Documente Academic
Documente Profesional
Documente Cultură
m,y
= Average net energy conversion efficiency of power unit m in
year y (ratio)
m = All power units serving the grid in year y except low-
cost/must-run power units
y = The relevant year as per the data vintage chosen
Where several fuel types are used in the power unit, use the fuel type with the
lowest CO
2
emission factor for EFCO
2
,m,i,y.
The Simple OM is calculated using the data of all operational fossil fuel fired
power plants generating electricity to the grid for the years 2006, 2007 and
2008.
The calculations of OM were based on specific individual plant specific data
as provided by the Energy Commission, SESB and SEB. Based on data
availability and reliability, the conservative method was adopted to estimate
the fuel consumption of electricity generating plants. Table 2 indicates the
Operating Margins for the three regions.
Table 2: Operating Margin Result Based on Grids System for 2008
Grid System Operating Margin
( tCO
2
/MWh)
Peninsular Malaysia Grid 0.603
Sarawak Grid 0.813
Sabah Grid 0.705
3.4.2 Calculation of the Simple Adjusted Operating Margin
The Simple Adjusted OM. emission factor (EF
OM,simple adjusted,y
) is a variation on
the previous method, where the power sources (including imports) are
separated in low-cost/must-run power sources (k) and other power sources
(m). As with the simple OM, it can be calculated as follows:
Based on data on net electricity generation, the average efficiency of
each power unit and the fuel type(s) used in each power unit, as
follows:
CDM Electricity Baseline
Pusat Tenaga Malaysia
17
Where
Where:
EF
grid,OM-adj,y
= Simple adjusted operating margin CO
2
emission factor in year y
(tCO
2
/MWh)
y
= Factor expressing the percentage of time when low-cost/must-
run power units are on the margin in year y
EG
m,y
= Net quantity of electricity generated and delivered to the grid by
power unit m in year y (MWh)
EG
k,y
= Net quantity of electricity generated and delivered to the grid by
power unit k in year y (MWh)
EF
EL,m,y
= CO
2
emission factor of power unit m in year y (tCO
2
/MWh)
EF
EL,k,y
= CO
2
emission factor of power unit k in year y (tCO
2
/MWh)
m = All grid power units serving the grid in year y except low-
cost/must-run power units
k = All low-cost/must run grid power units serving the grid in year
y
y = The relevant year as per the data vintage chosen
y
were calculated as follows:-
where lambda ( y ) should be calculated as follows (see figure below):
Step i) Plot a Load Duration Curve. Collect chronological load data (typically
in MW) for each hour of a year, and sort load data from highest to
lowest MW level. Plot MW against 8760 hours in the year, in
descending order.
Step ii) Organize Data by Generating Sources. Collect data for, and calculate
total annual generation (in MWh) from low-cost/must-run resources
(i.e. k GENk,y).
Step iii) Fill Load Duration Curve. Plot a horizontal line across load duration
curve such that the area under the curve (MW times hours) equals the
total generation (in MWh) from lowcost/must-run resources (i.e. k
GENk,y).
Step iv) Determine the Number of hours per year for which low-cost/must-run
sources are on the margin. First, locate the intersection of the
horizontal line plotted in step (iii) and the load duration curve plotted in
step (i). The number of hours (out of the total of 8760 hours) to the
CDM Electricity Baseline
Pusat Tenaga Malaysia
18
right of the intersection is the number of hours for which low-
cost/must-run resources are on the margin. If the lines do not
intersect, then one may conclude that low-cost/must-run sources do
not appear on the margin and y is equal to zero. Lambda ( y) is the
calculated number of hours divided by 8760.
Figure 4: Illustration of Lambda Calculation for Simple Adjusted OM Method
The Lambda (y) calculation for the Simple Adjusted OM is to determine
whether the low-cost/must-run resources (Hydro) are operating at margin.
The lambda calculation shows that there is no intersection of the horizontal
line plotted (low-cost/must-run resources) in step (iii) and the load duration
curve plotted in step (i) for all main grids in Malaysia namely Peninsular
Malaysia, West Sabah and Sarawak as illustrated in Figures 5, 6 and 7.
These results indicate that the low-cost/must-run resources are not operating
at margin at any hours in a year for all 3 of the main grids. Hence the values
of lambda are zero for all 3 main grids. When calculating the Simple Adjusted
OM, it was found that the results were similar to those for the Simple OM.
This is due to the fact that low-cost/must-run sources constitute less than
50% of the total grid generation, and it can be demonstrated by the Simple
OM that the low-cost/must-run sources do not operate on margin. The rest of
this study and the calculations of the baseline will therefore only focus and be
based on the Simple Operating Margin.
CDM Electricity Baseline
Pusat Tenaga Malaysia
19
Figure 5: Load Duration Curve and Low-Cost/Must-Run Resources (Hydro)
Peninsular Malaysia for 2008
Peninsular Malaysia : Load Duration Curve- Yr 2008
0
2000
4000
6000
8000
10000
12000
14000
16000
1 299 597 895 1193 1491 1789 2087 2385 2683 2981 3279 3577 3875 4173 4471 4769 5067 5365 5663 5961 6259 6557 6855 7153 7451 7749 8047 8345 8643
Hours
M
W
Source: Energy Commission (2008)
Low Cost/Must Run Resources (Hydro) 781 MW
CDM Electricity Baseline
Pusat Tenaga Malaysia
20
Figure 6: Load Duration Curve and Low-Cost/Must-Run Resources (Hydro)
Sabah for 2008
Sabah : Load Duration Curve- Yr 2008
0
100
200
300
400
500
600
700
800
1 422 843 1264 1685 2106 2527 2948 3369 3790 4211 4632 5053 5474 5895 6316 6737 7158 7579 8000 8421
Hours
M
W
Source: Energy Commission (2008)
Figure 7: Load Duration Curve and Low-Cost/Must-Run Resources (Hydro)
Sarawak for 2008
Sarawak: Load Duration Curve Year 2008
0
100
200
300
400
500
600
700
800
900
0
3
6
5
7
3
0
1
0
9
5
1
4
6
0
1
8
2
5
2
1
9
0
2
5
5
5
2
9
2
0
3
2
8
5
3
6
5
0
4
0
1
5
4
3
8
0
4
7
4
5
5
1
1
0
5
4
7
5
5
8
4
0
6
2
0
5
6
5
7
0
6
9
3
5
7
3
0
0
7
6
6
5
8
0
3
0
8
3
9
5
8
7
6
0
Hour
M
W
Source: Sarawak Energy Berhad (2008)
Low Cost/Must Run Resources (Hydro) 52 MW
Low Cost/Must Run Resources (Hydro) 59 MW
CDM Electricity Baseline
Pusat Tenaga Malaysia
21
3.4.3 Calculation of Build Margin (BM)
According to the tool, the sample group of power units m used to calculate
the build margin consists of either:
4
a) The set of five power units that have been built most recently;or
b) The set of power capacity additions in the electricity system that
comprise 20% of the system generation (in MWh) and that have been
built most recently.
5
Project participants should use the set of power units that comprises the
larger annual generation.
As a general guidance, a power unit is considered to have been built at the
date when it started to supply electricity to the grid.
Power plant registered as CDM project activities should be excluded from the
sample group m. However, If the group of power units, not registered as CDM
project activity, identified for estimating the build margin emission factor
includes power unit(s) that is(are) built more than 10 years ago then:
i. Exclude power unit(s) that is (are) built more than 10 years ago from
the group; and
ii. Include grid connected power projects registered as CDM project
activities, which are dispatched by dispatching authority to the
electricity system.
6
Capacity additions from retrofits of power plants should not be included in the
calculation of the build margin emission factor
In terms of vintage of data, project participants can choose between one of
the following two options: These include:
Option 1, for the 1
st
crediting period, takes an ex ante approach, based on
the most recent information available on plants already built, at the time of
CDM-PDD submission to the DOE for validation. Ex-ante refers to the
period before the proposed project activity is starting. For the second
crediting period, the build margin emission factor should be updated
based on the most recent information available on units already built at
the time of submission of the request for renewal of the crediting period to
the DOE. For the third crediting period, the build margin emission factor
calculated for the second crediting period should be used. This option
does not require monitoring the emission factor during the crediting
period.
4
If this approach does not reasonably reflect the power plants that would likely be built in the absence of
the project activity, project participants are encouraged to submit alternative proposals for consideration by
the CDM Executive Board.
5
If 20% falls on part capacity of a unit, that unit is fully included in the calculation.
6
This information shall be provided by the host country.
CDM Electricity Baseline
Pusat Tenaga Malaysia
22
Option 2, in the 1
st
crediting period, the Build Margin shall be updated
anually is calculated ex post including those units built up to the year of
registration of the project activity or, if information up to the year of
registration is not yet available, including those units built up to the latest
year for which information is available. For the second crediting period,
the build margin emissions factor shall be calculated ex ante, as
described in Option 1 above. For the third crediting period, the build
margin emission factor calculated for the second crediting period should
be used.
In this study, Option 1 is selected and the Build Margin emissions factor (BM)
is calculated as the generation-weighted average emission factor of the 5
most recently built plants, using the following formula:
Where:
EF
grid,BM,y
= Build margin CO
2
emission factor in year y (tCO
2
/MWh)
EG
m,y
= Net quantity of electricity generated and delivered to the grid
by power unit m in year y (MWh)
EF
EL,m,y
= CO
2
emission factor of power unit m in year y (tCO
2
/MWh)
m = Power units included in the build margin
y = Most recent historical year for which power generation data is
available
The final results of Build Margin are shown in Table 3 below.
Table 3: Build Margin Results Based on Grid System for 2008
Grid System Build Margin
( tCO
2
/MWh)
Peninsular Malaysia Grid 0.741
Sarawak Grid 0.837
Sabah Grid 0.597
CDM Electricity Baseline
Pusat Tenaga Malaysia
23
3.4.4 Calculation of Combined Margin (CM)
The combined margin emission factor is calculated as the weighted average
of the emissions factor of the OM and the BM. The formula that is used to
calculate this weighted average emission factor is as follows:
Where:
EF
grid,BM,y
= Build margin CO
2
emission factor in year y (tCO
2
/MWh)
EF
grid,OM,y
= Operating margin CO
2
emission factor in year y (tCO
2
/MWh)
w
OM
= Weighting of operating margin emissions factor (%)
w
BM
= Weighting of build margin emissions factor (%)
The emissions factors of the OM and BM are weighted equally, each 50%, by
default, although different weightage may be used with appropriate
justification. The final results of Combined Margin are follows:-
Table 4: Combined Margin Results Based on Grid System for 2008
Grid System Combined Margin
(tCO
2
/MWh)
Peninsular Malaysia Grid 0.672
Sarawak Grid 0.825
Sabah Grid 0.651
4.0 Data collection and assumptions
The baseline has been calculated using data on the overall plant efficiency for
each power plant to determine the fuel consumption as obtained from the
Energy Commission, SESB and SEB for the year 2006, 2007 and 2008. In
addition, as shown in Table 5, carbon content and oxidation factor were also
used to derive the CO
2
emission coefficient which was also accounted for the
baselines calculation. The emission coefficient chosen was based on the
lower value of the 95% confidence interval for conservativeness.
CDM Electricity Baseline
Pusat Tenaga Malaysia
24
Table 5: Emission Factors Based on Fuel Types
Fuel Default
Carbon
Content
(kg/GJ)
Default
carbon
oxidation
factor
Effective CO
2
Emission
Factor
(kg/TJ)
CO
2
Emission
Coefficient
(t CO
2
/t
Fuel)
95%
Confidence
Interval
A B C =
A*B*44/12
D
1
= B*C Lower
LIQUID FOSSIL
Secondary
Fuels/Products
Gas/Diesel Oil 20.2 1 74.1 74.1 72.6
Residual Fuel Oil 21.1 1 77.4 77.4 75.5
SOLID FOSSIL
Primary Fuels
Other Bituminous
Coal
25.8 1 94.60 94.6 89.5
GASEOUS
FOSSIL
Natural Gas (Dry) 15.3 1 56.10 56.1 54.3
Source: 2006 IPCC Guidelines for National Greenhouse Gas Inventories
4.1 Leakage
No leakage emissions are considered. The main emissions potentially giving rise
to leakage in the context of electric sector projects are emissions arising due to
activities such as power plant construction and upstream emissions from fossil
fuel use (e.g. extraction, processing, transport). These emissions sources are
neglected.
For most renewable energy projects, including hydro and biogas, conversion
to electricity results no potential sources of leakage except for hydro project
that have the power density between 4W/m
2
to 10W/m
2
. However, for projects
involving the use of biomass, leakage may be identified due to the fact that
the biomass used may result in extra emissions related to the transporting of
the biomass. A good example is when using the Empty Fruit Bunches (EFB)
from more than one mill that have to be transported to the site where the
power will be generated. Such emissions may have to be quantified. It will
depend on each individual project whether such leakage is applicable or not.
As this issue is project specific, it is not considered further in this study.
CDM Electricity Baseline
Pusat Tenaga Malaysia
25
5.0 BASELINE EMISSION FACTOR IN MALAYSIA
The CO
2
emissions were calculated using a conservative method where the
plant efficiency for specific power plants was used as the determinants. The
plant efficiency was provided by the Energy Commission (EC), SEB and
SESB. The data on plant efficiency is originated from the specific plant
operator (data as per original design of the power plant).
This section will present the results of applying ACM0002. Towards verifying
the data, the efficiency of the plant is separately reviewed by EC, SEB for
Sarawak and TNB for Peninsular Malaysia.
5.1 BASELINE FOR PENINSULAR MALAYSIA
The calculation of Operating Margin is based on the generation-weighted
emissions per electricity unit of all power plants generating units serving the
grid system in Peninsular Malaysia. This excludes the generation from
Hydro as a must-run/ low-cost fuel source. The data available for the most
recent 3 years are the years 2006, 2007 and 2008 for calculating of operating
margin for 2008. These 3 years of historical data are illustrated in Table 6
below:
Table 6: Simple Operating Margin for Peninsular Malaysia for 2008
Years Generation
(GWh)
CO
2
Emission
(tonnes)
Baselines
(t CO
2
/MWh)
2008
90,215 56,322,476 0.624
2007
89,241 53,938,845 0.604
2006
84,906 49,333,299 0.581
Average Operating Margin for 3 years 0.603
a) Simple Operating Margin 2008
0.624+ 0.604+0.581
or 0.603 tonnes CO
2
/MWh
3
The calculation of Build Margin is based on the weighted average emissions
of the 5 most recently installed power plants in Peninsular Malaysia as
tabulated in Table 7. This sample group of power plant capacity must
comprise more than 20% of the total system generation, as stipulated in the
methodology. In year 2008, the total system generation is 97,053,880 MWh,
inclusive of hydro generating plants. The total output generated by these 5
plants is 36,119,630 MWh resulting in 37.2% of the total system generation in
Peninsular Malaysia, thus justifying the use of this method.
CDM Electricity Baseline
Pusat Tenaga Malaysia
26
Table 7: Build Margin for Peninsular Malaysia for 2008
Name of Power
Plants/ Fuel Types
Year of
Operation
Capacity
(MW)
Total
Generation
(MWh)
CO
2
Emission
(tCO
2
)
1. SKS Prai Power
Station/Gas &
Distillate 2002 350 2,472,020 1,015,403
2. Panglima Power
Station/Gas &
Distillate 2003 720 5,077,840 2,018,341
3. Janamanjung
Power Station/Coal 2003 2100 11,890,810 11,331,615
4. Tuanku Jaafar
Power Station/Gas
& Distillate 2005 715 5,747,640 2,312,158
5. Tanjung Bin
Power Station/Coal 2006/2007 2100 10,931,320 10,103,475
Total
36,119,630 26,780,992
Source: Energy Commission, 2008
The Build Margin for Peninsular Malaysia in 2008 is calculated as follows
CO
2
Emissions divided by the total generation i.e.
26,780,992 tonne CO
2
or 0.741 tonnes of CO
2
/MWh
36,119,630 MWh
Finally the Combined Margin is calculated by averaging the Simple
Operating Margin with the Build Margin. Therefore the Combined Margin
is
0.603 + 0.741
or 0.672 tonnes of CO
2
/MWh
2
CDM Electricity Baseline
Pusat Tenaga Malaysia
27
5.2 BASELINE FOR SARAWAK
The backbone of the Sarawak grid is the 275 kV transmission connecting
Kuching to Miri with a distance of 765 km. This main grid lies along the
coastal area or western region of Sarawak.
Plants outside the grid provide less than 5% of the states energy and these
are either small diesel generating sets or mini-hydro plants. These plants
have been excluded from the calculation as they are considered to be outside
the project boundary since they are not interconnected.
The data available for the most recent 3 years are the years 2006, 2007 and
2008 for calculating of operating margin for 2008.These 3 years of historical
data are illustrated in Table 8 below:
Table 8: Simple Operating Margin for Sarawak for 2008
Years Generation
(MWh)
CO
2
Emission
(tonnes)
Baselines
(t CO
2
/MWh)
2008 4,790,240 3,871,357
0.808
2007 4,694,610 3,782,930 0.806
2006 4,280,757 3,533,976 0.826
Average Operating Margin for 3 years 0.813
Source: Sarawak Electricity Supply Corporation, 2008
The Simple Operating Margin has been calculated based on the average of
3 years of historical data and is
0.808+0.806+0.826
or 0.813 tonnes of CO
2
/MWh
3
The calculation of Build Margin is based on the weighted average emissions
of the 5 most recently installed power plants in Sarawak as tabulated in Table
9. This sample group of power plant capacity must comprise more than 20%
of the total system generation, as stipulated in the methodology. In year 2008,
the total system generation is 5,304,240 MWh, inclusive of hydro generating
plants. The total output generated by these 5 plants is 3,784,610 MWh,
resulting in 71.4% of the total system generation in Sarawak, thus justifying
the use of this method.
CDM Electricity Baseline
Pusat Tenaga Malaysia
28
Table 9: Build Margin for Sarawak for 2008
Name of Power
Plants/ Fuel
Types
Year of
Operation
Capacity
(MW)
Total
Generation
(MWh)
CO
2
Emission
(tCO
2
)
1. Miri Power
Station/Gas &
Diesel 1994 79 448,790 383,208
2. Bintulu Power
Station
(SESCO)/Gas &
Distillate 1997 66 383,310 262,683
3.Sejingkat
Power Station
(SPC 1) / Coal 1998 100
731,860 786,018
4. Bintulu Gas
Power Station
(IPP) / Gas &
Distillate 1999 210 1,471,270 958,731
5.Sejingkat
Power Station
(SPC 2)/Coal 2004 110 749,380 778,872
Total 3,784,610
3,169,511
Source : Sarawak Electricity Supply Corporation, 2008
The Build Margin for Sarawak for 2008 is calculated as follows
CO
2
Emissions divided by the total generation i.e.
3,784,610 tonnes CO
2
or 0.837 tonnes CO
2
/MWh
3,169,511 MWh
The Combined Margin is calculated by averaging the Simple Operating
Margin with the Build Margin. Therefore the Combined Margin for
Sarawak is
0.813 + 0.837
or 0.825 tonnes CO
2
/MWh
2
CDM Electricity Baseline
Pusat Tenaga Malaysia
29
5.3 BASELINE FOR SABAH
Power transmission in Sabah for this year will be interconnected as one main
grid. A fully integrated grid connecting the West Coast Grid to the East Coast
Grid was completed on 28 July 2007, and about 90% of the customers are
now connected to this integrated grid.
The data available for the most recent 3 years are the years 2006, 2007 and
2008 for calculating of operating margin for 2008.These 3 years of historical
data are illustrated in Table 10 below:
Table 10: Simple Operating Margin for Sabah for 2008
Years Generation
(MWh)
CO
2
Emission
(tonnes)
Baselines
(t CO
2
/MWh)
2008
3785,951 2,423,097 0.640
2007 3455,506 2,567,930 0.743
2006 2,900,420 2,122,073 0.732
Average Operating Margin for 3 years 0.705
Source: Sabah Electricity Sdn. Bhd. and Energy Commission, 2008
The average baseline of Simple Operating Margin for 3-year vintages for the
Sabah grid is
0.640+ 0.743+ 0.732
or 0.705 tonnes CO
2
/MWh
3
The calculation of Build Margin is based on the weighted average emissions
of the 5 most recently installed power plants in Sabah as tabulated in Table
11. This sample group of power plant capacity must comprise more than 20%
of the total system generation, as stipulated in the methodology. In year 2008,
the total system generation is 4,240,951 MWh, inclusive of hydro generating
plants. The total output generated by these 5 plants is 2,426,840 MWh,
resulting in 57.2% of the total system generation in Sabah, thus justifying the
use of this method.
CDM Electricity Baseline
Pusat Tenaga Malaysia
30
Table 11: Build Margin for Sabah
Name of Power
Plants / Fuel
Types
Year of
Operation
Capacity
(MW)
Total
Generation
(MWh)
CO
2
Emission
(tCO
2
)
1.Powertron
Resources /Gas &
Diesel 1998 190 1,176,740 671,334
2. Sepanggar Bay
Power Corporation
(SBPC)/Gas 2006 100 641,410 376,063
3. Sutera Harbour
/Diesel 2006 36 134,290 87,745
4. Stratavest Sdn.
Bhd. 1998 60 291,630 190,267
5. Sandakan Power
Corporation (SPC) 1999 32 182,770 123,452
Total
2,426,840
1,448,861
Source: Sabah Electricity Sdn. Bhd. and Energy Commission (2008)
The Build Margin for Sabah is calculated as follows
CO
2
Emissions divided by the total generation i.e.
1,448,861 tonnes CO
2
or 0.597 tonnes CO
2
/MWh
2,426,840 MWh
The Combined Margin is calculated by averaging the Simple Operating
Margin with the Build Margin. Therefore the Combined Margin for Sabah
is
0. 705+ 0.597
or 0.651 tonnes CO
2
/MWh
2
CDM Electricity Baseline
Pusat Tenaga Malaysia
31
6.0 SUMMARY OF RESULTS
In summary, the following 2008 emission figures are used as the baseline for
the three regions in Malaysia:
Grid Systems
Simple OM
(tCO
2
/MWh)
Build Margin
(tCO
2
/MWh)
Combined Margin
(tCO
2
/MWh)
Peninsular
Malaysia
0.603 0.741 0.672
Sarawak 0.813 0.837 0.825
Sabah 0.705 0.597 0.651
CDM Electricity Baseline
Pusat Tenaga Malaysia
32
7.0 COMPARISON BETWEEN 2006, 2007 AND 2008 CDM BASELINE
EMISSION FACTORS
Tables 12 - 14 below show the comparisons of CDM Baseline Emission
Factors for 2006, 2007 and 2008. The results for some regions were either
slightly lower or higher compared to 2007 data due mainly to the generation
mix and plants efficiency.
In 2008, the slight decrease in the baselines for all of the grid was anticipated
whereby the lower emission factor was used for a conservativeness approach
in producing the emission factors. For Sabah and Sarawak, the fuel
consumption and plant efficiency varied from year 2008. The slight decrease
in 2008 could be attributed to less amount of gas used in some power plants
due to full major inspection for about 5 weeks in the case of Sarawak. For
Sabah, for year 2008, the emission factor is considered as 1 grid as the grid
has interconnected. On the other hand, the reduction on fuel consumption as
well as the electricity generation was also observed in East Sabah.
Table 12: Simple OM
Grid System
2006
(tCO
2
/MWh)
2007
(tCO
2
/MWh)
2008
(tCO
2
/MWh)
Peninsular
Malaysia
0.613 0.611 0.603
Sarawak 0.959 0.863 0.813
Sabah 0.818 0.828 0.705
Table 13: Build Margin
Grid System
2006
(tCO
2
/MWh)
2007
(tCO
2
/MWh)
2008
(tCO
2
/MWh)
Peninsular
Malaysia
0.710 0.757 0.741
Sarawak 0.897 0.882 0.837
Sabah 0.783 0.787 0.597
Table 14: Combined Margin
Grid System
2006
(tCO
2
/MWh)
2007
(tCO
2
/MWh)
2008
(tCO
2
/MWh)
Peninsular
Malaysia
0.661 0.684 0.672
Sarawak 0.928 0.873 0.825
Sabah 0.801 0.807 0.651
CDM Electricity Baseline
Pusat Tenaga Malaysia
33
8.0 REFERENCES
CDM Executive Board : Approved Consolidated Baseline Methodology
ACM0002, Version 10
CDM Executive Board: AMS I.D. Grid Connected Renewable
Electricity Generation, Version 15
CDM Executive Board: Tool to calculate the Emission factor, Version
2
2006 IPCC Guidelines for National Greenhouse Gas Inventories
Study on Grid Connected Electricity Baselines in Malaysia, 2006 &
2007, Pusat Tenaga Malaysia
National Energy Balance 2008, Ministry of Energy, Green Technology
and Water, Malaysia.
CDM Electricity Baseline
Pusat Tenaga Malaysia
34