Sunteți pe pagina 1din 83

ELECTRIC

DISTRIBUTION
ESTIMATING
BOOK
2009

Avista Utilities, Distribution Design


PO Box 3727, Spokane WA 99220-3727 (509) 489-0500

2004 Avista Utilities. All Rights Reserved.

LOADED DOLLARS PER MAN-HOUR

ZONE1A
ZONE1B
ZONE1C
ZONE1D
ZONE1E
ZONE1F
ZONE2A
ZONE2B
ZONE2C
ZONE3A
ZONE3B
ZONE3C
ZONE4A
ZONE4B
ZONE4C
ZONE5A
ZONE5B
ZONE5C
ZONE6A
ZONE6B
ZONE6C

3-Man Crew

4-Man Crew

5-Man Crew

67.05
77.53
88.73
102.99
118.23
135.38
90.88
105.98
123.55
92.71
108.41
126.74
94.40
110.59
129.64
96.02
112.76
132.52
98.16
115.62
136.35

63.27
72.93
83.91
96.20
110.11
125.72
86.58
100.65
116.99
88.91
102.88
119.93
89.80
106.56
122.66
91.30
106.91
125.32
93.26
109.55
128.86

58.02
66.75
76.64
87.69
100.13
114.11
80.05
92.93
107.82
81.58
94.94
110.49
82.99
96.80
112.95
84.33
98.61
115.36
86.11
100.97
118.53

WEIGHTED
AVERAGE
62.78
72.41
83.09
95.63
109.49
125.07
85.84
99.85
116.12
87.73
102.08
119.06
89.06
104.65
121.75
90.55
106.10
124.40
92.51
108.71
127.91

LOADING MULTIPLIERS FOR ESTIMATING


WEIGHTED MATERIAL MULTIPLIER
WITHOUT TRANSPORTATION
1.120

AVERAGE UNLOADED LABOR RATE PER MAN-HOUR


3-Man Crew
$35.20

4-Man Crew
$33.29

1-1

5-Man Crew
$30.57

05/09

INSTALLED COST FOR 30-FOOT POLE


1

(Assume Zone 1A - Wiring and Luminaire Not Included)


2
3
4
5

6
Purchase
Retirement
Value
183.55
202.69
237.90
273.65
294.27
316.97
326.09
336.34
301.86
336.66
372.85
322.71
360.33
342.80
377.42
395.94
417.28
440.31
463.34
503.84
538.89
565.63
628.99
669.33
684.26
739.86
762.42
685.63
741.24
728.50
812.72
886.53

Year
Installed
Depreciation
Current
Price to
Install
Cost
Percent
Value
Customer
1978
183.55
42.0%
77.15
1.00
1979
202.69
43.9%
88.98
1.00
1980
237.90
45.8%
108.89
1.00
1981
273.65
47.6%
130.37
1.00
1982
294.27
49.5%
145.69
12.93
1983
316.97
51.4%
162.86
30.10
1984
326.09
53.3%
173.64
40.88
1985
336.34
55.1%
185.39
52.63
1986
301.86
57.0%
172.03
39.27
1987
336.66
58.9%
198.16
65.40
1988
372.85
60.7%
226.43
93.67
1989
322.71
62.6%
202.02
69.26
1990
360.33
64.5%
232.30
99.55
1991
342.80
66.3%
227.41
94.65
1992
377.42
68.2%
257.44
124.68
1993
395.94
70.1%
277.47
144.72
1994
417.28
72.0%
300.23
167.47
1995
440.31
73.8%
325.04
192.28
1996
463.34
75.7%
350.70
217.94
1997
503.84
77.6%
390.78
258.02
1998
538.89
79.4%
428.04
295.28
1999
565.63
81.3%
459.86
327.10
2000
628.99
83.2%
523.13
412.55
2001
669.33
85.0%
569.20
480.80
2002
684.26
86.9%
594.69
528.47
2003
739.86
88.8%
656.85
612.81
2004
762.42
90.7%
691.13
669.27
2005
685.63
92.5%
634.34
634.34
2006
741.24
94.4%
699.66
699.66
2007
728.50
96.3%
701.25
701.25
2008
812.72
98.1%
797.52
797.52
2009
886.53
100.0%
886.53
886.53
COLUMN NOTES:
1
Year Installed
2
Installed Cost: All costs are for Zone 1A, with 3-man crew.
3
Depreciation Percent: Annual depreciation rate (see page 1-3).
4
Current Value: Installed cost times depreciation percent.
5
Purchase Price to Customer: CURRENT VALUE minus REMOVAL
(1.98 MH x 3-man crew-Zone 1A rate) plus SALVAGE (page 6-2).
Company property must be sold for no less than $1.00.
Obtain a Bill of Sale for our records when selling poles to customers.

1-2

05/09

UNRECOVERED COST
Refer to the following table and find the Account Number for the Depreciable
Property. Each account must be figured separately for each year.

EXAMPLE:
(1) 30P85
2009
- 1985
24

Acct. 364 (has an average life span of 45 years)


(depreciable property) (installed cost $336.34)
(present year)
(year installed)
x 1.87% (Annual Dep. Rate) = 0.4488

Installed Cost x Depreciation Rate = $336.34 x 0.4488 = $150.95


Unrecovered Cost =
$336.34 - $150.95 = $185.39
FERC
Account
Number

361
362
364
365
366
367
368
369
370
373
373.4

Account Title

Annual
Depreciation Rate
Rate (%)

DISTRIBUTION PLANT
Structures and Improvements
Station Equipment
Poles, Towers and Fixtures
Overhead Conductors/Devices
Underground Conduit
Underground Conductors/Devices
Line Transformers
Services
Meters
Street Lighting and Signals
High Pressure Sodium Vapor Lights

2.13
2.47
1.87
1.30
1.88
2.27
2.65
2.13
3.28
2.21
6.05

1-3

05/09

WIRE WEIGHTSOVERHEAD CONDUCTOR


(Pounds per 1000 Feet)

COPPER - BARE SOLID


Size
Pounds
8
50
6 (SD & HD)
79
4 (SD & HD)
126
2 (SD & HD)
201

COPPER - STRANDED
Size
Pounds
2
205
1/0
326
2/0 (SD & HD)
411
3/0
518
4/0
653
250 (SD & HD)
772
350
1081
500
1544
750
2316
1000
3088

COPPERWELD - BARE
Size
Pounds
8
46
6 Sol
73
4A
162
6A
102
8A
74
6 Iron
112
6 Crapo
112
9-1/2 D
56

Size
4
2
1/0
2/0
4/0
336.4
397.5
556.5
795

ALUMINUM - ACSR
Name
Pounds
Swanate
67
Sparrow
91
Raven
145
Quail
183
Penguin
291
Merlin
366
Ibis
547
Parakeet
717
Drake
1094

Size
6
4
266.8
336.4
556.5
795
954
1272

ALUMINUM - AAC
Name
Pounds
Peachbell
25
Tie Wire
39
Laurel
250
Tulip
316
Dahlia
522
Arbutus
746
Magnolia
900
Narcissus
1194

GUY WIRE
Size
Pounds
9 Iron
58
6 Iron
112
5/16 (3W)
171
5/6 EHS
205
3/8 UG
273
7/16 UG
399
1/2 UG
517

COPPER - COVERED SOLID


Size
Pounds
6 (SD)
87

1-4

05/09

WIRE WEIGHTSOVERHEAD CONDUCTOR


SECONDARY 600V
(Pounds per 1000 Feet)
COPPER - INSULATED 600V
Size
Pounds
2
230
1/0
367
3/0
572
250
810
500
1600

ALUMINUM-INSULATED 600V
Size
Name
Pounds
6DX
Sheppard
77
4TX
Periwinkle
172
2TX
Cockle
230
2/0TX
Cavolinia
460
4/0TX
Cerapus
695
2QX
Palomino
355
2/0QX
Grullo
690
4/0QX
Appaloosa
1034

WIRE WEIGHTSUNDERGROUND
PRIMARY & SECONDARY
(Pounds per 1000 Feet)
ALUMINUM JACKETED with
CONCENTRIC NEUTRAL
Size
Pounds
2
550
1 Sol
600
1/0 (Full N)
623
1/0 (1/3N)
560
350 (1/3N)
1120
750 (1/3N)
2000
1000 EPR (1/8N)
2160
1 Sol TX
1800
1 (25kV)
675
1/0 (35kV)
920

ALUMINUM-INSULATED 600V
Size
Name
Pounds
6DXUG
Claflin
100
2TXUG
Stephens
275
2/0TXUG
Converse
525
4/0TXUG
Sweetbriar
765
350TXUG
Wesleyan
1161
2/0QXUG
Syracuse
705
4/0QXUG
Wake Forest
1038
350QXUG
Slippery Rock
1552
(3)350
Rutgers
1350
(3)750
Sewanee
2730

MISCELLANEOUS OH & UG
SINGLE STRAND CONDUCTOR - 600V
Size
Name
Pounds
2AL
Clemson
100
2/0AL
Yale
190
4/0AL
Beloit
280
350AL
Rutgers
450
750AL
Sewanee
910

1-5

05/09

ZONE INDICATOR
Each Zone Indicator consists of two characters which signify the location of a job
site with respect to a temporary headquarters (THQ) and/or a permanent
headquarters (HQ). All of the indicators currently in use can be interpreted from
the general form below.
ZONE

1.
2.
3.
4.
5.
6.

THQ to HQ
No THQ exists
31-40 Miles
41-50 Miles
51-60 Miles
61-70 Miles
71-80 Miles

A.
B.
C.
D.
E.
F.

SITE to THQ
0-10 Miles
11-20 Miles
21-30 Miles
31-40 Miles
41-50 Miles
51-60 Miles

Examples:
ZONE 1CThe job site is located within 21-30 miles of the permanent
headquarters.
ZONE 3BThe job site is within 11-20 miles of the temporary headquarters. The
THQ in turn is located within 41-50 miles of the permanent headquarters.
ASSIGNED ZONES FOR LOCATIONS SERVED FROM HEADQUARTERS (HQ)
AND FROM TEMPORARY HEADQUARTERS (THQ). ONE DAY BASIS FROM HQ
AND ONE WEEK BASIS FROM THQ.

SPOKANE AREA - S50


Miles
From
HQ
10
20
12
9
17
7
21
14
17
12
7
15

Zone
Subzone
1A
1A
1B
1B
1A
1B
1A
1C
1B
1B
1B
1A
1B

Spokane
Airway Hts
Cheney
Colbert
Dartford
Deep Creek
Dishman
Espanola
Four Lakes
Liberty Lake
Marshall
Mead
Medical Lake

1-6

Miles
From
5
14
9
11

Zone
Subzone
1A
1B
1B
1B

Millwood
Nine Mile Falls
Opportunity
S.I.P.

HQ
9
4
4
16
12
11
10

1A
1A
1A
1A
1B
1B
1B
1A

Deer Park
Chattaroy
Clayton
Denison
Deer Lake
Elk
Loon Lake
Williams Valley

05/09

COEUR D' ALENE AREA - L53


Miles
From
HQ
31
1
3
38
6
9
4
11

Zone
Subzone
1A
1D
1A
1A
1D
1A
1A
1A
1B

Coeur d'Alene
Blanchard
Clarkville
Dalt. Gard.
Harrison
Hayden
Hayden Lake
Huetter
McGuire

Miles
From
7
13
24
14
18

Zone
Subzone
1A
1B
1C
1B
1B

WASH
HQ
40

1A
1D

Post Falls
Rathdrum
Spirit Lake
State Line
Twin Lakes

Coeur d'Alene
Newport

SANDPOINT AREA - J53


Miles
From
IDAHO
HQ
25
3
21
18
3
33
31
2
22
13
12

Zone
Subzone
1A
1C
1A
1C
1B
1A
1D
1D
1A
1C
1B
1B

Sandpoint
Clark Fork
Douer
E-Hope
Hope
Kootenai
N. of Priest River
Old Town
Pend Oreille
Priest River
Sagle
Sunnyside

KELLOGG/ST. MARIES AREA - H53


Miles
From
HQ
11
8
7
26
24
18
23
7
4
5

Zone
Subzone
1A
1B
1A
1A
1C
1C
1B
1C
1A
1A
1A

Kellogg
Cataldo
Enaville
Kingston
Lane
Lookout Pass
Mullan
Murray
Osburn
Page
Pinehurst

1-7

Miles
From
22
20
3
12
2

Zone
Subzone
1C
1B
1A
1B
1A

Pritchard
Rose Lake
Smelterville
Wallace
Wardner

HQ
49
27
13
16

1A
1E
1C
1B
1B

St. Maries
Avery
Calder
Harrison
St. Joe

05/09

COLVILLE AREA - G50


Miles
From
HQ
15
6
25
18
25
22
20
31
33
6
35
8
38
20
9
47
42
27

Zone
Subzone
1A
1B
1A
1C
1B
1C
1C
1B
1D
1D
1A
1D
1A
1D
1C
1A
1E
1E
1C

Colville
Addy
Arden
Barstow
Blue Creek
Bissell Lake
Bossburg
Boyds
Daisy
Deep Lake
Finley Gulch
Gifford
Greenwood
Inchelium
Kelly Hill
Kettle Falls
Kewa
Laurier
Marble

1-8

Miles
From
14
15
35
10
31
4
18
26
12
8
45

Zone
Subzone
1B
1B
1D
1A
1D
1A
1B
1C
1B
1A
1E

24
2
18
6
2
10

1C
1A
1B
1A
1A
1A

Marcus
North Basin
Northport
Onion Creek
Orient
Orin
Pleasant Valley
Rice
Summit Valley
Tiger Highway
Twin Lakes

Chewelah
Burnt Valley
Deer Creek
Grouse Creek
Sand Canyon
Waitts Lake

05/09

LEWIS-CLARK AREA - D53


Miles
From
IDAHO
HQ
26
13
2
45

Zone
Subzone
1A
1C
1B
1A
1E

Clarkston
Culdesac
Lapwai
Lewiston
Orofino

HQ
15
33
8
61
48
24
7
27
25
32
46

1A
1B
1D
1A
1F
1E
1C
1A
1C
1C
1D
1E

Grangeville
Cottonwood
Craigmont
Denver
Elk City
Fall Creek
Ferdinand
Fern
Kamiah
Kooskia
Nez Perce
Reubens

1-9

Miles
From

Zone
Subzone

20
41

1C
1E

Stites
Winchester

THQ
19
19

5A
5B
5B

Elk City
Fall Creek
Red River

THQ
9
52
39
26

5A
3A
3E
3D
3C

Orofino
Greer
Headquarters
Pierce
Weippe

WASH
HQ
6
8
3

1A
1A
1A
1A

Clarkston
Asotin
Silcott
Wilma

05/09

OTHELLO - H50 / DAVENPORT - P50 AREA


Miles
From
HQ
36
41
48
24
32
10
16
41

Zone
Subzone
1A
1D
1E
1E
1C
1D
1A
1B
1E

Othello
Lind
Lotus
Ritzville
Roxboro
Schrag
Taunton
Warden
Washtucna

HQ
41
21
23
30
35
33
36
14

1A
1E
1C
1C
1C
1D
1D
1D
1B

Davenport
Almira
Creston
Edwall
Enterprise
Ford
Fruitland
Govan
Harrington

1-10

Miles
From
37
28
28
38
13
62
38
46
41
25
33
30

Zone
Subzone
1D
1C
1C
1D
1B

1D
1E
1E
1C
1D
1C

Hunters
Little Falls
Long Lake
Odessa
Reardan
RIT (See Oth.)
Sprague
Springdale
Tumtum
Waukon
Wellpinit
Wilbur

THQ
16
31
24
28

4A
4B
4C
4C
4C

Ritzville (HQ
Oth. or Dav.)
Lind
Odessa
Sprague
Washtucna

05/09

PULLMAN AREA - B53


Miles
From
IDAHO
HQ
40
30
59
21
28
34
10
35
31
4
22
24
23
18
13
WASH
HQ
11
20
16
28
38
52

Zone
Subzone
1A
1D
1C
1F
1C
1C
1D
1A
1D
1D
1A
1C
1C
1C
1B
1B

Pull Serv. Cntr.


Bovill
Deary
Elk River
Genesee
Harvard
Helmer
Joel
Juliaetta
Kendrick
Moscow
Onaway
Potlatch
Princeton
Troy
Viola

1A
1B
1B
1B
1C
1D
1F

Pull Serv. Cntr.


Albion
Colfax
Colton
Diamond
Endicott
Ewan

1-11

Miles
From

Zone
Subzone

65
34
31
14
47
55
45
37
20
48
44
71
40
55
45
45
30
43
50
31
35
19
50
22
44

1F
1D
1D
1B
1E
1E
1E
1D
1B
1E
1D
1F
1D
1E
1E
1E
1D
1E
1E
1D
1D
1B
1E
1C
1D

Fairfield
Farmington
Garfield
Johnson
Lacrosse
Latah
Malden
Oakesdale
Palouse
Pine City
Plaza
Rockford
Rosalia
Spangle
Spring Valley
St. John
Steptoe
Sunset
Tekoa
Thera
Thornton
Uniontown
Waverly
Wawawai
Winona

05/09

Schedule 51 Costs
WASHINGTON
The costs on this page are published in Schedule 51 and must be used
whenever they fit the situation. They are applicable to all single-phase
extensions in the companys service territory and to all single-phase
customers up to 72,000 kWh per year.
NOTES: These are the only costs published in the tariff.
Do not apply zone multipliers to the costs on this page.
Design Fee (for each design after the first and for all
large or complex jobs)

$100 per
design

Tariffed Construction Costs


Type
OH
OH
OH
OH

Facility
Primary
Secondary
Service
Transformer

Fixed Cost
$3774
$253
$253
$1173

UG
UG
UG
UG

Primary
Secondary
Service
Transformer

$1384
$199
$199
$1659

DEVEL

ALL

$1701

+
+
+

Variable Cost
$4.04
$4.23
$4.23

+
+
+

$8.45
$6.80
$6.80

per foot
per foot
per foot
per xfmr
per foot
per foot
per foot
per xfmr
per lot

Tariffed Allowances (see Page 2-5)


New Load
Temporary
0 to 4800 kWH Per Year
Mobile Home Not On An Improved Lot
With 4800 to 72,000 kWH/Year:
Schedule 1
Single Family Residence
Duplex Residence
Multiple Family Residence
Schedule 11 or 12

Allowances
$0
$0
$0

per customer
per customer
per customer

$1000
$800
$600
$1300

per customer
per living unit
per living unit
per customer

Development Costs
Advance Payment, Credit Instrument or
Promissory Note (up to 175 ft. frontage)
$1701
$522 Maximum
Cost Reductions for Work by Developer
Advance Payment with Maximum Cost Reduction
$1179
Maximum Allowable Refund
$1179
Builder Charge for Service Installation
$766

2-1

per lot
per lot
per lot
per lot
per lot

WASHINGTON 05/09

General Comments on Schedule 51


The tariff covers all distribution construction in the company including
single-phase, three-phase, large and small loads, conversions from
overhead to underground, and relocations of either overhead or underground
primary or services.
The only costs in the tariff are for single-phase loads.
Other costs can be estimated from a layout of the extension or using the
average costs of construction on the following pages.
Additional information and examples are available in the Electric Line
Extension Practices manual and from the Distribution Engineering
Supervisor.

IPUC and WUTC


If the customer disagrees with your interpretation of Schedule 51 and you
have confirmed that interpretation with others in the company, you should
refer the customer to the appropriate commission.
IPUC

(208) 334-0300

WUTC

1-800-562-6150

Zone Multipliers
Do not apply zone multipliers to the single-phase extension costs
published in the tariff. Those extension costs are already weighted for the zones
in which construction activity has been occurring.
However, if you use other average costs in Section 2 of the Distribution
Estimating Book, multiply by the appropriate zone multiplier below to
estimate the on-site cost.
These multipliers are averages for all normal construction including
Exceptional Costs.

Zone Multipliers for (Non-Tariffed) New OH and UG Construction


1A ..
1B ..

1.00
1.10

1C ..
1D ..

1.20
1.30

2-2

1E ..
1F ..

1.45
1.55

WASHINGTON 05/09

Overhead Primary Construction Costs


Average installed costs through 2/0 ACSR with dirt holes. See zone multipliers
on page 2-2.
Phases
2 & Nt
3 & Nt

Fixed Cost
$5185
$5706

+
+

Variable Cost
$4.59
$5.27

per foot
per foot

Add Phases To Existing Pole Line


Average costs through 2/0 ACSR. Includes crossarms but no new poles and
no hot work (see Exceptional Costs). Fixed Cost is for circuit only.
Wire Added Fixed Cost
3rd
$806
4th
$209
3rd & 4th
$1095

+
+
+

Variable Cost
$1.05
$0.69
$1.60

per foot
per foot
per foot

If a transformer bank will be modified in the section where wire will be added,
add $523 for mounting bracket, cutout and lightning arrester for each
transformer added.

Underground Primary Construction Costs


Average installed costs for #1 or 1/0 ALCN in dirt. Variable cost includes
cable, ditch and conduit (CDT). Cost of PLOWing is assumed to be $2.50
per foot. See zone multipliers on page 2-2.

Phases
2
3

Fixed Cost
$2187
+
$2066
+

CDT
$13.45
$16.88

Variable Cost
DB
Plow
$10.75
$7.35
$13.15
$9.75

per foot
per foot

Cable Pulls: Use the following guideline for cable pulls in conduit. Count one
setup for every transformer and junction enclosure; and one pull for every cable
leaving the setup location.
SETUP:
1/2 man-hour
EACH PULL:
1 man-hour per cable

Note: The fixed costs are nearly the same because more materials are
provided by Avista Utilities at the load end of the 2-phase extension (i.e. 2 pads,
2 ground sleeves & 2 grounds vs. 1 ground sleeve & 1 ground). The 3-phase
concrete pad is normally provided by the customer.

2-3

WASHINGTON 05/09

Overhead Service Construction Costs


Use zone multipliers on page 2-2.

Type
Parallel TX
QX
Parallel QX

Source
OH
OH
OH

Fixed Cost
$126
$273
$292

+
+
+

Variable Cost
$6.28
$6.76
$11.64

per foot
per foot
per foot

Underground Service Construction Costs


Use zone multipliers on page 2-2.

Type
Source
Parallel TXUG
UG
QXUG
UG
Parallel QXUG
UG

Fixed Cost
$298
$255
$397

+
+
+

Variable Cost
DB
CDT
$8.24 $11.06
$7.48 $10.30
$10.77 $13.59

per foot
per foot
per foot

Street Lights
Use the following cost for the Exceptional Cost for developer-contributed
street light standards. They cover the difference between the installed cost
of a wood pole and the installed cost of a metal standard with base and
grounding.
DIRECT-BURIED STEEL
PEDESTAL-BASE FBRGLS GREEN
PEDESTAL-BASE LONG STEEL
PEDESTAL-BASE SHORT STEEL

$1074
$1628
$1726
$1604

per standard
per standard
per standard
per standard

Monthly rates cover the cost of installation and maintenance of the street
light. The rates do not include ditch or conduit. If the street lights are
requested after the ditch is closed, the customer is responsible for the
cost of trenching. If conduit is required, the customer is responsible for the
cost of conduit.

2-4

WASHINGTON 05/09

Cost Reductions (System Average)


All Cost Reductions allow for inspection by Avista Utilities. Cost Reductions are
based on costs used to develop the tariffed costs. Use local bids or zone multipliers
to adjust for distance from headquarters.

For Individual Customers and Backbones:


FOR:
Plowed installation of cable*
Service ditch by customer
Primary ditch by customer
Conduit by customer (2 in.)
Avista ditch; Joint with Gas

SUBTRACT:
$2.46
$3.64
$4.31
$1.08
$2.01

per foot
per foot
per foot
per foot
per foot

*NOTE: Enter the cost reduction for plowing (credit) under


Exceptional Costs on the Construction Contributions page of the
Electric Service Agreement form. (See pages 3-12 and 3-13 in the
Electric Line Extension Practices manual).

For Developments:
Maximum Cost Reduction shall not exceed $522 per lot or the values below,
whichever is less.
FOR:
Ditch by Developer
Avista Utilities Ditch:
Conduit by Developer -- Primary
-- Secondary
Avista Utilities Ditch; Joint with Gas

SUBTRACT:
$522

per lot

$92
$15
$173

per lot
per lot
per lot

Allowances For Large Customers


When the customers usage is expected to exceed 72,000 kWh per year, multiply
the expected annual usage by the appropriate factor in the following table to find the
customers allowance. Determine the usage from similar buildings and industries or
customer histories.
Schedule
11 or 12
21 or 22
31 or 32
25

Load
General
Large General
Pumping
Extra Large General

2-5

Allowance Factor
WA
0.09313
x kWh
0.04295
x kWh
0.06858
x kWh
Contact Rates & Tariffs

WASHINGTON 05/09

*Exceptional/Customer-Requested Costs
Use zone multipliers on page 2-2 for items on this page.
Clearing:
Light
$0.35
per foot
Medium
$0.70
per foot
Medium w/Cleanup
$1.05
per foot
Heavy w/Cleanup
$1.40
per foot
Pole Haul in Rock
30 to 55 ft. Poles
$540
per pole
or Frozen Ground:
60 to 70 ft. Poles
$695
per pole
Ditch Adders:
Dirt
Loose Rock
24 in.
0
$2.90
per foot
30 in.
0
$4.11
per foot
36 in.
$0.94
$5.72
per foot
42 in.
$1.90
$7.32
per foot
Cable Burial Costs:
Fixed
Variable
Cut & Replace Asphalt
$325
+ $9.09
per sq foot
Cut & Replace Concrete
$662
minimum
(4 in. thick)
$88
per sq yard
Boring with Conduit (1-3 phases)
$20
per foot
Compaction:
90%
$2.52
per foot
95%
$6.05
per foot
Sandpadding
$0.71
per foot
Temporary Transformer (Overhead)
$559
each
Temporary Transformer (Underground)
$612
each
Service Costs (N2):
Fixed
Variable
Reconnect OH Service
$52
each
Reconnect UG Service
$70
each
Temp Service 100 ft or shorter
$90
each
Temp Service over 100 ft long
$10.55
+ $0.80
per foot
Long Ladder Jobs
$401
each
UG Service in OH Area:
Fixed
DB
in CDT
TXUG
$210
$1.98
$3.17
Parallel TXUG
$514
$1.96
$4.78
QXUG
$422
0.95
$2.14
Parallel QXUG
$653
--$2.42
Extra Junction Enclosure:
New Line
Existing Line
JE1
$1211
$1682
each
JE2
$1916
$2809
each
JE3
$2664
$3978
each
Submersible Enclosures (Add to JE Cost):
SE1
$2422
extra each
SE2
$3177
extra each
SE3
$2933
extra each

2-6

WASHINGTON 05/09

*Exceptional/Customer-Requested Costs (continued)


Do not use zone multipliers for items on this page.
Rights of Way: (Contact Real Estate for more information).
On Private Property
$Variable
On Public R/W
$Variable Franchise Fee
Highway Crossing
$150 to $500
BNSF Crossing
$2750 to $3750
UPRR Crossing
$1,500
DNR Crossing/State Parks
$1,500
DNR Crossing (variable)
+ 150% of land value
Overtime Rates: (N3)
1A
$66.58
1B
$73.24
1C
$79.90
1D
$86.55
1E
$96.54
1F
$106.53

per structure/acre
per crossing
per crossing
per crossing
administrative fee
easement fee
per manhour
per manhour
per manhour
per manhour
per manhour
per manhour

Notes:
N1. Use local bids when possible.
N2. The reconnection costs that are shown apply to services disconnected
at customers request. If service was disconnected by Avista Utilities
because customer failed to comply with the companys rules and
regulations (Schedule 70 Rule 14), the reconnection charge is $16.00
during working hours and $32.00 on overtime.
The rates for temporary service allow for labor and materials that cannot
be used for the permanent service.
N3. If the customer requests that work be performed before or after normal
company work hours, charge an Exceptional Cost based on the rate for
the work zone and the overtime manhours. The values in the table are
estimates.
N4. The Ditch Adders do not include conduit, sandpadding, compaction, etc.
Add the appropriate costs from the Cable Burial Costs.

2-7

WASHINGTON 05/09

Overhead Primary Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Phase
1
2
3

Fixed
$555
$887
$963

+
+
+

Variable
$0.39
$0.44
$0.47

per circuit foot


per circuit foot
per circuit foot

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
Phase
1
2
3

Fixed
$290
$748
$1125

+
+
+

Variable
$0.136
$0.312
$0.393

per circuit foot


per circuit foot
per circuit foot

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.
2005 ..
2000 ..
1995 ..

0.65
0.45
0.40

1990 ..
1985 ..
1980 ..

0.30
0.20
0.10

1975 ..
1970 ..
1965 ..

0.05
0.00
0.00

Example
A customer requests removal of a 1973 three-span tap (600 feet) of singlephase line on his property. His cost will be Removal less Salvage plus
Remaining Value. The zone is 1C.
Removal
Salvage
Remaining Value:
New cost (pg 2-1)
Rem value factor

(555 +(0.39 x 600)) x 1.40

3774 + (4.04 x 600)


0.05

$1105
-0$6198
x 0.05

Termination Cost

_310_
$1415

Note: If the tap is greater than 10 years old, the salvage value is zero.

2-8

WASHINGTON 05/09

Underground Primary Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Phase
1
2
3

Fixed
$59
$111
$106

Variable
CDT
DB
$0.15
$0.014
$0.014
$0.29
$0.014
$0.42

+
+
+

per circuit foot


per circuit foot
per circuit foot

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
Phase
1
2
3

Fixed
$352
$663
$332

Variable
$0.175
$0.039
$0.039

+
+
+

per circuit foot


per circuit foot
per circuit foot

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.
2005 ..
2000 ..
1995 ..

0.65
0.45
0.40

1990 ..
1985 ..
1980 ..

0.30
0.20
0.10

1975 ..
1970 ..
1965 ..

0.05
0.00
0.00

Example
A customer requests removal of a 2000 750-foot three-phase conduited UG tap
on his property. His cost will be Removal less Salvage plus Remaining Value.
The zone is 1B.
Removal
Salvage
Remaining Value:
New cost (pg 2-3)
Rem value factor

(106 + (0.42 x 750)) x 1.20


332 + (0.039 x 750)

$505
-361

(2066 + (16.88 x 750)) x 1.10


0.45

$16,199
x 0.45

Termination Cost

7290
$7434

Note: If the tap is greater than 10 years old, the salvage value is zero.
2-9

WASHINGTON 05/09

Overhead Service Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TX
Parallel TX
QX
Parallel QX

Average
$129
$225
$116
$197

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.85
2.10

Salvage Value
Type
TX
Parallel TX
QX
Parallel QX

Average
$25
$28
$32
$42

per service
per service
per service
per service

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.
2005 ..
2000 ..
1995 ..

0.65
0.45
0.40

1990 ..
1985 ..
1980 ..

0.30
0.20
0.10

2-10

1975 ..
1970 ..
1965 ..

0.05
0.00
0.00

WASHINGTON 05/09

Underground Service in Underground Area


Removal Costs
For removal of an underground service in an overhead area, see page 2-12.
The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

DB
$3
$5
$3
$7

Average
CDT
$60
$120
$61
$122

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

DB
$0
$0
$0
$0

Average
CDT
$1
$2
$5
$9

per service
per service
per service
per service

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.
2005 ..
2000 ..
1995 ..

0.65
0.45
0.40

1990 ..
1985 ..
1980 ..

2-11

0.30
0.20
0.10

1975 ..
1970 ..
1965 ..

0.05
0.00
0.00

WASHINGTON 05/09

Underground Service in Overhead Area


Removal Costs
For removal of an underground service in an underground area, see page 2-11.
The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

Average
DB
CDT
$49
$106
$98
$213
$51
$108
$101
$216

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
The DB salvage is for the riser.
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

Average
DB
CDT
$52
$53
$104
$106
$52
$53
$104
$106

per service
per service
per service
per service

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.
2005 ..
2000 ..
1995 ..

0.65
0.45
0.40

1990 ..
1985 ..
1980 ..

0.30
0.20
0.10

2-12

1975 ..
1970 ..
1965 ..

0.05
0.00
0.00

WASHINGTON 05/09

Overhead Extensions
Longer than 1500 Feet
Washington
Charge an Exceptional Cost for the overhead primary length in excess of 1500 feet.

EXAMPLE
A customer requests a 2350-foot single-phase extension. The line will be overhead
with an overhead service. Do a layout and estimate the cost of construction of the
primary for the appropriate construction Zone.

BASIC COST
Variable
Fixed
GROSS BASIC COST
ALLOWANCE
NET BASIC COST
EXCEPTIONAL COST
Long OH
TOTAL CONSTRUCTION

14

NOTES:

b
c
3
4
5
6
f

Service
40 FT
169
253
422
(422)

Transf
15 Kva
1173
1173
(578)
595

Primary
2310 FT
9332
3774
13,106
0
13,106

TOTAL

405

405
14,106

9501
5200
14,701
(1000)
13,701

Estimated Cost
(from layout)
Primary Tariffed Cost
Cost Difference

= $14,250 2310 ft =

$6.17 per foot

= $13,106 2310 ft =

$5.67 per foot


$0.50 per foot

Exceptional Cost

= (2310 ft -1500 ft) x ($6.17/ft - $5.67/ft)


= 810 ft x $0.50/ft
= $405

For more information, see the Electric Line Extension Practices manual..

2-13

WASHINGTON 05/09

Schedule 51 Costs
IDAHO
The costs on this page are published in Schedule 51 and must be used
whenever they fit the situation. They are applicable to all single-phase
extensions in the companys service territory. Three-phase primary costs
are also published in Schedule 51 and are shown on page 2-3.
NOTES: These are the only costs published in the tariff.
Do not apply zone multipliers to the costs on this page.
Design Fee (for each design after the first and for all
large or complex jobs)

$185 per
design

Tariffed Construction Costs


Type
OH
OH
OH
OH

Facility
Primary
Secondary
Service
Transformer

Fixed Cost
$3774
$253
$253
$1173

UG
UG
UG
UG

Primary
Secondary
Service
Transformer

$1384
$199
$199
$1659

DEVEL

ALL

$1701

+
+
+

Variable Cost
$4.04
$4.23
$4.23

+
+
+

$8.45
$6.80
$6.80

per foot
per foot
per foot
per xfmr
per foot
per foot
per foot
per xfmr

(Excludes service costs)

per lot

Tariffed Allowances (see Page 2-5)


New Load
Temporary
0 to 2500 kWH Per Year
Mobile Home Not On An Improved Lot
With at least 2500 kWH/Year:
Schedule 1
Single Family Residence
Duplex Residence
Multiple Family Residence
All other Schedules refer to page 2-5

Allowances
$0
$0
$0

per customer
per customer
per customer

$1000
$800
$600

per customer
per living unit
per living unit

Development Costs
Advance Payment, Credit Instrument or
Promissory Note (up to 175 ft. frontage)
$1701
$522 Maximum
Cost Reductions for Work by Developer
Advance Payment with Maximum Cost Reduction
$1179
Maximum Allowable Refund
$1179
Builder Charge for Service Installation
$766

2-1

per lot
per lot
per lot
per lot
per lot

IDAHO 05/09

General Comments on Schedule 51


The tariff covers all distribution construction in the company including
single-phase, three-phase, large and small loads, conversions from
overhead to underground, and relocations of either overhead or underground
primary or services.
The only costs in the Idaho tariff are for single-phase and three-phase loads.
Other costs can be estimated from a layout of the extension or using the
average costs of construction on the following pages.
Additional information and examples are available in the Electric Line
Extension Practices manual and from the Distribution Engineering
Supervisor.

IPUC and WUTC


If the customer disagrees with your interpretation of Schedule 51 and you
have confirmed that interpretation with others in the company, you should
refer the customer to the appropriate commission.
IPUC

(208) 334-0300

WUTC

1-800-562-6150

Zone Multipliers
Do not apply zone multipliers to the single-phase extension costs
published in the tariff. Those extension costs are already weighted for the zones
in which construction activity has been occurring.
However, if you use other average costs in Section 2 of the Distribution
Estimating Book, multiply by the appropriate zone multiplier below to
estimate the on-site cost.
These multipliers are averages for all normal construction including
Exceptional Costs.

Zone Multipliers for (Non-Tariffed) New OH and UG Construction


1A ..
1B ..

1.00
1.10

1C ..
1D ..

1.20
1.30

2-2

1E ..
1F ..

1.45
1.55

IDAHO 05/09

Overhead Primary Construction Costs


Average installed costs through 2/0 ACSR with dirt holes. See zone multipliers
on page 2-2.
Phases
2 & Nt
*3 & Nt

Fixed Cost
$5185
$5706

+
+

Variable Cost
$4.59
$5.27

per foot
per foot

Add Phases To Existing Pole Line


Average costs through 2/0 ACSR. Includes crossarms but no new poles and
no hot work (see Exceptional Costs). Fixed Cost is for circuit only.
Wire Added Fixed Cost
3rd
$806
4th
$209
3rd & 4th
$1095

+
+
+

Variable Cost
$1.05
$0.69
$1.60

per foot
per foot
per foot

If a transformer bank will be modified in the section where wire will be added,

add $523 for mounting bracket, cutout and lightning arrester for each
transformer added.

Underground Primary Construction Costs


Average installed costs for #1 or 1/0 ALCN in dirt. Variable cost includes
cable, ditch and conduit (CDT). Cost of PLOWing is assumed to be $2.50
per foot. See zone multipliers on page 2-2.
Phases
2
*3

Fixed Cost
$2187
+
$2066
+

CDT
$13.45
$16.88

Variable Cost
DB
Plow
$10.75
$7.35
$13.15
$9.75

per foot
per foot

Cable Pulls: Use the following guideline for cable pulls in conduit. Count one
setup for every transformer and junction enclosure; and one pull for every cable
leaving the setup location.
SETUP:
1/2 man-hour
EACH PULL:
1 man-hour per cable
Note: The fixed costs are nearly the same because more materials are
provided by Avista Utilities at the load end of the 2-phase extension (i.e. 2 pads,
2 ground sleeves & 2 grounds vs. 1 ground sleeve & 1 ground). The 3-phase
concrete pad is normally provided by the customer.
*The costs as disclosed in the tariff are done as general guidelines for
3-phase costs to meet commission requirements. These do not represent
all of the 2-phase and 3-phase configuration options. If the actual line
extension configuration is different than those that are associated with the
3-phase costs that are in the tariff, use the appropriate costs with the actual
method of construction as shown above.

2-3

IDAHO 05/09

Overhead Service Construction Costs


Use zone multipliers on page 2-2.

Type
Parallel TX
QX
Parallel QX

Source
OH
OH
OH

Fixed Cost
$126
$273
$292

+
+
+

Variable Cost
$6.28
$6.76
$11.64

per foot
per foot
per foot

Underground Service Construction Costs


Use zone multipliers on page 2-2.

Type
Source
Parallel TXUG
UG
QXUG
UG
Parallel QXUG
UG

Fixed Cost
$298
$255
$397

+
+
+

Variable Cost
DB
CDT
$8.24 $11.06
$7.48 $10.30
$10.77 $13.59

per foot
per foot
per foot

Street Lights
Use the following cost for the Exceptional Cost for developer-contributed
street light standards. They cover the difference between the installed cost
of a wood pole and the installed cost of a metal standard with base and
grounding.
DIRECT-BURIED STEEL
PEDESTAL-BASE FBRGLS GREEN
PEDESTAL-BASE LONG STEEL
PEDESTAL-BASE SHORT STEEL

$1074
$1628
$1726
$1604

per standard
per standard
per standard
per standard

Monthly rates cover the cost of installation and maintenance of the street
light. The rates do not include ditch or conduit. If the street lights are
requested after the ditch is closed, the customer is responsible for the
cost of trenching. If conduit is required, the customer is responsible for the
cost of conduit.

2-4

IDAHO 05/09

Cost Reductions (System Average)


All Cost Reductions allow for inspection by Avista Utilities. Cost Reductions are
based on costs used to develop the tariffed costs. Use local bids or zone multipliers
to adjust for distance from headquarters.

For Individual Customers and Backbones:


FOR:
Plowed installation of cable*
Service ditch by customer
Primary ditch by customer
Conduit by customer (2 in.)
Avista ditch; Joint with Gas

SUBTRACT:
$2.46
$3.64
$4.31
$1.08
$2.01

per foot
per foot
per foot
per foot
per foot

*NOTE: Enter the cost reduction for plowing (credit) under


Exceptional Costs on the Construction Contributions page of the
Electric Service Agreement form. (See pages 3-12 and 3-13 in the
Electric Line Extension Practices manual).

For Developments:
Maximum Cost Reduction shall not exceed $522 per lot or the values below,
whichever is less.
FOR:
Ditch by Developer
Avista Utilities Ditch:
Conduit by Developer -- Primary
-- Secondary
Avista Utilities Ditch; Joint with Gas

SUBTRACT:
$522

per lot

$92
$15
$173

per lot
per lot
per lot

Allowances For Large Customers


Multiply the expected annual usage by the appropriate factor in the following table to
find the customers allowance. For Idaho customers, use this table for all
commercial and industrial customers, regardless of usage. Determine the usage
from similar buildings and industries or customer histories.
Schedule
11 or 12
21 or 22
31 or 32
25

Load
General
Large General
Pumping
Extra Large General

2-5

Allowance Factor
ID
0.10703
x kWh
0.06000
x kWh
0.06000
x kWh
Contact Rates & Tariffs

IDAHO 05/09

*Exceptional/Customer-Requested Costs
Use zone multipliers on page 2-2 for items on this page.
Clearing:
Light
$0.35
per foot
Medium
$0.70
per foot
Medium w/Cleanup
$1.05
per foot
Heavy w/Cleanup
$1.40
per foot
Pole Haul in Rock
30 to 55 ft. Poles
$540
per pole
or Frozen Ground:
60 to 70 ft. Poles
$695
per pole
Ditch Adders:
Dirt
Loose Rock
24 in.
0
$2.90
per foot
30 in.
0
$4.11
per foot
36 in.
$0.94
$5.72
per foot
42 in.
$1.90
$7.32
per foot
Cable Burial Costs:
Fixed
Variable
Cut & Replace Asphalt
$425
+ $10.64
per sq foot
Cut & Replace Concrete
$662
minimum
(4 in. thick)
$88
per sq yard
Boring with Conduit (1-3 phases)
$20
per foot
Compaction:
90%
$2.52
per foot
95%
$6.05
per foot
Sandpadding
$0.71
per foot
Temporary Transformer (Overhead)
$559
each
Temporary Transformer (Underground)
$612
each
Service Costs (N2):
Fixed
Variable
Reconnect OH Service
$52
each
Reconnect UG Service
$70
each
Temp Service 100 ft or shorter
$90
each
Temp Service over 100 ft long
$10.55
+ $0.80
per foot
Long Ladder Jobs
$401
each
UG Service in OH Area:
Fixed
DB
in CDT
TXUG
$210
$1.98
$3.17
Parallel TXUG
$514
$1.96
$4.78
QXUG
$422
0.95
$2.14
Parallel QXUG
$653
--$2.42
Extra Junction Enclosure:
New Line
Existing Line
JE1
$1211
$1682
each
JE2
$1916
$2809
each
JE3
$2664
$3978
each
Submersible Enclosures (Add to JE Cost):
SE1
$2422
extra each
SE2
$3177
extra each
SE3
$2933
extra each

2-6

IDAHO 05/09

*Exceptional/Customer-Requested Costs (continued)


Do not use zone multipliers for items on this page.
Rights of Way: (Contact Real Estate for more information).
On Private Property
$Variable
On Public R/W
$Variable Franchise Fee
Highway Crossing
$150 to $500
BNSF Crossing
$2750 to $3750
UPRR Crossing
$1,500
DNR Crossing/State Parks
$1,500
DNR Crossing (variable)
+ 150% of land value
Overtime Rates: (N3)
1A
$66.58
1B
$73.24
1C
$79.90
1D
$86.55
1E
$96.54
1F
$106.53

per structure/acre
per crossing
per crossing
per crossing
administrative fee
easement fee
per manhour
per manhour
per manhour
per manhour
per manhour
per manhour

Notes:
N1. In Idaho exceptional costs may be covered in whole or part by any
remaining allowance.
N2. Use local bids when possible.
N3. The rates for temporary service allow for labor and materials that cannot
be used for the permanent service.

N4. If the customer requests that work be performed before or after normal
company work hours, charge an Exceptional Cost based on the rate
for the work zone and the overtime manhours. The values in the table
are estimates.
N5. The Ditch Adders do not include conduit, sandpadding, compaction,
etc. Add the appropriate costs from the Cable Burial Costs.
* Exceptional Cost is the cost of labor and/or materials which are
necessary to construct the Line Extension, but which are not reflected in
the Basic Cost. In Idaho, Exceptional Costs may be covered in whole or
in part by any remaining allowance. Customer-Requested Cost is the
cost of unusual labor and/or materials which is requested by the
customer but which is not necessary to construct the Line Extension
based on the companys minimum design, construction and operating
practices. All Customer-Requested Costs must be paid in full by the
customer, regardless of the allowance.

2-7

IDAHO 05/09

Overhead Primary Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Phase
1
2
3

Fixed
$555
$887
$963

+
+
+

Variable
$0.39
$0.44
$0.47

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

per circuit foot


per circuit foot
per circuit foot

..
..

1.80
2.10

Salvage Value
Phase
1
2
3

Fixed
$290
$748
$1125

+
+
+

Variable
$0.136
$0.312
$0.393

per circuit foot


per circuit foot
per circuit foot

Example
A customer requests removal of a 2001 three-span tap (600 feet) of singlephase line on his property. His cost will be Removal less Salvage.
The zone is 1C.
Removal
Salvage

(555 +(0.39 x 600)) x 1.40


290 + (0.136 x 600)

$1105
-372

Termination Cost

$733

Note: If the tap is greater than 10 years old, the salvage value is zero.
Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-8

IDAHO 05/09

Underground Primary Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Phase
1
2
3

Fixed
$59
$111
$106

Variable
DB
CDT
$0.15
$0.014
$0.014
$0.29
$0.014
$0.42

+
+
+

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

per circuit foot


per circuit foot
per circuit foot

..
..

1.80
2.10

Salvage Value
Phase
1
2
3

Fixed
$352
$663
$332

Variable
$0.175
$0.039
$0.039

+
+
+

per circuit foot


per circuit foot
per circuit foot

Example
A customer requests removal of a 2001 750-foot three-phase conduited UG tap
on his property. His cost will be Removal less Salvage.
The zone is 1B.
Removal
Salvage

(106 + (0.42 x 750)) x 1.20


332 + (0.039 x 750)

$505
-361

Termination Cost

$144

Note: If the tap is greater than 10 years old, the salvage value is zero.
Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-9

IDAHO 05/09

Overhead Service Removal Costs


The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TX
Parallel TX
QX
Parallel QX

Average
$129
$225
$116
$197

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
Type
TX
Parallel TX
QX
Parallel QX

Average
$25
$28
$32
$42

per service
per service
per service
per service

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-10

IDAHO 05/09

Underground Service in Underground Area


Removal Costs
For removal of an underground service in an overhead area, see page 2-12.
The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

DB
$3
$5
$3
$7

Average
CDT
$60
$120
$61
$122

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

DB
$0
$0
$0
$0

Average
CDT
$1
$2
$5
$9

per service
per service
per service
per service

Note: There is no longer a remaining value charged in Idaho. Please see


Tariff, page 51L for revised conversion/relocation formula.

2-11

IDAHO 05/09

Underground Service in Overhead Area


Removal Costs
For removal of an underground service in an underground area, see page 2-11.
The cost of terminating a facility may be estimated since it is not specified in
Schedule 51.

Removal Cost
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

Average
DB
CDT
$49
$106
$98
$213
$51
$108
$101
$216

per service
per service
per service
per service

Apply the following zone multipliers to removal costs:


1A .. 1.00
1C .. 1.40
1E
1B .. 1.20
1D .. 1.60
1F

..
..

1.80
2.10

Salvage Value
The DB salvage is for the riser.
Type
TXUG
Parallel TXUG
QXUG
Parallel QXUG

Average
DB
CDT
$52
$53
$104
$106
$52
$53
$104
$106

per service
per service
per service
per service

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-12

IDAHO 05/09

Overhead Extensions
Longer than 1500 Feet
Idaho
Charge an Exceptional Cost for the overhead primary length in excess of 1500 feet.

EXAMPLE
A customer requests a 2350-foot single-phase extension. The line will be overhead
with an overhead service. Do a layout and estimate the cost of construction of the
primary for the appropriate construction Zone.

BASIC COST
Variable
Fixed
GROSS BASIC COST
ALLOWANCE
NET BASIC COST
EXCEPTIONAL COST
Long OH
TOTAL CONSTRUCTION

14

NOTES:

b
c
3
4
5
6
f

Service
40 FT
169
253
422
(422)

Transf
15 Kva
1173
1173
(578)
595

Primary
2310 FT
9332
3774
13,106
0
13,106

TOTAL

316

316
14,017

9501
5200
14,701
(1000)
13,701

Estimated Cost
(from layout)
Primary Tariffed Cost
Cost Difference

= $14,000 2310 ft =

$6.06 per foot

= $13,106 2310 ft =

$5.67 per foot


$0.39 per foot

Exceptional Cost

= (2310 ft -1500 ft) x ($6.06/ft - $5.67/ft)


= 810 ft x $0.39/ft
= $316

For more information, see the Electric Line Extension Practices manual..

2-13

IDAHO 05/09

TASK NUMBER
(Used with Capital Blanket Project Numbers)

300100

Design and Engineering

107110

Add Overhead Primary Plant

107120

Add Underground Primary Plant

107199

Add Transformer - Materials Only

107200

Add Service Plant

107215

Add Development Joint Service

108000

Remove/Salvage/Retire Old Plant

3-1

05/09

CAPITAL BLANKET PROJECT NUMBERS


Residential Commercial
Revenue
Revenue
Blanket

Develop.
Revenue

Street
Lights

Area
Lights

ER1000

ER1000

ER1000

ER1004

ER1005

SPOKANE
NW County
NW City
Deer Park
NE County
NE City
Valley
Central
Network
West Plains
SW City

95001100
95101100
95201100
95301100
95401100
95501100
95601100
95701100
95801100
95901100

95001101
95101101
95201101
95301101
95401101
95501101
95601101
95701101
95801101
95901101

95001102
95101102
95201102
95301102
95401102
95501102
95601102
95701102
95801102
95901102

95001300
95101300
95201300
95301300
95401300
95501300
95601300
95701300
95801300
95901300

95001370
95101370
95201370
95301370
95401370
95501370
95601370
95701370
95801370
95901370

CDA
Post Falls

90101100
90101100

90101101
90101101

90101102
90101102

90101300
90101300

90101370
90101370

COLVILLE
Chewelah
Gifford/
Inchelium
Northport

96001100
96101100
96301100
96301100
96201100

96001101
96101101
96301101
96301101
96201101

96001102
96101102
96301102
96301102
96201102

96001300
96101300
96301300
96301300
96201300

96001370
96101370
96301370
96301370
96201370

KELLOGG
St. Maries
Wallace

90701100
90601100
90801100

90701101
90601101
90801101

90701102
90601102
90801102

90701300
90601300
90801300

90701370
90601370
90801370

LEWIS-CLARK
Clarkston
92201100
Craigmont
91201100
Elk City
91501100
Grangeville
91001100
Lewiston
93201100
Moscow
93301100
Orofino
91301100
Pierce
91401100

92201101
91201101
91501101
91001101
93201101
93301101
91301101
91401101

92201102
91201102
91501102
91001102
93201102
93301102
91301102
91401102

92201300
91201300
91501300
91001300
93201300
93301300
91301300
91401300

92201370
91201370
91501370
91001370
93201370
93301370
91301370
91401370

3-2

05/09

CAPITAL BLANKET PROJECT NUMBERS


UG
Cable
Replace

Dist. Plant
Replace
OH/UG

Misc. Cust
Requested/
Caused

Road
Relocates

Failed
Plant/
Storms

ER2054

ER2055

ER2055

ER2056

ER2059

SPOKANE
NW County
NW City
Deer Park
NE County
NE City
Valley
Central
Network
West Plains
SW City

95001330
95101330
95201330
95301330
95401330
95501330
95601330
95701330
95801330
95901330

95001340
95101340
95201340
95301340
95401340
95501340
95601340
95701340
95801340
95901340

95001341
95101341
95201341
95301341
95401341
95501341
95601341
95701341
95801341
95901341

95001350
95101350
95201350
95301350
95401350
95501350
95601350
95701350
95801350
95901350

95001520
95101520
95201520
95301520
95401520
95501520
95601520
95701520
95801520
95901520

CDA
Post Falls

90101330
90101330

90101340
90101340

90101341
90101341

90101350
90101350

90101520
90101520

COLVILLE
Chewelah
Gifford/
Inchelium
Northport

96001330
96101330
96301330
96301330
96201330

96001340
96101340
96301340
96301340
96201340

96001341
96101341
96301341
96301341
96201341

96001350
96101350
96301350
96301350
96201350

96001520
96101520
96301520
96301520
96201520

KELLOGG
St. Maries
Wallace

90701330
90601330
90801330

90701340
90601340
90801340

90701341
90601341
90801341

90701350
90601350
90801350

90701520
90601520
90801520

LEWIS-CLARK
Clarkston
92201330
Craigmont
91201330
Elk City
91501330
Grangeville
91001330
Lewiston
93201330
Moscow
93301330
Orofino
91301330
Pierce
91401330

92201340
91201340
91501340
91001340
93201340
93301340
91301340
91401340

92201341
91201341
91501341
91001341
93201341
93301341
91301341
91401341

92201350
91201350
91501350
91001350
93201350
93301350
91301350
91401350

92201520
91201520
91501520
91001520
93201520
93301520
91301520
91401520

Blanket

3-3

05/09

CAPITAL BLANKET PROJECT NUMBERS


Residential Commercial
Revenue
Revenue
Blanket

Develop.
Revenue

Street
Lights

Area
Lights

ER1000

ER1000

ER1000

ER1004

ER1005

OTHELLO
Davenport
Long Lake
Odessa/
Wilber
Ritzville

97001100
97401100
97501100
97601100
97601100
97101100

97001101
97401101
97501101
97601101
97601101
97101101

97001102
97401102
97501102
97601102
97601102
97101102

97001300
97401300
97501300
97601300
97601300
97101300

97001370
97401370
97501370
97601370
97601370
97101370

PALOUSE-WA
PALOUSE-ID
Colfax
Deary
Garfield/
Rosalia
Genesee-WA
Genesee-ID
Kamiah
Pullman
Tekoa-WA
Tekoa-ID

92801100
93801100
94201100
91701100
94101100
94101100
92601100
93601100
91101100
92301100
92701100
93701100

92801101
93801101
94201101
91701101
94101101
94101101
92601101
93601101
91101101
92301101
92701101
93701101

92801102
93801102
94201102
91701102
94101102
94101102
92601102
93601102
91101102
92301102
92701102
93701102

92801300
93801300
94201300
91701300
94101300
94101300
92601300
93601300
91101300
92301300
92701300
93701300

92801370
93801370
94201370
91701370
94101370
94101370
92601370
93601370
91101370
92301370
92701370
93701370

SANDPOINT-ID

93001100
90501100
94001100

93001101
90501101
94001101

93001102
90501102
94001102

93001300
90501300
94001300

93001370
90501370
94001370

Priest River
Sandpoint-MT

3-4

05/09

CAPITAL BLANKET PROJECT NUMBERS


UG
Cable
Replace
Blanket

Dist. Plant Misc. Cust


Replace
Requested/
OH/UG
Caused

Road
Relocates

Failed
Plant/
Storms

ER2054

ER2055

ER2055

ER2056

ER2059

OTHELLO
Davenport
Long Lake
Odessa/
Wilber
Ritzville

97001330
97401330
97501330
97601330
97601330
97101330

97001340
97401340
97501340
97601340
97601340
97101340

97001341
97401341
97501341
97601341
97601341
97101341

97001350
97401350
97501350
97601350
97601350
97101350

97001520
97401520
97501520
97601520
97601520
97101520

PALOUSE-WA
PALOUSE-ID
Colfax
Deary
Garfield/
Rosalia
Genesee-WA
Genesee-ID
Kamiah
Pullman
Tekoa-WA
Tekoa-ID

92801330
93801330
94201330
91701330
94101330
94101330
92601330
93601330
91101330
92301330
92701330
93701330

92801340
93801340
94201340
91701340
94101340
94101340
92601340
93601340
91101340
92301340
92701340
93701340

92801341
93801341
94201341
91701341
94101341
94101341
92601341
93601341
91101341
92301341
92701341
93701341

92801350
93801350
94201350
91701350
94101350
94101350
92601350
93601350
91101350
92301350
92701350
93701350

92801520
93801520
94201520
91701520
94101520
94101520
92601520
93601520
91101520
92301520
92701520
93701520

SANDPOINT-ID 93001330

93001340
90501340
94001340

93001341
90501341
94001341

93001350
90501350
94001350

93001520
90501520
94001520

Priest River
90501330
Sandpoint-MT 94001330

3-5

05/09

LOCATION NUMBERS
FOR CAPITAL ACCOUNTS
Washington Counties

Idaho Counties

Chewelah
Clarkston-Lewiston WA
Colfax
Colville
Davenport
Deer Park
Garfield/Rosalia
Genesee-WA
Gifford/Inchelium
Long Lake
Northport
Odessa/Wilbur
Othello
Palouse-WA
Pullman-Moscow WA
Ritzville
Spokane County NW
Spokane City NW
Spokane County NE
Spokane City NE
Spokane County Valley
Spokane County Central
Spokane Network
Spokane County West Plains
Spokane City SW
Tekoa-WA

961
922
942
960
974
952
941
926
963
975
962
976
970
928
923
971
950
951
953
954
955
956
957
958
959
927

General Locations
Washington
Idaho
Montana
Common to Washington/Idaho

028
038
048
098

Coeur dAlene/Post Falls


Craigmont
Deary
Elk City
Genesee-ID
Grangeville
Kamiah
Kellogg
Clarkston-Lewiston ID
Pullman-Moscow ID
Orofino
Palouse-ID
Pierce
Priest River
Sandpoint-ID
St. Maries
Tekoa-ID
Wallace

901
912
917
915
936
910
911
907
932
933
913
938
914
905
930
906
937
908

Montana Counties
Sandpoint-MT

3-6

940

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


30P
POLE - CEDAR - 30FT IN DIRT
35P
POLE - CEDAR - 35FT IN DIRT
40P
POLE - CEDAR - 40FT IN DIRT
45P
POLE - CEDAR - 45FT IN DIRT
50P
POLE - CEDAR - 50FT IN DIRT
55P
POLE - CEDAR - 55FT IN DIRT
60P
POLE - CEDAR - 60FT IN DIRT
65P
POLE - CEDAR - 65FT IN DIRT
70P
POLE - CEDAR - 70FT IN DIRT
75P
POLE - CEDAR - 75FT IN DIRT

248.45
312.00
427.67
619.69
679.76
757.82
1060.26
1206.59
1904.59
2201.36

HANDDIG (Additional Manhours)


HANDSET (Additional Manhours)
CUT & REPLACE ASPHALT/CONCRETE (Addt'l Manhours)

6.20
6.20
6.20
6.60
6.60
7.00
7.00
7.00
7.00
10.10

886.53
964.52
1120.65
1349.33
1476.51
1565.20
1965.61
2176.29
3056.81
3675.91

4.00
10.00
2.00/5.00

30PR
35PR
40PR
45PR
50PR
55PR
60PR
65PR
70PR
75PR

POLE - CEDAR - 30FT IN ROCK


POLE - CEDAR - 35FT IN ROCK
POLE - CEDAR - 40FT IN ROCK
POLE - CEDAR - 45FT IN ROCK
POLE - CEDAR - 50FT IN ROCK
POLE - CEDAR - 55FT IN ROCK
POLE - CEDAR - 60FT IN ROCK
POLE - CEDAR - 65FT IN ROCK
POLE - CEDAR - 70FT IN ROCK
POLE - CEDAR - 75FT IN ROCK

248.45
312.00
427.67
619.69
679.76
757.82
1060.26
1206.59
1904.59
2201.36

12.20
12.20
12.20
12.20
12.60
12.60
14.10
14.10
14.10
15.10

1479.20
1557.18
1713.32
1947.27
2075.80
2167.13
2674.54
2887.86
3770.99
4194.75

14SF/BA
16SF/BA
SS10
SS10HD
SS11HD

POLE STUB - BANDED 14'


POLE STUB - BANDED 16'
POLE STUB - STEEL FOR 30-35 FOOT POLE
POLE STUB - STEEL FOR 40-45 FOOT POLE
POLE STUB - STEEL FOR 50-55 FOOT POLE

29.43
29.43
292.11
308.93
360.39

6.20
6.20
2.00
2.00
2.00

615.61
615.61
515.56
547.96
634.42

5FA2P
9FHA
11FHA

CROSSARM SINGLE FIBERGLASS 5' 2 PHASE


CROSSARM SINGLE FIBERGLASS 9' HEAVY DUTY
CROSSARM SINGLE FIBERGLASS 11' HEAVY DUTY

108.52
108.12
130.78

0.30
0.85
0.85

163.00
210.37
283.57

9FDEA-LT
9FDEA-HVY
11FDEA-HVY

CROSSARM DEADEND FIBERGLASS 9' LIGHT


CROSSARM DEADEND FIBERGLASS 9' HEAVY
CROSSARM DEADEND FIBERGLASS 11' HEAVY

200.44
236.51
313.35

0.85
0.85
0.85

327.62
360.70
469.05

5A
5DA

CROSSARM SINGLE WOOD 5'


CROSSARM DOUBLE WOOD 5'

28.69
48.61

0.85
1.42

115.74
194.00

4-1

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FILE DESCRIPTION

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


22HA
CROSSARM SINGLE 22' HEAVY DUTY
22HDA
CROSSARM DOUBLE 22' HEAVY DUTY
22STEEL
STEEL CROSSARM 22"
16TIMBER
TIMBER 16' X 4" X 6"

316.05
639.12
62.72
119.29

1.52
2.28
1.64
0.87

534.62
1005.68
230.99
229.42

BB
W

BACKBRACE FOR HD XARM W/EXTENSIONS


WISHBONE BRACE FOR CROSSARM

150.69
23.61

0.50
0.85

233.11
108.85

PP
PP35
DPP
DPP35

POLE TOP PIN SINGLE - 13/25kV


POLE TOP PIN SINGLE - 35kV
POLE TOP PIN DOUBLE - 13kV
POLE TOP PIN DOUBLE - 25/35kV

8.71
10.40
16.38
19.80

0.32
0.32
0.32
0.32

41.82
42.67
53.37
55.12

SP
SPH
SP25
SP35
SPC
SPC25

STEEL PIN - 13KV FOR STANDARD XARM


STEEL PIN - 13KV FOR HEAVY DUTY XARM
STEEL PIN - 25KV FOR STANDARD XARM
STEEL PIN - 25/35KV FOR STNDRD OR HD XARM
STEEL PIN - CORNER 13KV
STEEL PIN - CORNER 25KV

3.93
5.45
3.74
12.29
13.37
14.86

0.13
0.13
0.13
0.13
0.13
0.13

17.11
18.81
17.04
27.30
28.68
30.52

PDEHW
PDEDEHW
NPDEHW
NPDEDEHW
DADEHW
DADEDEHW

HARDWARE D.E. PRIMARY-ONE WAY ON POLE


HARDWARE D.E. PRIMARY-TWO WAY ON POLE
HARDWARE D.E. NEUTRAL-ONE WAY ON POLE
HARDWARE D.E. NEUTRAL-TWO WAY ON POLE
HARDWARE D.E. ONE WAY ON DBL CROSSARM
HARDWARE D.E. TWO WAY ON DBL CROSSARM

9.23
18.46
4.02
8.04
2.71
5.43

0.16
0.21
0.16
0.21
0.16
0.21

26.14
42.57
19.73
29.71
17.90
26.07

1RS
1RH
3R
3RHDEDE
3RH
NS

SEC. RACK 1 SPOOL - SERVICE


SEC. RACK 1 SPOOL WITH EXT, HEAVY DUTY
SEC. RACK 3 SPOOL
SEC. RACK 3 SPOOL DOUBLE DEADEND
SEC. RACK 3 SPOOL HEAVY DUTY
NEUTRAL SUPPORT

4.80
13.30
82.69
165.81
85.69
5.16

0.50
0.48
0.84
1.12
0.98
0.38

52.01
60.90
180.83
310.53
198.11
41.80

4-2

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


3/8DGKIT
DOWN GUY PREASSEMBLED KIT 3/8" 15KV
3/8DGKIT(2)
(2)DOWN GUY PREASSEMBLED KIT 3/8" 15KV
3/8FKIT
DOWN GUY PREASSEMBLED KIT 3/8" 25/35KV
3/8FKIT(2)
(2)DOWN GUY PREASSEMBLE KIT 3/8" 25/35KV

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

89.35
252.93
101.16
266.46

1.85
1.85
1.85
1.85

283.70
485.73
298.52
503.47

DOWN GUY PREASSEMBLED KIT 7/16" 15KV


(2) DOWN GUY PREASSEMBLED KIT 7/16" 15KV
DOWN GUY 7/16" (LIGHT) 15KV
7/16FKIT
DOWN GUY PREASSEMBLED KIT 7/16" 25/35KV
7/16FKIT(2)
(2) DOWN GUY PREASSEMBL KIT 7/16" 25/35KV
7/16DGKITFG
DOWN GUY ASMB KIT 7/16" FG DE XARM 15KV
7/16DGKITFG(2) (2)DOWN GUY ASMB KIT 7/16" FG DE ARM 15KV

177.76
309.78
124.76
178.70
301.55
116.18
248.20

1.85
3.70
1.85
1.85
3.70
1.85
3.70

393.34
729.26
328.11
394.52
719.69
316.79
652.71

3/8SG
3/8FSG
7/16SG
7/16FSG
#9IRONSG
#6IRONSG
6IRONFSG

SPAN GUY 3/8' 15KV


SPAN GUY 3/8" 25/35KV
SPAN GUY 7/16' 15KV
SPAN GUY 7/16" 25/35KV
SPAN GUY #9 IRON 15KV
SPAN GUY #6 IRON 15KV
SPAN GUY #6 IRON 25/35KV

60.31
91.80
96.71
121.43
16.44
55.67
82.48

2.45
2.45
2.45
2.45
2.45
2.45
2.45

304.16
337.46
349.40
380.10
249.93
298.03
331.33

3/8SWGKIT
3/8FSWGKIT
PUSHBRACE

SIDEWALK GUY PREASSEMBLED KIT 3/8" 15KV


SIDEWALK GUY PREASSEMBL KIT 3/8" 25/35KV
PUSH BRACE BRACKET

164.32
176.14
30.00

3.65
3.65
0.50

545.74
560.57
83.67

1MR2
1MR1
1MRSR

ANCHOR MANTA RAY MR-2, 1" X 7' 40K LB


ANCHOR MANTA RAY MR-1, 1" X 7' 40K LB
ANCHOR MANTA RAY MRSR, 1" X 7' 40K LB

78.02
90.71
126.07

1.50
1.50
1.50

236.45
252.19
296.08

5/8X
3/4X
3/4E
1X

ANCHOR PLATE 5/8" X 6' X 16"


ANCHOR PLATE 3/4" X 8' X 20"
ANCHOR PLATE 3/4" X 8' EXPANDING
ANCHOR PLATE 1" X 10' X 24"

22.21
32.27
7.69
64.64

3.00
3.00
1.50
3.00

307.46
320.05
149.14
360.09

5/8R
1RA
1RA53
1RA72
1RA96

ANCHOR ROCK 5/8" X 6'


ANCHOR ROCK 1" X 10'
ANCHOR ROCK 1" X 53"
ANCHOR ROCK 1" X 72"
ANCHOR ROCK 1" X 96"

18.34
38.53
37.80
46.11
54.26

4.40
5.86
5.86
5.86
5.86

433.37
587.40
525.96
536.28
546.42

1S1
1S1-14
1SE
1S3

ANCHOR SCREW-1" ROD 1-10" HELIX


ANCHOR SCREW-1" ROD 1-14" HELIX
ANCHOR SCREW EXTENSION ROD 1.5" X 3.5'
ANCHOR TRIPLE HELIX

48.60
65.77
29.81
129.61

1.50
1.50
1.50
1.50

199.93
223.27
176.58
300.50

7/16DGKIT
7/16DGKIT(2)
7/16DGKIT-LIGHT

4-3

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FILE DESCRIPTION

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


TMHW
TRANSF MOUNTING HARDWARE 3-25 kVA
TMHWMED
TRANSF MOUNT HARDWARE-MEDIUM 37-50 kVA
TMHWHD
TRANSF MOUNTING HARDWARE-HD 75-100 kVA
TMB2
2 TRANSF MOUNTING BRACKET, TO (2) 100 kVA
TMB3
3 TRANSF MOUNTING BRACKET, TO (3) 50 kVA
TMB3HD
3 TRANSF MOUNT BRACKET HD, TO (3) 167 kVA

2.66
3.62
6.02
108.94
84.29
153.66

0.25
0.25
0.25
0.87
0.87
0.87

26.60
27.99
31.16
216.15
186.40
275.08

ALPLTHD
RR1P
RS2PHD

2078.78
1451.20
5999.88

2.50
2.00
12.00

2815.95
1990.15
8573.98

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


6CU
CONDUCTOR 6 COPPER BARE /1000 FT
4CU
CONDUCTOR 4 COPPER BARE /1000 FT
2CU
CONDUCTOR 2 STR. COPPER BARE /1000 FT

319.20
589.68
878.37

3.40
3.40
3.40

718.09
1072.70
1438.45

4ACSR
2ACSR
1/0ACSR
2/0ACSR
4/0ACSR
336ACSR

CONDUCTOR 4 ACSR /1000 FT


CONDUCTOR 2 ACSR /1000 FT
CONDUCTOR 1/0 ACSR /1000 FT - FOR REPAIR USE
CONDUCTOR 2/0 ACSR /1000 FT
CONDUCTOR 4/0 ACSR /1000 FT
CONDUCTOR 336KCM ACSR /1000 FT

110.00
170.00
280.00
310.00
490.00
820.00

4.10
4.10
4.10
4.10
4.10
4.45

527.59
593.46
729.96
765.60
1010.66
1434.02

336AAC
556AAC
795AAC

CONDUCTOR 336KCM AAC /1000 FT


CONDUCTOR 556KCM AAC /1000 FT
CONDUCTOR 795KCM AAC /1000 FT

800.00
1070.00
1520.00

7.00
7.00
7.00

1658.42
1986.12
2549.71

13GRP4
13GRP2
35GRP4
35GRP2

GRIP, SLACK SPAN DEADEND (13/24KV) 4 ACSR


GRIP, SLACK SPAN DEADEND (13/24KV) 2 ACSR
GRIP, SLACK SPAN DEADEND (35KV) 4 ACSR
GRIP, SLACK SPAN DEADEND (35KV) 2 ACSR

4.26
3.59
4.04
4.10

0.04
0.04
0.04
0.04

8.62
7.77
8.35
8.42

13TW4
13TW2
13TW2/0
13TW4/0
13TW336A
13TW336
13TW556
13TW795

PREFORMED TIE WIRE (13KV) 4 ACSR


PREFORMED TIE WIRE (13KV) 2 ACSR
PREFORMED TIE WIRE (13KV) 2/0 ACSR
PREFORMED TIE WIRE (13KV) 4/0 ACSR
PREFORMED TIE WIRE (13KV) 336 ACSR
PREFORMED TIE WIRE(13KV) 336 AAC
PREFORMED TIE WIRE (13KV) 556 AAC
PREFORMED TIE WIRE (13KV) 795 AAC

2.17
2.29
2.51
2.96
2.74
2.57
3.61
2.99

0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04

5.99
6.21
6.44
7.01
6.72
6.52
7.81
7.03

13STW4
13STW2
13STW2/0
13STW556

PREFORMED SIDE TIE WIRE (13KV) 4ACSR


PREFORMED SIDE TIE WIRE (13KV) 2ACSR
PREFORMED SIDE TIE WIRE (13KV) 2/0ACSR
PREFORMED SIDE TIE WIRE (13KV) 556AAC

1.81
1.75
2.16
5.58

0.04
0.04
0.04
0.04

5.57
5.51
6.01
10.24

PLATFORM, ALUMAFORM 16' 2-POLE HD


REGULATOR RACK 1POLE MOUNT 1PH 15/25KV
REG STRUCT 2POLE PLTFRM MNT 3PH 15/25KV

4-4

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


24DT4
PRFMD DOUBLE TIE WIRE (13/24KV) 4ACSR
24DT2
PRFMD DOUBLE TIE WIRE (13/24KV) 2ACSR
24DT2/0
PRFMD DOUBLE TIE WIRE (13/24KV) 2/0ACSR
24DT336
PRFMD DOUBLE TIE WIRE (13/24KV) 336AAC
24DT556
PRFMD DOUBLE TIE WIRE (13/24KV) 556AAC
24DT795
PRFMD DOUBLE TIE WIRE (13/24KV) 795AAC

6.71
7.07
7.54
12.95
10.82
15.76

0.08
0.08
0.08
0.08
0.08
0.08

16.24
16.70
17.29
23.99
21.35
27.49

24DST4
24DST2
24DST2/0
24DST4/0
24DST336A
24DST336
24DST556

PRFMD DBL SIDE TIE WIRE (13/24KV) 4ACSR


PRFMD DBL SIDE TIE WIRE (13/24KV) 2ACSR
PRFMD DBL SIDE TIE WIRE (13/24KV) 2/0ACSR
PRFMD DBL SIDE TIE WIRE (13/24KV) 4/0ACSR
PRFMD DBL SIDE TIE WIRE (13/24KV) 336ACSR
PRFMD DBL SIDE TIE WIRE (13/24KV) 336AAC
PRFMD DBL SIDE TIE WIRE (13/24KV) 556AAC

3.23
3.50
4.39
3.78
5.73
6.68
5.99

0.08
0.08
0.08
0.08
0.08
0.08
0.08

11.93
12.25
13.37
12.62
15.03
16.21
15.34

24TW4
24TW2
24TW2/0
24TW4/0
24TW556

PREFORMED TIE WIRE (24KV) 4 ACSR


PREFORMED TIE WIRE (24KV) 2 ACSR
PREFORMED TIE WIRE (24KV) 2/0 ACSR
PREFORMED TIE WIRE (24KV) 4/0 ACSR
PREFORMED TIE WIRE (24KV) 556 AAC

1.83
2.02
2.56
2.54
3.45

0.04
0.04
0.04
0.04
0.04

5.59
5.85
6.50
6.49
7.61

35TW4
35TW1/0
35TW2/0

PREFORMED TIE WIRE (35KV) 4 ACSR


PREFORMED TIE WIRE (35KV) 1/0 ACSR
PREFORMED TIE WIRE (35KV) 2/0 ACSR

1.39
2.71
3.46

0.04
0.04
0.04

5.05
6.69
7.68

35DT4
35DT2/0

PREFORMED DOUBLE TIE WIRE (35KV) 4 ACSR


PREFORMED DOUBLE TIE WIRE (35KV) 2/0 ACSR

7.38
9.95

0.08
0.08

12.49
20.27

35DST4
35DST2/0

PRFMD DBL SIDE TIE WIRE (35KV) 4 ACSR


PRFMD DBL SIDE TIE WIRE (35KV) 2/0 ACSR

3.67
6.03

0.08
0.08

7.87
15.40

ST4
ST2
ST1/0
ST2/0
ST4/0

PREFORMED TIE WIRE - SPOOL 4ACSR


PREFORMED TIE WIRE - SPOOL 2ACSR
PREFORMED TIE WIRE - SPOOL 1/0 ACSR
PREFORMED TIE WIRE - SPOOL 2/0 ACSR
PREFORMED TIE WIRE - SPOOL 4/0 ACSR

1.56
1.61
1.55
1.86
2.30

0.04
0.04
0.04
0.04
0.04

5.26
5.32
5.24
5.64
6.19

SLVA6CP
SLVA6C
SLVA4C
SLVA2C
SLVA20C

SLEEVE AUTOMATIC FOR 6A COMP


SLEEVE AUTOMATIC FOR 6 CU
SLEEVE AUTOMATIC FOR 4 CU
SLEEVE AUTOMATIC FOR 2 CU
SLEEVE AUTOMATIC FOR 2/0 CU

3.75
3.09
3.36
5.80
8.89

0.20
0.20
0.20
0.20
0.20

24.11
23.20
23.37
26.38
30.23

4-5

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FILE DESCRIPTION

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


SLVA4AC
SLEEVE AUTOMATIC FOR 4 ACSR
SLVA2AC
SLEEVE AUTOMATIC FOR 2 ACSR
SLVA10AC
SLEEVE AUTOMATIC FOR 1/0 ACSR
SLVA20AC
SLEEVE AUTOMATIC FOR 2/0 ACSR
SLVA40AC
SLEEVE AUTOMATIC FOR 4/0 ACSR

4.53
4.53
10.76
10.76
11.57

0.20
0.20
0.20
0.20
0.20

25.25
25.25
33.44
33.44
33.56

SLVAMRLN
SLVADHLA

SLEEVE AUTOMATIC FOR 336 ACSR & AAC


SLEEVE AUTOMATIC FOR 556 AAC

14.59
18.85

0.20
0.20

37.30
42.61

PI8W
PI13
PI13-795
PI25
PI35

INSULATOR, PIN - 8KV (WHITE)


INSULATOR, PIN - 13KV
INSULATOR, PIN - 13KV - FOR 795 AAC
INSULATOR, PIN - 25KV
INSULATOR, PIN - 35 KV

4.27
2.57
3.92
5.23
8.91

0.02
0.02
0.02
0.02
0.02

24.04
22.40
24.08
26.46
30.25

PIPL15
PIPL25

INSULATOR, PIN - PLASTIC 15KV


INSULATOR, PIN - PLASTIC 25KV

8.29
9.15

0.02
0.02

28.29
30.57

NDE
DEINPL15
DEINPL25
DEINPL35

INSULATOR, DEADEND NEUTRAL


INSULATOR, DEADEND PLASTIC 15KV
INSULATOR, DEADEND PLASTIC 25KV
INSULATOR, DEADEND PLASTIC 35KV

7.10
9.13
16.28
18.89

0.01
0.01
0.01
0.01

9.62
12.14
21.03
24.04

CDES4-20
CDES
CDES336
CDES795
CDEPINC

CLAMP D.E. STRAIGHTLINE FOR 4-2/0 ACSR


CLAMP D.E. STRAIGHTLINE 4/0ACSR-556AAC
CLAMP D.E. STRAIGHTLINE 336ACSR-1113ACSR
CLAMP D.E. STRAIGHTLINE FOR 795AAC
CLAMP D.E. PINCO FOR 8-1/0 CU

6.37
12.59
21.96
21.96
4.07

0.20
0.25
0.25
0.25
0.25

27.11
39.04
48.83
48.83
28.46

CDEA6CP
CDEA6CW
CDEA6C
CDEA4C
CDEA2C
CDEA10C
CDEA20C
CDEA40C

CLAMP D.E. AUTOMATIC FOR 6A COMP


CLAMP D.E. AUTOMATIC FOR 6 CPRWLD
CLAMP D.E. AUTOMATIC FOR 6 CU
CLAMP D.E. AUTOMATIC FOR 4 CU
CLAMP D.E. AUTOMATIC FOR 2 CU
CLAMP D.E. AUTOMATIC FOR 1/0 CU
CLAMP D.E. AUTOMATIC FOR 2/0 CU
CLAMP D.E. AUTOMATIC FOR 4/0 CU

6.92
5.23
5.23
5.41
10.12
11.64
12.16
18.06

0.20
0.20
0.20
0.20
0.20
0.20
0.20
0.20

28.17
25.91
25.91
25.91
31.74
33.65
34.32
41.63

CDEA4AW
CDEA4AC
CDEA2AC
CDEA10AC
CDEA20AC
CDEA40AC

CLAMP D.E. AUTOMATIC FOR 4 AWAC


CLAMP D.E. AUTOMATIC FOR 4 ACSR
CLAMP D.E. AUTOMATIC FOR 2 ACSR
CLAMP D.E. AUTOMATIC FOR 1/0 ACSR
CLAMP D.E. AUTOMATIC FOR 2/0 ACSR
CLAMP D.E. AUTOMATIC FOR 4/0 ACSR

18.06
6.41
8.19
14.78
14.78
15.29

0.20
0.20
0.20
0.20
0.20
0.20

41.63
27.15
29.36
37.53
37.53
38.19

4-6

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


HOTTAP-S
HOT TAP - SMALL 8-1/0 to 6-1/0
HOTTAP-M
HOT TAP - MEDIUM 6-336 to 6-3/0
HOTTAP-L
HOT TAP - LARGE 4/0-795 to 6-336

7.99
8.37
15.75

0.25
0.25
0.25

33.13
33.80
42.96

SDEA4AC
SDEA2AC
SDEA20AC

SPOOL-NEUT & SEC DE AUTO - 4ACSR


SPOOL-NEUT & SEC DE AUTO - 2ACSR
SPOOL-NEUT & SEC DE AUTO - 2/0 & 1/0 ACSR

6.85
6.85
15.24

0.07
0.07
0.07

14.96
14.96
25.33

LA10
LA15
LA18
LA27

LIGHTNING ARRESTER - 10KV FOR 13KVYG


LIGHTNING ARRESTER - 15KV FOR 20KVYG
LIGHTNING ARRESTER - 18KV FOR 25KVYG
LIGHTNING ARRESTER - 27KV FOR 35KVYG

72.88
56.85
62.65
81.61

0.75
0.75
0.75
0.75

161.53
141.66
148.83
172.40

LABK

ARRESTER BRACKET FOR HD/STD XARMS

15.16

0.10

28.48

GND
GNDSP
GNDSP-GLV
GNDT

GROUND ROD - NO.4 COPPER


GROUND, COPPER - AT STEEL POLE
GROUND, GALVANIZED - AT STEEL POLE
GROUND - OH TRANSFORMER

39.21
19.55
17.63
16.42

1.70
1.70
0.50
0.08

201.66
71.18
68.86
28.73

DISC15-25
DISCIL336/15-25
DISCIL556/15-25
DISCIL795/15-25

DISCONNECT SWITCH 900A 1-PHASE 15/25KV


DISCON SWITCH 900A 336AAC 1PH INLINE 15/25kV
DISCON SWITCH 900A 556AAC 1PH INLINE 15/25kV
DISCON SWITCH 900A 795AAC 1PH INLINE 15/25kV

258.85
513.38
522.66
532.69

3.00
3.00
3.00
3.00

604.17
920.18
931.70
944.14

AS900/15-25
AIR SWITCH 900A 15/25kV 3-PHASE
AS900HOG15-25 AIR SWITCH 900A HOTSTICK GANG OP 3PH 15/25kV

3674.63
2426.00

20.00
10.00

6448.72
3953.03

UGDIPDSC600-15 UG DIP KIT - 15KV, 600 AMP, w/DISCONNECTS


UGDIPDSC600-20 UG DIP KIT - 20KV, 600 AMP, w/DISCONNECTS
UGDIPDSC600-25 UG DIP KIT - 25KV, 600 AMP, w/DISCONNECTS

1142.49
1169.91
1187.30

12.00
12.00
12.00

2429.07
2463.13
2484.66

UGDIPSW600-15 UG DIP KIT - 15KV, 600 AMP, FOR HOG SWITCH


UGDIPSW600-20 UG DIP KIT - 20KV, 600 AMP, FOR HOG SWITCH
UGDIPSW600-25 UG DIP KIT - 25KV, 600 AMP, FOR HOG SWITCH

266.48
293.90
311.29

1.50
1.50
1.50

470.48
504.55
526.07

OCR1
OCR3

RECLOSER, OCR, KYLE V4H, 1-PHASE, 15KV


RECLOSER, OCR, KYLE V6H, 3-PHASE, 15KV

1932.73
6948.22

6.00
6.00

2965.12
9192.37

FI-STROBE

FAULT IND OH LOAD TRACKER STROBE

150.00

0.10

280.69

4-7

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FILE DESCRIPTION

FERC ACCOUNT 368.00 - LINE TRANSFORMERS


13CO1/10
* CUTOUT 13 KV 100A 10,000 INT
13CO2/10
* CUTOUT 13 KV 200A 10,000 INT
20-35CO1/8
* CUTOUT 20-35 KV 100A 8,000 INT
20-35CO2/8
* CUTOUT 20-35 KV 200A 8,000 INT

83.96
140.31
104.02
150.48

0.75
0.75
0.75
0.75

175.03
244.47
199.93
257.60

BLADE13
BLADE20-35
DOOR200A13

BLADE, SOLID 13 KV, 300A


BLADE, SOLID 20-35 KV, 300A
FUSE HOLDER, 13KV, 200A

40.30
34.35
56.34

0.05
0.05
0.05

54.18
46.67
73.62

BRKT-SO
COB

BRACKET, SO FG POLE-MNT FOR TRM, LA, CO


CUTOUT BRACKET FOR HD/STD XARMS

34.14
15.16

0.20
0.20

61.57
38.11

LABK

ARRESTER BRACKET FOR HD/STD XARMS

15.16

0.10

28.48

LA10T
LA15T
LA18T
LA27T

TRANSFORMER LIGHTNING ARRESTER - 10KV


TRANSFORMER LIGHTNING ARRESTER - 15KV
TRANSFORMER LIGHTNING ARRESTER - 18KV
TRANSFORMER LIGHTNING ARRESTER - 27KV

41.97
51.11
56.91
75.87

0.75
0.75
0.75
0.75

123.08
134.43
141.60
165.17

GUARD
GUARD-HOT

TRANSFORMER WILDLIFE GUARD


TRANSFORM WILDLIFE GUARD-Hot Stick Installable

5.00
7.43

0.25
0.25

30.18
32.74

900CAP13-3P
600CAP13-3P
300CAP13-3P
400CAP13
300CAP13
200CAP13
100CAP13

CAPACITOR BANK, 3 PHASE, 13KV, 600 KVAR


CAPACITOR BANK, 3 PHASE, 13KV, 600 KVAR
CAPACITOR, 3 PHASE, 13KV, 300 KVAR
CAPACITOR, 1 PHASE, 13KV, 400 KVAR
CAPACITOR, 1 PHASE, 13KV, 300 KVAR
CAPACITOR, 1 PHASE, 13KV, 200 KVAR
CAPACITOR, 1 PHASE, 13KV, 100 KVAR

5444.69
2091.83
1883.69
470.00
380.00
416.32
347.57

16.00
16.00
16.00
3.55
3.55
3.55
3.55

8268.53
4105.90
3847.48
918.12
806.37
851.46
766.11

1200CAP20-3P
600CAP20-3P
400CAP20
200CAP20

CAPACITOR BANK, 3 PHASE, 20 KV,1200 KVAR


CAPACITOR BANK, 3 PHASE, 20 KV, 600 KVAR
CAPACITOR, 1 PHASE, 20 KV, 400 KVAR
CAPACITOR, 1 PHASE, 20 KV, 200 KVAR

2823.85
2392.68
800.00
700.00

16.00
16.00
3.55
3.55

5015.81
4480.51
1327.82
1203.67

600CAP25-3P
400CAP25
300CAP25
200CAP25
100CAP25

CAPACITOR BANK, 3 PHASE, 25 KV, 600 KVAR


CAPACITOR, 1 PHASE, 25KV, 400 KVAR
CAPACITOR, 1 PHASE, 25KV, 300 KVAR
CAPACITOR, 1 PHASE, 25KV, 200 KVAR
CAPACITOR, 1 PHASE, 25KV, 100 KVAR

2149.31
705.60
400.00
467.11
452.55

16.00
3.55
3.55
3.55
3.55

4172.69
1210.61
831.21
914.53
896.45

* CUTOUTS ARE 368.00 IF USED TO FUSE A TRANSFORMER,


365.00 IF USED TO FUSE A PRIMARY OVERHEAD CIRCUIT,
AND 367.00 IF USED TO FUSE AN UNDERGROUND DIP.

4-8

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 0369.10 - SERVICES


4TX
SERVICE 4 ALUMINUM TRIPLEX /100 FT
2TX
SERVICE 2 ALUMINUM TRIPLEX /100 FT
2/0TX
SERVICE 2/0 ALUMINUM TRIPLEX /100 FT
4/0TX
SERVICE 4/0 ALUMINUM TRIPLEX /100 FT

45.00
52.00
104.00
142.00

1.70
1.70
1.70
2.05

229.07
237.71
304.46
387.87

2QX
2/0QX
4/0QX

SERVICE 2 ALUMINUM QUADRUPLEX /100 FT


SERVICE 2/0 ALUMINUM QUADRUPLEX /100 FT
SERVICE 4/0 ALUMINUM QUADRUPLEX /100 FT

78.00
149.00
235.00

1.90
1.90
2.29

292.30
381.19
527.20

FERC ACCOUNT 0373.20 - STREET LIGHTING - CIRCUIT


6DX
CONDUCTOR #6 ALUMINUM DUPLEX /1000 FT

230.00

2.50

525.77

GNDUGSL
GNDSP-GLV

12.84
17.63

0.50
0.50

64.50
70.49

189.49
520.55
198.63
189.06
222.42

1.40
1.40
1.40
1.40
1.40

369.90
780.98
381.30
369.42
411.41

2060.28
1,393.66
1,819.13
1,407.45

3.60
3.60
3.60
6.20

2904.51
2124.98
2605.11
2344.78

415.00
317.00

3.60
3.60

861.88
740.21

FERC ACCOUNT 0373.40 - STREET LIGHTING - FIXTURES


2.5MA
STREET LIGHT MAST ARM - 2.5 FT
8MA
STREET LIGHT MAST ARM - 8 FT
12MA
STREET LIGHT MAST ARM - 12 FT
16MA
STREET LIGHT MAST ARM - 16 FT
FLMA
ARM, FLOOD LIGHT ANGLE BRACKET

37.80
89.94
111.14
152.21
22.11

1.64
1.64
1.64
1.64
1.64

204.99
270.52
301.27
352.77
185.75

DECACORN
DECACORNGRN
DECCOLBK
DECCOLBR
DECCNTBK
DECCNTBR
DECSALEM
DECTRAD

469.75
569.69
142.42
148.91
160.37
174.88
162.07
434.77

0.80
0.80
0.80
0.80
0.80
0.80
0.80
0.80

660.22
784.29
253.86
261.88
276.10
297.99
278.22
616.78

GROUND, COPPER AT STEEL ST LIGHT STNDRD


GROUND, GALVANIZED - AT STEEL POLE

FERC ACCOUNT 0373.30 - STREET LIGHTING - STEEL POLES


16FG
STANDARD 16' DECORATIVE FBRGLS BLACK
16FGGRN
STANDARD 16' DECORATIVE FBRGLS GREEN
20FGBK
STANDARD 20' DECORATIVE FBRGLS BLACK
20FGBR
STANDARD 20' DECORATIVE FBRGLS BRONZE
25FGBK
STANDARD 25' DECORATIVE FBRGLS BLACK
25GRNPB
30STLPB
30STLDA
35STLDB

STANDARD 25' PED BASE GREEN w/Decor Shroud


STEEL STANDARD 30' PEDESTAL BASE
STEEL STANDARD 30' DOUBLE ARM PED BASE
STEEL STANDARD 35' DIRECT BURY

BASELONG
BASESHORT

BASE, CONCRETE, STREET LIGHT - LONG 11"


BASE, CONCRETE, STREET LIGHT - SHORT 11"

LUMINAIRE HPS DECORATIVE 100W ACORN


LUMINAIRE HPS DECOR 100W ACORN GREEN
LUMINAIRE HPS DECOR 100W COLONIAL BLACK
LUMINAIRE HPS DECOR 100W COLONIAL BROWN
LUMINAIRE HPS DECOR 100W CONTEMP BLACK
DECOR 100W CONTEMP BROWN

LUMINAIRE HPS

LUMINAIRE HPS DECOR 100W SALEM BLACK


LUMINAIRE HPS DECOR 100W TRADITIONAL

4-9

05/09

OVERHEAD ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 0373.40 - STREET LIGHTING - FIXTURES


100HPS2
LUMINAIRE COBRA-HEAD HPS W/SS 100W 2-WAY
100HPS4
LUMINAIRE COBRA-HEAD HPS W/SS 100W 4-WAY
200HPS2
LUMINAIRE COBRA-HEAD HPS W/SS 200W 2-WAY
400HPS2
LUMINAIRE COBRA-HEAD HPS W/SS 400W 2-WAY

101.39
107.32
115.22
158.01

0.80
0.80
0.80
0.80

202.88
210.93
221.99
273.18

250HPSFL
400HPSFL

LUMINAIRE HPS 250W FLOOD


LUMINAIRE HPS 400W FLOOD

168.33
168.35

0.80
0.80

286.00
286.02

VNDL SHLD

VANDAL SHIELD FOR 200W HPS LUMINAIRE

358.45

1.00

540.89

4.70
33.24

1.40
0.40

125.65
72.26

FERC ACCOUNT 596 - MAINTENANCE OF STREET LIGHTING


SSW
SUNSWITCH D-2 WITH M-2 BRACKET
REFRACT
REFRACTOR, 175W, 4-WAY

4-10

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

FERC ACCOUNT 0366.00 - UG CONDUIT


2RSR-6
RISER, CONDUIT 2 IN w/6.5" STANDOFF BRKTS
2RSR-10
RISER, CONDUIT 2 IN w/10" STANDOFF BRKTS
2RSR-15
RISER, CONDUIT 2 IN w/15" STANDOFF BRKTS
(2)2RSR-15
RISER, CONDUIT (2) 2 IN w/15" STANDOFF BRKTS
(3)2RSR-15
RISER, CONDUIT (3) 2 IN w/15" STNDOFF BRKTS
3RSR-10
RISER, CONDUIT 3 IN w/10" STANDOFF BRKTS
3RSR-15
RISER, CONDUIT 3 IN w/15" STANDOFF BRKTS
4RSR-10
RISER, CONDUIT 4 IN w/10" STANDOFF BRKTS
4RSR-15
RISER, CONDUIT 4 IN w/15" STANDOFF BRKTS
(3)4RSR600
RISER, 600AMP CONDUIT (3) 4" w/15" SO BRKTS
(6)4RSR600
RISER, 600AMP CONDUIT (6) 4" w/15" SO BRKTS
2CDTCAP
CONDUIT CAP FOR 2 IN. PVC RISER

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

31.56
56.94
63.98
88.04
112.11
76.81
83.85
90.84
97.88
256.39
427.48
8.78

1.50
1.50
1.50
2.00
2.25
1.50
1.50
1.50
1.50
2.50
5.00
0.03

160.26
202.15
200.52
271.26
321.88
226.16
224.52
243.63
242.00
519.79
934.09
10.87

PVCPE2CPL
P2CPL
2CPL
3CPL
4CPL

COUPLING, 2 IN. PVC TO POLY


COUPLING 2 IN. POLY
COUPLING 2 IN. PVC
COUPLING 3 IN. PVC
COUPLING 4 IN. PVC

7.51
1.44
0.98
2.15
3.38

0.36
0.05
0.20
0.20
0.20

29.35
5.26
17.10
18.59
20.08

2CDTPL
3CDTPL
4CDTPL

CONDUIT - 2 IN. PVC /FT


CONDUIT - 3 IN. PVC /FT
CONDUIT - 4 IN. PVC /FT

0.53
1.08
1.47

0.01
0.01
0.01

1.09
2.14
2.62

2CDTFLX
2POLYRIB-G

FLEX CONDUIT 2 IN. PVC /FT


CONDUIT CONT POLY 2" COIL WAVERIB GRAY /FT

1.17
0.59

0.01
0.01

2.25
1.13

2SCDTPL
3SCDTPL
4SCDTPL

SPLIT CONDUIT 2 IN. PVC /FT


SPLIT CONDUIT 3 IN. PVC /FT
SPLIT CONDUIT 4 IN. PVC /FT

3.42
5.54
8.17

0.05
0.05
0.05

8.48
26.74
14.48

2CDTSTL
3CDTSTL
4CDTSTL

CONDUIT - 2 IN. STEEL /FT


CONDUIT - 3 IN. STEEL /FT
CONDUIT - 4 IN. STEEL /FT

4.61
7.93
9.99

0.02
0.02
0.02

7.34
11.44
14.01

DUCT4WAY
DUCT6WAY
DUCT9WAY

4-WAY DUCT BANK - FORMS & CONCRETE /FT


6-WAY DUCT BANK - FORMS & CONCRETE /FT
9-WAY DUCT BANK - FORMS & CONCRETE /FT

9.12
11.47
13.99

0.35
0.50
0.50

37.82
52.87
55.66

DUCTSPBASE4
DUCTSPINTR4
DUCTREBARHOLD
CONCRETE-FTB
CONCRETE-4000

SPACER, CONDUIT BASE, 4" PVC


SPACER, CONDUIT, INTERMEDIATE, 4" PVC
DUCT SPACER REBAR HOLDER
FLUIDIZED THERMAL BACKFILL /cu yd
CONCRETE, THERMAL BACKFILL 4000 PSI /cu yd

0.75
0.71
0.94
70.00
90.00

0.02
0.02
0.02
0.25
0.25

2.27
2.23
2.52
97.64
119.81

5-1

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

FERC ACCOUNT 0366.00 - UG CONDUIT


2SWEEP
SWEEP, BEND, 2 IN. 90 DEGREE PVC
2SWEEP-22DEG
SWEEP, BEND, 2 IN. 22.5 DEGREE PVC
2SWEEP-45DEG
SWEEP, BEND, 2 IN. 45 DEGREE PVC
3SWEEP
SWEEP, BEND, 3 IN. 90 DEGREE PVC
3SWEEP-22DEG
SWEEP, BEND, 3 IN. 22.5 DEGREE PVC
3SWEEP-45DEG
SWEEP, BEND, 3 IN. 45 DEGREE PVC
4SWEEP
SWEEP, BEND, 4 IN. 90 DEGREE PVC
4SWEEP-22DEG
SWEEP, BEND, 4 IN. 22.5 DEGREE PVC
4SWEEP-45DEG
SWEEP, BEND, 4 IN. 45 DEGREE PVC

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS COST

3.82
3.88
4.27
10.39
7.35
9.14
14.84
9.75
13.95

0.12
0.12
0.12
0.12
0.12
0.12
0.12
0.12
0.12

14.38
14.47
14.94
22.54
18.78
20.98
28.08
21.76
24.89

S444
S575
S644
S676
S4484
S5106

SUBM ENCL CONC 48"X48"X4 w/CVR & STL LID


SUBM ENCL CONC 7'X4'8"X5' w/CVR, DBL STL LIDS
SUBM ENCL CONC 6'X4'X4' w/CVR, DBL STL LID
SUBM ENCL CONC 6'3"X7'9"X7'2"w/CVR,DBLSTL LIDS
SUBM ENCL CONC 9' 0" X 5' '0"' X 7' 2" W/LID
SUBM ENCL CONC 6X11X7 w/CVR & 3 STL LIDS

1710.53
2800.00
2124.58
4500.00
4979.00
5364.00

6.50
7.00
6.50
7.00
8.00
8.00

2646.02
4038.19
3160.07
6148.77
6161.56
6588.33

S575ST
S577ST

SUBM ENCL CONC 4'8"X7'X5' SUB TFMR 25-50 kVA


SUBM ENCL CONC 4'8"X7'X6'8"SUB TFMR 75-167kVA

2656.00
2923.00

8.00
8.00

3586.51
3882.47

S333
SECPED
SECENCLPAD3PH
SECENCL-BOXPAD
HH
HH-POLYCRETE
HHL
HHL-POLYCRETE

SUBM ENCL CONC (SECONDARY HH) 36"X42"X35"


SECONDARY PEDESTAL - SINGLE PHASE
SECONDARY ENCLOSURE, PADMOUNT 3PH
SECONDARY ENCL BOX PAD 46"X46"X24"H
SEC. HANDHOLE 13"X24"
SEC. HANDHOLE, POLY CONCRETE 13"X24"
SEC. HANDHOLE, LARGE 17"X30"
SEC. HANDHOLE, POLY CONC LG 17"X30"

879.00
97.88
2957.16
492.50
49.28
187.95
70.88
247.32

6.50
1.00
0.50
0.80
1.00
1.00
1.00
1.00

1376.21
201.86
3781.16
651.57
141.58
313.69
168.18
387.37

BOXPAD
BOXPADLID
P44PL

TRANSFORMER BOX PAD


COVER FOR TRANSFORMER BOX PAD
PLASTIC PAD FOR 1-PHASE TRANSFORMER

190.99
106.88
63.03

0.80
0.80
0.20

301.49
197.07
94.14

JE1-GNDSLV
JE2-GNDSLV
JE3-GNDSLV
JE3-5POS-GNDSLV
JE3-600-GNDSLV

GROUND SLEEVE 1PH JE1, JE1-25KV 15/25KV


GROUND SLEEVE 2PH JE2, JE2-25KV 15/25KV
GROUND SLEEVE 3PH JE3, JE3-25KV 15/25KV
GROUND SLEEVE 3PH JE3-5POSITION 15/25KV
GROUND SLEEVE 3PH JE3-600 15/25KV

202.59
251.23
340.57
641.75
331.61

0.80
0.80
0.80
0.80
1.00

320.28
381.30
491.95
864.19
498.91

GNDSLV600L
GNDSLV1
GNDSLV1L
GNDSLV2
GNDSLV3
GNDSLV3LRG

GROUND SLEEVE 1PH TRANSFORMER 15/25kV


GRND SLV w/LID 1PH TFMR, JE1, JE1-25KV 15/25kV

610.60
198.99
261.41
251.23
113.90
332.11

1.00
0.80
0.80
0.80
0.80
0.80

838.41
315.87
388.91
376.27
205.83
475.98

GROUND SLEEVE 2PH TRANSFORMER 15/25kV


GROUND SLEEVE 3PH TFMR 45-500 kVA 15/25kV
GROUND SLEEVE 3PH TFMR 750-1500 kVA 15/25kV
GROUND SLEEVE w/LOCKING LID 600A JE3

5-2

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

FERC ACCOUNT 0366.00 - UG CONDUIT


CABLE RACK SUPPORT 14 HOLE 27-1/2" MOUNT
CBLRACK
HOOK-6
CABLE RACK HOOK 6"
HOOK-10
CABLE RACK HOOK 10"
HOOK-15
CABLE RACK HOOK 15"
FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES
1CN15
CBL UG 1 AL w/CN 15KV /100 FT
4/0CN15
CBL UG 4/0 AL w/CN 15KV /100 FT
350CN15
CBL UG 350 AL w/CN 15KV /100 FT
750CN15
CBL UG 750 AL w/CN 15KV /100 FT
1000CN15
CBL UG 1000 AL w/CN 15KV /100 FT
1CN25
CBL UG 1 AL w/CN 25KV /100 FT
350CN25
CBL UG 350 AL w/CN 25KV /100 FT
1000CN25
CBL UG 1000 AL w/CN 25KV /100 FT
1/0CN35
CBL UG 1/0 AL w/CN 35KV /100 FT
CBLPULL
LABOR FOR SET UP & PULLING CABLE /HR
SETUP = .50 M/H EACH PULL = 1.00 M/H
GNDCA
GROUNDING KIT FOR UG CABLE
GNDUG
GROUND - AT PAD OR VAULT
GNDUGALT
GROUND ROD ALTERNATIVE - 2/0 COPPER
GNDUG600
NEUTRAL FOR 600 AMP INSTALLATIONS
GNDVLTBUS
SUBSURFACE VAULT INTERNAL GROUND BUS

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

29.28
12.04
15.07
19.91

0.33
0.01
0.01
0.01

62.91
15.61
19.36
25.38

140.00
233.00
350.00
427.00
558.00
167.00
256.00
750.00
184.00
0.00

0.66
0.66
0.92
1.67
1.67
0.70
0.92
1.67
0.70
1.00

227.67
343.05
508.95
665.36
827.50
262.41
392.06
966.60
242.10
81.12

68.67
12.84
195.24
1.88
143.89

2.70
0.50
0.33
0.25
0.50

306.67
56.19
270.16
3.01
219.86

FIUG
FIUGREMOTE

FAULT IND UG LOAD TRACKER TEST POINT


FAULT INDICATOR FIBER OPTIC REMOTE

12.06
29.37

0.10
0.10

23.11
44.71

BI15
BI25
FTBI15
FTBI25

BUSHING INSERT 15KV


BUSHING INSERT 25KV
FEED THRU BUSHING INSERT 15KV
FEED THRU BUSHING INSERT 25KV

23.67
35.55
107.32
139.46

0.05
0.05
0.50
0.50

32.88
51.51
173.55
231.36

BC15
BC25
BC600MALE
BC600FEMALE

BUSHING CAP 15KV


BUSHING CAP 25KV
BUSHING CAP, MALE 15/25KV 600A
BUSHING CAP, FEMALE 15/25KV 600A

20.69
36.78
61.10
94.67

0.05
0.05
0.05
0.05

29.15
49.14
79.31
120.99

BE15600/200
BE25600/200

BUSHING EXTENSION 15KV 600A/200A


BUSHING EXTENSION 25KV 600A/200A

198.96
253.24

0.17
0.17

260.82
328.21

FTB15
FTB25
SOB15
SOB25
SOBPI600
SOBPG600

FEED THRU STANDOFF BUSHING 15KV


FEED THRU STANDOFF BUSHING 25KV
STANDOFF BUSHING 15KV
STANDOFF BUSHING 25KV
PLUG INSULATING STANDOFF 15/25KV 600 AMP
PLUG GROUNDED STANDOFF 15/25KV 600 AMP

88.44
139.28
37.66
62.78
63.94
101.86

0.50
0.50
0.10
0.10
0.10
0.10

148.69
213.14
54.98
85.85
87.63
134.70

5-3

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FILE DESCRIPTION

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


S15
SPLICE 15KV FOR #1 ALCN
S15L
SPLICE, LONG 15KV FOR #1 ALCN - FOR REPAIR
S15/2
SPLICE 15KV FOR #2 ALCN - FOR REPAIR
S151/0
SPLICE 15KV FOR 1/0 ALCN
S151/0L
SPLICE, LONG 15KV FOR 1/0 ALCN - FOR REPAIR
S154/0
SPLICE 15KV FOR 4/0 ALCN
S15/350
SPLICE 15KV FOR 350 AL
S15/750
SPLICE 15KV FOR 750 ALCN
S15/1000
SPLICE 15KV FOR 1000 ALCN
S25
SPLICE 25KV FOR #1 ALCN
S25/2
SPLICE 25KV FOR #2 ALCN
S25/350
SPLICE 25KV FOR 350 ALCN
S25/1000
SPLICE 25KV FOR 1000 ALCN
S351/0
SPLICE 35KV FOR 1/0 ALCN

48.45
106.80
48.45
46.91
100.94
54.51
186.53
204.96
256.57
75.55
73.67
263.69
287.08
119.40

1.50
1.50
1.50
1.50
1.50
1.50
2.25
2.25
2.25
1.5
1.5
2.25
2.25
1.5

180.87
253.28
180.87
178.95
246.00
188.35
413.32
436.35
500.27
214.51
212.16
479.16
505.09
266.43

CASK-S
CASK-L

CABLE ACCESSORY SEALING KIT #1 & 1/0 ALCN


CABLE ACCESSORY SEALING KIT 350 - 750 ALCN

7.64
12.27

0.10
0.10

17.72
23.47

EB15
EB151/0
EB154/0
EB25
EB25/2
LRTP#1
LRTP1/0
LRTP4/0
LRTP350
LRTP750
LRTP1000
LRTP350-25
LRTP1000-25

ELBOW 15KV FOR #1 ALCN


ELBOW 15KV FOR 1/0 ALCN
ELBOW 15KV FOR 4/0 ALCN
ELBOW 25KV FOR #1 ALCN
ELBOW 25KV FOR #2 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV #1 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV 1/0 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV 4/0 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV 350 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV 750 ALCN
EB w/LD RED TAP PLUG 600-200A 15kV 1000 ALCN
EB w/LD RED TAP PLUG 600-200A 25kV 350 ALCN
EB w/LD RED TAP PLUG 600-200A 25kV 1000 ALCN

33.24
33.59
33.47
49.08
55.87
237.62
237.64
237.08
245.85
242.82
245.64
300.13
300.43

0.65
0.65
0.65
0.65
0.65
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00

93.99
94.34
94.17
113.56
122.02
456.64
456.67
455.97
466.87
463.10
466.60
534.25
534.63

LAUG10
LAUG18
RLA10
RLA15
RLA18
RLA27

LIGHTNING ARRESTER UG EB 10KV FOR 13KVYG


LIGHTNING ARRESTER UG EB 18KV FOR 20/24KVYG
ARRESTER RISER POLE - 10KV FOR 13 KVYG
ARRESTER RISER POLE - 15KV FOR 20 KVYG
ARRESTER RISER POLE - 18KV FOR 25 KVYG
ARRESTER RISER POLE - 27KV FOR 35 KVYG

70.25
108.65
76.60
65.75
71.55
90.51

0.75
0.75
0.53
0.53
0.53
0.53

148.68
195.76
138.09
124.59
131.77
155.34

TRM15
TRM151/0
TRM154/0
TRM15350
TRM15750
TRM151000

TERMINATOR POLE 15KV FOR #1 ALCN


TERMINATOR POLE 15KV FOR 1/0 ALCN
TERMINATOR POLE 15KV FOR 4/0 ALCN
TERMINATOR POLE 15KV FOR 350 ALCN
TERMINATOR POLE 15KV FOR 750 ALCN
TERMINATOR POLE 15KV FOR 1000 ALCN

26.72
23.36
38.10
98.34
131.20
148.08

0.63
0.63
0.63
0.63
0.63
0.63

84.44
80.27
98.58
173.38
214.18
235.14

5-4

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL
INSTALLED
COST MANHRS
COST

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


TRM25
TERMINATOR POLE 25KV FOR #1 ALCN
TRM25350
TERMINATOR POLE 25KV FOR 350 ALCN
TRM251000
TERMINATOR POLE 25KV FOR 1000 ALCN
TRM351/0
TERMINATOR POLE 35KV FOR 1/0 ALCN
TRMBKT
TERMINATOR MOUNTING BRACKET
COBRLA15
CUTOUT BRACKET, MOUNT RLA BELOW CO

38.90
114.80
157.95
74.62
17.63
35.14

0.63
0.63
0.63
0.63
0.10
0.20

99.61
193.81
247.40
143.96
30.14
60.31

13CO1/10
13CO2/10
20-35CO1/8
20-35CO2/8
BLADE13
BLADE20-35
DOOR200A13

CUTOUT 13 KV 100A 10,000 INT


CUTOUT 13 KV 200A 20,000 INT
CUTOUT 20-35 KV 100A 8,000 INT
CUTOUT 20-35 KV 200A 8,000 INT
BLADE, SOLID 13 KV, 300A
BLADE, SOLID 20-35 KV, 300A
FUSE HOLDER, 13KV, 200A

83.96
140.31
104.02
150.48
40.30
34.35
56.34

0.75
0.75
0.75
0.75
0.05
0.05
0.05

165.01
234.46
189.92
247.60
53.51
45.99
72.99

UGDIP15-1
UGDIP1/0

UG DIP KIT 15KV 100 AMP, #1 ALCN


UG DIP KIT 15KV 200 AMP, 1/0 ALCN

183.56
236.55

2.86
2.86

459.42
524.71

JE1
JE1-25KV
JE2
JE2-25KV
JE3
JE3-5POSITION
JE3-25KV
JE3-600

JUNCTION ENCL 15 KV 1 PHASE, 4-POSITION


JUNCTION ENCL 25 KV 1 PHASE, 4-POSITION
JUNCTION ENCL 15/25 KV 2 PHASE, 4-POSITION
JUNCTION ENCL 15/25 KV 2 PHASE, 4-POSITION
JUNCTION ENCL 15 KV 3 PHASE, 4-POSITION
JUNCTION ENCL 15 KV, 3PH, 5-POSITION + INSERTS
JUNCTION ENCL 25 KV 3 PHASE, 4-POSITION
JUNCTION ENCL 600A 15/25 KV 3 PHASE, 4-POSITION
JUNCTION ENCL BACK PLATE 5-POS JUNCTNS 15KV

481.25
557.52
728.75
1111.30
1003.60
2346.84
1254.37
907.89
777.39

2.50
2.50
3.50
3.50
4.50
4.50
4.50
6.50
0.25

1050.52
1147.33
1499.71
1974.65
2041.92
4073.98
2343.71
2064.06
985.19

JUNCTION BUS PRI 4-POSITION w/BRKT 15KV


JUNCTION BUS PRI 4-POSITION w/BRKT 25KV
JUNCTION BUS PRI 5-POSITION w/BRKT 15KV
JUNCTION BUS PRI 5-POSITION without BRKT 15KV

154.03
305.85
791.47
713.46
168.68
254.95
275.96
327.15
449.46
2241.30

0.50
0.50
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

232.00
420.30
1084.18
986.97
289.73
397.63
423.71
487.27
639.12
2863.72

10.00
10.00
0.00

0.01
0.00
0.00

12.07
11.08
665.10

JE5POSBACKPLATE

J415
J425
J515VLT
J515JE
J3600
J3600VLT
J4600
J4600VLT
J4600/200
J12Y600
CLDPTCH
CLDPTH-C
CONC-M/C

JUNCTION BUS PRI 3-POSITION 15/25KV 600A


JUNCTION BUS PRI 3-POS w/BRKT 15/25KV 600A
JUNCTION BUS PRI 4-POSITION 15/25KV 600A
JUNCTION BUS PRI 4-POS w/BRKT 15/25KV 600A
JUNCTION BUS PRI 4-POS 15/25KV (2)600A (2)200A
JUNCTION BUS PRI 12-POS Y TYPE 15/25KV 600A
COLD PATCH ONLY - BY AVISTA CREW /FT
COLD PATCH ONLY - BY CONTRACTOR /FT
CONCRETE-CUT & REPLACE (MIN CHG)

5-5

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


ASPH-C&R2 ASPHALT CUT & REPLACE 2 FT /100FT
ASPH-C&R3 ASPHALT CUT & REPLACE 3 FT /100FT
ASPH-C&R4 ASPHALT CUT & REPLACE 4 FT /100FT
ASPHALT CUT&REPL JACKHAMMER /100FT
ASPHJACK

ADD M/H
SETUP
0.50
0.50
0.50
0.50

MATERIAL
COST

MAN
HRS

ZONE 1A
INSTALLED
COST

4.50
5.00
5.50
4.50
0.00
0.00
0.00

2677.50
3275.72
3874.59
2677.50
3206.88
4242.22
5277.56

ASPHG&R2
ASPHG&R3
ASPHG&R4

ASPHALT GRIND & REPLACE 2 FT /100FT


ASPHALT GRIND & REPLACE 3 FT /100FT
ASPHALT GRIND & REPLACE 4 FT /100FT

0.00
0.00
0.00
0.00
0.00
0.00
0.00

BJ2
BJ3
BJ4
BROCK
BORE
GBORE$
GBORE1
GBORE2
GBORE3
GBORE4
MISSILE
HOERAM
BLAST

BORING OR JACKING 2 IN CONDUIT /FT


BORING OR JACKING 3 IN CONDUIT /FT
BORING OR JACKING 4 IN CONDUIT /FT
BORE THROUGH ROCK /FT
BORE w/ROD BORING MACHINE /100FT
GUIDED BORING /FT
GUIDEBORE, FOR 1 ITEM /100FT
GUIDEBORE, FOR 2 ITEMS /100FT
GUIDEBORE, FOR 3 ITEMS /100FT
GUIDEBORE, FOR 4 ITEMS /100FT
MISSILE DIRT DITCH /100FT
HOERAM FOR ROCK DITCH /50FT
BLAST /FT

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.30
0.30
0.30
0.30
12.00
0.01
1.00
2.00
2.00
3.00
7.00
2.50
0.50

45.97
45.97
45.97
86.25
1124.30
2.41
241.03
341.47
360.90
461.35
602.00
238.94
85.22

DD24
DD30
DD36
DD42

BACKHOE DIRT DITCH 24 IN


BACKHOE DIRT DITCH 30 IN
BACKHOE DIRT DITCH 36 IN
BACKHOE DIRT DITCH 42 IN

0.00
0.00
0.00
0.00

3.06
3.62
4.31
5.01

192.11
227.26
270.58
314.53

DLR24
DLR30
DLR36
DLR42

LOOSE ROCK DITCH 24 IN


LOOSE ROCK DITCH 30 IN
LOOSE ROCK DITCH 36 IN
LOOSE ROCK DITCH 42 IN

0.00
0.00
0.00
0.00

6.12
7.79
9.19
10.58

384.21
489.06
576.95
664.21

DD24PLOW
DD30PLOW
DD36PLOW
DD42PLOW

PLOW DIRT DITCH 24 IN /100FT


PLOW DIRT DITCH 30 IN /100FT
PLOW DIRT DITCH-USE CAT 36 IN /100FT
PLOW DIRT DITCH-USE CAT 42 IN /100FT

0.00
0.00
0.00
0.00

1.49
1.49
3.95
3.95

93.54
93.54
247.98
247.98

DR24
DR30
DR36
DR42

ROCK DITCH 24 IN
ROCK DITCH 30 IN
ROCK DITCH 36 IN
ROCK DITCH 42 IN

0.00
0.00
0.00
0.00

24.49
30.06
35.90
41.75

1537.48
1887.17
2253.80
2621.07

TRCH30
TRCH36

TRENCHER 30 IN DEPTH /70FT


TRENCHER 36 IN DEPTH /65FT

0.00
0.00

1.40
1.40

130.90
138.54

2.00
2.00
2.00
2.25
2.50
2.75
0.50
0.20
1.00

/100FT
/100FT
/100FT
/100FT

/100FT
/100FT
/100FT
/100FT

/100FT
/100FT
/100FT
/100FT
0.33
0.33

5-6

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL MAN INSTALLED
COST
HRS
COST

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


CUSTDTCHE
CUSTOMER DITCH INSPECTION /100 FT
BCKFILL
BACKFILL DITCH ONLY /100FT
SAND
SAND MATERIAL /1 CU YD
SANDPAD
LABOR - SAND PADDING, 6" ROCK DITCH /100 FT
SANDCOV
LABOR - SAND PADDING, COVER ONLY /100 FT

0.00
0.00
21.26
0.00
0.00

0.00
0.00
18.90
0.00
0.00

8.22
52.55
23.56
56.06
39.50

LS
WT6
WT3
CMT

22.25
19.09
10.33
2.06

0.05
0.01
0.01
0.05

31.12
23.69
12.80
6.03

FERC ACCOUNT 0369.30 - SERVICES


2/0ALUG
CABLE UG 2/0 ALUMINUM 600V /100 FT
4/0ALUG
CABLE UG 4/0 ALUMINUM 600V /100 FT
350ALUG
CABLE UG 350 ALUMINUM 600V /100FT
750ALUG
CABLE UG 750 KCM ALUMINUM 600V /100FT

54.00
75.00
111.00
203.00

0.66
0.66
1.00
1.00

121.90
148.55
221.13
336.28

2TXUG
2/0TXUG
4/0TXUG
350TXUG

CABLE UG 2 ALUM. TRIPLEX 600V /100 FT


CABLE UG 2/0 ALUM. TRIPLEX 600V /100 FT
CABLE UG 4/0 ALUM. TRIPLEX 600V /100 FT
CABLE UG 350 ALUM. TRIPLEX 600V /100FT

67.00
101.00
135.00
243.00

0.66
0.66
0.66
0.66

138.47
178.32
222.47
357.26

2/0QXUG
4/0QXUG
350QXUG

CABLE UG 2/0 ALUM. QUADRUPLEX /100FT


CABLE UG 4/0 ALUM. QUADRUPLEX /100FT
CABLE UG 350 QUADRUPLEX /100FT

142.00
203.00
329.00

1.00
1.00
1.00

260.31
335.98
492.65

SLSV6-2/0
SLSV4-4/0
SLSV4/0-500

SECONDARY SPLICE 6 - 2/0 UG


SECONDARY SPLICE 4 - 4/0 UG
SECONDARY SPLICE 4/0 - 500 UG

2.68
2.84
5.38

0.20
0.20
0.20

20.05
20.23
23.39

BUS30
BUS40
BUS66
BUS88

SEC. BUS - 3 POS. SINGLE-SCREW CONNECTOR


SEC. BUS - 4 POS. SINGLE-SCREW CONNECTOR
SEC. BUS - 6 POS. SINGLE-SCREW CONNECTOR
SEC. BUS - 8 POS. SINGLE-SCREW CONNECTOR

9.16
11.20
14.78
23.07

0.25
0.25
0.25
0.25

32.27
33.56
39.32
49.55

BUS40LRG
BUS60LRG
BUS80LRG

SEC. BUS - 4 POS. TWO-SCREW CONNECTOR


SEC. BUS - 6 POS. TWO-SCREW CONNECTOR
SEC. BUS - 8 POS. TWO-SCREW CONNECTOR

54.37
60.52
74.47

0.25
0.25
0.25

89.83
94.35
113.35

BUS40DUAL
BUS60DUAL
BUS80DUAL

SEC. BUS - 4 POS. DUAL ENTRY 2-SCREW CONN


SEC. BUS - 6 POS. DUAL ENTRY 2-SCREW CONN
SEC. BUS - 8 POS. DUAL ENTRY 2-SCREW CONN

76.37
60.82
91.20

0.25
0.25
0.25

115.71
96.42
134.14

LOCATION SIGN FOR UNDERGROUND CABLE


WARNING TAPE 6 IN. FOR UG CBL /1000' ROLL
WARNING TAPE 3 IN. FOR UG CBL /1000' ROLL
CABLE END MARKER

5-7

05/09

UNDERGROUND ASSEMBLIES
U/A
CODE

FILE DESCRIPTION

ZONE 1A
MATERIAL MAN INSTALLED
COST
HRS
COST

FERC ACCOUNT 0369.30 - SERVICES


BUS8TS58
SEC. BUS - 8 POS. THREADED STUD 5/8 IN
BUS8TS10
SEC. BUS - 8 POS. THREADED STUD 1 IN
BUSCVR8
SEC. BUS COVER 8 POS. THREADED STUD

14.64
19.85
11.92

0.10
0.10
0.04

26.49
32.96
17.62

SEC BUS - 6 POS THRD STUD, 3PH PAD #6-500


SEC BUS COVER 6 POS THRD STUD 3PH PAD #6-500

13.15
9.40

0.10
0.04

24.64
14.49

BUSCVR3P1/0-750

SEC BUS - 6 POS THRD STUD, 3PH PAD 1/0-750


SEC BUS COVER 6 POS THRD STUD 3PH PAD 1/0-750

41.51
7.95

0.10
0.04

65.05
12.69

BUSADAPT4
BUSADAPT6
BUSADAPT8

SEC. BUS ADAPTER, SET SCREW 4 POS. 1/0-1000


SEC. BUS ADAPTER, SET SCREW 6 POS. 1/0-1000
SEC. BUS ADAPTER, SET SCREW 8 POS. 1/0-1000

107.03
145.10
180.44

0.25
0.25
0.25

155.98
205.20
245.16

LUG #1
LUG2/0
LUG25
LUG35
LUG2-4/0B
LUG2-4/0T
LUG350B
LUG350T
LUG500B
LUG500T
LUG600B
LUG600T
LUG750B
LUG750T

LUG FOR #1 AL/CU


LUG FOR 2/0 AL/CU
LUG FOR 250 AL/CU
LUG FOR 350 AL/CU
LUG STACKING BOTTOM FOR 2 TO 4/0 AL/CU
LUG STACKING TOP FOR 2 TO 4/0 AL/CU
LUG STACKING BOTTOM FOR 350 KCM AL/CU
LUG STACKING TOP FOR 350 KCM AL/CU
LUG STACKING BOTTOM FOR 500 KCM AL/CU
LUG STACKING TOP FOR 500 KCM AL/CU
LUG STACKING BOTTOM FOR 600 KCM AL/CU
LUG STACKING TOP FOR 600 KCM AL/CU
LUG STACKING BOTTOM FOR 750 KCM AL/CU
LUG STACKING TOP FOR 750 KCM AL/CU

1.13
1.46
2.79
3.08
9.79
3.82
10.34
4.96
12.51
7.46
14.62
7.86
15.99
12.87

0.10
0.10
0.17
0.17
0.17
0.17
0.17
0.17
0.17
0.17
0.17
0.17
0.17
0.17

9.72
10.13
18.03
18.38
26.39
19.34
27.39
20.73
30.10
23.83
32.44
24.33
34.42
30.56

SERVCONN

SERVICE CONNECTION LABOR (PER l00 KVA)

0.00

1.00

83.88

33.00
2.68
7.70
0.24
15.76
19.11
12.84
17.63
10.23
7.74

0.40
0.12
1.50
0.01
0.01
0.01
0.50
0.50
1.00
0.16

82.07
24.37
166.24
1.34
21.56
49.90
68.34
74.33
117.55
26.31

BUS3P6-500
BUSCVR3P6-500

BUS3P1/0-750

FERC ACCOUNT 0373.20 - STREET LIGHTING - UG CIRCUITS & DITCH


6DXUG
CBL UG - 6 ALUMINUM DUPLEX /100 FT
SLSV6
SEALING SLEEVES FOR #6DX
1RSR
RISER, CONDUIT 1 IN
1CDTPL
CONDUIT 1 IN PVC /FT
BUS2SL
SEC BUS - 2-POSITION STREET LIGHT
BUS3SL
SEC BUS - 3-POSITION STREET LIGHT
GNDUGSL
GROUND, COPPER AT STEEL STREET LIGHT STAND
GNDSP-GLV
GROUND, GALVANIZED - AT STEEL POLE
HH10
SEC. HANDHOLD - ROUND w/LID (10"X10")
HH10LID
LID FOR SEC. HANDHOLD - ROUND (10" DIA)
NOTE: CABLE AND HANDHOLES ARE 373.20 IF USED FOR
STREET LIGHTS OR 369.30 IF USED FOR SERVICES.

5-8

05/09

FERC ACCOUNT
108.00 REMOVAL
FERC
Acct.

FERC
Acct.

ManHrs

364 Pole
1.98
Pole - Stubbed
2.31
Crossarm -Single
0.41
Crossarm - Double
0.65
Down Guy
0.59
Span Guy
0.42
Sidewalk Guy
0.86
Rack - 1 Spool
0.12
Rack - 3 Spool
0.20
Neutral Support
0.12
Pole Top Pin
0.17
Steel Pin
0.10
Transf. Mtg. Bracket 0.50
Transf. Rack
1.98
365 Conductor
.007/lb.
Insulator- Pin
0.00
Insulator- Deadend
0.17
Clamp
0.07
Ground
0.33
Air Switch
5.00
366 Riser, Conduit
0.50
Handhole - Sec
0.25

ManHrs

367

Lightning Arrester
Cutout
Sec. Bus
Feed Thru Bushing
Feed Thru Bushing Insert
Standoff Insulator
Splice
Y-Splice
Bushing Cap
Bushing Insert
Elbow
Terminator
Junction
368 Cutout
Lightning Arrester
369.1 Service
373.1 Street Light
Luminaries Only
Mast Arm Only
Ballast Only
Relay
Sunswitch
373.2 Riser, Conduit

See man-hour rates on page 1-1

6-1

05/09

0.10
0.10
0.25
0.10
0.05
0.10
0.10
0.15
0.05
0.05
0.05
0.10
0.25
0.10
0.10
0.85
0.70
0.33
0.37
0.17
0.10
0.10
0.50

SALVAGEOVERHEAD
POLES & CROSSARMS - For poles and crossarms 0-10 years of age, use the
following salvage table: (Older than 10 years - NO SALVAGE)
Pole & Crossarm
Reduction per Year.

Current Mat'l. Cost


10 x 1.120

Salvage Value = (Reduction/Year) (10-Age)


POLES
30'
35'
40'
45'
50'

$22.18
$27.86
$38.18
$55.33
$60.69

55'
60'
65'
70'
75'

$67.66
$94.67
$107.73
$170.05
$196.55

Note: Obtain a Bill of Sale for our records when selling poles to customers.

Size
5 Ft.
9 Ft.
9HA
11HA

CROSSARMS
Single
$2.56
$5.90
$7.72
$9.67

Double
$4.34
$9.93
$13.56
$17.46

Salvage Value = (Total Material Cost/Material Multiplier)


9' Crossarm - Single (Hdwr only) ................................................................ $27.86
9' Crossarm - Double (Hdwr only) ............................................................... $37.11
9' Crossarm - Single HD (Hdwr only) .......................................................... $27.63
9' Crossarm - Double HD (Hdwr only) ......................................................... $36.49
Steel Stub ....................................................................................................$275.83
Rack Secondary - 1 Spool w/ext ................................................................. $11.88
Rack Secondary - 3 Spool w/ext ................................................................. $76.51
Neutral Support ........................................................................................... $4.61
Pole Top Pin - 13kV (Double) ..................................................................... $7.78
Pole Top Pin - 13kV (Double) ..................................................................... $14.63
Steel Pin - 13kV (No Adpt) .......................................................................... $3.51
Steel Pin - 25kV (No Adpt) .......................................................................... $10.97
2 Transf Mount Bracket ............................................................................... $97.27
3 Transf Mount Bracket (to 50KVA) ............................................................ $75.26
3 Transf Mount Bracket (75 to 167KVA) ..................................................... $137.20

6-2

05/09

SALVAGEOVERHEAD

Insulator Pin Type - 8kV (Br) .................................................................... $3.81


Insulator Pin Type - 8kV (Wh) .................................................................. $3.81
Insulator Pin Type - 13kV ......................................................................... $2.29
Insulator Pin Type - 25kV .......................................................................... $4.67
Insulator Deadend 8kV .............................................................................. $6.34
Insulator Deadend 13kV ............................................................................ $8.15
Clamp Pinco .............................................................................................. $3.63
Clamp 4-2/0 ACSR .................................................................................... $5.69
Clamp 556 AAC .........................................................................................$11.24
Ground - Rod .............................................................................................$35.01
Cutout - Open 13kV 100 Amp ................................................................... $74.96
Lightning Arrester - 10kV ...........................................................................$65.07

SCRAP CONDUCTOR
Copper Bare
ACSR

$1.86 /lb
$0.22 /lb

6-3

Alum.Bare
Alum.WP

$1.14 /lb
$0.28 /lb

05/09

SALVAGE UNDERGROUND
(Current Material Cost/Material Multiplier)
Conduit Riser - 2" ........................................................................................ $57.13
Conduit Riser - 3" ........................................................................................ $74.87
Conduit Riser - 4" ........................................................................................ $87.39
Riser Pole Arrester 10kV ............................................................................. $68.39
Plastic Pad - Single Phase .......................................................................... $56.28
Groundsleeve - Single Phase ...................................................................... $177.67
Cutout - Open 13kV 100 Amp ......................................................................$74.96
Cutout - Bracket for Heavy Arms ................................................................. $13.54
Ground Rod - Pad or Vault .......................................................................... $11.46
Bus - Bar 30 ................................................................................................. $8.18
Bus - Bar 40 ................................................................................................. $10.00
Bus - Bar 66 ................................................................................................. $13.20
Feed Thru Bushing - 15kV ........................................................................... $78.96
Feed Thru Bushing - 25kV ........................................................................... $124.36
Feed Thru Bushing Insert- 15kV .................................................................. $95.82
Feed Thru Bushing Insert - 25kV ................................................................. $124.52
Standoff Bushing - 15kV .............................................................................. $33.63
Standoff Bushing - 25kV .............................................................................. $56.05
Bushing Cap- 15kV ...................................................................................... $18.47
Bushing Cap - 25kV ..................................................................................... $32.84
Bushing Insert - 15kV .................................................................................. $21.13
Bushing Insert - 25kV .................................................................................. $31.74
Elbow - 15kV ................................................................................................$29.68
Elbow - 25kV ................................................................................................$43.82
Junction Bus - Pri 4 Position - 15kV ............................................................ $137.53
Junction Bus - Pri 5 Position - 15kV ............................................................ $637.02
Junction Bus - Pri 4 Position - 25kV ............................................................ $273.08

6-4

05/09

MAINTENANCE
Use the following as a guideline for estimating maintenance cost of new
MAN-HRS
TASK#
PER UNIT
TASK

MAINT
COSTS

583000 (OH) Install or Remove Transformer

1-25 KVA
2.15
37-167 KVA
2.35
200-750 KVA
3.55
1000-2000 KVA*
4
2500 KVA*
7.5
Transfer
1.5 x Install
Trench Pole
8.60
Up or Down
Guy
1.85
Single Arm
0.85
Double Arm
1.42
Spool Rack
0.48
Transformer Bracket
0.87
Retie Conductor to pole
0.08
Reclamp Conductor
0.20
Relocate Conductor (per Insulator)
0.2
Up or Down
Line Cutout
0.75
Line OCR
0.75
Service (OH)
0.96
Tree Trim (Avista Utilities Crew)
Tree Trim (Contract Crew)
Clear Line-Light
0.01
Medium
0.01
Heavy
0.02
Up or Down
Terminator
0.63
Arrester
0.75
Cutout
0.75
Riser
3.00
Up or Down
Cutout for Transf or Cap
0.75
Arrester for Transf or Cap
0.75
Cap Bank 300-75 KVAR
3.55
900-1200 KVAR
4.00
Up or Down
Street Light & Bracket
2.86
Luminaire
0.80
Relay
1.40
Sunswitch
1.40

and
(System Average)
584010 (UG)

593010

593020

593031

594010

595000

596010

M
U
L
T
I
P
L
Y
T
H
E
S
E

174
191
288
599
883
605
130
60
100
34
61
6
14
14
53
53
68

X
1.5

0.35/ft
0.70/ft
F 1.05/ft
O
44
R
53
53
T
211
R
53
A
53
N
250
S
281
F
166
E
56
R
98
98

Notes:
1. Use ZONE, HOT WORK, CONTRACT & OMISSION corrections as required, except for transformers.
2. * Includes Cost of Crane ($275)
3. The Maintenance Cost column equals the Man-Hours Per Unit column times the appropriate 4-man
crew rate, times the material multiplier. (See man-hour rates on page 1-1).
4. Transfer refers to removal and installation of an item on the same day without leaving the job site.
Multiply the man-hours or maintenance cost by 1.5 for transfer.

6-5

05/09

$425

$734

$918

$809

$1,437

$1,898

$2,550

$3,783

$5,048

$6,672

15

25

37.5

50

75

100

167

250

333

500

120/240

7-1

*Not stocked by Avista Utilities. Must special order. Prices include shipping.
Prices do not include sales tax, material overheads or installation.

05/09

$7,797

$6,227

$4,413

$3,652

$2,362

$1,970

$1,431

$1,193

$934

$751

$4,237

$2,466

$2,016

$1,469

$1,337

$1,047

$758

277/480Y 120/240

$3,351

$2,462

$1,998

$1,427

$1,081

$803

$1,967

$1,550

$1,235

$967

$808

$1,836

$1,597

$1,633

$1,038

$1,472

$1,176

$2,291

$1,011

$976

277/480Y

19920/34500Y

150kV BIL

277/480Y 120/240

14400/24900Y

125kV BIL

277/480Y 120/240

12000/20800Y

7620/13200Y

KVA

125kV BIL

95kV BIL

NEW TRANSFORMER COST FOR


DISTRIBUTION ESTIMATING
SINGLE-PHASE OVERHEAD TYPE
(WITH TAPS & NO TAPS)

NEW TRANSFORMER COST FOR


DISTRIBUTION ESTIMATING
SINGLE-PHASE PADMOUNT TYPE

KVA
15
25
37.5
50
75
100
167

95kV BIL
13200Y/7620
240/120
WITH & NO TAPS
$1,170
$1,453
$1,613
$1,893
$2,265
$2,814
$3,699

125kV BIL
20800Y/12000
240/120
NO TAPS
$1,231
$1,449
*
$1,882
$2,320
$2,898
$3,833

125kV BIL
24900Y/14400
240/120
NO TAPS
$1,338
$1,529
*
*
*
*
*

2 - 2-1/2 taps above and below 7620 volts are required for 12.5 kV system.
*Not stocked by Avista Utilities. Must special order.
Prices include shipping. Prices do not include sales tax, material overheads
or installation.

7-2

05/09

NEW TRANSFORMER COST FOR


DISTRIBUTION ESTIMATING
THREE-PHASE PADMOUNT TYPE
(WITH TAPS & FUSES)

KVA
45
75
112
150
225
300
500
750
1000
1500
2500

95kV BIL
13200Y/7620
208Y/120 480Y/277
$4,845
$4,904
$5,138
$5,480
$5,993
$6,186
$6,659
$6,456
$7,473
$7,189
$9,112
$8,443
$14,346
$11,941
$16,227
$14,723
$19,598
$22,779
*
$23,782
*
*

125kV BIL
20800Y/12000
208Y/120 480Y/277
*
*
$5,604
$5,997
$6,330
$6,375
$6,579
$6,623
$7,473
$7,323
$9,175
$8,746
$12,411
*
*
$14,907
*
$20,610
*
*
*
$40,123

125kV BIL
24900Y/14400
208Y/120 480Y/277
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*

*Not stocked by Avista Utilities. Must special order. Prices include shipping.
Prices do not include sales tax, material overheads or installation.

7-3

05/09

SERVICE VOLTAGE DROP


IN PERCENT AT 100% POWER FACTOR
120/240 VOLT SERVICE
4TX OVERHEAD
WINTER LOADS:
FEET

50
100
150
200
250
300
350
400

KVA:
5
10
AMPS at 240 volts:
21
42
0.46
0.93
0.93
1.85
1.39
2.78
1.85
3.71
2.32
4.64
2.78
5.56
3.24
6.49
3.71
7.42

15

20

25

63
1.39
2.78
4.17
5.56
6.95
8.34
9.73
11.13

83
1.85
3.71
5.56
7.42
9.27
11.13
12.96
14.83

104
2.32
4.64
6.95
9.27
11.59
13.91
16.22
18.54

120/240 VOLT SERVICE


2TX OVERHEAD
WINTER LOADS:
FEET

50
100
150
200
250
300
350
400

KVA:
10
15
AMPS at 240 volts:
42
63
0.59
0.88
1.17
1.76
1.76
2.63
2.34
3.51
2.93
4.39
3.51
5.27
4.10
6.14
4.68
7.02

20

25

30

35

83
1.17
2.34
3.51
4.68
5.85
7.02
8.19
9.36

104
1.46
2.93
4.39
5.85
7.31
8.78
10.24
11.70

125
1.76
3.51
5.27
7.02
8.78
10.53
12.29
14.04

146
2.05
4.10
6.14
8.19
10.24
12.29
14.33
16.38

SHADED VALUES ARE FOR REFERENCE ONLY.

8-1

05/09

SERVICE VOLTAGE DROP


IN PERCENT AT 100% POWER FACTOR
120/240 VOLT SERVICE
2/OTXUG
KVA:
10
15
20
FEET
AMPS at 240 volts:
42
63
83
50
0.30 0.44 0.59
100
0.59 0.89 1.18
150
0.89 1.33 1.77
200
1.18 1.77 2.36
250
1.48 2.21 2.95
300
1.77 2.66 3.54
350
2.07 3.10 4.13
400
2.36 3.54 4.72
450
2.66 3.98 5.31
500
2.95 4.43 5.90
550
3.25 4.87 6.49
600
3.54 5.31 7.08

WINTER
LOADS:
25

30

35

40

45

50

104
125
146
167
188
0.74 0.89 1.03 1.18 1.33
1.48 1.77 2.07 2.36 2.66
2.21 2.66 3.10 3.54 3.98
2.95 3.54 4.13 4.72 5.31
3.69 4.43 5.16 5.90 6.64
4.43 5.31 6.20 7.08 7.97
5.16 6.20 7.23 8.26 9.30
5.90 7.08 8.26 9.44 10.63
6.64 7.97 9.30 10.63 11.95
7.38 8.85 10.33 11.81 13.28
8.12 9.74 11.36 12.99 14.61
8.85 10.63 12.40 14.17 15.94

208
1.48
2.95
4.43
5.90
7.38
8.85
10.33
11.81
13.28
14.76
16.23
17.71

120/240 VOLT SERVICE


4/OTXUG
KVA:
30
35
40
FEET
AMPS at 240 volts:
125
146
167
50
0.57 0.67 0.76
100
1.15 1.34 1.53
150
1.72 2.01 2.29
200
2.29 2.67 3.06
250
2.86 3.34 3.82
300
3.44 4.01 4.58
350
4.01 4.68 5.35
400
4.58 5.35 6.11

WINTER
LOADS:
45

50

55

60

188
0.86
1.72
2.58
3.44
4.30
5.16
6.02
6.88

208
0.95
1.91
2.86
3.82
4.77
5.73
6.68
7.64

229
1.05
2.10
3.15
4.20
5.25
6.30
7.35
8.40

250
1.15
2.29
3.44
4.58
5.73
6.88
8.02
9.17

65

70

271
292
1.24 1.34
2.48 2.67
3.72 4.01
4.97 5.35
6.21 6.68
7.45 8.02
8.69 9.36
9.93 10.69

SHADED VALUES ARE FOR REFERENCE ONLY.

8-2

05/09

SERVICE VOLTAGE DROP


IN PERCENT AT 100% POWER FACTOR
120 VOLT SERVICE (STREET LIGHTS)
6DX
MULTIPLE LIGHTS:
FEET
50
100
150
200
250
300
350
400

WATTS:
50
100
0.03 0.06
0.06 0.12
0.09 0.18
0.12 0.24
0.15 0.29
0.18 0.35
0.21 0.41
0.24 0.47

200
0.12
0.24
0.35
0.47
0.59
0.71
0.82
0.94

250
0.15
0.29
0.44
0.59
0.74
0.88
1.03
1.18

400
0.24
0.47
0.71
0.94
1.18
1.41
1.65
1.88

500
0.29
0.59
0.88
1.18
1.47
1.76
2.06
2.35

600
0.35
0.71
1.06
1.41
1.76
2.12
2.47
2.82

700
0.41
0.82
1.24
1.65
2.06
2.47
2.88
3.29

SHADED VALUES ARE FOR REFERENCE ONLY.

8-3

05/09

800
0.47
0.94
1.41
1.88
2.35
2.82
3.29
3.76

TRANSFORMER 160% - LOAD CURRENT


SINGLE-PHASE CURRENT
IN AMPS
TRANSF
KVA
3
5
7.5
10
15
25
37.5
50
75
100
167
250
333
500

120
40
67
100
133
200
333
500
667
1,000
1,333
2,227
3,333
4,440
6,667

240
20
33
50
67
100
167
250
333
500
667
1,113
1,667
2,220
3,333

208
133
200
333
500
667
1,000
1,334
2,223
3,335
4,446
6,670

240
116
173
289
434
578
867
1,156
1,927
2,890
3,854
5,780

KVA x 1000 x 1.6


Phase to Ground Voltage

PHASE-TO-GROUND VOLTAGE:
277
480 2400 7200 7620 14400 19900
17
10
2
1
1
0
0
29
17
3
1
1
1
0
43
25
5
2
2
1
1
58
33
7
2
2
1
1
87
50
10
3
3
2
1
144
83
17
6
5
3
2
217
125
25
8
8
4
3
289
167
33
11
10
6
4
433
250
50
17
16
8
6
578
333
67
22
21
11
8
965
557
111
37
35
19
13
1,444
833
167
56
52
28
20
1,923 1,110
222
74
70
37
27
2,888 1,667
333
111
105
56
40

THREE-PHASE CURRENT
IN AMPS
BANK
KVA
30
45
75
112.5
150
225
300
500
750
1000
1500

= Bank KVA x 1000 x 1.6


1.732 x Phase to Ground Voltage

PHASE-TO-PHASE VOLTAGE:
480
4160 12470 13200 24900 34500
58
7
2
2
1
1
87
10
3
3
2
1
145
17
6
5
3
2
217
25
8
8
4
3
289
33
11
11
6
4
434
50
17
16
8
6
578
67
22
21
11
8
963 111
37
35
19
13
1,445 167
56
53
28
20
1,927 222
74
70
37
27
2,890 333
111
105
56
40

8-4

05/09

TRANSFORMER FULL - LOAD CURRENT


SINGLE-PHASE CURRENT
IN AMPS
TRANSF
KVA
3
5
7.5
10
15
25
37.5
50
75
100
167
250
333
500

120
25
42
63
83
125
208
313
417
625
833
1,392
2,082
2,775
4,167

240
13
21
31
42
63
104
156
208
313
417
696
1,042
1,388
2,083

PHASE-TO-GROUND VOLTAGE:
277
480 2400 7200 7620 14400 19900
11
6
1
0
0
0
0
18
10
2
1
1
0
0
27
16
3
1
1
1
0
36
21
4
1
1
1
1
54
31
6
2
2
1
1
90
52
10
3
3
2
1
135
78
16
5
5
3
2
181
104
21
7
7
3
3
271
156
31
10
10
5
4
361
208
42
14
13
7
5
603
348
70
23
22
12
8
903
521
104
35
33
17
13
1,202
694
139
46
44
23
17
1,805 1042
208
69
66
35
25

THREE-PHASE CURRENT
IN AMPS
BANK
KVA
30
45
75
112.5
150
225
300
500
750
1000
1500

208
83
125
208
312
416
625
833
1,388
2,082
2,776
4,164

240
72
108
180
271
361
541
722
1,203
1,804
2,406
3,608

KVA x 1000
Voltage

= KVA x 1000
1.732 Voltage

PHASE-TO-PHASE VOLTAGE:
480
4160 12470 13200 24900 34500
36
4
1
1
1
1
54
6
2
2
1
1
90
10
3
3
2
1
135
16
5
5
3
2
180
21
7
7
3
3
271
31
10
10
5
4
361
42
14
13
7
5
601
69
23
22
12
8
902
104
35
33
17
13
1,203
139
46
44
23
17
1,804
208
69
66
35
25

8-5

05/09

OVERHEAD MAXIMUM AMPACITY TABLES


ACSR

Size

Code

Weight
(Lb./Ft.)

#4
#2
1/O
2/O
4/O
266.8 kCM
336.4 kCM
397.5 kCM
556.5 kCM

Swanate
Sparrow
Raven (N1)
Quail
Penguin
Partridge (N2)
Merlin (N2)
Ibis (N2)
Parakeet (N2)

0.0670
0.0913
0.1450
0.1831
0.2911
0.3673
0.3653
0.5469
0.7168

Conductor

Maximum Ampacity (Amps)


Summer
Winter
121
161
210
241
314
397
451
510
625

176
241
309
355
465
590
671
761
937

ALL ALUMINUM
Conductor
Size

Code

#4
336.4 kCM
556.5 kCM
795 kCM
1272 kCM

Tie Wire
Tulip
Dahlia
Arbutus
Nacrissus

Weight
(Lb./Ft.)
0.3900
0.3158
0.5220
0.7460
1.1940

Maximum Ampacity (Amps)


Summer
Winter
100
452
610
762
1014

150
676
913
1146
1535

COPPER

Size

Code

Weight
(Lb./Ft.)

#6

---

0.0800

Conductor

Maximum Ampacity (Amps)


Summer
Winter
110

156

For additional information, refer to Overhead Construction Standards


DO-3.110 through DO-3.140.
N1. Not for new Distribution Construction.
N2. For neutrals with secondary mid-span taps only.

8-6

05/09

OVERHEAD MAXIMUM AMPACITY TABLES


SERVICES
Conductor
Size

Neutral
ACSR (6/1)

Cond Weight
(Lb./Ft.)

#6 DX
#4 TX
#2 TX
2/0 TX
4/0 TX
#2 QX
2/0 QX
4/0 QX
2/0 SNGL
4/0 SNGL
350 ALWP
750 ALWP
250 CUWP
500 CUWP

#6
#4
#4
#1
#2/0
#2
#2/0
#4/0
None
None
None
None
None
None

0.0770
0.1720
0.2360
0.4680
0.7290
0.3600
0.7000
1.0700
0.1900
0.2800
0.4390
0.9050
0.8100
1.6000

Maximum Ampacity (Amps)


Summer
Winter
59
78
106
165
224
95
149
202
232
312
431
707
445
695

86
114
155
241
328
139
216
295
311
418
578
949
556
933

For additional information, refer to Overhead Construction Standard DO-6.101.

Ampacity is for each phase conductor.

8-7

05/09

UNDERGROUND MAXIMUM AMPACITY TABLES


ALUMINUM CROSS-LINKED POLYETHYLENE
90 Degrees C

Voltage
15 kV
15 kV
15 kV
15 kV
15 kV
15 kV
25 kV
25 kV
25 kV
35 kV

Conductor
Size
1
1/0
4/0
350
750
1000
1
350
1000
1/0

Neutral
Size
Full
Full
1/2
1/3
1/3
1/8
Full
1/3
1/8
Full

Weight
(Lb./Ft.)
0.60
0.70
0.81
1.12
2.00
2.70
0.68
1.38
2.87
0.92

Maximum Ampacity (Amps)


Summer
Winter
145
160
180
205
270
310
340
380
585
665
675
770
160
180
380
430
670
760
185
210

For additional information, refer to Underground Construction Standard


DU-4.105.
Ampacity values are for 3-phase construction with one cable per conduit.

8-8

05/09

UNDERGROUND MAXIMUM AMPACITY TABLES


ALUMINUM CROSS-LINKED POLYETHYLENE MULTIPLEX
90 deg. 600 VOLT INSULATION

Conductor
Size
6DXUG
2TXUG
2/0TXUG
4/0TXUG
2/0QXUG
4/0QXUG
3 x 350AL
3 x 750AL

Neutral
Size
#6
#4
#1
#2/0
#1
#2/0
#4/0 AL
350 AL

Cond Weight
(Lb./Ft.)
100
275
525
765
705
1038
1630
3180

Maximum Ampacity (Amps)


Summer
Winter
58
76
102
133
159
208
217
283
159
208
217
283
303
395
488
637

Multiply ampacity values by 1.6 for two parallel sets of conductors.


Ampacity is for each phase conductor in conduit.
For additional information, refer to Underground Construction Standard
DU-7.101.

8-9

05/09

URD TRANSFORMERS AND


JUNCTION ENCLOSURES

JUNCTION ENCLOSURES
Type
JE1
JE2
JE3

Equipped With
(1) J4__, (4) BI
(2) J4__, (8) BI
(3) J4__, (12) BI

Items to Order
EBs, BCs, (1) GNDSLV1, GNDUG
EBs, BCs, (1) GNDSLV2, GNDUG
EBs, BCs, (1) GNDSLV3, GNDUG

Note: Order BCs to cover unused positions on the J4 primary bus.

SINGLE PHASE PADMOUNT TRANSFORMERS


To install a single phase padmount transformer you will need to order
the following items:

KVA
15
25
37.5
50
75
100
167

FTBI
To exit twice
To exit twice
To exit twice
To exit twice
To exit twice
To exit twice
To exit twice

P44PL
PAD
1
1
1
1
1
1
1

SCOOP
1GNDSLV1
1GNDSLV1
1GNDSLV1
1GNDSLV1
1GNDSLV1
1GNDSLV1
1GNDSLV1

GNDUG
1
1
1
1
1
1
1

Notes:
1) New single phase padmount transformers are shipped from the factory
with the following primary components:
Two primary bushings and two bushing inserts (BI) for feed through
2-200 amp elbows (EB) in a prepackaged kit
Additional primary components needed:
If you are going into the transformer with a primary conductor and out
of the transformer with a primary conductor, no additional primary
components need to be ordered.
If you are not going out of the transformer with a primary conductor,
order a bushing cap (BC).
If you intend to take two primary conductors out of the transformer,
order a feed through bushing insert (FTBI) and an additional 200 am elbow (EB).

8-10

05/09

URD TRANSFORMERS AND


JUNCTION ENCLOSURES

SINGLE PHASE PADMOUNT TRANSFORMERS

Notes: (continued)
2) All new single phase padmount transformers are shipped from the
factory with the following secondary connectors:
15-75 kVA transformers are shipped with eight position secondary
connectors on 5/8" studs (BUS8TS58). Boot covers are included on X1
and X3.
100-167 kVA transformers are shipped with eight position secondary
connectors on 1" studs (BUS8TS10). Boot covers are included on X1
and X3.
3) It is typically not necessary to order SOBs for transformers.
4) Whenever it is practical to do so, replace subsurface transformers with
padmount units when the subsurface unit fails. Poly concrete pad
(54"x48") stock number 571-2010 should be ordered.

8-11

05/09

URD TRANSFORMERS AND


JUNCTION ENCLOSURES
THREE PHASE PADMOUNT TRANSFORMERS

Three phase padmount transformers come in 45, 75, 112.5, 150, 225, 300,
500, 750, 1000, and 1500 kVA ratings. All three phase padmount transformers
are wired for wye secondary voltages of either 208Y/120 or 480Y/277.
Notes:
1) All three phase padmount transformers are shipped from the factory
with the following primary components:
Three primary bushings and three bushing inserts (BI)
3-200 amp elbows (EB) in a prepackaged kit
Additional primary components needed:
If the service feeds a single transformer, no additional primary
components need to be ordered.
If the transformer is being used in a feed through application, three
feed through bushing inserts (FTBI) and three 200 amp elbows (EB)
must be ordered.
2) Secondary connectors are either set screw style with boot covers pre
installed, or spade connectors as follows:
KVA
45-75
112.5-225
300
500-1000
1500

208Y/120
six pos set screw #6-500KCM
six pos set screw 1/0-750KCM
16 hole supported
16 hole supported
N/A

480Y/277
six pos set screw #6-500KCM
six pos set screw 1/0-750KCM
six pos set screw 1/0-750KCM
16 hole supported
16 hole supported

The holes required are in addition to any holes used to support and/or connect
to the terminal.
Three phase padmount transformers do not come with their own plastic base
pad. They require a poured concrete pad for installation. For most applications,
the customer is required to supply a concrete pad that meets Avista Utilities'
standards. Remember to order a three phase scoop (GNDSLV3 or
GNDSLV3LRG) to be installed in the concrete pad. See DU-5.122.
If the customer proposes more than 3 wires per phase, they may be required
to provide a secondary enclosure. See DU-5.124 for guidelines; and DU-5.122
and DU-5.123 for fiberglass box pad or concrete pad.

8-12

05/09

Copyright

2004 Avista Utilities.

All rights reserved under U.S. and foreign law, treaties and
conventions. No part of this work may be copied or reproduced,
stored in retrieval system, or transmitted in any form, graphic,
electronic or mechanical, without permission of the copyright
owner.

S-ar putea să vă placă și