1.
a.
delivers a
minimum of 200 ft3/min of water in the course of a year (1 m = 3.28 ft). lf the target energy to be supplied to the village in a year is 85 MWh,
calculate the efficiency of the hydro power plant, and [5 marks]
b.
As an engineer of Manjung Thermal Power station, you have been appointed to lead a task force to solve the problem of low thermal
efficiency at the thermal power station. State in your report the TWO (2) factors that will be the cause of the problem and propose the solution.
[5 marks]
c.
Discuss the TWO (2) advantages and disadvantages of gas turbine power
plant over steam power plant. Justify how they can be used
cogeneration.
in
[5 marks]
EB84043
2.
a.
An impulse generator has eight stages with each condenser rated for
0.16 pF and 1 25 kV. The load capacitor available is 1000 pF.
lf
i.
b.
c'
A single stage
impulse generator
voltages more than 200 kV. Justify this statement and propose a suitable type of impulse generator for voltages more than 200 kV.
[5 marks]
EB84043
3.
a.
is implementing a high voltage insulation cable testing. The testing voltage required is 400 kv A.c. As an engineer,
Cable-Tech company
propose a technique that can be used to generate 400 kV for the testing purpose, and justify your answer.
[5 marks]
b.
quaTizng brandr
FIGURE Q3
c-
compare the use of uniform field electrode spark gap with sphere gap for measuring peak value voltages.
[5 marks]
4
EBB4O43
4.
a.
As a consultant, you are required to design a Green Building that applies the concept of solar energy. The information of the Green Building are as
follow: Peak power required = 1B kW
- 23 kAh
Expected maximum number of continuous cloudy days = 1.2 days Average sun hours per day = 5.5 hours
Rated current of solar module = 7 A
m2
i.
ii.
the total peak power output of battery bank if the charge amp-hours
is 350 Ah.
[5 marks]
b.
With the aid of a diagram, explain how electric current is generated in photovoltaic cell.
[5 marks]
c.
EB84043
5.
a.
be developed, either non-renewable energy or renewable energy) in your area, describe what recommendations you will make and justify.
[5 marks]
b.
At Pulau Perhentian, Terengganu a 100 kw wind farm is to be installed. The annual average wind speed is given in FIGURE e4. The rotor
diameter of the wind turbine is 1o m. The density of air, pis 1.2 kg/m3 at sea level and the target efficiency js 40 %.
calculate the power output in kw, if the wind resource at 10 m and propose number of wind turbine to be installed.
[5 marks]
ii.
calculate the energy generated by one wind turbine in each year and how many houses can utilize the generated power if all the
Tidal power has the potential for future electricity generation as compared to solar power. Support this statement.
[5 marks]
EBB4O43
/
5
-4 It (u
E? c"
TL ttt
tt c q-
'/
c,
05101s2A25
Height, m
FIGURE Q4