TOTAL CARRIED TO SUMMARY

* Tenderer to delete where not applicable ** Designer to decide which is applicable # Duration to be inserted by tenderer based on tendered period

BQ1 - 4/4

PROJEK :

CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM)

ITEM NO. 2.1 2.1.1

SITE CLEARANCE Upgrading of existing road a) General site clearance ha. 1

2.1.2

Construction of new road a) Bushes b) Paddy Plantation c) Swampy Land d) Plantation e) Forest Reserve f) . g) ha. ha. ha. ha. ha. ha. ha. 0.5 N/A N/A 0.2 N/A

2.2

DEMOLITION AND REMOVAL FROM SITE OF ALL BUILDINGS AND EXISTING STRUCTURES Buildings a) Brickwork buildings i) Single storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 ii) Double storey -Plan plan area area :: less less than than 100m 100m2 100 - 200m2 exceeding 200m2 iii) storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2

2.2.1

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

Carried to Collection

* Delete where not applicable

BQ 2 - 1/10

PROJEK :

CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM)

ITEM NO.

b) Concrete buildings i) Single storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 ii) Double storey -Plan plan area area :: less less than than 100m 100m2 100 - 200m2 exceeding 200m2 iii) storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 c) Mansonry buildings i) Single storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 ii) Double storey -Plan plan area area :: less less than than 100m 100m2 100 - 200m2 exceeding 200m2 iii) storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 d) Steel buildings i) Single storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 ii) Double storey -Plan plan area area :: less less than than 100m 100m2 100 - 200m2 exceeding 200m2 iii) storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 Carried to Collection

nr nr nr

8 N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

* Delete where not applicable

BQ 2 - 2/10

PROJEK :

CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM)

ITEM NO.

e) Timber buildings i) Single storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 ii) Double storey -Plan plan area area :: less less than than 100m 100m2 100 - 200m2 exceeding 200m2 iii) storey Plan area : less than 100m2 100 - 200m2 exceeding 200m2 f) . 2.2.2 Other Structures a) Fences and Gates b) (.Type.) Bridges ...m length x ...m width c) Pipe Culverts ..mm diameter Box Culverts .. x .mm d) Surface lined drains ( irrespective of size ) e) Guardrails f) Sump . x .m g) Retaining Wall h) Inlet / outlet structures i) ...

nr nr nr

N/A N/A N/A

nr nr nr

N/A N/A N/A

nr nr nr .

N/A N/A N/A

m m2

N/A N/A

m m m m nr m2 nr

N/A N/A N/A N/A N/A 1000 N/A

Carried to Collection

* Delete where not applicable

BQ 2 - 3/10

PROJEK :

CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM)

ITEM NO. 2.3

DISMANTLE AND SEND TO STORE FOR REUSE AS DIRECTED BY S.O/P.D*. a) Fences and Gates b) Guardrails c) Sign Board d) ... e) ... m m nr N/A N/A N/A

Carried to Collection

* Delete where not applicable

BQ 2 - 4/10

PROJEK :

CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM)

ITEM NO.

COLLECTION PAGE

BQ 2 - 1/5 BQ 2 - 2/5 BQ 2 - 3/5 BQ 2 - 4/5

TOTAL CARRIED TO SUMMARY

* Delete where not applicable

BQ 2 - 5/10

AI DENGAN JALAN

AMOUNT (SEN)

* Delete where not applicable

BQ 2 - 6/10

AI DENGAN JALAN

AMOUNT (SEN)

* Delete where not applicable

BQ 2 - 7/10

AI DENGAN JALAN

AMOUNT (SEN)

* Delete where not applicable

BQ 2 - 8/10

AI DENGAN JALAN

AMOUNT (SEN)

* Delete where not applicable

BQ 2 - 9/10

AI DENGAN JALAN

AMOUNT (SEN)

* Delete where not applicable

BQ 2 - 10/10

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 3 - EARTHWORKS ITEM NO. DESCRIPTION OF WORKS UNIT RATE (RM) 3.1 3.1.1 STRIPPING OF TOPSOIL Stripping topsoil average depth 150mm and dispose to Contractor's dump site as approved by the S.O/P.D*. Stripping topsoil average depth 150mm and stockpile for reuse. EXCAVATE, LOAD, HAUL AND DEPOSIT TO FORM EMBANKMENT Common excavation in cuttings or in bulk to form embankment. Excavation of hard material in cuttings or in bulk to form embankment. Rock excavation by open blasting to form embankment. Rock excavation by control blasting to form embankment. Rock excavation by ripper unit to form embankment. Rock excavation by pneumatic to form embankment. EXCAVATE, LOAD, HAUL AND DISPOSE Common excavation in cuttings or in bulk and dispose to Contractor's dump site as approved by S.O/P.D*. Excavation of hard material in cuttings or in bulk and dispose to Contractor's dump site as approved by S.O/P.D*. Rock excavation by open blasting and dispose to Contractor's dump site as approved by S.O./P.D*. AMOUNT (RM) (SEN)

QTY

1500

3.1.2

N/A

3.2

3.2.1

m3

6300

3.2.2

m3

N/A

3.2.3

m3

N/A

3.2.4

m3

20

3.2.5

m3

N/A

3.2.6

10

3.3 3.3.1

m3

1000

3.3.2

m3

50

3.3.3

m3

20

Carried to Collection

* Delete where not applicable

BQ 3 - 1/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 3 - EARTHWORKS ITEM NO. DESCRIPTION OF WORKS UNIT RATE (RM) 3.3.4 Rock excavation by control blasting and dispose to Contractor's dump site as approved by S.O./P.D*. Rock excavation by ripper unit and dispose to Contractor's dump site as approved by S.O./P.D*. Rock excavation by pneumatic and dispose to Contractor's dump site as approved by S.O./P.D*. EXCAVATE UNSUITABLE MATERIAL, LOAD, HAUL AND DISPOSE Excavate unsuitable material below embankments, below culverts or below formation in cuttings as shown in drawing or as per specification as approved by S.O/P.D* and dispose to Contractor's dump site. m3 3.4.2 Excavate unsuitable material in cuttings as per specification as approved by S.O/P.D* and dispose to Contractor's dump site. SPREAD, GRADE AND COMPACT TO FORM EMBANKMENT Suitable material from common excavation to form embankment. Imported suitable material to form embankment from Contractor's own source. Suitable hard material from excavation to form embankment. Rockfill from rock excavation to form embankment. Imported rock to form embankment from Contractor's own source. m3 500 AMOUNT (RM) (SEN)

QTY

10

3.3.5

N/A

3.3.6

3.4

3.4.1

m3

N/A

3.5

3.5.1

N/A

3.5.2

m3

6300

3.5.3

m3

N/A

3.5.4

m3

N/A

3.5.5

m3

N/A

Carried to Collection

* Delete where not applicable

BQ 3 - 2/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 3 - EARTHWORKS ITEM NO. DESCRIPTION OF WORKS UNIT RATE (RM) 3.6 3.6.1 3.6.2 3.6.3 3.6.4 TURFING AND HYDROSEEDING Close turfing. Hydroseeding. Hydroseeding with fibromat or equivalent. Vertiver grass or equivalent at 250mm spacing (in group of 3 rows). FIELD DENSITY TEST Carry out compaction test to verify the degree of compaction by using sand replacement method or other approved method by S.O/P.D*. no 20 m2 m2 m2 1200 N/A N/A AMOUNT (RM) (SEN)

QTY

N/A

3.7 3.7.1

Carried to Collection

* Delete where not applicable

BQ 3 - 3/4

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 3 - EARTHWORKS ITEM NO. DESCRIPTION OF WORKS UNIT RATE (RM) AMOUNT (RM) (SEN)

QTY

COLLECTION PAGE

BQ 3 - 1/4 BQ 3 - 2/4 BQ 3 - 3/4

TOTAL CARRIED TO SUMMARY

* Delete where not applicable

BQ 3 - 4/4

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. 4.1 ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

TEMPORARY WORKS Provide, erect,maintain and remove from site on completion of works temporary crossing all in accordance with the relevant sub section of the specification for the proposed culverts.

sum

4.4

NEW PRECAST BOX CULVERT FOR SIZE < 3.0m WIDE Earthworks i) Excavate, load, haul and deposit to spoil any material except rock to any depth for structural foundation. -Ditto- for rock

4.4.1

m3 m3

20 15

ii) 4.4.2 4.4.2.1

Types of Foundation Normal Foundation

Fill, spread, grade and compact granular fill material. iii) Lean concrete grade 15/20, 100mm thick. m2 20

4.4.2.2

Pile Foundation i) Allow for mobilization and demobilization of all labour, plants piling, equipments, etc on site for proposed piling works 150 x 150mm precast RC piles 12m length, inclusive of all reinforcements,mild steel plates and provision for extension and lifting holes nr N/A

sum

N/A

ii)

4.4.3

Precast Box Culvert Box culvert and flat lid including joint. i) ii) 1200mm x 1200mm size box culvert. 1500mm x 1500mm size box culvert. m m 13 N/A

Carried to Collection

BQ 4 - 1/6

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. 4.4.4 ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

Inlet / Outlet Structures Reinforced concrete headwall, wingwall, base slab including excavation work, formworks, concrete, reinforcement, lean concrete and shoring for:i) Box culvert (irrespective size) nr 4

4.4.5

Fill Material i) Filling with suitable material in layers up to formation level including compaction.

20

4.6

CAST INSITU BOX CULVERT FOR SIZE < 3.0 m WIDE Earthworks i) Excavate, load, haul and deposit to spoil any material except rock to any depth for structural foundation. -Ditto- for rock

4.6.1

m3 m3

N/A N/A

ii) 4.6.2 4.6.2.1

Types of Foundation Normal Foundation

Fill, spread, grade and compact granular fill material. i) Mining / river sand * ii) Crushed aggregate.

m3 m3 m2

N/A N/A N/A

iii) Lean concrete grade 15/20, 100mm thick.

Carried to Collection

BQ 4 - 2/6

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. 4.6.2.2 Pile Foundation i) Allow for mobilization and demobilization of all labour, plants piling, equipments, etc on site for proposed piling works 350 x 350mm precast RC piles 36m length, inclusive of all reinforcements,mild steel plates and provision for extension and lifting holes ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

sum

N/A

ii)

nr

N/A

4.6.3

Formwork Formwork for box culvert,headwall and wingwall with Class F1 Finishes.

N/A

4.6.4 4.6.4.1

Reinforcement

Reinforcement for insitu box culvert High Yield Steel. i) 12mm diameter ii) 16mm diameter iv) 25mm diameter t t t N/A N/A N/A

4.6.5

Concrete Grade 40/20 concrete at box culvert, wingwall and headwall. m3

100

4.6.9

Fill Material i) Filling with suitable material in layers up to formation level including compaction.

m3

500

Carried to Collection

BQ 4 - 3/6

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. 4.8 ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

SURFACE DRAINS Unlined drains, half round glazed earthenware and Insitu Reinforced Concrete grade 20/20 drains at any inclination including excavation,cascading,lean concrete,jointing,reinforcement,formwork,rendering, fixing precast RC slab,backfilling and disposal of surplus material.

4.8.1

Roadside Drains For Rural Area i) 900mm U Drain m 250

4.8.7

Shoulder Drain i) Embankment shoulder drain Type 1 (SD 1 ) - 300mm to 500mm deep

N/A

4.8.8

Cascade Drain i) Stone pitching Type 1 (OD1) with handrails. m N/A

4.10 4.10.2

SUMPS Sump At Fill Brick sump including excavation, lean concrete, concrete bedding, plastering, formworks, joints, backfilling and disposal of surplus material. i) Type SF1 at shoulder . nr N/A

4.11

RUBBLE RETAINING WALLS 225mm thick grouted stone pitching including all necessary excavation works at both inlet and outlet of culverts as show in the drawing.

m2

50

Carried to Collection

BQ 4 - 4/6

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. 4.12 ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

EARTH CHANNELS EXCAVATION Excavate for earth channels to shapes and sizes as shown in the drawings including slopes protection. i) Earth Channel excavation. m
3

N/A

Carried to Collection

BQ 4 - 5/6

Project : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO 4 - DRAINAGE WORKS ITEM NO. ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

COLLECTION PAGE BQ 4 - 1/6 BQ 4 - 2/6 BQ 4 - 3/6 BQ 4 - 4/6 BQ 4 - 5/6

TOTAL CARRIED TO SUMMARY

BQ 4 - 6/6

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1 5.1.1 5.1.1.1 DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

FLEXIBLE PAVEMENT NEW PAVEMENT Preparation of Formation Preparation of formation as specified and as directed by the S.O/P.D* for receiving road pavement. m2 1,368

5.1.1.2 5.1.1.2.1

Carriageway and Paved Shoulder Subbase Subbase material (CBR > 30 %) complying with Type C or Type D grading limits of Table 4.1 of the standard specifications. a) Granular Material - 150 mm thick b) Cement-Bound Granular Material - .mm thick m2 m2 1,026 N/A

5.1.1.2.2

Roadbase a) Spread, grade and compact roadbase material complying with Type I or Type II grading limits of Table 4.3 of the standard specifications. i) Crushed Aggregate - 300 mm thick m
2

1,026 N/A N/A N/A

ii) Wet Mix Macadam - ... mm thick iii) Dry Bound Macadam - ... mm thick iv) Cement-Bound Granular Material - . mm thick b) Roadbase material complying with Table 4.12 of the standard specifications. i) Bound Roadbase BMR 40 - ... mm thick

m2 m2 m
2

N/A

ii) Bound Roadbase BMR 28 - ... mm thick

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 1/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.1.2.3 Surfacing a) Bituminous Prime Coat b) Bituminous Tack Coat c) Asphaltic Concrete Asphaltic concrete material complying with Table 4.8 of the standard specifications. i) Asphaltic concrete binder course - 70 mm thick m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (SEN) (RM)

m2 m
2

1,026 1,026

1,026

ii) Asphaltic concrete wearing course - 50 mm thick d) Bituminous Macadam Roadbase material complying with Table 4.12 of the standard specifications. i) Levelling Course BML 10

m2

1,026

t m2 m2 m2

N/A N/A N/A N/A

ii) Binder Course BMB 28 - .. mm thick iii) Binder Course BMB 20 - ... mm thick iv) Wearing Course BMW 14 - ... mm thick

v) Wearing Course BMW 20 - ... mm thick

m2

N/A

e) Micro Surfacing 10 to 12 mm nominal thickness modified micro surfarcing in 2 layers of material according to the standard specifications. f) Chip Sealing Single / double layer chip seal of material according to standard specifications. m
2

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 2/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. i) DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

Rubber modified bitumen for the chip seal layer for bitumen application rate ... to ... litres / m2.

m2

N/A

ii) Precoated cover aggregate as "Chip Seal" layer - .mm thick iii) - ditto - for second "Chip Seal" layer .mm thick 5.1.1.3 5.1.1.3.1 Median and Island Subbase Subbase material (CBR > 30 %) complying with Type C or Type D grading limits of Table 4.1 of the standard specifications. a) Granular Material - ... mm thick b) Cement-Bound Granular Material - . mm thick 5.1.1.3.2 Roadbase a) Roadbase material complying with Type I or Type II grading limits of Table 4.3 of the standard specifications. i) Crushed Aggregate - ... mm thick

N/A

N/A

m2 m2

N/A N/A

m2 m2 m2 m
2

N/A N/A N/A N/A

ii) Wet Mix Macadam - ... mm thick iii) Dry Bound Macadam - ... mm thick iv) Cement-Bound Granular Material - . mm thick b) Roadbase material complying with Table 4.12 of the standard specifications. i) Bound Roadbase BMR 40 - ... mm thick

m m

N/A N/A

ii) Bound Roadbase BMR 28 - ... mm thick

Carried to Collection

* Delete where not applicable

BQ 5 - 3/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.1.3.3 Surfacing a) Bituminous Prime Coat b) Bituminous Tack Coat c) Asphaltic Concrete Asphaltic concrete material complying with Table 4.8 of the standard specifications. i) Asphaltic concrete binder course - .. mm thick m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (SEN) (RM)

m2 m
2

N/A N/A

N/A

ii) Asphaltic concrete wearing course - ... mm thick d) Bituminous Macadam Roadbase material complying with Table 4.12 of the standard specifications. i) Levelling Course BML 10

m2

N/A

t m2 m2 m
2

N/A N/A N/A N/A

ii) Binder Course BMB 28 - .. mm thick iii) Binder Course BMB 20 - ... mm thick iv) Wearing Course BMW 14 - ... mm thick

v) Wearing Course BMW 20 - ... mm thick

N/A

5.1.1.4 5.1.1.4.1

Bus Lay By Subbase Subbase material (CBR > 30 %) complying with Type C or Type D grading limits of Table 4.1 of the standard specifications. a) Granular Material - ... mm thick b) Cement-Bound Granular Material - .. mm thick Carried to Collection m2 m2 N/A N/A

* Delete where not applicable

BQ 5 - 4/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.1.4.2 Roadbase a) Roadbase material complying with Type I or Type II grading limits of Table 4.3 of the standard specifications. i) Crushed Aggregate - .. mm thick m2 m2 m2 m2 N/A N/A N/A N/A DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

ii) Wet Mix Mcadam - .. mm thick iii) Dry Bound Macadam - .. mm thick iv) Cement-Bound Granular Matterial - . mm thick b) Roadbase material complying with Table 4.12 of the standard specifications. i) Bound Roadbase BMR 40 - ... mm thick

m2 m2

N/A N/A

ii) Bound Roadbase BMR 28 - ... mm thick 5.1.1.4.3 Surfacing a) Bituminous Prime Coat b) Bituminous Tack Coat c) Asphaltic Concrete Asphaltic concrete material complying with Table 4.8 of the standard specifications. i) Asphaltic concrete binder course - .. mm thick

m2 m2

N/A N/A

m2

N/A

ii) Asphaltic concrete wearing course - ... mm thick d) Bituminous Macadam Roadbase material complying with Table 4.12 of the standard specifications. i) Levelling Course BML 10

m2

N/A

m2

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 5/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

ii) Binder Course BMB 28 - .. mm thick iii) Binder Course BMB 20 - ... mm thick iv) Wearing Course BMW 14 - ... mm thick

m2 m m
2

N/A N/A N/A

v) Wearing Course BMW 20 - ... mm thick

N/A

5.1.1.5 5.1.1.5.1

Access Road Subbase Subbase material (CBR > 30 %) complying with Type C or Type D grading limits of Table 4.1 of the standard specifications. a) Granular Material - ... mm thick b) Cement-Bound Granular Material - . mm thick m2 m2 N/A N/A

5.1.1.5.2

Roadbase a) Roadbase material complying with Type I or Type II grading limits of Table 4.3 of the standard specifications. i) Crushed Aggregate - ... mm thick m2 m2 m2 m2 N/A N/A N/A N/A

ii) Wet Mix Macadam - ... mm thick iii) Dry Bound Macadam - ... mm thick iv) Cement-Bound Granular Material - . b) Roadbase material complying with Table 4.12 of the standard specifications. i) Bound Roadbase BMR 40 - ... mm thick

m2 m2

N/A N/A

ii) Bound Roadbase BMR 28 - ... mm thick

Carried to Collection

* Delete where not applicable

BQ 5 - 6/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.1.5.3 Surfacing a) Bituminous Prime Coat b) Bituminous Tack Coat c) Asphaltic Concrete Asphaltic concrete material complying with Table 4.8 of the standard specifications. i) Asphaltic concrete binder course - .. mm thick m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (SEN) (RM)

m2 m
2

N/A N/A

N/A

ii) Asphaltic concrete wearing course - ... mm thick d) Bituminous Macadam Roadbase material complying with Table 4.12 of the standard specifications. i) Levelling Course BML 10

m2

N/A

t m2 m2 m
2

N/A N/A N/A N/A

ii) Binder Course BMB 28 - .. mm thick iii) Binder Course BMB 20 - ... mm thick iv) Wearing Course BMW 14 - ... mm thick

v) Wearing Course BMW 20 - ... mm thick

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 7/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.1.6 DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

Fill Material On Unpaved Shoulder Earth shoulder material complying with sub section 2.2.1 of the standard specifications and constructed to method specified in clause 4.3.3 of the standard specifications. a) Suitable material from common excavation. b) Imported suitable material from Contractor's own source. m m
3

N/A N/A

5.1.1.7

Fill Material On Unpaved Median and Island Earth shoulder material complying with sub section 2.2.1 of the standard specifications and constructed to method specified in clause 4.3.3 of the standard specifications. a) Suitable material from common excavation. b) Imported suitable material from Contractor's own source. m3 m3 N/A N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 8/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.2 5.1.2.1 DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

TREATMENT TO EXISTING PAVEMENT

Patching Mark, cut, break up existing pavement and cart away to designated spoil dumping ground, clearing of debris, patch and compact with asphaltic concrete ACW 20 including tack coat application. m3 N/A

5.1.2.2

Milling
a) Milling of existing pavement including clean and

N/A

remove all debris to receive new surface inlay . mm thick.


b) Tack coat to receive ACB 28. c) . mm thick ACB 28 inlay.

m2 m2

N/A N/A

5.1.2.3

Regulation Bituminous macadam levelling course BML 10 to the required formation level. t 3

5.1.2.4 5.1.2.4.1

Reconstruction Of Existing Pavement Mark, cut, break up, remove and cart away Mark, cut, break up, remove existing pavement and cart away spoil to designated dumping ground - up to .. mm thick m
2

N/A

5.1.2.4.2

Subbase Subbase material (CBR > 30 %) complying with Type C or Type D grading limits of Table 4.1 of the standard specifications. a) Granular Material - ... mm thick b) Cement-Bound Granular Material - . mm thick m2 m
2

N/A N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 9/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.1.2.4.3 Roadbase a) Roadbase material complying with Type I or Type II grading limits of Table 4.3 of the standard specifications. i) Crushed Aggregate - ... mm thick m m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (SEN) (RM)

N/A N/A N/A N/A

ii) Wet Mix Macadam - ... mm thick iii) Dry Bound Macadam - ... mm thick iv) Cement-Bound Granular Material - . mm thick b) Roadbase material complying with Table 4.12 of the standard specifications. i) Bound Roadbase BMR 40 - ... mm thick

m2 m
2

m2

N/A

ii) Bound Roadbase BMR 28 - ... mm thick

m2

N/A

5.1.2.5

Overlay a) Bituminous Prime Coat b) Bituminous Tack Coat c) Asphaltic Concrete Asphaltic concrete material complying with Table 4.8 of the standard specifications. i) Asphaltic concrete binder course - . mm thick m2 N/A m2 m2 200 200

ii) Asphaltic concrete wearing course - 50 mm thick d) Bituminous Macadam Roadbase material complying with Table 4.12 of the standard specifications.

m2

200

Carried to Collection

* Delete where not applicable

BQ 5 - 10/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. i) DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

Levelling Course BML 10 for regulating

t m2 m m
2

N/A N/A N/A N/A

ii) Binder Course BMB 28 - ... mm thick iii) Binder Course BMB 20 - ... mm thick iv) Wearing Course BMW 14 - ... mm thick

v) Wearing Course BMW 20 - ... mm thick

N/A

e) Micro Surfacing 10 mm to 12 mm nominal thickness modified micro surfarcing in 2 layers of material according to the standard specifications. f) Chip Sealing Single / double layer chip seal of material according to standard specifications. i) Rubber modified bitumen for the chip seal layer for bitumen application rate . litres / m2 to . litres / m2. m2 N/A m2 N/A

ii) Precoated cover aggregate as "Chip Seal"

m2

N/A

layer - . mm thick.
iii) - ditto - for second "Chip Seal" layer - .

m2

N/A

mm thick.

Carried to Collection

* Delete where not applicable

BQ 5 - 11/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.2 5.2.1 5.2.1.1 DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

CONCRETE PAVEMENT NEW PAVEMENT Preparation Of Formation Preparation of formation as specified and as directed by the S.O/P.D* for receiving road pavement. m2 N/A

5.2.1.2 5.2.1.2.1

Carriageway And Paved Shoulder Subbase a) Unbound Subbase material according to Table 4.1 of the standard specifications i) Sand m2 m2 N/A N/A

ii) Crushed aggregate b) Lean Concrete mm thick lean concrete grade . : i) Manual laying

m2 m2

N/A N/A

ii) Slip forming 5.2.1.2.2 Curing Compound For Lean Concrete Wax based emulsion curing compound using mechanical spraybar. 5.2.1.2.3 Bond Breaking Treatment Bond breaking compound using wax based emulsion or equivalent as approved by S.O/P.D*. 5.2.1.2.4 Plain Concrete mm thick plain concrete Grade .: a) Manual laying Carried to Collection

N/A

N/A

m2

N/A

* Delete where not applicable

BQ 5 - 12/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

b) Slip forming 5.2.1.2.5 Formwork a) Manual laying i) Steel side formwork .. mm deep for lean concrete.

m2

N/A

N/A

ii) Steel side formwork .. mm deep for plain concrete. 5.2.1.2.6 Longitudinal Construction Joint Steel bars for longitudinal construction joint as shown in the drawings. a) U - shape Y.mm bars b) Y.mm bars c) mm long Y .mm tiebars. 5.2.1.2.7 Transverse Contraction Joint Steel bar for tranverse contraction joint at . m interval as shown in the drawings. a) U - shape Y.mm bars b) Y.mm bars c) ...mm long Y ... mm dowel bars. 5.2.1.2.8 Expansion Contraction Joint Steel bar for expansion contraction joint at ... m interval as shown in the drawings. a) U - shape Y.mm bars b) Y.mm bars c) ...mm long Y ... mm dowel bars.

N/A

nr t t

N/A N/A N/A

nr t t

N/A N/A N/A

nr t t

N/A N/A N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 13/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.2.1.2.9 DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

Construction Joint at Transverse Contraction Joint Steel bar for construction joint at transverse contraction joint as shown in the drawings a) U - shape Y.mm bars b) Y.mm bars c) ..mm long Y ... mm dowel bars inclusive of sleeve. nr t t N/A N/A N/A

5.2.1.2.10

Texturing Texturing on plain concrete slab surface. m2 N/A

5.2.1.2.11

Curing Compound Curing compound/sealer coat on finished concrete slab. m2 N/A

5.2.1.2.12

Silicone Sealant Silicone sealant to form contraction joint as shown in the drawings. m N/A

5.2.1.2.13

Anchor Beam Anchor beam (..mm x mm) using Concrete Grade .... as shown in the drawings. m N/A

5.2.1.2.14

Movable Shaded Cover To provide movable shaded cover for protection of plain concrete pavement and lean mix concrete subbase from rain during paving, as shown in the drawings and as directed by the S.O/P.D*. on site. m
2

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 14/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. 5.2.1.2.15 Surface Stamp To provide labour and necessary equipment to stamp concrete slab surface with letterings as shown in the drawings and as directed by the S.O/P.D* on site. 5.2.1.3 Fill Material On Unpaved Shoulder Earth shoulder material complying with sub section 2.2.1 of the standard specifications and constructed to method specified in clause 4.3.3 of the standard specifications. a) Suitable material from common excavation. b) Imported suitable material from Contractor's own source. 5.2.1.4 Filter Material a) Crushed Aggregate Crushed aggregate as filter material .mm thick complying with Table 3.4 of the standard specifications. b) Geotextile KET - 9 Single layer of filter geotextile KET - 9 or equivalent as per standard specification. m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (SEN) (RM)

nr

N/A

m3 m3

N/A N/A

m3

N/A

N/A

Carried to Collection

* Delete where not applicable

BQ 5 - 15/16

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGAI HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMBUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 5 - PAVEMENT WORKS ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (SEN) (RM)

COLLECTION PAGE BQ 5 - 1/16 BQ 5 - 2/16 BQ 5 - 3/16 BQ 5 - 4/16 BQ 5 - 5/16 BQ 5 - 6/16 BQ 5 - 7/16 BQ 5 - 8/16 BQ 5 - 9/16 BQ 5 - 10/16 BQ 5 - 11/16 BQ 5 - 12/16 BQ 5 - 13/16 BQ 5 - 14/16 BQ 5 - 15/16

TOTAL CARRIED TO SUMMARY

* Delete where not applicable

BQ 5 - 16/16

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. 6.1 6.1.1 SIGNBOARDS Destination Signboard Destination sign type high intensity retroreflective sheeting inclusive of posts, footing and frames as specified and shown in the drawing. a) b) c) d) e) 6.1.2 Not exceeding 1 m 2 1-2m 2 2-3m 2 3-4m 2 More than 4 m
2

DESCRIPTION OF WORKS

UNIT

QTY

RATE (RM)

AMOUNT (RM) (SEN)

nr nr nr nr nr

N/A N/A N/A N/A N/A

Gantry Directional Signboard Fabrication, deliver to site and installation of overhead gantry not exceeding ..m span with installation of directional sign type high intensity retroreflective sheeting inclusive of foundations, posts, purlin frames and connections as specified and shown in the drawing. a) Not exceeding 10 m 2 b) More than 10 m
2

nr nr

N/A N/A

6.1.3

Butterfly gantry Fabrication, deliver to site and installation of butterfly gantry with installatiom of directional sign type high intensity retroreflective sheeting inclusive of foundations, posts, purlins frames and connections as specified and shown in the drawing. a) Not exceeding 10 m 2 b) More than 10 m
2

nr nr

N/A N/A

6.1.4

Warning and Regulatory Traffic signs a) b) c) d) Type 'RP 27' (mm x..mm) Type 'WD 39' (mm x ..mm) Type 'WD 44' (..mm x ..mm) nr nr nr 2 3 1

Carried to Collection

* Delete where not applicable

BQ 6 - 1/6

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. 6.2 6.2.1 DESCRIPTION OF WORKS TRAFFIC BARRIER Guardrails a) Single mounted corrugated steel beam guardrail inclusive of delineators. i) 1.95m post spacing ii) 3.8m post spacing b) Double mounted corrugated steel beam guardrail inclusive of delineators. i) 1.95m post spacing ii) 3.8m post spacing c) Guardrail Ends i) Type 1 ii) Type 2 iii) Type 3 6.2.2 New Jersey Barrier (NJB) a) Precast concrete NJB b) Cast insitu concrete NJB 6.2.3 Wire rope Wire rope as shown in the drawing. 6.3 6.3.1 ROAD MARKING Hot-applied superimposed reflectorised thermoplastic road markings Hot-applied superimposed reflectorised thermoplastic road markings with 20% glassbead as specified in BS 3262 and in the drawing. a) b) c) d) e) Type 1 Type 2 Type 3 Type 4 Type 5 m m m m m N/A N/A N/A N/A N/A m N/A m m N/A N/A m m N/A N/A m m 114 N/A UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

nr nr nr

1 1 N/A

Carried to Collection

* Delete where not applicable

BQ 6 - 2/6

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. f) g) h) i) j) k) l) m) n) o) p) q) 6.3.2 DESCRIPTION OF WORKS Type 6 Type 7 Type 8 Type 9 (Pedestrian zebra crossing) Type 10 Type 11 Type 12 Type 13 Type 14 (Yellow box marking) Chevron marking Transverse bar Raised rib thermoplastic UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

m m m 2 m m m m m 2 m 2 m 2 m
2

450 N/A N/A N/A 250 N/A N/A N/A N/A N/A N/A

Directional Arrow for roads in urban area a) b) c) d) Single Straight Single turning Double headed Pavement marking nr nr nr 2 m N/A N/A N/A N/A

6.3.3

Directional Arrow for roads in rural area a) Single Straight b) Single turning c) Double headed nr nr nr N/A N/A N/A

6.4

BUS-SHELTER

Bus-shelter inclusive of roofing, RC foundation, seating, railing, lighting etc as shown in the drawing. 6.5 MS RAILING Mild steel pedestrian railing as shown in the drawing or as directed by the S.O/P.D*. ANTIGLARE SCREEN Antiglare screen as shown in the drawing or as directed by S.O/P.D*.

nr

N/A

N/A

6.6

N/A

Carried to Collection

* Delete where not applicable

BQ 6 - 3/6

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. 6.7 DESCRIPTION OF WORKS INTERLOCKING PAVING BLOCK FOR FOOTPATH Interlocking paving block to approved colour and patern inclusive of compacted sand layer and other accessories as shown in the drawing or as directed by the S.O/P.D*. 6.8 KILOMETRE POST Kilometre post inclusive of all necessary works at location and details as shown in the drawing or as directed by the S.O/P.D* a) Type A b) Type B 6.9 CONCRETE KERB a) Cast-in-situ concrete kerb including jointing, excavation, backfilling, bedding and disposal of surplus materials as shown in the drawing or as directed by the S.O/P.D* all in accordance with Sub-Section 6.4 of the standard specification. i) Type SM1 ii) Type SM2 b) Precast concrete kerb including jointing, excavation, backfilling, bedding and disposal of surplus materials as shown in the drawing or as directed by the S.O/P.D* all in accordance with Sub-Section 6.4 of the standard specification. i) Type SM1 ii) Type SM2 6.10 6.10.1 DELINEATORS Delineator post Delineator post as shown in the drawing. nr N/A m m N/A N/A m m N/A N/A nr nr N/A N/A UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

N/A

Carried to Collection

* Delete where not applicable

BQ 6 - 4/6

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. 6.10.2 DESCRIPTION OF WORKS Retroreflective Raised Pavement Marker (Road Stud) Retroreflective Raised Pavement Marker as shown in the drawing. 6.10.3 Chevron delineators Chevron delineators as shown in the drawing. 6.10.4 Flexible post Flexible post as shown in the drawing. 6.11 IMPACT ATTENUATOR Impact attenuator with number of bays of overall length .mm including nose, concrete pad, anchor block, and all necessary fitting as specified and shown in the Drawing. 6.12 RIGHT OF WAY MARKER Right of Way marker as shown in the drawing. nr N/A nr N/A nr N/A UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

nr

100

nr

N/A

Carried to Collection

* Delete where not applicable

BQ 6 - 5/6

PROJECT : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 6 - ROAD FURNITURE ITEM NO. DESCRIPTION OF WORKS UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

COLLECTION PAGE BQ 6 - 1/6 BQ 6 - 2/6 BQ 6 - 3/6 BQ 6 - 4/6 BQ 6 - 5/6

TOTAL CARRIED TO SUMMARY

* Delete where not applicable

BQ 6 - 6/6

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.1 7.1.1 7.1.1.1 7.1.1.2 7.1.1.3 7.1.1.4 DESCRIPTION OF WORK UNIT SOFT GROUND IMPROVEMENT SOFT GROUND REPLACEMENT / STABILITY (type) non-woven geotextile as separator. (tensile strength)... woven geotextile. Placement and compaction of river/mining* sand. Placement and compaction of excavated suitable material from the road way. Placement and compaction of imported earth from Contractor's own source. PREFABRICATED VERTICAL DRAINS Mobilization/demobilization including moving of equipment and plant from location to location. (type) non-woven geotextile as separator. (tensile strength)... woven geotextile. mm thick river/mining* sand as drainage blanket. (type)...prefabricated vertical drains. Placement and compaction of river/mining* sand. STONE COLUMNS / GEOPIERS / SOIL CEMENT COLUMNS / CHEMICAL COLUMNS / SAND COLUMNS* Mobilization/demobilization including moving of equipment and plant from location to location. (type) non-woven geotextile as separator. (tensile strength)... woven geotextile. m2 m2 m3 N/A N/A N/A QTY RATE (RM) AMOUNT (RM) (SEN)

m3

N/A

7.1.1.5

m3

N/A

7.1.2 7.7.2.1

Sum m2 m2

N/A N/A N/A

7.1.2.2 7.1.2.3 7.1.2.4

m2 m m3

N/A N/A N/A

7.1.2.5 7.1.2.6 7.1.3

7.1.3.1

Sum m
2

N/A N/A N/A

7.1.3.2 7.1.3.3

m2

Carried to Collection

* Delete where not applicable.

BQ7 - 1/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.1.3.4 DESCRIPTION OF WORK UNIT mm diameter stone columns / soil cement columns / chemical columns / geopiers / sand columns* as shown in Drawing. mm thick river/mining* sand as drainage blanket. Placement and compaction of river/mining* sand. Carry out load test to maximum test load of .. kN as per Specification. Carry out load test on group columns (4 no. per group) to maximum test load of ... kN as per Specification. SURCHARGE i) Excavated suitable fill materials from roadway as surcharge. m3 m3 QTY RATE (RM) AMOUNT (RM) (SEN)

N/A

7.1.3.5

m2 m3

N/A N/A

7.1.3.6 7.1.3.7

nr

N/A

7.1.3.8

nr

N/A

7.1.4 7.1.4.1

N/A N/A

ii) Imported fill materials as surcharge. 7.1.4.2 i) Excavate and transport surcharge material to place of fill for reuse.

m3

N/A

ii) Removal of surplus surcharge material from site. 7.1.5 7.1.5.1 PILED EMBANKMENT .. x .. mm PRECAST Reinforced Concrete PILES : Allow for mobilization and demobilization of all labour, plants, piling and drilling equipments, etc. on site, for the proposed piling works. Supply and deliver to site .m length initial piles. Supply and deliver to site ..m length extension pile Handle, pitch and drive vertical piles.

m3

N/A

7.1.5.1.1

sum nr

N/A N/A

7.1.5.1.2 7.1.5.1.3

nr m

N/A N/A

7.1.5.1.4

Carried to Collection

* Delete where not applicable.

BQ7 - 2/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.1.5.1.5 7.1.5.1.6 7.1.5.1.7 DESCRIPTION OF WORK UNIT Handle, pitch and drive raked piles. Lengthening of piles by jointing to detail. Cutting off piles head to required length including stripping off to expose main reinforcements to detail. Handle, pitch and drive raked piles. Lengthening piles by jointing to detail. m nr QTY N/A N/A RATE (RM) AMOUNT (RM) (SEN)

nr m nr

N/A N/A N/A

7.1.5.1.8 7.1.5.1.9

7.1.5.1.10 Cutting off piles head to required length including stripping off to expose main reinforcements to detail. 7.1.5.1.11 Provide all labour, plants, temporary staging, kentledge, testing equipments etc. and test load on preliminary pile to the maximum load test.. kN (... working load). 7.1.5.1.12 Provide all labour, plants, temporary staging, kentledge, testing equipments etc. and test load on working pile to the maximum load test.. kN (twice working load). 7.1.5.1.13 Carry out pile driving analyser (PDA) monitoring on pile complete with all necessary preparation for installing transducers, setting up the necessary equipment and monitoring by experience personnel.

nr

N/A

nr

N/A

nr

N/A

nr 7.1.5.2 7.1.5.2.1 RC Slab Excavate in any material except rock to any depth for structural foundation. Suitable material as fill up to O.G.L 50mm thick grade 10/20 lean concrete Construct .mm thick reinforced concrete slab grade 30/20. Rate to include all necessary formwork and reinforcement as shown in the drawing.

N/A

m3 m m
3

N/A N/A N/A

7.1.5.2.2 7.5.12.3 7.1.5.2.4

m2

N/A

Carried to Collection

* Delete where not applicable.

BQ7 - 3/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.2 7.2.1 7.2.2 7.2.3 DESCRIPTION OF WORK UNIT INSTRUMENTATION Supply and install surface settlement marker. Supply and install settlement gauge. Supply and install ..(type)... piezometers. i) not exceeding 5m ii) exceeding 5m but not exceeding 10m iii) exceeding 10m but not exceeding 20m Supply and install ..(type).. inclinometers. i) not exceeding 10m ii) exceeding 10m but not exceeding 20m iii) exceeding 20m but not exceeding 30m Install deep levelling datum penetrating to hard stratum to about .m depth or as instructed and complete the setting of temporary bench mark station as instructed by SO/PD*. Monitoring and analysing of data obtain from all instruments. 3 copies of the monthly monitoring report. SLOPE STABILISATION WORKS SOIL NAILING Provide the necessary drilling and grouting equipment and all other appliances required for the installation of the soil nails including staging, storage of the above on Site during the progress of work and removal from the site on completion as directed by the S.O/P.D*. 100mm diameter soil nails at .....m centres or directed by S.O/P.D* complete with head assembly including drilling borehole, grouting ...(size).. bar into 50mm diameter corrugated PVC tube with plastic cap using 20N/mm2 water/cement grout. The end of ...(size).. bar to extend out from soil for anchorage into nail wall as shown in the Drawings. N/A nr nr N/A N/A QTY RATE (RM) AMOUNT (RM) (SEN)

nr nr nr

N/A N/A N/A

7.2.4

nr nr nr

N/A N/A N/A

7.2.5

nr

N/A

7.2.6

trip Sum

N/A N/A

7.2.7 7.3 7.3.1 7.3.1.1

Sum

N/A

7.3.1.2

Carried to Collection

* Delete where not applicable.

BQ7 - 4/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. a) b) c) d) DESCRIPTION OF WORK UNIT 6.0m long 9.0m long 12m long Exceeding 12m long but not exceeding 18m long. (....m long) nr nr nr nr QTY N/A N/A N/A N/A RATE (RM) AMOUNT (RM) (SEN)

7.3.1.3

Provide all equipment, labour, materials and everything else necessary to carry out pull out test on the soil nails. a) 6.0m long soil nail to . times working load (..kN) b) 9.0m long soil nail to . times working load (.kN) c) 12.0m long soil nail to . times working load (..kN) d) Exceeding 12.0m long but not exceeding 18m long soil nail to . times working load (..m, ..kN)

nr nr nr

N/A N/A N/A

nr nr

N/A N/A

7.3.1.4 7.3.1.5

Proof test for soil nail ..m long .mm diameter horizontal drains with ..mm diameter perforated pvc pipe wrapped with non-woven geotextile as shown in the Drawings. .mm thick guniting grade 25 concrete on slope face inclusive of weepholes nail head preparation and . layer of Steel Fabric Reinforcement as shown in the Drawings. ROCK BOLT Provide the necessary drilling and grouting equipment and all other appliances required for the installation of the rock bolt including staging, storage of the above on site during the progress of work and removal from the site on completion as directed by the S.O/P.D*. Installation of rock bolt as specified. a) 2m long b) 4m long

nr

N/A

7.3.1.6

m2

N/A

7.3.2 7.3.2.1

Sum nr

N/A N/A

7.3.2.2

Carried to Collection

* Delete where not applicable.

BQ7 - 5/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. DESCRIPTION OF WORK UNIT c) 6m long d) exceeding 6m long but not exceeding 9m (.....m) 7.3.2.3 Construct ...mm thick sprayed grade . concrete on unstable fractured rock face as shown in the drawing. Carry out pull-out test rock bolt GROUND ANCHORAGE Provide the necessary drilling and grouting equipment and all other appliances required for the installation of the ground anchor including staging, storage of the above on site during the progress of work and removal from the site on completion as directed by the S.O/P.D*. Supply and install ...kN ground anchors as shown in drawing including anchor heads and necessary inspection as specified. Pull out anchor test as specified HORIZONTAL DRAINS Supply and install ..mm diameter horitonzal darins with ..mm diameter perforated pvc pipe wrapped with non-woven geotextile as shown in the drawing. a) 9m long b) 12m long nr nr N/A N/A QTY RATE (RM) AMOUNT (RM) (SEN)

m2 nr

N/A N/A

7.3.2.4 7.3.3 7.3.3.1

Sum

N/A

7.1.3.2b

nr nr

N/A N/A

7.1.3.3b 7.3.4 7.3.4.1

Carried to Collection

* Delete where not applicable.

BQ7 - 6/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.4 7.4.1 7.4.1.1 DESCRIPTION OF WORK UNIT RETAINING SYSTEM REINFORCED SOIL WALLS Provide teams of competent and experienced personnel including mobilisation of plant and equipment, workmanship and everything else necessary for the installation of reinforced soil wall including storage of the above on Site during the progress of work and removal from site on completion as directed by the S.O/PD*. Supply and delivery of reinforced soil wall components consisting of ........ shaped precast concrete panels, reinforcing tendons, anchor blocks, joint fillers, cushion pads, fasterners and inclusive of cast-in-situ wall panels as per specification and drawings. Erection and installation of . shaped precast concrete panels in successive horizontal lifts to form reinforced soil wall components consisting of tendons to the panels and anchor blocks and insertion of joint fillers as per specification and drawings. 350mm x 150mm cast-in-situ mass concrete grade 20 levelling pad. QTY RATE (RM) AMOUNT (RM) (SEN)

Sum

N/A

7.4.1.2

m2

N/A

7.4.1.3

m2

N/A

7.4.1.4

N/A

7.4.1.5 ..mm single size aggregate as drainage blanket including .(type) non woven geotextile as filter. 7.4.1.6 River/mining* sand fill to reinforced soil wall as per specification. REINFORCED SOIL SLOPES Geogrid ..(strength)... or equivalent for reinforced walls or slopes on interface of cut & fill areas inclusive of non-woven geotextile reinforcement facing all as shown in the drawing. Geogrid (strength) or equivalent to stabilise embankment toe as shown in the drawing. m
2

N/A

m3

N/A

7.4.2 7.4.2.1

N/A

7.4.2.2

m2

N/A

4.00 Carried to Collection

* Delete where not applicable.

BQ7 - 7/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. 7.4.3 7.4.3.1 DESCRIPTION OF WORK UNIT REINFORCED CONCRETE RETAINING WALL Excavate in any material except rock to any depth for structural foundation. 50mm thick grade 15/20 lean concrete Formwork with Class F1 finish. Grade 30 concrete 75mm dia. UPVC pipes at 2000 mm centres wrapped with approved filter cloth. ..mm thick river/mining* sand as free draining material. .mm wide PVC waterstop for construction joint as shown in Drawing. .mm diameter m.s. dowel bars galvanised for expansion joint as in shown in Drawing. Joint sealer at ..m interval. High Yield Steel Reinforcement: i) Up to 12mm diameter. ii) 16mm diameter. iii) 20mm diameter. iv) 25mm diameter. v) 32mm diameter. Apply two layers of bituminous coating to internal surfaces of retaining walls as directed by the S.O. QTY RATE (RM) AMOUNT (RM) (SEN)

2200 400 1100 2200

7.4.3.2 7.4.3.3 7.4.3.4 7.4.3.5

m2 m
2

m3

nr

1100

7.4.3.6

m2

N/A

7.4.3.7

nr

100

7.4.3.8

nr m

700 N/A

7.4.3.9 7.4.3.10

t t t t t

60 60 N/A N/A N/A

7.4.3.11

N/A

Carried to Collection

* Delete where not applicable.

BQ7 - 8/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALA BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ), DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 7 GEOTECHNICAL WORKS ITEM NO. DESCRIPTION OF WORK UNIT QTY RATE (RM) AMOUNT (RM) (SEN)

COLLECTION PAGE

BQ 7 - 1/9 BQ 7 - 2/9 BQ 7 - 3/9 BQ 7 - 4/9 BQ 7 - 5/9 BQ 7 - 6/9 BQ 7 - 7/9 BQ 7 - 8/9

TOTAL CARRIED TO SUMMARY

* Delete where not applicable.

BQ7 - 9/9

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 12 - PROVISIONAL SUM ITEM NO. 12.1 DESCRIPTION OF WORKS AMOUNT (RM)

TELEPHONE BILLS FOR S.O/P.D* 20,000.00 Allow a Provisional Sum of RM 20,000.00 to provide for telephone bills for S.O/P.D*.

12.2

STREET LIGHTING AND TRAFFIC LIGHTS Allow a Provisional Sum of RM 250,000.00 to provide for street lighting and traffic lights. 250,000.00

12.3

LANDSCAPING Allow a Provisional Sum of RM . for landscaping works. N/A

12.4

RELOCATION OF UTILITY SERVICES Allow a Provisional Sum of RM 350,000.00 for the protection and / or relocation of the following utilities services : i) TNB 350,000.00

ii) Telecommunication iii) Waterworks iv) Gas Supply v) Sewerage 12.5 KTMB Allow Provisional Sum of RM for KTMB flaging and inconvenience charges. 12.6 ADDITIONAL TESTING OF MATERIALS AND WORKS Allow a Provisional Sum of RM . for the the testing of materials and works as stipulated in Clause 9 of the Conditions of Contract. 12.7 ADDITIONAL S.I WORKS DURING CONSTRUCTION Allow a Provisional Sum of RM 70,000.00 to carry out additional S.I works during construction. 12.8 ADDITIONAL UTILITY DETECTION AND MAPPING Allow a Provisional Sum of RM 50,000.00 to carry out utility detection and mapping during construction. Carried to Collection 50,000.00 70,000.00 N/A N/A

* Delete where not applible

BQ 12 - 1/3

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 12 - PROVISIONAL SUM ITEM NO. 12.9 AERIAL INSPECTION Allow a Provisional Sum of RM . to carry out aerial inspection of the project site. 12.10 INTELLIGENCE "I-SUPERVISION" Allow a Provisional Sum of RM . to carry out I-supervision of the progress of works during construction. 12.11 CONSTRUCTION SUPERVISION Allow a Provisional Sum of RM . to carry out construction supervision during construction. 12.12 TRAINING AND NEW TECHNOLOGY Allow a Provisional Sum of RM . to train JKR staff and for the acquisition of new technology. 12.13 RECONSTRUCTION OF ACQUIRED GOVERNMENT / PUBLIC FACILITIES Allow a Provisional Sum of RM . for the acquisition of government / public facilities. N/A N/A N/A N/A N/A DESCRIPTION OF WORKS AMOUNT (RM)

12.14

TEMPORARY RELOCATION AND PROTECTION OF UTILITIES AND OTHER SERVICES Allow a Provisional Sum of RM 100,000.00 to identify, temporary protection and temporary relocation of utilities and other services. 100,000.00

12.15

ADDITIONAL SURVEY WORK Allow a provisional sum of RM30,000.00 to carry out additional survey work 30,000.00

Carried to Collection

* Delete where not applible

BQ 12 - 2/3

PROJEK : CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT (ALL ITEMS ARE PROVISIONAL) BILL NO. 12 - PROVISIONAL SUM ITEM NO. DESCRIPTION OF WORKS AMOUNT (RM)

COLLECTION PAGE

BQ 12 - 1/3 BQ 12 - 2/3

TOTAL CARRIED TO SUMMARY

* Delete where not applible

BQ 12 - 3/3

S-ar putea să vă placă și